National Roads Authority Volume 1 Section 2

Design Manual for Roads and Bridges Part 1 BD 36/92


Addendum Back to Main Index

NRA ADDENDUM TO

BD 36/92

EVALUATION OF MAINTENANCE COSTS


IN COMPARING ALTERNATIVE DESIGNS
FOR HIGHWAY STRUCTURES

Standard BD 36/92 - Evaluation of Maintenance Costs in Comparing Alternative Designs for Highway
Structures - is applicable in Ireland with the following amendments:

GENERAL
1. This is an interim Addendum to BD 36. It should be used until the publication of a new edition of the
Standard, which is currently being prepared by the UK Highways Agency. It is intended that the new edition
of the Standard, when available, will be implemented by the National Roads Authority.

2. This Standard provides detailed advice on the evaluation of commuted maintenance costs for
alternative highway designs in the United Kingdom. For use in Ireland, Design Organisations shall agree
with the National Roads Authority the procedures to be followed and the economic parameters to be used.

3. At several locations:

For: “Overseeing Department”


Read: “National Roads Authority”;

For: “highway”
Read: “road”.

SPECIFIC
1. Page 1/1, Paragraph 1.3:
Delete paragraph and replace with:
“1.3 Please note that BD 36 (DMRB 1.2.1) is
inconsistent with the current version of the
QUADRO Manual (DMRB 14.1). BD 36 uses a
Test Discount Rate of 8% and commutes all prices
to 1988. However, in 1997 the UK Department of
Transport revised the Test Discount Rate to 6%
and changed the Present Value Year to 1994.
Although the QUADRO manual was updated, BD
36 remained unchanged. Consequently, for use of
this Standard in Ireland, Design Organisations
shall agree the most appropriate economic
parameters with the National Roads Authority.”

December 2000 1
National Roads Authority Volume 1 Section 2
Design Manual for Roads and Bridges Part 1 BD 36/92
Addendum

2. Page 1/1, Paragraph 1.5:


Delete Paragraph 1.5 and replace with:
“1.5 This Standard should be used forthwith for
all schemes for the construction and/or
improvement of national roads. The Standard
should be applied to the design of schemes already
being prepared unless, in the opinion of the
National Roads Authority, application would result
in significant additional expense or delay progress.
In such cases, Design Organisations should
confirm the application of this Standard to
particular schemes with the National Roads
Authority.”

3. Page 3/1, Paragraph 3.1 line 5:


For: “Test Discount Rate, currently 8%”
Read: “Test Discount Rate, currently 5%”.

4. Page 3/1, Paragraph 3.1:


[Note: Design Organisations shall agree the Present Value Year with the National Roads Authority.]

5. Page 3/1, Paragraph 3.1, line 15:


Delete sentence: “However,….in Table 3/5.” and replace with:
“However, specific estimates may also be used
with the approval of the National Roads Authority.
For specific estimates, present values shall be
calculated using the maintenance cycles given in
Table 3/5.”

6. Page 3/1, Paragraph 3.4, line 3:


For: “agreed as Departures from Standard.”
Read: “agreed with the National Roads Authority.”

7. Page 3/2, Tables 3/1 to 3/3:


Delete Tables 3/1 to 3/3 and replace with:

“Table 3/1 - Concrete Bridge Decks

BRIDGE DECK TYPE Commuted Rate/m2


plan area of deck in 1988 prices
a. Post-tensioned slab bridges and post- €3.56
tensioned main members
b. Reinforced concrete main members €0.51
c. Reinforced concrete slab bridges €1.52
d. Deck slabs supported by main €1.02
members (in addition to a or b)

December 2000 2
National Roads Authority Volume 1 Section 2
Design Manual for Roads and Bridges Part 1 BD 36/92
Addendum

Table 3/2 - Steel and Steel/Concrete Composite Bridge Decks

ITEM Commuted Rate/m2


plan area of deck in 1988 prices
a. Exterior paintwork - painted area €3.21
b. Interior (box-girder) paintwork or steelwork €1.27
otherwise enclosed - painted area
c. Associated access provisions for painting at 15 year
intervals

Where headroom does not exceed 7.5m – plan


€2.34
Where headroom exceeds 7.5m ………… Specific estimate

(in addition to a and/or b)

* Enclosure of steelwork may be considered as


providing permanent access
d. Deck slab including access for inspection and €1.02
maintenance – plan area of deck

Table 3/3 - Substructures

ITEM Commuted Rate/m2


plan area of deck in 1988 prices
a. Steelwork - exterior paintwork – painted area €3.21

b. Concrete within 5m or less from carriageway - €1.52


surface area

c. Concrete more than 5m from carriageway - €0.51


surface area

8. Page 3/3, Paragraph 3.6, line 2:
After “QUADRO” add:
“or an alternative method agreed with the National Roads Authority.”

9. Page 3/3, Paragraph 3.9(i), lines 4 and 5:


For: “Bridges Division of the Overseeing Department.”
Read: “National Roads Authority”.

10. Page 3/3, Paragraph 3.9(ii), lines 3 and 5:


For: “2025”
Read: “2030”.

11. Page 3/3, Paragraph 3.9(iv):


Delete Paragraph 3.9(iv).

December 2000 3
National Roads Authority Volume 1 Section 2
Design Manual for Roads and Bridges Part 1 BD 36/92
Addendum

12. Page 3/3, Paragraph 3.10:


Delete first sentence, “The results…….factors given in Table 3/4.”

13. Page 3/4, Table 3/4:


Delete Table 3/4.

14. Page 4/1, Paragraph 4.1:


Delete Paragraph 4.1 and replace with:
“4.1 Design Manual for Roads and Bridges

Volume 14: Economic Assessment of Road Maintenance (QUADRO manual).”

15. Page 4/1, Paragraph 4.2, reference to BE 5/76:


For: “(Clause 5 and Appendix 1 are superseded by BD 36/92)”
Read: “(Now withdrawn)”.

16. Page 5/1, Section 5:


Delete text and replace with:
“5.1 All technical enquiries or comments on this Standard should be sent in writing to:

Head of Project Management and Engineering


National Roads Authority
St Martin’s House
Waterloo Road
Dublin 4”

…………………………………………

E O’CONNOR
Head of Project Management and
Engineering

December 2000 4

You might also like