IRC & Packing List

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

Inspection Release Certificate

Refinery Development Master Plan (RDMP) Project

RDMP-26071-100-POA-JF04-
IRC Number Date of Issue 14th March, 2023
00001-IRC-0012

Refinery Development Master


Project Name Vendor Name SAMIL
Plan (RDMP) Project

PO Number 26071-100-POA-JF04-00001 PO Description Flow Element

Item Number Item Description Quantity Remarks

- Flow Element 2,082EA


Refer to the
Packing List
(2 Package)

Total: 2,082 EA

Total Partial

Condition

No remaining(open) NCR.
All documents related inspection have been approved.
Packing list has been reviewed by RDMP JO.
Condition:
N/A

Attachment
#1. Packing List
#2. FAT Test report

Issued by RDMP JO

Andry Arifin
Name/Signature: Dong-Keun, Lee
JO QA/QC Manager

WE HEREBY CERTIFY THAT ABOVE MENTIONED COMMODITY HAS SATISFACTORILY PASSED


THE TEST & INSPECTION IN ACCORDANCE WITH THE CONTRACTUAL SPECIFICATION.
HOWEVER, THIS CERTIFICATE DOES NOT RELIEVE VENDOR FROM THE GUARANTEES AND
OBLIGATIONS WHICH ARE SET FORTH IN THE PURCHASE ORDER AND ATTACHMENTS.

You might also like