RCC (1:2:4) (Mechanical)
RCC (1:2:4) (Mechanical)
Wet RCC = 10
Factor = 1.50
Dry PCC = 15.0
Material:-
Cement = 62.857 bags
Sand = 4.4
Crush = 8.8
Steel = 1% volume of concrete
= 10/100x1x7850
= 785 kg
Labour:-
Mason = 0.1 day/
Waterman = 2.13 day/
Labour = 0.3day/
Steel Cutter = 250 kg/day
Steel fixer = 1000kg/day
Machinery:-
Viberator = 1 hour for 10
= 0.125 days
Concrete Mixer + Lift Arrangement = 0.45days
Wet RCC = 10
Factor = 1.50
Dry PCC = 15.0
Material:-
Cement = 77.92 bags
Sand = 4.09
Crush = 8.18
Steel = 2% volume of concrete
= 10/100x2x7850
= 1570 kg
Labour:-
Mason = 0.1 day/
Waterman = 2.13 day/
Labour = 0.3day/
Steel Cutter = 250 kg/day
Steel fixer = 1000kg/day
Machinery:-
Viberator = 1 hour for 10
= 0.125 days
Concrete Mixer + Lift Arrangement = 0.45days