Batch ILR Operations Training - FCF Runruno - Dec2019
Batch ILR Operations Training - FCF Runruno - Dec2019
Operations Training
FCF Minerals Corporation
Runruno Gold-Molybdenum Project
Batch InLine Leach Reactor Operation
• Safety
• Operating Procedure
• Maintenance
ILR SAFETY - REAGENTS
• Description
• Operation Steps
• Operator Interface
• Manual Operation
• Automatic Operation
BATCH ILR DESCRIPTION
• Reactor drum
• Level controlled
sump and pump
• Concentrate Feed
Cone
• Solution Storage
Tank
Reactor Drum
• Reactor drum
• Feed seal
• Drum drive
• Drum rollers
• Discharge
• Drain
• Proximity Switch
BATCH ILR DESCRIPTION
Reactor Drum
• Reactor drum
• Feed seal
• Drum drive
• Drum rollers
• Discharge
• Drain
• Proximity Switch
BATCH ILR DESCRIPTION
• Pump
• Level sensor
• pH probe
• Dump valve
• Overflow
BATCH ILR DESCRIPTION
Feed Cone
• Feed Cone
• Overflow
• Discharge valve
• Flush valve
• Load cell
BATCH ILR DESCRIPTION
Solution Cone
• Solution storage
tank
• Reagent addition
• Load cell
BATCH ILR DESCRIPTION
Control Valves
• All On/Off
• Tails valve
• Solution recirculation valve
• Solution Return valve
• Sample valves
• Wash water transfer valve
• Electrowinning transfer valve
• Reagents
BATCH ILR OPERATING STEPS
Stage Duration
1. Load Concentrate – mass controlled ~ 20 min
2. Make up Leach Solution – mass & time ~ 20 min
3. Leach – time based 3 - 18 hr
4. 0. Clarify Solution – time based 50 - 70 min
5. 0. Transfer Pregnant Solution – mass based ~ 10 min
6. 1. Wash Leached Solids – mass based ~ 15 min
4. 1. Clarify Solution – time based 50 - 70 min
5. 1. Transfer Wash Solution – mass based ~ 10 min
7. Wash by Time (to CIL) – time based 20 min
8. Transfer Solid Tails – time based 45 - 60 min
9. Drain Drum 10 min
STEP 0 - IDLE
• ILR is Idle, waiting
for start
• Gravity
concentrators
continue running,
filling feed cone
• Electrowinning
process
downstream
continues previous
ILR Batch
BATCH ILR OPERATING STEPS
STEP 3 – Leach
• Leaching continues
for a set time
period of 6 – 18
hours
• Oxidant is
continuously dosed
• Oxidant is initially
dosed at a high rate
and then slows
down towards end
of leach
• Drum is running
forwards, pump
circulates solution
BATCH ILR OPERATING STEPS
Cyanide Leaching
Reaction rate dependent on:
• Particle size
• Diffusion of reactants and products
• Cyanide concentration
• This picture shows the
• Oxygen solubility of leachant
diffusion layer created in the
leach process
Cyanide Leaching Aids • Continuous removal of this
layer significantly improves
• Oxidants – Oxygen, Peroxide,
leach kinetics
• Leachwell, Lead Nitrate
BATCH ILR OPERATING STEPS
Laboratory Test
Each concentrate has a unique leach response based on presence and nature
of valuable and non-valuable minerals.
Drum Discharge
BATCH ILR OPERATING STEPS
• Control Cabinet
• PLC
• HMI
• Other components / breakers
OPERATOR INTERFACE
• Electrical Cabinet
• Pump VSD
• Drum VSD
• Other components / breakers
OPERATOR INTERFACE
• Alarms
– All alarms will bring up a banner on the PanelView.
– Shutdown Alarms – ILR switches into manual – drive faults, solution
loss, pump blocked and Low Low pH. Also EW Tank interlocks.
– Audible/Visual alarm will sound for most alarms. Accept All will
silence alarm for 10 minutes.
– Low Air Pressure Alarm will close all valves except XV05 and XV07.
Pump will continue to operate normally.
OPERATOR INTERFACE
• Settings Pages
• From Main Menu – takes you
to Settings Menu
• Settings are divided by type
– Valve timers and type of control
– Level settings for water addition
and drain points
– Cycle timers and options for
Steps
– Alarm settings and activation
METAL ACCOUNTING
– During this time (Feed Cone) NO FEED must enter the Feed Cone
from Knelson / Falcon concentrators.
INSTRUMENT CALIBRATION
• Electrical isolation points are provided for every electrical drive in the
ILR. Use Danger Tags and Locks to LockOut / TagOut.
• All pipes around the ILR can be isolated and drained or flushed with
water. The following procedures are examples of some common or
hazardous tasks. The same principles apply to all maintenance
functions around the ILR.
ISOLATION AND CLEANING
PROCEDURES
Isolation and Wash Down – ILR Pump
• Pump seal uses a high flow expeller and grease packed gland.
• Gland must be greased regularly – daily.
• Gland must be checked and adjusted at least weekly.
• Bearings should be lightly greased weekly (outer grease nipples only).
MECHANICAL MAINTENANCE
ITEMS
• ILR slurry pump – Seal, bearings, wear.
• ILR Drum – tyres, rollers, bearings, alignment, feed seal, internal.
• ILR Drum Drive – chain, gearbox, sprockets.
• Valves – butterfly, knifegate, ball.
• Peroxide pump (or oxygen sparger).
• Flocculant pump.
E & I MAINTENANCE ITEMS
Lifters:
75 mm width
10 mm thick
Diffuser OK
Feed Manifold and Top Seal
• Opening = 16 X 44 mm
Orifice Plate (cont’d)
Recommend:
• Replace orifice with standard unit (25 X 43 mm)
Function:
• Regulate flow of solution recirculating
from solution cone back into the drum
• High flow – disrupt pump PID & faster
passing of fines through drum
• Low flow - blockages
ILR Operations