Method Statement - Stub Setting
Method Statement - Stub Setting
Method Statement - Stub Setting
Consultant NA
Subcontractor / Specialized
NA
Agency (if applicable)
Discipline Civil
Document No.
Date
Page 1 of 7
RAISSY HGPT COMPANY LIMITED
TABLE OF CONTENTS
1.0 TITLE..............................................................................................................................3
2.0 PURPOSE.......................................................................................................................3
3.0 REFERENCES................................................................................................................3
4.0 ABBREVIATION & DEFINITIONS.................................................................................3
5.0 GENERAL AND SAFETY REQUIREMENTS................................................................3
6.0 RESPONSIBILITIES.......................................................................................................4
6.1 PROJECT MANAGER...................................................................................................4
6.2 CONSTRUCTION MANAGER........................................................................................4
6.3 SITE ENGINEER............................................................................................................4
7.0 TOOLS AND EQUIPMENT’S.........................................................................................5
8.0 METHOD STATEMENT / WORK METHOD..................................................................5
7.1. PILE CAP PREPARATION............................................................................................5
7.2 INSTALL STUB & STUB TEMPLATE...........................................................................6
9.0 INSPECTION..................................................................................................................6
10.0 EMERGENCY RESPONSE............................................................................................6
11.0 HAZARD IDENTIFICATION & RISK ASSESSMENT DETERMINING CONTROLS.....7
12.0 RECORDS......................................................................................................................7
13.0 ATTACHMENT...............................................................................................................7
Page 2 of 7
RAISSY HGPT COMPANY LIMITED
INSTALLATION OF 110kV DOUBLE CIRCUIT OVERHEAD TRANSMISSION LINE FOR
(110/33KV BAWAT SUBSTATION MADINAH) ON STEEL STRUCTURES (TWIN
CONDUCTOR(S) PER PHASE)
1.0 Title
Stub Setting
2.0 Purpose
The purpose of this method statement is to provide guidelines for pile cap preparation, setting out and
installation of stub, stub template & inserts for tower structures.
Further, the Method Statement also describes the Quality Management and HSE Management specific to
the activity.
3.0 References
Contract specifications
- PTS-18EN106 – Scope of Work (SOW) and Technical Specification (TS)
- TCS-P-122.05 Rev.0 – Installation of Steel Structure Foundation
Risk Assessment shall be prepared including mitigation measures, and responsibility for
implementation. This shall be coordinated with site Safety In-charge and attach to this method
statement.
Before commencing any work, all permits shall be checked and ensured that they are valid until
completion of activity.
All works shall be referred to the IFC Drawings and specifications.
All materials shall be approved, sampled, tested, & accepted (as applicable) by client prior to
incorporation to the work.
All staff and workmen shall wear Personnel Protective Equipment (PPE).
Toolbox talks shall be conducted every day before commencement of work.
All personnel shall be cautioned while working near live lines and other services.
Prior to commencement of activities/works, the entire area shall be barricaded.
Adequate sign boards shall be kept to forewarn all.
Accumulated debris shall be cleared from the work site on daily basis.
Page 3 of 7
RAISSY HGPT COMPANY LIMITED
INSTALLATION OF 110kV DOUBLE CIRCUIT OVERHEAD TRANSMISSION LINE FOR
(110/33KV BAWAT SUBSTATION MADINAH) ON STEEL STRUCTURES (TWIN
CONDUCTOR(S) PER PHASE)
It will be ensured that all men working in high-level are wearing necessary safety harness
complying with the safety requirements and following precautionary measures on safety aspects.
When the wind speed exceeds the limit, all works at height specially lifting activities shall not be
permitted.
All equipment shall be calibrated and accompanied by the competent operators prior to
commencement of any works.
In case of any emergency please contact the emergency contact nos.
6.0 Responsibilities
Below mentioned personnel with the responsibilities entrusted to them shall be responsible for carrying
out below mentioned works. In addition to their roles and responsibilities disseminated in the Project
Quality & EHS Plans and the following specific activity functions shall be carried out:
Provide the team with appropriate resources to ensure that works are done in accordance with the
project Quality and EHS requirements and shall be responsible for the approval of method
statement and overall project management.
Page 4 of 7
RAISSY HGPT COMPANY LIMITED
INSTALLATION OF 110kV DOUBLE CIRCUIT OVERHEAD TRANSMISSION LINE FOR
(110/33KV BAWAT SUBSTATION MADINAH) ON STEEL STRUCTURES (TWIN
CONDUCTOR(S) PER PHASE)
Quality In-charge shall review method statements and ensure all requirements are included.
Check & ensure availability of ITP & checklists for the activity.
Inspect the equipment for calibration.
Guide QC inspectors and ensure inspections & test of the activities are conducted as per ITP.
Schedule inspection of works as per ITP.
Check the activities as per ITP & checklist and prepare records and obtain approval.
Prepare & maintain inspection log and records.
Review Quality Control records and ensure correctness.
Disseminate EHS requirements specific to the activities involved and facilitate implementation.
Facilitate for work specific Hazard / Aspect Identification, Risk / Impact Assessment.
Ensure work is carried out in safe manner by coordinating with site engineer, sub-
contractors etc.
Page 5 of 7
INSTALLATION OF 110kV DOUBLE CIRCUIT OVERHEAD TRANSMISSION LINE FOR
(110/33KV BAWAT SUBSTATION MADINAH) ON STEEL STRUCTURES (TWIN
CONDUCTOR(S) PER PHASE)
9.0 Inspection
Quality In charge shall prepare ITP identifying inspection check points and submitted
to customer representative for review and acceptance prior to start work.
Inspection with Customer representative shall be carried out as per ITP for witness and
hold points.
An inspection request shall be submitted to client one day prior to scheduled date of
inspection.
AMBULANCE 997
FIRE 998
POLICE 999
PROJECT MANAGER
NEAREST HOSPITAL
Page 6 of 7
RAISSY HGPT COMPANY LIMITED
HIRADC plan showing activity, risk, mitigation measures, responsibility are prepared to
ensure safe working. Activity based HIRADC plan is attached in this method statement.
12.0 Records
13.0 Attachment
Page 7 of 7
Page 8 of 7