CP 300 (A) - QCP-040 Interlock Concrete Paving Blocks Installat
CP 300 (A) - QCP-040 Interlock Concrete Paving Blocks Installat
CP 300 (A) - QCP-040 Interlock Concrete Paving Blocks Installat
M ET H O D CP 300(a)-QCP-040
S T AT E M E N T
J&P (O) Ltd. /
Page: 1 of 7
J&P–AVAX S.A. J.V.
Document Title:
METHOD STATEMENT
INTERLOCK CONCRETE PAVING BLOCKS INSTALLATION
F-P.810/1-0
J&P Document number:
M ET H O D CP 300(a)-QCP-040
S T AT E M E N T
J&P (O) Ltd. /
Page: 2 of 7
J&P–AVAX S.A. J.V.
1. SCOPE
2. FIELD OF APPLICATION
3. REFERENCES
4. MATERIALS
4.4 Water
5. TOOLS/EQUIPMENTS
6. RESPONSIBILITIES ON SITE
6.2 The Land Surveyor shall be responsible for the correct layout of
the alignment and elevation of the garden kerb and interlock
concrete paving blocks.
6.3 The Site Engineer shall raise the necessary Request for
Inspection (RFI) for all the paving blocks sub-base compaction,
placing of sand laying course and inspection of laid interlock
concrete paving blocks. All other intermediate activities shall be
under surveillance point.
6.4 The Site Engineer shall be responsible for the quality aspect of
the work and compliance with this Method Statement and Project
Specifications.
7. WORK PROCEDURE
Length: +/-2mm
Width: +/-2mm
Thickness: +/-3mm
The surface of paving blocks shall not exhibit any defects such as
flaking.
Mix the mortar bedding for the garden kerb comprising of 1 part
cement & 4 parts sand by volume to a trowellable consistency.
Lay the garden kerb to the correct alignment and elevation set by
the Surveyor.
F-P.810/1-0
J&P Document number:
M ET H O D CP 300(a)-QCP-040
S T AT E M E N T
J&P (O) Ltd. /
Page: 5 of 7
J&P–AVAX S.A. J.V.
Allow the OPC 20/20 concrete sidings to set firmly after which
backfilling and compaction of fill material on both sides of the
garden kerb shall be made simultaneously, avoiding any
unbalanced lateral load which may displace the garden kerb.
The joints between the paving blocks shall be filled with dry
jointing sand by spreading it over the surface and brushing it into
the joints. The dry sand shall be natural and shall comply with the
corresponding grading requirement given in Table 8.2 Section 6
F-P.810/1-0
J&P Document number:
M ET H O D CP 300(a)-QCP-040
S T AT E M E N T
J&P (O) Ltd. /
Page: 6 of 7
J&P–AVAX S.A. J.V.
8. SAFETY PROCEDURES
8.1 The responsible Site Engineer shall physically inspect the working
area to confirm that it is cleared of any hazard and/or obstructions
that may hinder access or proper execution of the work.
8.2 The Site Engineer shall ensure that all personnel engaged in the
interlock concrete paving blocks installation works and related
activities are wearing the required Personal Protective
Equipments (PPE).
F-P.810/1-0
J&P Document number:
M ET H O D CP 300(a)-QCP-040
S T AT E M E N T
J&P (O) Ltd. /
Page: 7 of 7
J&P–AVAX S.A. J.V.
9. REVISIONS
F-P.810/1-0