EAC Chapter 1 Notes
EAC Chapter 1 Notes
Technical Sanction:- It is the sanction given by the highest authority of the executive
department to the detailed estimate of the proposed project prepared by executive division. OR
Technical sanction means the sanction of the detailed estimate, design, rates and cost of work.
Budget Provision: After the need of the project and its appraisal, a project report is prepared in
which raw materials, organizational setup and total cost required for execution of project are
mentioned. Then according to 5-year plan in the budget provision for such type of projects,
finance is sanctioned after the administrative approval of the project.
1. To give the rough idea of probable expenditure in short time without calculating the
actual quantities, from the cost of similar structure having similar specification, construction
& locality.
2. In case of Government & public bodies, for sanctioning of the expenditure required for
the project in the form of Administrative approval.
3. In case of commercial projects to study the cost-benefit ratio. If it is justified the project is
carried out.
4. For BOT/PPP Systems approximate estimates plays important role for decision making &
for preparation of Feasibility Report of Project
5. For framing Tax Schedule & Insurance requirement.
6. For buying & sailing and Rent Fixation.
1) Revised estimate
1) A revised estimate is a detailed estimate for the revised quantities and rates of items of works
originally provided in the estimate without material deviations of a structural nature from the design
originally approved for a project.
2) It is accompanied with a comparative statement abstract form showing the probable variations for
quantity, rate and amount for each item of work of the project as compared with the original estimate
side by side stating the reasons of variations.
3) A revised estimate is prepared and submitted for fresh technical sanction. It is required to be
prepared for the following reasons-
1. When a sanctioned estimate is likely to exceed by more than 5% either from the rates being
found insufficient or from any cause whatsoever except important structural alterations
2. When the expenditure of work exceeds or is likely to exceed by more than 10% of the
administrative approval (for work more than Rs 5 lakhs)
3. When there are material deviations from the original proposal but not due to material deviation
of a structural nature.
4. When it is found that the sanctioned estimate is more than the actual requirement
2) Supplementary estimate
1. While a work is in progress, some changes or additional works due to material deviation of a
structural nature from the design originally approved may be thought necessary for the development
of a project. An estimate is then prepared to include all such works. This is known as a
supplementary estimate.
2. The method of preparation of a supplementary estimate is the same as that of a detailed estimate and
it should be accompanied by a full report of the circumstances which render its necessity.
3. The abstract must show the amount of the original estimate and the total of the sanction required
including the supplementary amount
1) Revised estimate: Revised estimate is a detailed estimate and is required to be prepared under
any one of the following circumstances.
2) Supplementary estimate.
It is detailed estimate of additional work and is prepared when additional works or changes are
required to supplement the original works, during the execution of work. Then a fresh detailed
estimate of additional works is prepared in addition to the original works. The abstract should
show the amount of the original estimate and the total amount including the Supplementary
amount, for which sanctioned is required.
3. Complete estimate
This is a complete estimate or list of quantities for all items of work required to complete the
concerned project. The quantity of each individual item of work is worked out from respective
dimensions on the drawing of the structure To find the cost of an item its quantity is multiplied by
the rate per unit for that item. The purpose of the Bill of quantities is to provide a complete list of
1. Site clearance: It is measured in lumpsum quantities. Measurements of plot are taken just for observation
and quotations are taken from the contractor for removing garbage if any, water ditches shall be filled and
plot must be levelled. Machinery required for this activity are J.C.B. buldozer and roller.
2. Earthwork in excavation in foundation: It is measured in cubic metre. The quantity of this Item is
calculated by observing length, breadth and depth from the drawing. Length of this item is calculated by
centre line method or long wall and short wall method. This item must include suporting soll of sides of
trenches, removing water etc. and complete.
3. P.C.C. bed in foundation: This item is measured in cubic metre. The quantity of this item is calculated
by multiplying length, breadth and thickness of P.C.C. This includes mixing, laying, compaction, curing and
finishing also.
4. U.C.R. masonry in foundation in C.M. (1:6): This item is measured in cubic metre. The quantity of this
item is calculated by multiplying length, breadth, and height of U.C.R. work. If stepped footing is provided,
then quantity of each step is calculated separately and then added together.
5. D.P.C. in C.C. (1:3): This Item is measured in square metre. The quantity of this item is calculated by
multiplying length and breadth of 9.P.C. provided below the brick masonry and at plinth level. The width of
door opening is deducted on the length of D.P.C.
6. Brick masonry in C.M. (1:6): This item is measured in cubic metre. The quantity of this item is
calculated by multiplying length, breadth or thickness and height of masonry. Deduction for openings of
door, window, grills and ventilator shall be done as per IS-1200 rules. Deduction for lintel above doors and
windows shall be done by multiplying length of lintel, width of lintel and height of lintel.
= Width+0.15-2
7. Plinth filling: This item is measured in cubic metre. The quantity of this item is calculated by multiplying
length, width and height as shown in drawing. The quantity of plinth fingis calculated for every room
separately.
Length for plinth filling for a room = Length of room+0.5 Width of masonry at plinth x2
Width of plinth filling for a room = width of room + 0.5 Width of masonry at plinth x 2
Height of plinth filling = Height of murum filling + Height of rubble filling +Height of P.C.C. as shown in
drawing.
8. Flooring: This item is measured in square metre. The quantity of this item is calculated by multiplying
length and width of the rooms of building. The different types of flooring is taken as different items for
different rooms. Same type of flooring if provided in many rooms, then they shall be grouped under one
Item. Addition of flooring material for openings shall be done in total quantity.
9. Internal Plaster: This item is measured in square metre. The quantity of plastering (internal) is calculated
by multiplying length of wall and height of walls. Deductions of openings of door, window and grills shall
be done as per the rules of IS-1200.
10. External Plaster: This item is measured in square metre. The quantity of external plaster of a building is
calculated by formula:
Quantity of external plaster = Perimeter of exterior of building x Height Door, windows and other openings
on external wall of building are deducted from the quantity of external plaster.
1. Site clearance: It is measured in lumpsum quantity. It is done on the basis of size of plot.
2. Excavation in foundation: This quantity is measured in cubic metre. This quantity is calculated by
observing the size of footing from drawing.
3. P.C.C. bed in foundation: This quantity is measured in cubic metre. This quantity is calculated by
observing length, width and depth of footing from drawing.
4. R.C.C. in footing: This quantity is calculated in cubic metre. This quantity is calculated by determining
volume of concrete by prismoidal formula. Quantity of concrete can be calculated by finding volume of
5.Plinth beam: This Item is measured in cubic metre. The quantity of concrete for plinth is calculated by
determining volume. Volume of beam is calculated by multiplying length, breadth and depth of beam. If
there are many beams having same cross-sections, they shall be placed in the same group under item of
R.C.C. beam. The quantity of steel is calculated either on % basis or according to drawing.
6. Column: This item is measured in cubic metre. The quantity of concrete for a column is calculated by
taking out volume of column.
7. Floor beams: The quantity of this item is measured is cubic metre. The quantity of concrete is determined
by knowing volume of one beam and then multiplying with number of beams having same cross-section and
length. The quantity of steel is taken as a % of concrete or by detailed drawing.
8. Slab: The quantity of this item is measured in cubic metre. The quantity of concrete is determined by
knowing volume of slab (L x B x H). The quantity of steel is calculated as a % of concrete or by knowing
detailed drawing.
9. Stair case: The quantity of stair case components is calculated in cubic metre. Quantity of concrete for
waist slab is calculated by knowing its volume. Quantity of concrete for landing slab is calculated by taking
out volume of slab (LxBxH). Quantity of steel is taken as a % of concrete or by knowing details of
reinforcement from drawing.
10. Plinth filling: This Item is measured in cubic metre. The quantity of filling of rubble, soil, murum and
P.C.C. is determined by knowing volume (LxBxH).
11. B. B. masonry for superstructure: This item is measured in cubic metre. The quantity of this item is
calculated by multiplying length, breadth or thickness and height of masonry. Deduction for openings of
door, window, grills and ventilator shall be done as per IS-1200 rules. Deduction for lintel above doors and
windows shall be done by multiplying length of lintel, width of lintel and height of lintel.
12. Flooring: This item is measured in square metre. The quantity of this item is calculated by multiplying
length and width of the rooms of building. The different types of flooring are taken as different items for
different rooms. Same type of flooring if provided in many rooms, then they shall be grouped under one
item. Addition of flooring material for openings shall be done in total quantity.
13. Internal plaster: This item is measured in square metre. The quantity of plastering (internal) is
calculated by multiplying length of wall and height of walls. Deductions of openings of door, window and
grills shall be done as per the rules of IS-1200.
1. Site Clearing
2. Excavation in foundation
3. Soiling
4. P.C.C. bed in foundation (1:4:8, 1:5:10)
5. R.C.C. in footing
6. Plinth beam
7. Column
8. Floor beams
9. Slab
10. Stair case
11. Plinth filling
12. B.B.M. for superstructure
13. Flooring
14. Internal plaster
15. External plaster
16. Internal painting
17. External painting (Note- For any 8 items of work give full marks)
1) Formwork-sq. m
2) U.C.R.masonry -cu.m.
3) Brick wall (10 cm thick): sq. m
Q. State the rules for deduction in masonry work as per IS 1200 (W-22-4)
No deduction for
1. Opening up to 0.1 sq.m
2. Ends of beams, posts, rafters, purling etc. up to 0.05 sq.m in section
3. Bed plates, wall plates, bearing of chajjas where thickness does not exceed 10 cm
4. Bearing of floor & roof slabs are not deducted from masonry in super structure.
Plastering usually 12mm thick is calculated in sq.m. Deduction in plastering are made in the following
manner
Q. State the rules for deduction of opening as per IS1200 for brickwork. (G-S-19-4)
2. As the rates vary from place to place, Maharashtra Government publishes list of rates as per
districts. These rates are in the form of printed booklet and called as District Schedule of Rates
(DSR).
3. This booklet is revised every year because of changes in cost of labor, material every year.
4. It includes Completed rates, per unit cost of item of work and Labor rates.
5. Labor rates include charges to be paid to head mason, mazdoor, coolie etc. depending on the
category of labor.
6. It also includes initial lead and lift and separate charges are applicable for more lead and lift.
Similarly the rates are applicable to ground floor only and they are increased for each upper floor.
A booklet containing rates of various engineering items for the preparation of detailed estimates
such as buildings, roads, bridges, canal etc,called as schedule of rates.
1. It also gives the rate of materials, daily wages of labour, carriage expenditure.
2. It is also given with table for quantities of various material required in construction.
3. Schedule of rates vary with region
4. Schedule of rates increases every year by certain percentage of previous year rates.
5. Schedule rates periodically revised
1.10 Standard formats for measurement, abstract & face sheet
Q. Prepare a format for face sheet (W-22-2)
Q. Draw the standard format of face sheet and abstract sheet (G-W-19-4)