Project Control Using EVM
Project Control Using EVM
Prepared by:
Consultant/ Mohamed Maged Hegazy
Admin of:
https://www.facebook.com/Prof.Planner
Instructor: Mohamed Maged Hegazy
Project Control Manager, LLM, MBA, B.Sc. of Civil engineering, with
experience in MENA region of (construction, infrastructure, and roads)
Mega projects, in professions of Contract administration, Procurement,
Tender estimating, Cost control, Planning & Claim analysis.
- Lowest level in WBS called Work Package, then it can be decomposed to Schedule Activities.
Baseline Schedule
8
The above
organizational process
flow of
There are three main
work authorization is
types of
captured in Work
organizational
Authorization
structures: functional,
Documents (WADs)
matrix, and project
that take many forms.
Cost Control
13
1) The estimator need to know how long the project will last in order to
estimate certain cost , particularly overhead.
Baseline Schedule
Cash Flow: Update:
Time phased Up to date
Budget Actual Value
Value of of Performed
Planned Work &
Work remaining
April 26, 2023
Earned Value
17
History
➢ When EV is useless:
If the WP = WS which
happens for sure at
the project
completion if the
scope is the same.
April 26, 2023
This’s Why Earned
20
Value…
CV = BCWP − ACWP
CPI = 1, on budget
BCWP CPI < 1, over budget
CPI = CPI > 1, under budget April 26, 2023
ACWP
Earned Value
22
Reporting - Schedule
➢ Schedule Variance (SV): Difference between the value of work that was
planned to be accomplished and the value of the work that was
actually completed
BCWS
Earned Value -
23
Forecasting
Activity cost m1 m2 m3 m4 m5 m6
A simple problem will help to illustrate the 1 $22000
application of the principles of earned
2 $10000
value . A project has been defined that
consist of 12 activities for which the 3 $18000
estimated cost and duration have been 4 $30000
defined see figure . 5 $50000
After three and a half month , the 6 $40000
activates 1,2,4,5,7 are completed and (6) 7 $6000
is half complete and (8) is three–fourth
8 $16000
complete and (3) is half complete. The
9 $13000
incurred cost to date are 152000$ . What is
the status of this project in terms of the 10 $4000
April 26, 2023
schedule and the budget? 11 $34000
12 $14000
Solution
25
ACWP =152000$
BCWS=22000+30000+50000+10000+18000+0.5(40000+
6000+16000)=161000$
BCWP=22000+30000+50000+10000+6000+0,5(40000)
+0.75(16000)+0.5(18000)= 159000$
EAC=ACWP+(BAC-BCWP)=152000+(257000-159000)
= 250000$
Earned Value:
26
Cost and Time
Status
Cost +
CV
II I
- +
Time
SV
III IV
(Factors)
28
(Forecast & TCPI)
29
-Magnify the cost
variance.
-Maintain the
variance till end.
-More accurate.
-Time (SV) affect he
cost as well as (CV).
Budget value
of remaining
work / Value of
cost to spend
(up to Budget
or to Estimate)
30
(EV)
Time-Based
31
Measures:
Earned
Schedule
SPI(time) = PT / AT
Forecast Time:
EAC (t) = BAC (t) / SPI
Estimated Duration
Scope Control:
Schedule factors based
on cost.
Time Control:
Schedule factors based
on time. April 26, 2023
Physical Units -
33
Resources
0%
Economics, Estimating,
Accounting & Finance
PAC
Month 08
Month 01
Month 02
Month 03
Month 04
Month 05
Month 06
Month 07
Month 09
Month 10
Month 11
Month 12
Month 13
Month 14
Month 15
Month 16
Month 17
Month 18
Month 19
Month 20
FAC
(EFCC – course)
Total Float Vs EVM
35
Schedule Factors
Misleading in Each:
remaining duration.
Earned Value
36
Management -
Tricky or Misleading
https://www.facebook.com/groups/prof.cost.engineers/
Earned Value Management - Arabic
M.Maged
[email protected]
mobile : 00966-580264968