Daily Report - W41

The daily report summarizes construction activities from November 7-8, 2022 at the EPC Pemasangan SP Lapangan Jati Asri project location in Jati Asri, Subang. It details 151 workers involved across various roles. On November 7, work included installing tank shells, setting roofs, welding, loading/unloading, and pouring concrete. Planned work for November 8 included setting additional tank shells, installing rebar, fabricating rebar, dismantling formwork, and welding tasks. Weather was clear during working hours.

Uploaded by

deludel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views14 pages

Daily Report - W41

The daily report summarizes construction activities from November 7-8, 2022 at the EPC Pemasangan SP Lapangan Jati Asri project location in Jati Asri, Subang. It details 151 workers involved across various roles. On November 7, work included installing tank shells, setting roofs, welding, loading/unloading, and pouring concrete. Planned work for November 8 included setting additional tank shells, installing rebar, fabricating rebar, dismantling formwork, and welding tasks. Weather was clear during working hours.

Uploaded by

deludel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 14

LAPORAN HARIAN KONSTRUKSI

DAILY REPORT CONSTRUCTION

Nomor Report : 278 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Monday, November 7, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 Install shell ke 4 tank 01A
2 Setting roof T02A
3 Install&welding roof
4 Welding tank 1b
5 Welding tank 2b
6 Welding Top Angle Tanki T10
7 Welding Shell ke Bottom tanki T10
8 Welding Top Angle tanki T80
9 Welding Shell ke Bottom tanki T80
10 Loading unloading
11 Pouring concrite Lantai K.O Drum / Close drain vassel
12 Pouring Concrite Lighting Protection System
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 Setting shell ke 5 tank 01B
2 Install roof to rafter tank T02A
3 Install Rebar Fire Wall K.O Drum / Close drain vessel
4 Fabrikasi Rebar K.O drum / Close drain vassel
5 Dismantel fomwork Wall waterpond
6 Welding bagian dalam Shell ke 4 horizontal tank 01B
7 Welding roof T02A
8 welding bottom ke Shell T80
9 fabrikasi spool pipe 4" utk over flow tanki
10 install platform T.02.A.lantai ke 4 bagian dalam
11 install scaffolding T.01A.lantai ke 4 bagian luar
12 Fit up shell ke4 pertical tank 02B
Comment & Issue :
Cuaca Waktu /Time
Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja

Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP
LAPORAN HARIAN 2

DAILY REPORT

Nomor Report : 279 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Tuesday, November 8, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 Holiday tes line 8 "fire water
2 Weld shell ke2 vertikal tank 04A
3 welding roof
4 welding bottom 1A/1B
5 welding shel vertical T04 A-B
6 Vabrication spool natural gas 4" dan TLB 8"
7 overflow pipe 4"
8 instal scaffolding Tanki
9 Weld nozle 4" untuk oper plow tank
10 Melanjutkan back fill line 8" fire water
11 Weld shoe anchor bolt
12 welding pipe 4" to over flow and natural gas 16 jts
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 Welding vertikal T03
2 Fabrication Piping
3 install scaffolding T 04 A bagian dalam
4 install scaffolding T 04 B bagian dalam
5 install and weld pipe 2" = 4 jts
6 install and weld pipe 3" = 8 jts
7 install and weld pipe 4" = 5 jts
8 install and weld pipe 6" = 11 jts
9 Vertikal T03 = 5.40 cm
10 Baricade stairway 11ea = 5.50 cm
11 Bed weld main hole/ roof T01B 24" = 1 join
12 Bed weld 10" T01B = join
13 Nozel 10" T02A= 1 join
14 reinforce 10" = 23"
15 Stoper pipa 6 " /2ea T04A/T04B = 1.60 cm
16 Nozel 8" T10= 1join
17 Reinforce 8"=19 "
18 Nozel 2" T 10= 1 join
19 Pipa 4" = 2 join = 8 "
20 Bill/up dan clening T01B / T04A/T04B
Comment & Issue :

Cuaca Waktu /Time


Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja

Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP
LAPORAN HARIAN
DAILY REPORT

Nomor Report : 280 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Wednesday, November 9, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 Welding vertikal T03
2 Fabrication Piping
3 install scaffolding T 04 A bagian dalam
4 install scaffolding T 04 B bagian dalam
5 install and weld pipe 2" = 4 jts
6 install and weld pipe 3" = 8 jts
7 install and weld pipe 4" = 5 jts
8 install and weld pipe 6" = 11 jts
9 Vertikal T03 = 5.40 cm
10 Baricade stairway 11ea = 5.50 cm
11 Bed weld main hole/ roof T01B 24" = 1 join
12 Bed weld 10" T01B = join
13 Nozel 10" T02A= 1 join
14 reinforce 10" = 23"
15 Stoper pipa 6 " /2ea T04A/T04B = 1.60 cm
16 Nozel 8" T10= 1join
17 Reinforce 8"=19 "
18 Nozel 2" T 10= 1 join
19 Pipa 4" = 2 join = 8 "
20 Bill/up dan clening T01B / T04A/T04B
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 continue install scaffolding T 03 bagian dalam
2 Install Formwork API Separator
3 continue install scaffolding T 03 bagian luar
4 Prepare Hydrotest T02B
5 Vertikal T03= 5.40 cm
6 Nozel 2" T80 = 6 join
7 Nozel 4" T80= 3 join
8 Reinforce 4" T80= 35.7"
9 Nozel 6"T80= 1 join
10 Reinforce 6" T80= 15.7"
11 Nozel 2"T 10 =2 join
12 Stair way tanga 12 ea = 5.40 cm.
13 Pipa waferflow 4" T04B = 2 join
14 Stoper pipa 6" /2 ea = 3.60cm
15 Bed weld main hole 24" T10 = 49 "
16 Bed weld main hole 24" T 80 = 49 "
17 Bedweld nozel 4" T 04 = 4 join
18 Bed weld nozel 2" T04A T04B = 6 join
Comment & Issue :

Cuaca Waktu /Time


Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja

Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP
LAPORAN HARIAN
DAILY REPORT

Nomor Report : 281 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Thursday, November 10, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 Setting shell ke 5 tank 01B
2 Install roof to rafter tank T02A
3 Install Rebar Fire Wall K.O Drum / Close drain vessel
4 Fabrikasi Rebar K.O drum / Close drain vassel
5 Dismantel fomwork Wall waterpond
6 Welding bagian dalam Shell ke 4 horizontal tank 01B
7 Welding roof T02A
8 welding bottom ke Shell T80
9 fabrikasi spool pipe 4" utk over flow tanki
10 install platform T.02.A.lantai ke 4 bagian dalam
11 install scaffolding T.01A.lantai ke 4 bagian luar
12 Fit up shell ke4 pertical tank 02B
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 Continue install platform T.01A.lantai ke 4 bagian luar
2 Install roof to rafter tank T02A
3 Fabrikasi Rebar K.O drum / Close drain vassel
4 Welding roof T02A
Comment & Issue :

Cuaca Waktu /Time


Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja

Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP
LAPORAN HARIAN
DAILY REPORT

Nomor Report : 282 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Friday, November 11, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 Continue install platform T.01A.lantai ke 4 bagian luar
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 fabrikasi spoll 2 oven drain'
2 fabrikasi spoll 8" natural gas
3 Install Rebar Fire Wall K.O Drum / Close drain vassel
4 Fabrikasi Rebar K.O drum / Close drain vassel
5 Dismantel fomwork Wall waterpond
6 Setting shell ke 5 tank 02B
7 Setting rafter untuk tank 01B
8 Weld shell ke4 harizontal tank 02B
9 install handreel T.01A.lantai ke 4
10 transfer material untuk platform T.01A.lantai ke 4
11 welding pipa 4" over flow = 5jts
12 install and welding pipe 8" = 3jts pipe 6" =1 jt pipe 4" = 1 jt total = 5 jts
13 install and weld pipe 2" open drain = 10 jts
14 Weld shell ke4 vertical tank 02A
15 Melanjutkan weld roof
16 Malanjutkan setting shoe angchor bolt
Comment & Issue :

Cuaca Waktu /Time


Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja
Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP
LAPORAN HARIAN
DAILY REPORT

Nomor Report : 283 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Saturday, November 12, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 fabrikasi spoll 2 oven drain'
2 fabrikasi spoll 8" natural gas
3 Install Rebar Fire Wall K.O Drum / Close drain vassel
4 Fabrikasi Rebar K.O drum / Close drain vassel
5 Dismantel fomwork Wall waterpond
6 Setting shell ke 5 tank 02B
7 Setting rafter untuk tank 01B
8 Weld shell ke4 harizontal tank 02B
9 install handreel T.01A.lantai ke 4
10 transfer material untuk platform T.01A.lantai ke 4
11 welding pipa 4" over flow = 5jts
12 install and welding pipe 8" = 3jts pipe 6" =1 jt pipe 4" = 1 jt total = 5 jts
13 install and weld pipe 2" open drain = 10 jts
14 Weld shell ke4 vertical tank 02A
15 Melanjutkan weld roof
16 Malanjutkan setting shoe angchor bolt
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 setting shell ke 5 Tank 02B
2 install platform T.01A.lantai ke4.bagian dalam
3 Backwell tank horizontal tank 02B Shell bagian dalam
4 backwell horizontal Shell no 04 T02A bagian luar
5 welding roof T02A dan T01B
6 fabrikasi spoll oven drain 2"
7 fabrikasi spoll natural gas 8"
8 Servis jalan menuju tank
9 Weld shell Ke 4 harizontal tank 02A
10 Grinda shell ke 4 tank 02B
11 Melanjutkan weld roof tank 02A
12 Weld rafter ke roof tank 01B
13 welding pipe 2"
14 open drain = 16 jts
15 welding pipe 8"
16 natural gas = 3 jts
17 welding pipe 4" = 2 jt
Comment & Issue :

Cuaca Waktu /Time


Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja

Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP
LAPORAN HARIAN
DAILY REPORT

Nomor Report : 284 Project No. : SP3MP N0. 002/PEP80000/SP3MP/2022-S0

Day / Date : Sunday, November 13, 2022 ( Day Shift )


Name Project : EPC Pemasangan SP Lapangan Jati Asri
Location : Jati Asri - Field Subang

Equipment dan Material yang digunakan


NO. Direct & Indirect Manpower Unit QTY Equipment and Materials used
Equipment & Tools Unit Qty Material Unit Qty
A Indirect Alat Survey set 2 Patok Lot 1
Cirebon Mesin Bor Tangan 4" Unit 3 Kayu Lot 1
1 Project Manager Prsn 1 Mesin Gerinda Tangan 4" Unit 2 Pasir Lot 1
2 Project Control Prsn 3 Genset SE7800.50Hz Unit 1 Triplek Lot 1
3 QA/QC Coordinator Prsn 1 Hand Compactor Hp-RM80H Unit 2 Ribar Lot 1
4 Engineer Coordinator Prsn 1 Pump Air Celup Unit 2
5 Engineer Prsn 5 Vibrator satu set Unit 1
6 Drafter Prsn 5 Circular saw.M5801B 7-1/4 Unit 1
A Site JAS Cutting Machine Ribar MT 243#14" Unit 2
1 Document Control Prsn 3 Excavator Unit 1
2 HSSE Prsn 4 Mixer Molen Unit 1
3 Site Manager Prsn 1 Foco Truck 9 Ton Unit 1
4 SUPERINTENDENT Prsn 1
5 QA/QC Civil Prsn 1
6 QA/QC Piping Prsn 1
7 QA/QC Coating Prsn 1
8 Electrical Inspector Prsn 1
9 Electrical Instrument Prsn 3
10 Humas Prsn 1
11 Supervisor Prsn 2
12 Admin Prsn 1
13 Driver Prsn 1
14 Medic Prsn 1
15 Mechanic Prsn 1
16 Fire Watcher Prsn 1
B Direct
1 Formen Prsn 6
2 Surveyor Prsn 2
3 Carpenter Prsn 15
4 Chainman Prsn 1
5 Scafolder Prsn 3
6 Rigger Prsn 3
7 Material Prsn 1
8 Operator Prsn 3
9 Helper Prsn 28
10 Welder Prsn 14
11 Blaster & Painter Prsn 7
12 Fitter Prsn 28
Total Prsn 151
Uraian Pekerjaan Hari ini Referensi Gambar
No. Item Unit Volume
Job Description Today Reference Drawing
1 setting shell ke 5 Tank 02B
2 install platform T.01A.lantai ke4.bagian dalam
3 Backwell tank horizontal tank 02B Shell bagian dalam
4 backwell horizontal Shell no 04 T02A bagian luar
5 welding roof T02A dan T01B
6 fabrikasi spoll oven drain 2"
7 fabrikasi spoll natural gas 8"
8 Servis jalan menuju tank
9 Weld shell Ke 4 harizontal tank 02A
10 Grinda shell ke 4 tank 02B
11 Melanjutkan weld roof tank 02A
12 Weld rafter ke roof tank 01B
13 welding pipe 2"
14 open drain = 16 jts
15 welding pipe 8"
16 natural gas = 3 jts
17 welding pipe 4" = 2 jt
Uraian Rencana Pekerjaan Besok Referens Gambar
No. Item Unit Volume
Description of the Work Plan Tomorrow Reference Drawing
1 Setting shell ke 5 tank 02A
2 Install Begesting Fire Wall K.O Drum / Close drain vassel
3 Dismantel fomwork Wall waterpond
4 Backwell horizontal tank 02A Shell no 4 bagian dalam
5 welding roof T01B
6 fabrikasi spoll open drain 2'
7 fabrication spoll 8" natural gas
8 Memindahkan roof siap di fabricasi untuk di weld
9 Melanjutkan setting shell kelima Tank 02A
10 install and weld pipe 8"natural gas = 6 jts
Comment & Issue :

Cuaca Waktu /Time


Weather 6:00 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00
Cerah
Berawan
Hujan
Cuaca tidak di jam kerja

Disiapkan oleh, Diperiksa oleh, Diperiksa oleh, Diketahui dan Disetujui oleh,
KSO WKSAI KSO WKSAI Pertamina EP zona 7 Pertamina EP zona 7

…......................... Noor I Wibowo ( ………...…………... ) ( ………………….……...…... )


Supervisor / Superintendent Site Manager Representative Construction PT. Pertamina EP