Core Risk Assessment For Summer
Core Risk Assessment For Summer
Contractor M/s Ghantoot Tpt & Gen. Cont. L.L.C. (Building Division) Document No.
Project Manager
1 Mobilization of Parking at live Employees 3 2 6 M Site OSH induction course mandatory Construction 1 1 1 L OSHAD-SF– Codes
Employees road to drop or for all working in this project. manager, of Practice CoP
Bus should be park at safe area with 44.0 Traffic
Page 1 of 1
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
OSHAD-SF – CoP
11.0 – Safety in
the Heat – V 3.0
OSHAD-SF –
Construction Element 6 -
Ensure that all Employees wear thin Emergency
manager, Management
and breathable clothing, preferably
Heat Rash due to
Working in Hot & Non wearing of Workers, cotton. OSH In OSHAD-SF –
Element 2 - Risk
2 Humid appropriate PPE. Engineers, Advice Engineer & workers to wear charge,
3 4 12 H 1 3 3 L Management
Conditions Visitors light colored clothes
HR staff, OSHAD SF-
Ensure that the clothes are washed Element- 5 –
Supervisor
on regular basis. Training and
awareness and
& competency
OSHAD-SF – COP
Individuals 4.0 – First Aid and
Medical
Emergency
Treatment - V 3.0
Acclimatization Workers, 3 3 9 H Allow time for acclimatization starting Construction 1 2 2 L OSHAD-SF –COP
Engineers, with a lower workload or shorter manager, 08.0 – General
Workplace
Page 2
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
OSH In
working duration, and gradually charge,
increasing the workload or duration
over a number of days. HR staff, Amenities – V 3.0
Visitors Supervisor
Strict supervision and monitoring is OSHAD-SF – CoP
11.0 – Safety in
required all the time by the site & the Heat – V 3.0
supervisor.
Individuals
Construction
Reschedule tasks requiring the
manager,
wearing of thick or vapour
impermeable clothing to cooler OSH In
Workers, periods of the day. charge,
More Workload Engineers, Reorganize the work to reduce OSHAD-SF – CoP
3 3 9 H HR staff, 1 2 2 L 11.0 – Safety in
Visitors intensity and pace of bodily the Heat – V 3.0
Supervisor
movement of the workers.
Workers to take rest and frequent &
breaks in between
Individuals
Construction
manager,
OSH In
Lack of Air Increase air flow with appropriate charge,
Workers, OSHAD-SF –COP
Movement in rest ventilation system, e.g. air-
Engineers, 08.0 – General
areas or work 3 4 12 H HR staff, 1 2 2 L
Visitors conditioning and/or portable fans. Workplace
zones Supervisor Amenities – V 3.0
&
Individuals
Page 3
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
Training and
and trainings, toolbox talks awareness and
HR staff, competency
Train workers regarding heat stress,
Supervisor
precautions to be taken to prevent OSHAD-SF –
Element 6 -
heat stress using HAAD materials. & Emergency
Management
Individuals
Musanada Key
HSE
Requirements
Page 4
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
Page 5
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
3 Emergency Fire All personnel 3 4 12 H All personnel to be safety inducted. CORE 1 3 OSHAD-SF –
situations Train and inform all employees 3 Codes of Practice
Collision Main CoP 17.0 – Safety
regarding fire Emergency Evacuation
Contractor Signage and
Electrocution Plan. Signals – Version
Initiate and maintain good 3.0
Failure to housekeeping OSHAD-SF –
Evacuation Codes of Practice
Ensure that all materials used in porta
CoP 43.0 –
cabin construction are fire rated. Temporary
Ensure that enough firefighting Structures -
equipment are made available on Version 3.0
Page 6
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
I have read, understood and accept the conditions of this method statement & Risk Assessment.
Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Page 7
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL
Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
All operatives involved with this job must sign below
I have read, understood and accept the conditions of this method statement and Risk Assessment.
Sr. Emirates ID
Name Emp. No. Designation Date Signature Remarks
No. No
1
2
3
4
5
6
7
8
9
10
11
12
13
Page 8
RISK ASSESSMENT