Fast Food Restaurant PreFeasibility SMEDA
Fast Food Restaurant PreFeasibility SMEDA
Fast Food Restaurant PreFeasibility SMEDA
Pre-Feasibility Study
3rd Floor, Building No. 3, 5TH Floor, Bahria Ground Floor Bungalow No. 15-A
Aiwan-e-Iqbal Complex, Complex II, M.T. Khan Road, State Life Building Chaman Housing Scheme
Egerton Road Lahore, Karachi. The Mall, Peshawar. Airport Road, Quetta.
Tel: (042) 111-111-456 Tel: (021) 111-111-456 Tel: (091) 9213046-47 Tel: (081) 831623, 831702
Fax: (042) 36304926-7 Fax: (021) 5610572 Fax: (091) 286908 Fax: (081) 831922
[email protected] [email protected] [email protected] [email protected]
September 2013
Pre-Feasibility Study Fast Food Restaurant
Table of Contents
1. DISCLAIMER.....................................................................................................1
2. PURPOSE OF THE DOCUMENT......................................................................2
3. INTRODUCTION TO SMEDA............................................................................2
4. INTRODUCTION TO SCHEME .........................................................................3
5. EXECUTIVE SUMMARY ...................................................................................3
6. BRIEF DESCRIPTION OF PROJECT AND PRODUCT ...................................4
7. CRITICAL FACTORS ........................................................................................5
8. INSTALLED AND OPERATIONAL CAPACITIES ............................................5
9. GEOGRAPHICAL POTENTIAL FOR INVESTMENT ........................................5
10. POTENTIAL TARGET MARKETS / CITIES .................................................6
11. PRODUCTION PROCESS FLOW ................................................................7
12. PROJECT COST SUMMARY .......................................................................8
12.1 PROJECT ECONOMICS ............................................................................... 8
12.2 PROJECT FINANCING ................................................................................. 8
12.3 PROJECT COST......................................................................................... 9
12.4 SPACE REQUIREMENT ............................................................................... 9
12.5 MACHINERY AND EQUIPMENT ................................................................... 10
12.6 FURNITURE AND FIXTURES ....................................................................... 11
12.7 RAW MATERIAL REQUIREMENTS ............................................................... 11
12.8 HUMAN RESOURCE REQUIREMENT ........................................................... 12
12.9 REVENUE GENERATION ........................................................................... 12
12.10 OTHER COSTS ........................................................................................ 13
13. CONTACTS - SUPPLIERS, EXPERTS/CONSULTANTS ..........................15
14. ANNEXURE ................................................................................................16
14.1 ANNEXURE 1 - INCOME STATEMENT .......................................................... 16
14.2 ANNEXURE 2 – STATEMENT OF CASH FLOW .............................................. 17
14.3 ANNEXURE 3 – BALANCE SHEET .............................................................. 18
14.4 USEFUL PROJECT MANAGEMENT TIPS ...................................................... 19
14.5 USEFUL LINKS ........................................................................................ 20
15. KEY ASSUMPTIONS .................................................................................22
September 2013
Pre-Feasibility Study Fast Food Restaurant
1. DISCLAIMER
This information memorandum is to introduce the subject matter and provide a
general idea and information on the said matter. Although, the material included
in this document is based on data/information gathered from various reliable
sources; however, it is based upon certain assumptions which may differ from
case to case. The information has been provided on as is where is basis without
any warranties or assertions as to the correctness or soundness thereof.
Although, due care and diligence has been taken to compile this document, the
contained information may vary due to any change in any of the concerned
factors, and the actual results may differ substantially from the presented
information. SMEDA, its employees or agents do not assume any liability for any
financial or other loss resulting from this memorandum in consequence of
undertaking this activity. The contained information does not preclude any further
professional advice. The prospective user of this memorandum is encouraged to
carry out additional diligence and gather any information which is necessary for
making an informed decision including taking professional advice from a qualified
consultant/technical expert before taking any decision to act upon the
information.
For more information on services offered by SMEDA, please contact our website:
www.smeda.org.pk
September 2013
Pre-Feasibility Study Fast Food Restaurant
September 2013
Pre-Feasibility Study Fast Food Restaurant
4. INTRODUCTION TO SCHEME
Prime Minister’s ‘Small Business Loans Scheme’, for young entrepreneurs, with
an allocated budget of Rs. 5.0 Billion for the year 2013-14, is designed to provide
subsidised financing at 8% mark-up per annum for one hundred thousand
(100,000) beneficiaries, through designated financial institutions, initially through
National Bank of Pakistan (NBP) and First Women Bank Ltd. (FWBL).
Small business loans with tenure up to 7 years, and a debt: equity of 90 : 10 will
be disbursed to SME beneficiaries across Pakistan, covering; Punjab, Sindh,
Khyber Pakhtunkhwah, Balochistan, Gilgit Baltistan, Azad Jammu & Kashmir and
Federally Administered Tribal Areas (FATA).
5. EXECUTIVE SUMMARY
The fast food restaurant is proposed to be established at a location that has a
continuous stream of traffic, convenient parking, and is in proximity to other
businesses, preferably near densely populated middle income areas or flat
complexes. Major cities like Karachi, Hyderabad, Sukkur, Larkana, Multan,
Lahore, Gujranwala, Faisalabad, Sialkot, Gujrat, Rawalpindi, Peshawar, Hub and
Quetta etc. are suitable to house the project. Common menu items at the
proposed fast food outlet include sandwiches, burgers, fried chicken, Chinese
soups and Chinese rice variants, French fries, salad and cold drinks.
The fast food would have an installed capacity to serve 335 clients per day;
however the restaurant would initially start business with 140-150 clients. 10
personnel would be required to manage the operations of fast food restaurant.
Total Cost Estimates are Rs. 2,216,365/- with a fixed investment of Rs.
1,894,750/- and an initial working capital requirement of Rs. 321,615/-.
Given the cost assumptions Internal rate of Return (IRR) and payback are 53%
and 2.25 years respectively.
The most critical considerations or factors for success of the project are:
1. Choosing the right location for the fast food outlet
2. Creating the right menu and menu pricing
3. Hiring experienced cooks and staff
4. Knowing the competition
September 2013
Pre-Feasibility Study Fast Food Restaurant
Technology: The proposed setup with used fast food cooking machinery
including fryers, grilling machine, soup containers and pre-processing
equipment would serve popular fast food and Chinese cuisine.
Location: The business is envisaged to be established as a fast food take-
away or satellite outlet with very limited seating capacity on rented premises
or shop of around 500 sqft. near a densely populated area suitable for fast
foods. Major cities like Karachi, Hyderabad, Sukkur, Larkana, Multan, Lahore,
Gujranwala, Faisalabad, Sialkot, Gujrat, Rawalpindi, Peshawar, Hub and
Quetta etc. are suitable to house the project.
Product: Four popular fast food items, including fried chicken, burgers,
sandwiches and Chinese fried rice and soups, have been selected to be
served separately or as combo meals through the outlet. The restaurant is
proposed to have an installed capacity of serving 335 clients per day but is
estimated to start with 140-150 clients per day.
Target Market: The middle income segment of major cities of the country
like Karachi, Hyderabad, Sukkur, Larkana, Multan, Lahore, Gujranwala,
Faisalabad, Sialkot, Gujrat, Rawalpindi, Peshawar, Hub and Quetta etc. is the
target market for the project under consideration.
Employment Generation: The proposed project will provide direct
employment to 10 people. Financial analysis shows the setup shall be
profitable from the very first year of operation.
September 2013
Pre-Feasibility Study Fast Food Restaurant
7. CRITICAL FACTORS
Whether an entrepreneur is opening a one-of-a-kind fast food no-frills restaurant
or trying to expand an existing fast food outlet into a multi-unit chain, there are
winning principles that can improve the chances of success. Some key success
factors are as follows:
Selecting the right location and layout
Hiring employees especially cooks and servers
Quality & Hygiene
Creating the right menu
Menu pricing
Operational consistency
Knowing the competition
September 2013
Pre-Feasibility Study Fast Food Restaurant
September 2013
Pre-Feasibility Study Fast Food Restaurant
People want quick and convenient meals; they do not want to spend a lot of time
preparing meals, traveling to pick up meals, or waiting for meals in restaurants.
As a result, consumers rely on fast food. However the major chunk of fast-food
goers, the middle income segment, prefers visiting outlets that offer fast food at
affordable prices. Fast Food outlets tend to focus on the “work while you eat” or
“shop while you eat” philosophy and fast food restaurants are rapidly becoming
the eatery "everyone can agree on", with many featuring menu combos for
children, play areas and fancy branding campaigns, designed to appeal to
younger customers.
The proposed fast food restaurant/outlet can be established in all major cities of
the country like Karachi, Hyderabad, Sukkur, Larkana, Multan, Lahore,
Gujranwala, Faisalabad, Sialkot, Gujrat, Rawalpindi, Peshawar, Hub and Quetta
etc., where there is traffic of the aforementioned market segment.
The service delivery diagram of the proposed fast food restaurant is as follows.
Meal preparation
Main course
Drive (Grill/Fry meat Take-
through Fry rice & curry away
customer Place order Prepare/heat soup
Order in
queue Assembling
Front desk order
Server
September 2013
Pre-Feasibility Study Fast Food Restaurant
The following table shows internal rates of return and payback period for fast-
food restaurant starting operations with 140-150 clients.
Table 1 - Project Economics
Description Details
Internal Rate of Return (IRR) 53%
Payback Period (yrs) 2 .25 years
Net Present Value (NPV) Rs 6,967,202
Returns on the project and its profitability are highly dependent on the location,
quality of food and service, efficiency of the service team, interest of the owner
manager and competition.
Following table provides details of the equity required and variables related to
bank loan;
Table 2 - Project Financing
Description Details
Total Equity (10%) Rs. 221,637
Bank Loan (90%) Rs. 1,994,728
Markup to the Borrower (%age/annum) 08%
Tenure of the Loan (Years) 07
September 2013
Pre-Feasibility Study Fast Food Restaurant
The land requirement is around 500 sqft. It is recommended that the fast food
outlet be opened on the ground floor of flat complexes or shopping mall or any
other area with high retail consumer traffic. As per the proposed service style, the
floor space needs to be carefully allocated to allow for maximum space for food
preparation and store. The allocation of space between different sections would
be as follows:
The proposed premises would be acquired on a rental basis with 3 month deposit
and 3 months advance rent after which rent will be payable every month. The
monthly rent is estimated at approximately Rs. 85/ Sq. feet amounting to Rs.
42,500 for the proposed fast food outlet (500 Sq Ft.). The premises renovation
September 2013
Pre-Feasibility Study Fast Food Restaurant
costs of Rs. 235,000/- would be depreciated at the rate of 10% per annum using
diminishing balance method.
Fast-food machines are easily available in the market where and entrepreneur
has the choice to select from international brands such as Spinzer, Frymaster,
Henny Penny, Lincoln, Ayrking, Keating, Mirror, Carpigiani, Lincat, Morretti, Ilsa,
Round-Up, Sanyo, Elettrobar etc. Chinese brands have gained popularity over
the years. The machines can be ordered through international vendors with a
minimum delivery period of 3 months while refurbished / reconditioned machines
are also available. There is also an option to procure used machines from closing
outlets but the durability and reliability factor must be taken into consideration
while buying such machines.
The typical fast food restaurant as outlined above would require the following
machine / equipment for its operations:
Table 5: List of Machinery and Equipment
Cost Total
Description Quantity
Rs/unit Rs.
Freezers (12 cf.) 2 40,000 80,000
Broast Machine (15 Pound
1 630,000 630,000
Capacity)*
Deep Well Fryer (Single Valve
1 40,000 40,000
With 2 Baskets)
Hot Plate for Burgers, Kebab,
1 33,000 33,000
Sandwiches (30"x22")
Bin Marry Soup Container (2
1 50,000 50,000
Valve With Steel Cabinet)
Potato Cutter (8mm) 1 3,500 3,500
Peeler (4.5 Kg Potato Peeling
1 7,000 7,000
Capacity)
Microwave 1 10,000 10,000
Generator 1.5 kva 1 75,000 75,000
Keg rack and others 2 10,000 20,000
Total 948,500
10
September 2013
Pre-Feasibility Study Fast Food Restaurant
It is assumed that material inventory for 5-6 days would be kept at the restaurant.
The cost of material required is as under.
Table 7: Cost of Raw Material
11
September 2013
Pre-Feasibility Study Fast Food Restaurant
Considering the size of the proposed establishment it is assumed that the owner
would be managing the overall affairs of the fast food setup. He will be required
to process and check bills, invoices, and cash and also maintain accounts, etc.
The owner will also ensure safe custody of all keys.
It is essential to hire experienced cooks trained in operating fast food machinery
for the project. The proposed project would need a total of 10 persons to handle
the fast food operations. Salaries of all employees are estimated to increase at
the rate of 10% annually.
The Sales are expected to increase by 12% every year. The 12% annual
increase in revenue is expected to result from a part increase in customer traffic
and part increase in product price. The prices used to calculate the gross
revenue earned are based on the billing rate at which the entrepreneur will
charge the customer.
The item-wise estimated revenue at the fast food restaurant is as follows
12
September 2013
Pre-Feasibility Study Fast Food Restaurant
First Year
Sales First Year
Sales
Item Description Unit Price Sales
Revenue
(Rs./Unit) (No.)
(Rs.)
Chicken Broast (Qtr.) No 145 4,320 626,400
Chicken Broast (Half) No 290 2,880 835,200
Chicken Broast (Full) No 550 1,440 792,000
Chicken Burger No 120 4,320 518,400
Chicken Cheese Burger No 140 3,600 504,000
Beef Burger No 100 3,600 360,000
Beef Cheese Burger No 120 3,600 432,000
Zinger Burger No 140 4,320 604,800
Chicken Sandwich No 120 3,600 432,000
Egg Sandwich No 100 1,440 144,000
Beef Sandwich No 110 720 79,200
Club Sandwich No 140 3,600 504,000
Hot & Sour Soup (2 Servings) No 150 1,440 216,000
Hot & Sour Soup (4 Servings) No 280 720 201,600
Chicken Corn Soup (2
Servings) No 150 1,440 216,000
Chicken Corn Soup (4 201,600
Servings) No 280 720
Plain Rice No 100 720 72,000
Chicken Fried Rice No 160 2,880 460,800
Vegetable Fried Rice No 110 1,080 118,800
Egg Fried Rice No 130 720 93,600
Beef Fried Rice No 150 720 108,000
Beef Chili (w/o rice) No 230 1,440 331,200
Chicken Chili (w/o rice) 1,800 450,000
French Fries (per plate) No 50 1,440 72,000
Cole Slaw No 25 1,440 36,000
Soft Drinks (Large) No 80 2,160 172,800
Soft Drinks (Regular 250ml) No 20 74,880 1,497,600
Total Sales Revenue 10,080,000
13
September 2013
Pre-Feasibility Study Fast Food Restaurant
around 1% to 5% of the total cost depending upon the use of the machine
and operator's skill. The maintenance cost for machinery is assumed at 2.5%
of the depreciated cost of machinery and equipment.
Rent and deposits: The proposed premises will be acquired on a rental
basis with 3 month deposit and 3 months advance rent after which rent will
be payable on a monthly basis. The rent is estimated to be Rs. 85/
Sqft/month amounting to Rs. 42,500 per month for the proposed fast food
outlet (500 Sq Ft.). A fixed Gas Security amounting to Rs. 250,000/- for gas
connection (GSD) would have to be deposited with the local utility agency.
Utilities Requirements: The following table presents the estiamted breakup
of utilities on a monthly basis:
Description Monthly
Charges (Rs.)
Electricity 35,000
Gas 22,000
Water 3,000
Telephone 3,000
Total 63,000
14
September 2013
Pre-Feasibility Study Fast Food Restaurant
Director General
National Institute of Food Science and Technology
University of Agriculture, Faisalabad
Phone:041-9200161-70/3011
15
September 2013
Pre-Feasibility Study Fast Food Restaurant
14. ANNEXURE
Revenue 10,080,000 11,289,600 12,644,352 14,161,674 15,861,075 17,764,404 19,896,133 22,283,669 24,957,709 27,952,634
Net Sales 10,080,000 11,289,600 12,644,352 14,161,674 15,861,075 17,764,404 19,896,133 22,283,669 24,957,709 27,952,634
Raw Material Cost 6,110,640 6,843,917 7,665,187 8,585,009 9,615,210 10,769,036 12,061,320 13,508,678 15,129,720 16,945,286
Labor & Salaries 1,548,000 1,702,800 1,873,080 2,060,388 2,266,427 2,493,069 2,742,376 3,016,614 3,318,275 3,650,103
Utilities 756,000 831,600 914,760 1,006,236 1,106,860 1,217,546 1,339,300 1,473,230 1,620,553 1,782,608
Cost of Sales 8,414,640 9,378,317 10,453,027 11,651,633 12,988,497 14,479,651 16,142,996 17,998,522 20,068,548 22,377,997
Gross Profit 1,665,360 1,911,283 2,191,325 2,510,041 2,872,578 3,284,754 3,753,136 4,285,146 4,889,161 5,574,636
Financial Charges (08% Per Annum) 151,573 133,188 113,277 91,713 68,359 43,067 15,676 0 0 0
Earnings Before Taxes 480,971 674,061 892,517 1,140,310 1,421,909 1,747,354 2,112,332 2,514,279 2,956,304 3,462,081
Tax 8,097 27,406 56,378 93,547 135,786 196,971 269,966 351,070 461,576 588,020
Net Profit 472,874 646,655 836,140 1,046,764 1,286,123 1,550,383 1,842,366 2,163,209 2,494,728 2,874,061
Monthly Profit After Tax 39,406 53,888 69,678 87,230 107,177 129,199 153,530 180,267 207,894 239,505
16
September 2013
Pre-Feasibility Study Fast Food Restaurant
Projected Statement of Cash Flows (Rs.) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Net Profit - 472,873.6 646,654.6 836,139.7 1,046,763.5 1,286,122.5 1,550,382.8 1,842,365.5 2,163,209.4 2,494,727.7 2,874,060.5
Add: Depreciation Expense - 136,475.0 122,827.5 110,544.8 99,490.3 89,541.2 80,587.1 72,528.4 65,275.6 58,748.0 52,873.2
Amortization Expense - 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 - - - - -
(Increase) / Decrease in RM Inventory - (10,454) (11,708) (13,113) (14,687) (16,449) (18,423) (20,634) (23,110) (25,883) (28,989)
Net Cash Flow From Operations - 603,895 762,774 938,571 1,136,567 1,364,215 1,612,547 1,894,260 2,205,375 2,527,593 2,897,945
Net Cash Flow From Financing Activities 2,216,365 (221,510) (239,895) (259,806) (281,370) (304,724) (330,016) (357,407) - - -
NET CASH FLOW 234,500 382,385 522,879 678,765 855,197 1,059,491 1,282,531 1,536,853 2,205,375 2,527,593 2,897,945
Cash at the Beginning of the Period - 234,500 616,885 1,139,764 1,818,528 2,673,725 3,733,216 5,015,747 6,552,600 8,757,976 11,285,568
Cash at the End of the Period 234,500 616,885 1,139,764 1,818,528 2,673,725 3,733,216 5,015,747 6,552,600 8,757,976 11,285,568 14,183,513
17
September 2013
Pre-Feasibility Study Fast Food Restaurant
Projected Balance Sheet (Rs.) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Assets
Current Assets
Cash & Bank Balance 234,500 616,885 1,139,764 1,818,528 2,673,725 3,733,216 5,015,747 6,552,600 8,757,976 11,285,568 14,183,513
Raw Material Inventory 87,115 97,568 109,277 122,390 137,076 153,526 171,949 192,583 215,692 241,576 270,565
Prepaid Rent and GSD 505,000 505,000 505,000 505,000 505,000 505,000 505,000 505,000 505,000 505,000 505,000
Total Current Assets 826,615 1,219,453 1,754,040 2,445,918 3,315,802 4,391,742 5,692,696 7,250,183 9,478,668 12,032,144 14,959,077
Fixed Assets
Fast Food Machinery 948,500 853,650 768,285 691,457 622,311 560,080 504,072 453,665 408,298 367,468 330,722
Shop 235,000 211,500 190,350 171,315 154,184 138,765 124,889 112,400 101,160 91,044 81,939
Office Fixtures 181,250 163,125 146,813 132,131 118,918 107,026 96,324 86,691 78,022 70,220 63,198
Total Fixed Assets 1,364,750 1,228,275 1,105,448 994,903 895,412 805,871 725,284 652,756 587,480 528,732 475,859
Total Assets 2,216,365 2,467,728 2,874,488 3,450,821 4,216,214 5,197,613 6,417,980 7,902,939 10,066,148 12,560,876 15,434,936
Owner's Equity 221,636 694,510 1,341,165 2,177,304 3,224,068 4,510,190 6,060,573 7,902,939 10,066,148 12,560,876 15,434,936
Long Term Liability 1,994,728 1,773,218 1,533,323 1,273,517 992,146 687,423 357,407 - - - -
Total Equity & Liabilities 2,216,365 2,467,728 2,874,488 3,450,821 4,216,214 5,197,613 6,417,980 7,902,939 10,066,148 12,560,876 15,434,936
18
September 2013
Pre-Feasibility Study Fast Food Restaurant
Technology
List of Machinery & Equipment
Description Quantity
Freezers (12 cf.) 2
Broast Machine (15 Pound Capacity)* 1
Deep Well Fryer (Single Valve With 2
1
Baskets)
Hot Plate for Burgers, Kebab, Sandwiches
1
(30"x22")
Bin Marry Soup Container (2 Valve With
1
Steel Cabinet)
Potato Cutter (8mm) 1
Peeler (4.5 Kg Potato Peeling Capacity) 1
Microwave 1
Generator 1.5 kva 1
Keg rack and others 2
19
September 2013
Pre-Feasibility Study Fast Food Restaurant
Human Resources
List of Human Resource
Description No. of
Employees
Owner Manager 1
Kitchen Supervisor 1
Cook 3
Servers 3
Dishwasher 1
Cleaner 1
Total Staff 10
20
September 2013
Pre-Feasibility Study Fast Food Restaurant
Government of Pakistan
www.pakistan.gov.pk
Government of Punjab
www.punjab.gov.pk
Government of Sindh
www.sindh.gov.pk
Government of Balochistan
www.balochistan.gov.pk
September 2013
Pre-Feasibility Study Fast Food Restaurant
www.fpcci.com.pk
Particulars Assumption
Sales Increase 12 % per year
Increase in Cost of Raw Materials 12 % per year
Increase in Staff Salaries 10 % per year
Increase in Utilities (Electricity / Water / Gas) 10 % per year
Increase in Rent 10 % per year
Increase in Office Expenses 10 % per year
Debt / Equity Ratio 90 : 10
Depreciation
o Plant Building 10 % per annum (Diminishing Balance)
o Machinery & Equipment 10 % per annum (Diminishing Balance)
o Office Furniture & Equipment 10 % per annum (Diminishing Balance)
Machine Annual Maintenance Cost 2.5% of Written Down Value
Raw Material Inventory 05 days
Loan Period 7 Years
Loan Installments Monthly
Financial Charges (Loan Rate) 08 % per annum
Tax Rate Tax rates for non-salaried individuals
22
September 2013