Core Risk Assessment For Summer

This document summarizes a risk assessment for upgrading existing buildings at the Al Wathba Phase 1 site. It identifies two main risks: 1) Mobilizing employees could risk injuries from parking in unsafe areas or carrying staff without proper training on local safety rules and conditions. Controls include mandatory induction training and enforcing traffic safety regulations. 2) Working in hot and humid conditions risks heat rash and illness without proper protective equipment like thin, breathable clothing. Controls require providing appropriate clothing, acclimatizing new workers, and allowing breaks in shaded areas.

Uploaded by

Ibrahim Esmat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
336 views8 pages

Core Risk Assessment For Summer

This document summarizes a risk assessment for upgrading existing buildings at the Al Wathba Phase 1 site. It identifies two main risks: 1) Mobilizing employees could risk injuries from parking in unsafe areas or carrying staff without proper training on local safety rules and conditions. Controls include mandatory induction training and enforcing traffic safety regulations. 2) Working in hot and humid conditions risks heat rash and illness without proper protective equipment like thin, breathable clothing. Controls require providing appropriate clothing, acclimatizing new workers, and allowing breaks in shaded areas.

Uploaded by

Ibrahim Esmat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Project Design & Build Upgrading of Existing Punitive &Reformatory Buildings Complex, Al Wathba Phase – 1 On Plot # P5

Employer MUSANADA Contract No.

Consultant: CORE ENGINEERING CONSULTANT Date: 10/06/2018

Contractor M/s Ghantoot Tpt & Gen. Cont. L.L.C. (Building Division) Document No.

RISKASSESSMENT TEAM SITE REPRESENTATIVES

NAME DESIGNATION SIGNATURE NAME DESIGNATION SIGNATURE

Project Manager

OSH Zafeer Arif

Subject Risk Assessment

1 Mobilization of Parking at live Employees 3 2 6 M  Site OSH induction course mandatory Construction 1 1 1 L OSHAD-SF– Codes
Employees road to drop or for all working in this project. manager, of Practice CoP
 Bus should be park at safe area with 44.0 Traffic

Page 1 of 1
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

carry Staff. double indicators and gate should not


open until bust fully stop.
Unfamiliar with the
 Proper training and guidance for all
local situation and Management and
new Employees
the Safety rules OSH In Logistics – Version
 Minimum PPE must be worn at all
charge, 3.0
Unfamiliar to the times
nature of work and  Follow site safety rules HR staff, OSHAD-SF –
weather condition  Follow the traffic safety regulations Supervisor Codes of Practice
 Medical Check up to be done CoP 08.0 – General
Lack of training &
 Special care for young people and Workplace
Younger workers should not be involved in high risky Individuals Amenities – Version
work 3.0
Medically not fit

OSHAD-SF – CoP
11.0 – Safety in
the Heat – V 3.0
OSHAD-SF –
Construction Element 6 -
 Ensure that all Employees wear thin Emergency
manager, Management
and breathable clothing, preferably
Heat Rash due to
Working in Hot & Non wearing of Workers, cotton. OSH In OSHAD-SF –
Element 2 - Risk
2 Humid appropriate PPE. Engineers,  Advice Engineer & workers to wear charge,
3 4 12 H 1 3 3 L Management
Conditions Visitors light colored clothes
HR staff, OSHAD SF-
 Ensure that the clothes are washed Element- 5 –
Supervisor
on regular basis. Training and
awareness and
& competency
OSHAD-SF – COP
Individuals 4.0 – First Aid and
Medical
Emergency
Treatment - V 3.0
Acclimatization Workers, 3 3 9 H  Allow time for acclimatization starting Construction 1 2 2 L OSHAD-SF –COP
Engineers, with a lower workload or shorter manager, 08.0 – General
Workplace

Page 2
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

OSH In
working duration, and gradually charge,
increasing the workload or duration
over a number of days. HR staff, Amenities – V 3.0
Visitors Supervisor
 Strict supervision and monitoring is OSHAD-SF – CoP
11.0 – Safety in
required all the time by the site & the Heat – V 3.0
supervisor.
Individuals

Construction
 Reschedule tasks requiring the
manager,
wearing of thick or vapour
impermeable clothing to cooler OSH In
Workers, periods of the day. charge,
More Workload Engineers,  Reorganize the work to reduce OSHAD-SF – CoP
3 3 9 H HR staff, 1 2 2 L 11.0 – Safety in
Visitors intensity and pace of bodily the Heat – V 3.0
Supervisor
movement of the workers.
 Workers to take rest and frequent &
breaks in between
Individuals

Construction
manager,

OSH In
Lack of Air  Increase air flow with appropriate charge,
Workers, OSHAD-SF –COP
Movement in rest ventilation system, e.g. air-
Engineers, 08.0 – General
areas or work 3 4 12 H HR staff, 1 2 2 L
Visitors conditioning and/or portable fans. Workplace
zones Supervisor Amenities – V 3.0

&

Individuals

Lack of Information Workers, 3 4 12 H  Display heat awareness signage, Construction 1 2 2 L OSHAD-SF –


, awareness Engineers,  Increase awareness for the workers manager, Element 2 - Risk
Visitors and engineers by posting signage Management
OSH In OSHAD SF-
charge, Element- 5 –

Page 3
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Training and
and trainings, toolbox talks awareness and
HR staff, competency
 Train workers regarding heat stress,
Supervisor
precautions to be taken to prevent OSHAD-SF –
Element 6 -
heat stress using HAAD materials. & Emergency
Management
 Individuals
Musanada Key
HSE
Requirements

 Ensure that all personnel are trained OSHAD-SF –


Element 3 –
regarding the emergency situation Management of
faced during working in hot Construction Contractors
conditions. manager, OSHAD-SF –
 Ensure that there is an emergency Element 2 - Risk
OSH In Management
vehicle on site at all times.
Workers, charge, OSHAD SF-
Emergency  Ensure that emergency procedures Element- 5 –
Engineers,
response 3 5 15 H are displayed in rest areas, notice HR staff, 1 2 2 L Training and
Visitors awareness and
boards, offices, site. Supervisor
competency
 Ensure that the procedures are well
& OSHAD-SF –
communicated with the workers. Element 6 -
 Ensure that there is a fully equipped Individuals Emergency
first aid room with a certified advance Management
first aider. Musanada Key
HSE
Requirements
Heat Illness , Workers, 3 4 12 H  Ensure that the TWL (Thermal Work Construction 1 2 2 L OSHAD-SF–COP
Engineers, limit) is measured on site on daily manager, 2.0 – Personal
Heat Stroke, Visitors Protective
basis and that precautionary
OSH In Equipment - V 3.0
Dehydration , measures are taken depending on the
charge, OSHAD-SF – COP
Humidity level of working zone readings. ( TWL 4.0 – First Aid and
Reading HR staff, Medical
 > 220- Unrestricted zone Supervisor Emergency
Treatment - V 3.0
 140-220- Acclimatization zone
& OSHAD-SF –COP
08.0 – General

Page 4
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 115-140- Buffer Zone. Individuals Workplace


 < 115- Withdrawal zone. Amenities – V 3.0
 Permit to work system to be in place if OSHAD-SF – CoP
the TWL limit goes below 115 w/m2. 11.0 – Safety in
the Heat – V 3.0
 Ensure that the TWL (Thermal Work
OSHAD-SF –
limit) is measured on site on daily COP 17.0 – Safety
basis and that precautionary Signage and
measures are taken depending on the Signals – V 3.0
level of working zone readings. ( TWL OSHAD-SF–
COP 21.0 – Permit
Reading
to Work Systems
 > 220- Unrestricted zone - V 3.0
 140-220- Acclimatization zone OSHAD-SF - COP
 115-140- Buffer Zone. 30.0 – Lone
Working and/or in
 < 115- Withdrawal zone.
Remote Locations
 Ensure that workers are provided – V 3.0
with sufficient shelter / shaded areas OSHAD-SF –
on site. If shaded shelter can’t be Element 3 –
prepared on work zone then Management of
Contractors
umbrellas to be provided.
OSHAD-SF –
 Ensure that the workers increase the Element 2 - Risk
intake of salt in the food provided that Management
they are not suffering from OSHAD SF-
hypertension. Element- 5 –
Training and
 Ensure that Oral Rehydration awareness and
solutions are provided to the workers competency
working in hot n humid conditions. OSHAD-SF –
 Ensure that workers are provided with Element 6 -
Emergency
water thermos with cool drinking Management
water.
Musanada Key
 Ensure that the site adhere to the HSE
UAE Ministry of Labour requirements Requirements
for a midday break during the
summer months for employees

Page 5
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

working outside. Signage to be


displayed and workers to be made
aware regarding the same.
 Ensure appropriate availability of
appropriate fluids (e.g. potable water)
for the employees to maintain
hydration levels;
 Ensure an allowance is made for self-
pacing of work and appropriate rest
breaks are provided to exposed
employees;
 Ensure that in the event an employee
is suffering from a suspected heat
related illness they have immediate
access to medical attention.
 Ensure that Lone working is not
permitted. Atleast two persons to
work together at all times.
 Ensure that An advance first Aider is
there on site at all times.
 Strict supervision and monitoring is
required all the time by the site
supervisor.

3 Emergency Fire All personnel 3 4 12 H  All personnel to be safety inducted. CORE 1 3 OSHAD-SF –
situations  Train and inform all employees 3 Codes of Practice
Collision Main CoP 17.0 – Safety
regarding fire Emergency Evacuation
Contractor Signage and
Electrocution Plan. Signals – Version
 Initiate and maintain good 3.0
Failure to housekeeping OSHAD-SF –
Evacuation Codes of Practice
 Ensure that all materials used in porta
CoP 43.0 –
cabin construction are fire rated. Temporary
 Ensure that enough firefighting Structures -
equipment are made available on Version 3.0

Page 6
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

site. ( Fire Ex., Fire Hose Reel)


 Ensure that fire alarm and Fire siren
are available on site and are fully
functional.
 No smoking in non-designated areas. OSHAD-SF –
Codes of Practice
 Ensurre that smoke detectors are CoP 08.0 –
installed inside all offices. General
 Ensure that workers are trained- how Workplace
Amenities –
to fight fire, what to do in case of an Version 3.0
emergency OSHAD SF-
 Ensure that enough assembly points Element- 5 –
are made available on site and Training and
awareness and
access to them is kept clear at all competency
times. OSHAD-SF –
 Ensure emergency numbers are Element 6 -
posted at strategic locations. Emergency
Management
 Ensure that Evacuation plan is posted
on notice boards and all are informed
about it during inductions.

Risk Assessment handover


Date: _ _ / _ _ /_ _ _

I have read, understood and accept the conditions of this method statement & Risk Assessment.
Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Page 7
RISK ASSESSMENT
RISK LEVEL RESIDUAL RISK LEVEL
S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
All operatives involved with this job must sign below
I have read, understood and accept the conditions of this method statement and Risk Assessment.

Sr. Emirates ID
Name Emp. No. Designation Date Signature Remarks
No. No
1
2
3
4
5
6
7
8
9
10
11
12
13

Page 8
RISK ASSESSMENT