EirGrid Simulation Requirements
EirGrid Simulation Requirements
Compliance Demonstration
Version 1.0
Page | 1
Simulation Studies and Modelling Requirements for Compliance Demonstration
Disclaimer
EirGrid, the Transmission System Operator (TSO) for Ireland, makes no warranties or representations of
any kind with respect of this document, including, without limitation, its quality, accuracy and
completeness. The TSO does not accept liability for any loss or damage arising from the use of this
document or any reliance on the information it contains. Use of this document and the information it
contains is at the user’s sole risk. In addition, the TSO strongly recommends that any party wishing to
make a decision based on the content of this document should consult the TSO in advance.
Version History
Governance
Any changes to this document made by Eirgrid are to be discussed at the Ireland Grid Code
Review Panel prior to the new release. Similarly, proposed changes from industry should be
raised through the relevant Grid Code channels. Note that changes to this document are not
subject to regulatory approval.
Page | 2
Simulation Studies and Modelling Requirements for Compliance Demonstration
Contents
Contents ..................................................................................................................................................... 3
PART 1. SYNCHRONOUS POWER GENERATING MODULES ................................................................... 8
1.1. General Provisions ...................................................................................................................... 8
1.2. Simulation Model Requirements ................................................................................................ 8
1.2.1. Static Model ........................................................................................................................ 8
1.2.2. RMS Model .......................................................................................................................... 9
1.2.3. Model Submission ............................................................................................................. 10
1.3. Simulation Studies..................................................................................................................... 12
1.3.1. FRT, Active Power Recovery .............................................................................................. 12
1.3.2. LFSM-U and LFSM-O .......................................................................................................... 13
1.3.3. Frequency Sensitive Mode ................................................................................................ 14
1.3.4. Islanded Operation (Load Rejection) ................................................................................. 15
1.3.5. Reactive Power Capability ................................................................................................. 15
1.3.6. Power System Stabiliser / AVR Control ............................................................................. 16
PART 2. POWER PARK MODULES ....................................................................................................... 18
2.1. General Provisions .................................................................................................................... 18
2.2. Simulation model requirements ............................................................................................... 18
2.2.1. Static Model ...................................................................................................................... 18
2.2.2. RMS Model ........................................................................................................................ 19
2.2.3. EMT Model Requirements ................................................................................................ 20
2.2.4. Harmonic Model Requirements ........................................................................................ 20
2.2.5. Model Submission ............................................................................................................. 21
2.3. PPM Simulation Studies ............................................................................................................ 23
2.3.2. LFSM-U and LFSM-O .......................................................................................................... 25
2.3.3. Frequency Sensitive Mode ................................................................................................ 26
2.3.4. Reactive Power Capability ................................................................................................. 27
2.3.5. Islanded Operation (Load Rejection) (Only if requested by EirGrid) ................................. 28
2.3.6. Power System Stabiliser / AVR Control (Not Applicable Presently) ................................... 28
PART 3. DEMAND FACILITIES, DISTRIBUTION FACILITIES and DISTRIBUTION SYSTEMS ...................... 30
3.1. General Provisions .................................................................................................................... 30
3.2. Simulation model requirements ............................................................................................... 30
Page | 3
Simulation Studies and Modelling Requirements for Compliance Demonstration
Page | 4
Simulation Studies and Modelling Requirements for Compliance Demonstration
Introduction
With the advent of the European Network Codes, and their integration into the Ireland Grid Code, it was
felt necessary to collate the requirements around simulations and modelling into one document,
particularly in areas where a more detailed description than that set out in the Grid Code is warranted.
Simulation studies are an integral part of power system design, analysis and operation as they provide
an easy to follow analytical process in establishing various system parameters during for example the
connection of a new facility to the grid. As such, provision of up-to-date and accurate models is an
imperative part of this process.
In general, simulation studies can be utilised to model and analyse power networks’ dynamic behaviour
in terms of voltage and frequency stability as well as other transient phenomena.
The detail and specifics of the model required is normally dictated by the type of study intended to be
used. For generation facilities, this usually implies analysis of behaviour in steady-state and quasi-
steady-state and as such static and RMS models to be used for various studies are required. The
following table provides a summary of the different model requirements for simulation purposes.
For non-synchronous generation, more detailed modelling is required in order to capture detailed
control system behaviour. This is because voltage source technologies can exhibit control instabilities
due to the use of technologies that is system voltage dependent. In addition, control interaction in close
proximity is a distinct possibility and the ability to model and predict these has become paramount.
Electromagnetic transient time domain modelling is the industry norm for such studies and hence
generator models (an in most cases the inverter/converter model) in EMT domain are required.
Power Quality
HF Transients
Short Circuit
Load flow
Transient
Stability
SSCI
Page | 5
Simulation Studies and Modelling Requirements for Compliance Demonstration
Compliance Process
Simulation studies and model provision is part of a larger compliance process that involves other items
as per the check list1 for the connection of a given category.
The process with regards to the provision of simulation studies and model, their check and provisional
acceptance and later update and final acceptance is summarised in the next flow chart.
The process as indicated in the flow chart should be followed by all connections (or modifications)
irrespective of technology.
It is expected that there may be some adjustment of dynamic model parameters between the initial
model submission, and following energisation and validation of the model, once final as-built technical
parameters become known. Users are required to confirm the final model parameters when they
submit model validation reports, as described in PC.A8.6.
1
https://www.eirgridgroup.com/customer-and-industry/general-customer-information/grid-code-compliance-
test/compliance-testing/
Page | 6
Simulation Studies and Modelling Requirements for Compliance Demonstration
models tests
receiving EON receiving ION prior to issuing FON
Update simulation
report comparing
actual tests with
simulations to
provide validation
Customer asked to
Customer asked to
EirGrid Network explain differences
resubmit models/
Data Provided to and inconsistencies
report or answer
Customer or re-submission Yes
Access Planning
queries
Yes required
18 months in advance of
No No
proposed Energisation date
Assess Customer Assess validated
simulation studies Report and simulation studies Reports and
report and usability Models Ok? and any other Models Ok?
of models update
Page | 7
Simulation Studies and Modelling Requirements for Compliance Demonstration
Generating facility shall provide technical data and documentation as part of the simulation
studies compliance procedures (Art 41-3-a and b). All data requirements are detailed in the
Planning Code Appendix of the Grid Code;
Generating facility shall provide an appropriate model as part of the simulation studies
compliance procedures (Art 41-3-c and d). The timeline of the model provision is covered by the
phases of Operational Notification Procedure;
EirGrid shall not accept an alternative set of simulations to those given as part of this
compliance procedure (Art 43-2-a);
EirGrid may require additional or alternative sets of simulations to those given in this procedure
when deemed insufficient to demonstrate compliance (Art 43-2-b);
Generation facility shall provide a report that includes modelling and results of all the simulation
studies detailed in this procedure (Art 41-3-e & Art 43-3);
Generation facility shall provide a validated simulation model as detailed in this procedure (Art
43-3);
EirGrid may perform its own simulation studies based on the simulation model, simulation
reports and compliance test measurements (Art 43-4);
EirGrid shall provide the generation facility owner system data in order to carry out the
simulation studies detailed in this procedure (Art 43-5); and
EirGrid shall not accept provision of equipment certificates submitted as part of demonstrating
compliance with relevant simulation study requirement (Art 52-1, 53-1, 55-1 and 56-2).
Page | 8
Simulation Studies and Modelling Requirements for Compliance Demonstration
providing calculated RMS values of all phases for all types of system faults (balanced and
unbalanced); and
providing control functionality with reference points for the following modes
o reactive power control mode
o voltage control mode including parameters for droop setting
o power factor control mode
For newly built synchronous power generating modules and for those installed but going through a
modification involving any part of the drive train, in addition to the standard RMS model, information
relating to mechanical mass model for each drive train element is also required. Specific information
required are:
inertia constants;
spring and damping constants;
torque shear stress; and
natural oscillation frequencies.
Page | 9
Simulation Studies and Modelling Requirements for Compliance Demonstration
For a generation facility that comprises more than one generator unit, the submitted simulation model
must be such that the characteristics of the generation facility is represented at the point of connection.
Submitted model parameters must contain all data sets for each unit.
The RMS simulation model submitted to EirGrid must be compatible with PSSE 34 and later versions,
and should be in a format that can be readily integrated into other simulation packages, such as
DigSilent PowerFactory, or DSA Tools. Information relating to the mechanical mass model can be
submitted in written data form rather than in a model. No special settings other than standard software
settings should be required for the submitted model to be implemented.
Model validation against test measurements is a requirement and the specific simulation that needs to
be validated are indicated.
The submitted simulation model and studies shall have the following accuracy requirements:
For a linear response over a frequency range of 0.1 to 5Hz, deviations between simulated and
measured waveforms of the control system must be less than 10% for amplitude and less than 5
degrees for the phase angle. Discrete waveform changes (amplitude spikes) on the simulated
waveform should be less than 10% in relation to measured quantity and in the case of where
this level is exceeded due to numerical integration issues, this should be documented in the
report.
For dynamic time domain simulations where non-linear response is included to replicate set
point changes or response to disturbances on the wider network, the following requirements
apply for deviations between simulated and measured response:
Page | 10
Simulation Studies and Modelling Requirements for Compliance Demonstration
o for rapid slopes within 10% for 95% of the samples recorded within a defined event
window2, and time offset of the gradient start or end time must be less than 20
milliseconds;
o for events (e.g. switching) resulting in positive and negative spikes, the amplitude must
be less than 10% from the corresponding measured value for 95% of the samples
recorded;
o oscillation in active power, reactive power, voltage and frequency in the 0.1-5Hz range
must have damping and the deviation in the frequency of oscillation must be less than
10% for 95% of the recorded samples;
o considering possible difference in the voltage at the point of connection, deviation in
active and reactive power response must be less than 10% for 95% of the samples;
o considering possible difference in the final settled value of voltage at the point of
connection, the final value of active and reactive power must settle to within 2% of the
plants rated capacity.
2
An event window is defined as the instant a reference value changes or a disturbance is initiated and lasts until
the response returns to within 5% of the maximum induced or reference quantity change.
Page | 11
Simulation Studies and Modelling Requirements for Compliance Demonstration
Generator Generator
POC System Voltage
Transformer feeder impedance source
Zth
Generator
Auxiliary
transformer ZF Sys tem
and load Fault
Figure 1
System impedance shown in the figure needs to be taken from Minimum System Strength Report.
A summary of the simulation studies for SPGM is given in the following table along with reference to the
EU Network Code (2016/631) simulation requirement and the related EirGrid Grid Code capability
requirement.
Set generator operation to P=Pmax, Q=Qmin (maximum leading reactive power) for the simulations.
Simulate:
phase-to-earth fault;
phase-to-phase fault;
Page | 12
Simulation Studies and Modelling Requirements for Compliance Demonstration
phase-to-phase-to-earth fault;
three-phase fault.
Under each of the above faults, set the faulted phases retained voltage at the POC to the values given
below for the given duration. In each case clear the fault and let steady-state condition be reached
before commencing the next study.
Rotor angle
Excitation Voltage
Success Criteria:
Generator remains synchronised and stable while meeting the capability requirements in CC.7.3.1.1.(y)
Simulate limited frequency response using the model as in Figure 1 with system impedance set to
minimum short circuit level and the generator operated at Limited Frequency Sensitive Mode with a
droop setting set to 4% with active power as indicated in the table and reactive power at zero
Simulate:
Apply the following frequency step and ramps at the given loading. Each setpoint change is only initiated
when steady state conditions are met.
Page | 13
Simulation Studies and Modelling Requirements for Compliance Demonstration
Frequency
Success Criteria:
Generator remains stable while meeting the capability requirements in OC.4.3.4.1.8 and OC.4.3.4.1.9
Simulate frequency sensitive mode using the model as in Figure 1 with system impedance set to
minimum short circuit level and the generator operated in Frequency Sensitive Mode.
Simulate:
Page | 14
Simulation Studies and Modelling Requirements for Compliance Demonstration
Frequency
Success Criteria:
Simulate:
While the generator is at maximum active power output, island the generator from the system by
opening the generator breaker such that it supplies only the house load.
Frequency
Success Criteria:
Generator remains connected and in operation while meeting the capability requirements in
CC.7.3.1.1.w and CC.7.3.1.1.x
Page | 15
Simulation Studies and Modelling Requirements for Compliance Demonstration
Simulate reactive power capability of the generator using the model in Figure 1 with system impedance
set to minimum short circuit level. Generator operating at various points as indicated.
Simulate:
Run load flow studies with the generator at various points on the VQ/Pmax diagram.
Check it can supply maximum leading and lagging reactive power at Pmax at specified voltage levels in
CC.7.3.6.5.
Check it can supply maximum leading and lagging reactive power at Pmin at specified voltage levels in
CC.7.3.6.5.
Success Criteria:
Simulation shows output within the boundaries of the VQ/Pmax diagrams given in CC.7.3.6.5.
Simulation 1:
This simulation is aimed at obtaining the response time of the AVR controls and is named idle response
or open circuit test.
Set generator active and reactive power to zero and apply 10% generator terminal voltage step change
to check excitation system response time.
Success Criteria:
Simulation 2:
Page | 16
Simulation Studies and Modelling Requirements for Compliance Demonstration
Use minimum system fault level impedance as in Figure 1 and set the generator active power to
maximum and reactive power to maximum leading reactive power (i.e. Qmin).
Apply 5% step to reference voltage to check PSS response to voltage disturbances. Repeat test with PSS
on and off.
Apply three-phase short-circuit at generator transformer HV side. Repeat it with PSS on and off.
Active power
Reactive power
Excitation voltage
Success Criteria:
Improved attenuation of system power fluctuation when PSS is on compared to when PSS is off.
Simulation 3:
This simulation is aimed at obtaining frequency response of the SPGM Excitation System in the form of
Bode diagrams (both gain and phase) in order to have an insight into possible stability margins. Two
separate frequency responses are expected:
Gain and phase Bode plot for open loop frequency response with PSS on and off.
Gain Bode plot for closed loop on load frequency response with PSS on and off. Generator is operating
at Pmax and unity pf.
Success Criteria:
Improved contribution with PSS operation with respect to the gain and phase margin of Excitation
System during open loop frequency response.
Improved active power damping with PSS during closed loop frequency response.
Page | 17
Simulation Studies and Modelling Requirements for Compliance Demonstration
Generating facility shall provide technical data and documentation as part of the simulation
studies compliance procedures (Art 41-3-a and b). All data requirements are detailed in the
Planning Code Appendix of the Grid Code;
Generating facility shall provide an appropriate model as part of the simulation studies
compliance procedures (Art 41-3-c and d). The timeline of the model provision is covered by the
phases of Operational Notification Procedure;
EirGrid shall not accept an alternative set of simulations to those given as part of this
compliance procedure (Art 43-2-a);
EirGrid may require additional or alternative sets of simulations to those given in this procedure
when deemed insufficient to demonstrate compliance (Art 43-2-b);
Generation facility shall provide a report that includes modelling and results of all the simulation
studies detailed in this procedure (Art 41-3-e & Art 43-3);
Generation facility shall provide a validated simulation model as detailed in this procedure (Art
43-3);
EirGrid may perform its own simulation studies based on the simulation model, simulation
reports and compliance test measurements (Art 43-4);
EirGrid shall provide the generation facility owner system data in order to carry out the
simulation studies detailed in this procedure (Art 43-5); and
EirGrid shall not accept provision of equipment certificates submitted as part of demonstrating
compliance with relevant simulation study requirement (Art 52-1, 53-1, 55-1 and 56-2).
Page | 18
Simulation Studies and Modelling Requirements for Compliance Demonstration
providing calculated RMS values of all phases for all types of system faults (balanced and
unbalanced),
providing control functionality with reference points
o reactive power control mode
o voltage control mode including parameters for droop setting
o power factor control mode
If an aggregated model instead of individual units is used, then the aggregated model must be able to
represent the characteristics of the whole facility at the point of connection. Descriptive information on
the aggregation approach and assumptions should be provided.
Page | 19
Simulation Studies and Modelling Requirements for Compliance Demonstration
The model should not contain any compiled parts in order to be embedded within a larger network
model without any restrictions.
The EMT model should be capable of recreating all the requirements of the static and RMS models and
in addition shall:
Represent all components, control and protection systems relevant for time domain analysis
Initialise at a fraction of the simulation time. Conditions under which the model can be assumed
initialised shall be documented.
Give the user the ability to set various activation schemes within the model (for example
activation of protection functions or apparent power dispatch)
Allow the user to set all parameters relevant to the analysis
Be repeatable, i.e. can be used multiple times within the same model without numerical issues
Be able to capture high frequency transients
Be capable of representing possible signal delays between various elements (for example park
controller to individual wind turbine generators)
• Include any relevant non-linearities, deadbands, saturation, limits or mathematical functions.
• Primarily be based on the use of standard components that are within the given software
environment
• In the case of compiled or encrypted part, not create any complications or incompatibility with
respect to its integration to a wider network model.
• Be capable of being used in later versions of the given software.
• Representing integer harmonic emissions at a single unit level from 2nd to 50th harmonic.
• Being defined either as Thevenin or Norton equivalent
• Passive response of the units (lumped impedance) within 50-2500 Hz range at a resolution of
1 Hz for all sequence networks.
• Specify a summation process from multiple units either using correct phase angles for injections
or utilising a summation law
• Dependency on the power park generating facilities level of generation or operating point –
model valid for at least three different operating regimes (minimum, average and maximum)
shall be submitted
• Details of power park generating facility infrastructure equipment such as cables, transformers,
shunt compensation etc as frequency dependent components.
Page | 20
Simulation Studies and Modelling Requirements for Compliance Demonstration
If the power park generating facility has more than one unit, an aggregated harmonic simulation model
can be submitted instead. The aggregated model shall be such that it represents the total emissions and
include the total passive harmonic impedance at the point of connection within the 5-2500 Hz frequency
range may be used.
instruction of integrating the provided model into a wider network model so as to be used as
part of wider system studies.
guidance on the interpretation of error messages and troubleshooting.
a comprehensive list of parameters, default and range of values applicable, block diagrams and
transfer functions.
model single line diagram showing main electrical components and connectivity to the network
interface point.
description of each individual model components and their related parameters,
description of initialisation of the model for simulations,
Laplace domain transfer functions, sequence diagrams and any arithmetic or logical sequence
modules within the model description
saturation, dead bands, non-linearity, time delays, any interpolation assumptions and any look-
up tables utilised within the parameters utilised
description of the electrical input and output signals, explanation on the measurement point
used, signal units and base values.
explanation on any restrictions on its use, limits applicable such as the maximum integration
step size, and accuracy of the model.
list of protection functionality that can be triggered by external events
diagrams of control system and any other equipment implemented within the control system in
the form of standardised block diagrams
information on applicable software version, compiler version if any and simulation model
unique version control.
For a power park that comprises more than one generator unit, the submitted simulation model must
be such that the characteristics of the power park is represented at the point of connection. Submitted
model parameters must contain all data sets for each unit.
The static and RMS simulation models submitted to EirGrid must be implemented in (or compatible
with) PSSE34 and later versions. No special settings other than standard software setting should be
required for the submitted model to be implemented.
The EMT model must be developed and delivered in PSCAD version 4.6.3 or later.
Page | 21
Simulation Studies and Modelling Requirements for Compliance Demonstration
RMS and EMT models require verification and validation which shall be included in the submitted
simulation report. The EMT model must be validated for simulations at different simulation time steps
and should also include comparison of the static and RMS dynamic model response. Model validation
against test measurements is a requirement and the specific simulation that needs to be validated
against actual tests are indicated above.
In general accuracy requirement for PPM models and simulation follow a similar line to SPGM as in the
previous section and repeated below. For EMT model and simulation accuracy, identical approach to
RMS is used. However, the comparison is evaluated using RMS quantities with an appropriate filtering
for power frequency component of measured and simulated parameters. The method of filtering must
be agreed between EirGrid and the facility owner prior to any measurements and simulations.
The submitted simulation model and studies shall have the following accuracy requirements:
For a linear response over a frequency range of 0.1 to 5Hz, deviations between simulated and
measured waveforms of the control system must be less than 10% for amplitude and less than 5
degrees for the phase angle. Discrete waveform changes (amplitude spikes) on the simulated
waveform should be less than 10% in relation to measured quantity and in the case of where
this level is exceeded due to numerical integration issues, this should be documented in the
report.
For dynamic time domain simulations where non-linear response is included to replicate set
point changes or response to disturbances on the wider network, the following requirements
apply for deviations between simulated and measured response:
o for rapid slopes within 10% for 95% of the samples recorded within a defined event
window3, and time offset of the gradient start or end time must be less than 20
milliseconds;
o for events (e.g. switching) resulting in positive and negative spikes, the amplitude must
be less than 10% from the corresponding measured value for 95% of the samples
recorded;
o oscillation in active power, reactive power, voltage and frequency in the 0.1-5Hz range
must have damping and the deviation in the frequency of oscillation must be less than
10% for 95% of the recorded samples;
o considering possible difference in the voltage at the point of connection, deviation in
active and reactive power response must be less than 10% for 95% of the samples;
o considering possible difference in the final settled value of voltage at the point of
connection, the final value of active and reactive power must settle to within 2% of the
plants rated capacity.
3
An event window is defined as the instant a reference value changes or a disturbance is initiated and lasts until
the response returns to within 5% of the maximum induced or reference quantity change.
Page | 22
Simulation Studies and Modelling Requirements for Compliance Demonstration
Generator Generator
POC System Voltage
Transformer feeder impedance source
Zth
Generator
Auxiliary
transformer ZF Sys tem
and load Fault
Figure 2
System impedance shown in the figure needs to be taken from Minimum System Strength Report.
A summary of the simulation studies for PPM is given in the following table along with reference to the
EU Network Code (2016/631) simulation requirement and the related EirGrid Grid Code capability
requirement.
Note: Please refer to the notes in Appendix A with respect to the interpretation of PPM1.4.2(c).
Page | 23
Simulation Studies and Modelling Requirements for Compliance Demonstration
phase-to-earth fault;
phase-to-phase fault;
phase-to-phase-to-earth fault;
three-phase fault.
Under each of the above faults, set the faulted phases retained voltage at the POC to the values given
below for the given duration. In each case clear the fault and let steady-state condition to be reached
before commencing the next study.
Success Criteria:
(i) Generator remains connected and stable while meeting the capability requirements in
PPM1.4.2.f
(ii) Show compliance against GC PPM1.4.2.a, PPM1.4.2.b and PPM1.4.2.c Note that Rise Time
and Settling will be checked in Simulation 2 below.
Apply a three-phase fault leading to a voltage step-change to 0.5 pu retained voltage at the POC.
Success Criteria:
Page | 24
Simulation Studies and Modelling Requirements for Compliance Demonstration
Show compliance against PPM1.4.2.c Rise Time and Settling Time criteria.
Simulate Limited Frequency Sensitive Mode response using the model in Figure 2 with system
impedance set to minimum short circuit level. The generator should be operated at LFSM with an active
power P as indicated in the curve shown below and reactive power set to zero.
Simulate:
Apply Curve 1 Resource Following Mode as shown in the next figure and table. Each setpoint change is
only initiated when steady state conditions are met.
Controllable WFPS Active Power Output
100
as a % of Available Active Power
% Reserve (Curve 2)
`
DMOL
0 FA FB FC FD FE
50
Frequency (Hz)
Page | 25
Simulation Studies and Modelling Requirements for Compliance Demonstration
Frequency
Success Criteria:
Generator remains stable while meeting the capability requirements in PPM1.5.3.11 and PPM1.5.3.12
Simulate Frequency Sensitive Mode response using the model in Figure 2 with system impedance set to
minimum short circuit level. The generator should be operated at FSM with an active power P as
indicated in the curve shown below and reactive power set to zero
Simulate:
Apply the Curve 1 Active Power Control Mode as shown in the next figure and table. Each setpoint
change is only initiated when steady state conditions are met.
Frequency f
(Hz)
100% AAP (Curve 1)
% Reserve (Curve 2)
`
DMOL
0 FA FB FC FD FE
50
Frequency (Hz)
Page | 26
Simulation Studies and Modelling Requirements for Compliance Demonstration
Frequency
Success Criteria:
Demonstrate reactive power capability using the model in Figure 2 with system impedance set to
minimum short circuit level and the generator operating at various points.
Simulate:
Run load flow studies with the generator at various points on the VQ/Pmax diagram.
Check it can supply maximum leading and lagging reactive power at Pmax at specified voltage levels in
PPM1.6.3.4.
Check it can supply maximum leading and lagging reactive power at Pmin at specified voltage levels in
PPM1.6.3.4.
Page | 27
Simulation Studies and Modelling Requirements for Compliance Demonstration
Success Criteria:
Simulation shows output within the boundaries of the VQ/Pmax diagrams given in PPM1.6.3.4.
Simulate:
While the generator is at maximum active power output, island the generator from the system by
opening the breaker connecting the power park to the system such that it supplies only the auxiliary and
any local load.
Frequency
Success Criteria:
Generator remains connected and in operation while meeting the capability requirements in
CC.7.3.1.1.w and CC.7.3.1.1.x
Simulate:
Page | 28
Simulation Studies and Modelling Requirements for Compliance Demonstration
Apply 5% step to reference voltage to check PSS response to voltage disturbances. Repeat test with PSS
on and off.
Apply an appropriate three-phase short-circuit at grid connection point, with PSS on and off, in order to
show improvement with PSS on.
Active power
Reactive power
Excitation voltage
Success Criteria:
Improved attenuation of system power fluctuation when PSS is on compared to when PSS is off.
Page | 29
Simulation Studies and Modelling Requirements for Compliance Demonstration
Page | 30
Simulation Studies and Modelling Requirements for Compliance Demonstration
Composition of load in terms of type (induction motor load, power electronic converter-based
load etc)
Installed embedded generation capacity
Reactive power data both from discrete components such as shunt reactors/capacitors and also
from those generated by equipment such as cables.
covering a range of frequencies (47 to 52 Hz) and voltages (0 to 1.4 pu),
representing the static and dynamic properties of the transmission-connected demand facility
or transmission connected distribution system
covering a range of frequencies (47 to 52 Hz) and voltages (0 to 1.4 pu)
representing the characteristics of the demand facility’s operating ranges for active and reactive
power,
providing calculated RMS values for all types of system faults (balanced and unbalanced),
representing the voltage dependency (overvoltage and undervoltage) of the facility
representing the frequency dependency of the facility
activating any internal protection functionality in the event of external network faults,
including any control functionality (such as tap changers or blocking functionality)
utilising any internal reclosing or swapping functionality (for example local demand to UPS)
providing a numerically stable simulation for a minimum of 60 seconds following any system
incidents/faults
initialising in a stable operating point
running under with a variable time step in the range of 1 to 10 ms
not requiring any special settings to be implemented into a larger network model
simulating the dynamic behaviour of the demand facility under system faults, voltage
disturbances and frequency disturbances
If an aggregated model instead of individual units is used, then the aggregated model must be able to
represent the characteristics of the whole facility at the point of connection. Descriptive information on
the aggregation approach and assumptions should be provided.
The model should not contain any compiled parts in order to be embedded within a larger network
model without any restrictions. We suggest using a standard library model if possible.
Page | 31
Simulation Studies and Modelling Requirements for Compliance Demonstration
• Representing integer harmonic emissions if any either as aggregate or at individual unit level
• Emissions being defined either as Thevenin or Norton equivalent
• Passive response of the facility (lumped impedance) within 50-2500 Hz range at a resolution of
1 Hz for all sequence networks.
• Specify a summation process from multiple units either using correct phase angles for injections
or utilising a summation law
An aggregated model representative of the demand facility’s total emissions, instead of multiple units
can be submitted. The aggregated model must be able to represent the characteristics of the whole
facility at the point of connection such that it represents the total emissions and include the total
passive harmonic impedance at the point of connection within the 5-2500 Hz frequency range.
Descriptive information on the aggregation approach and assumptions should be provided.
instruction on integrating the provided model into a wider network model so as to be used as
part of wider system studies.
guidance on the interpretation of error messages and troubleshooting.
a comprehensive list of parameters, default and range of values applicable, block diagrams and
transfer functions.
model single line diagram showing main electrical components and connectivity to the network
interface point.
description of each individual model components and their related parameters,
description of initialisation of the model for simulations,
Laplace domain transfer functions, sequence diagrams and any arithmetic or logical sequence
modules within the model description
saturation, dead bands, non-linearity, time delays, any interpolation assumptions and any look-
up tables utilised within the parameters utilised
description of the electrical input and output signals, explanation on the measurement point
used, signal units and base values.
explanation on any restrictions on its use, limits applicable such as the maximum integration
step size, and accuracy of the model.
list of protection functionality that can be triggered by external events
diagrams of control system and any other equipment implemented within the control system in
the form of standardised block diagrams
information on applicable software version and simulation model unique version control.
Page | 32
Simulation Studies and Modelling Requirements for Compliance Demonstration
The static and RMS simulation models submitted to EirGrid must be implemented in or compatible with
PSSE 34 and subsequent versions. No special settings other than standard software setting should be
required for the submitted model to be implemented.
RMS models require verification and validation which shall be included in the submitted simulation
report.
Accuracy requirement for PPM models and simulation follow a similar line to SPGM as in the previous
section and repeated below.
The submitted simulation model and studies shall have the following accuracy requirements:
For a linear response over a frequency range of 0.1 to 5Hz, deviations between simulated and
measured waveforms of the control system must be less than 10% for amplitude and less than 5
degrees for the phase angle. Discrete waveform changes (amplitude spikes) on the simulated
waveform should be less than 10% in relation to measured quantity and in the case of where
this level is exceeded due to numerical integration issues, this should be documented in the
report.
For dynamic time domain simulations where non-linear response is included to replicate set
point changes or response to disturbances on the wider network, the following requirements
apply for deviations between simulated and measured response:
o for rapid slopes within 10% for 95% of the samples recorded within a defined event
window4, and time offset of the gradient start or end time must be less than 20
milliseconds;
o for events (e.g. switching) resulting in positive and negative spikes, the amplitude must
be less than 10% from the corresponding measured value for 95% of the samples
recorded;
o oscillation in active power, reactive power, voltage and frequency in the 0.1-5Hz range
must have damping and the deviation in the frequency of oscillation must be less than
10% for 95% of the recorded samples;
o considering possible difference in the voltage at the point of connection, deviation in
active and reactive power response must be less than 10% for 95% of the samples;
o considering possible difference in the final settled value of voltage at the point of
connection, the final value of active and reactive power must settle to within 2% of the
plants rated capacity.
4
An event window is defined as the instant a reference value changes or a disturbance is initiated and lasts until
the response returns to within 5% of the maximum induced or reference quantity change.
Page | 33
Simulation Studies and Modelling Requirements for Compliance Demonstration
Simulate:
Run load flow studies with the demand facility or distribution system at various load and generation
conditions including minimum and maximum and simulate the lowest and highest reactive power
exchange.
Run load flow study to check the level of reactive power export while the facility or distribution system
is importing less than 25% of the maximum import capability.
Check that reactive power exchange is within the capability requirements specified in CC.7.4.2.4.
Success Criteria:
Simulate:
In an RMS dynamic simulation to mimic a low frequency event apply a frequency step and/or ramps
relative to the contractual agreement in place. There should be a contractually defined change of active
power related to a measure of rate-of-change-of-frequency and a response time for the very fact active
power control that should be less than 2 seconds.
Frequency
Page | 34
Simulation Studies and Modelling Requirements for Compliance Demonstration
Success Criteria:
Facility remains within the technical capability specified in the contractual agreement.
Page | 35
Simulation Studies and Modelling Requirements for Compliance Demonstration
PLEASE NOTE: PART 4 IS DRAFT AND NOT YET APPROVED, BUT IS INCLUDED FOR
COMPLETENESS.
EirGrid shall not accept an alternative set of simulations to those given as part of this
compliance procedure (Art 68-2-a)
EirGrid may require additional or alternative sets of simulations to those given in this procedure
when deemed insufficient to demonstrate compliance (Art 68-2-b)
HVDC system owner or DC-connected power park module owner shall provide a validated
simulation model as detailed in this procedure (Art 68-3)
HVDC system owner or DC-connected power park module owner shall provide a report that
includes modelling and results of all the simulation studies detailed in this procedure (Art 68-3)
EirGrid may perform its own simulation studies based on the provided simulation models,
simulation reports and compliance test measurements (Art 68-4)
EirGrid shall provide the HVDC system owner or DC-connected power park module owner
system data in order to carry out the simulation studies detailed in this procedure (Art 68-5)
EirGrid shall not (or shall) accept provision of equipment certificates submitted as part of
demonstrating compliance with relevant simulation study requirement (Art 73-1)
Page | 36
Simulation Studies and Modelling Requirements for Compliance Demonstration
Include the characteristics of the HVDC system’s operating ranges for active and reactive power
Function for a range of frequencies (47 to 52 Hz) and voltages (0 to 1.4 pu)
Include input/output signals which include as a minimum the following:
o Active power
o Reactive power
o Frequency control
o Runback
o Control functionality
active power
reactive power
power factor control
voltage control (with droop setting capability)
frequency control (with deadband)
protection activation
o Emergency power control (both active and reactive)
o Power Oscillation Damping (POD)
o Blackstart
o External component control (e.g. STATCOM or battery)
Be capable of activating an internal protection functionality in the event of external network
faults.
Be capable of simulating the dynamic behaviour of the HVDC system under system faults,
voltage disturbances and frequency disturbances
Provide calculated RMS values of all phases for all types of system faults (balanced and
unbalanced).
Be able to represent the HVDC plant's FRT characteristics.
Be able to operate with a variable time step for numerical integration running in the range of 1
to 10ms.
Initialise to a stable operating point and be numerically stable at instantaneous phase angle
jumps of up to 20 degrees.
Page | 37
Simulation Studies and Modelling Requirements for Compliance Demonstration
Be able to run in a stable manner for up to 100 seconds following any setpoint changes or
events on the system
Not require any special settings to be implemented into a larger network model
Not contain any encrypted or compiled parts
Include any special functionality provided by the actual HVDC system, such as control scheme
for weak grids.
In addition to the static and RMS model, an EMT model for the HVDC system shall be submitted to
EirGrid to be used in electromagnetic time domain studies.
The EMT model should be capable of recreating all the requirements of the static and RMS models and
in addition shall:
• Include implementation of network components and other assets including control systems and
protective devices that are part of the infrastructure to a level of detail valid for the EMT-
studies.
• Include component models especially with respect to power electronics at individual switching
device level.
• Include user adjustable simulation time for activation of protection functions
• Include user adjustable simulation time for apparent power dispatch
• Primarily be based on the use of standard components that are within the given software
environment
• In the case of compiled or encrypted part, not create any complications or incompatibility with
respect to its integration to a wider network model.
• Be capable of using it in later versions of the given software.
• Be suitable for use under black start and islanded operation
• Initialise at a fraction of the simulation time. Conditions under which the model can be assumed
initialised shall be documented.
Page | 38
Simulation Studies and Modelling Requirements for Compliance Demonstration
The static and RMS simulation models submitted to EirGrid must be implemented in or compatible with
PSSE 34. No special settings other than standard software setting should be required for the submitted
model to be implemented.
The EMT model must be developed and delivered in PSCAD version 4.6.3.
RMS and EMT models require verification and validation which shall be included in the submitted
simulation report. The EMT model must be validated for simulations at different simulation time steps
and should also include comparison of the static and RMS dynamic model response. Model validation
Page | 39
Simulation Studies and Modelling Requirements for Compliance Demonstration
against test measurements is a requirement and the specific simulation that needs to be validated
against actual tests are indicated.
Accuracy requirement for HVDC models and simulation follow a similar line to other technologies as in
the previous sections and repeated below. For EMT model and simulation accuracy, identical approach
to RMS is used. However, the comparison is evaluated using RMS quantities with an appropriate filtering
for power frequency component of measured and simulated parameters. The method of filtering must
be agreed between EirGrid and the facility owner prior to any measurements and simulations.
The submitted simulation model and studies shall have the following accuracy requirements:
For a linear response over a frequency range of 0.1 to 5Hz, deviations between simulated and
measured waveforms of the control system must be less than 10% for amplitude and less than 5
degrees for the phase angle. Discrete waveform changes (amplitude spikes) on the simulated
waveform should be less than 10% in relation to measured quantity and in the case of where
this level is exceeded due to numerical integration issues, this should be documented in the
report.
For dynamic time domain simulations where non-linear response is included to replicate set
point changes or response to disturbances on the wider network, the following requirements
apply for deviations between simulated and measured response:
o for rapid slopes within 10% for 95% of the samples recorded within a defined event
window5, and time offset of the gradient start or end time must be less than 20
milliseconds;
o for events (e.g. switching) resulting in positive and negative spikes, the amplitude must
be less than 10% from the corresponding measured value for 95% of the samples
recorded;
o oscillation in active power, reactive power, voltage and frequency in the 0.1-5Hz range
must have damping and the deviation in the frequency of oscillation must be less than
10% for 95% of the recorded samples;
o considering possible difference in the voltage at the point of connection, deviation in
active and reactive power response must be less than 10% for 95% of the samples;
o considering possible difference in the final settled value of voltage at the point of
connection, the final value of active and reactive power must settle to within 2% of the
plants rated capacity.
5
An event window is defined as the instant a reference value changes or a disturbance is initiated and lasts until
the response returns to within 5% of the maximum induced or reference quantity change.
Page | 40
Simulation Studies and Modelling Requirements for Compliance Demonstration
DC connected Power Park Modules and remote-end HVDC converter stations are also subject to
simulation studies and these are given in the following table. Studies associated with DC connected
PPMs should in principle follow a similar line to any other controllable PPM and the remote-end HVDC
converter station simulation study should follow the study line for HVDC converter station.
Capability Area EU – NC (2016/1447) EirGrid GC Capability Validate against test
Fast Fault Current (DC PPM) Art 74(2) PPM1.4.2.c
Active Power Recovery (DC Art 74(3) PPM1.4.2.b
PPM)
Reactive Capability (DC Art 74(4) PPM1.6.3.5 Yes
PPM)
Reactive Capability (remote Art 74(5) CC.7.5.10.(f) Yes
end HVDC)
Power Oscillation Damping Art 74(6) N/A
(DC PPM)
Fault Ride Through (DC Art 74(7) PPM1.4.2.f
PPM)
Page | 41
Simulation Studies and Modelling Requirements for Compliance Demonstration
Simulate:
phase-to-earth fault;
phase-to-phase fault;
phase-to-phase-to-earth fault;
three-phase fault.
Under each of the above faults, set the faulted phases retained voltage at the POC to the values given
below for the given duration. In each case clear the fault and let steady-state condition to be reached
before commencing the next study.
Success Criteria:
HVDC system remains connected and stable while meeting the capability requirements in xyz [GC clause
that specifies the voltage against time profile – CC.7.5.12.1 but may change!]
Active power at HVDC station terminals grid side of the converter station transformer and POC
Page | 42
Simulation Studies and Modelling Requirements for Compliance Demonstration
Reactive power at HVDC station terminals grid side of the converter station transformer POC
Success Criteria:
HVDC system provides fault current within the rating of the interconnector converter station with a rise
time and settling times as specified in GC CC.7.5.12.4.
Simulate:
Apply a fault and clear within 500 ms (all four fault types).
Apply a fault and clear at a time longer than 500 ms (all fault types).
Success Criteria:
Show compliance against GC active power recovery requirements in xyz [current proposals indicate
CC.7.5.12.6 but may change!]
Simulate reactive power capability of the HVDC installation using the model in Figure 1 with system
impedance set to minimum short circuit level. HVDC converter station operating at various points as
indicated.
Simulate:
Page | 43
Simulation Studies and Modelling Requirements for Compliance Demonstration
Run load flow studies with the HVDC system at various points on the VQ/Pmax diagram given in Grid
Code CC.7.5.10.(d).
Check that the HVDC system can supply maximum leading and lagging reactive power at Pmax at
specified voltage levels in CC.7.5.1.1.(v) [voltage levels will be those that come due to the requirements
of Art 18 from the EU code – they are given in Annex III].
Check that the HVDC system can supply maximum leading and lagging reactive power at Pmin at
specified voltage levels in CC.7.5.1.1.(v) [voltage levels will be those that come due to the requirements
of Art 18 from the EU code – they are given in Annex III].
Check that the HVDC system operating point can move and operate anywhere within the VQ/Pmax
diagram when operating at P<Pmax.
Success Criteria:
Simulation shows output within the boundaries of the VQ/Pmax diagrams given in GC CC.7.5.10.(d).
Simulate:
Apply system fault leading to oscillations of electromechanical nature. The time domain simulations
should be of sufficient duration in order to identify stabilization (this is particularly the case for
oscillations involving frequency variations) – around 60 to 100 seconds.
Time domain studies shall be supported with additional eigenvalue studies in order to demonstrate the
oscillation modes and damping performance with and without the POD controller in operation.
Page | 44
Simulation Studies and Modelling Requirements for Compliance Demonstration
An additional time domain simulation is to introduce a change of active power transfer of the HVDC
system (level is project specific and should be agreed with EirGrid).
Voltage, frequency, speed, active power flow as applicable at the point (busbar, generator terminals etc)
required to demonstrate oscillation mode (local, inter-area etc) and the poorly damped oscillation itself.
Eigenvalues, eigenvectors and the frequency of oscillation with damping values and a classification on
whether these are well damped, damped, poorly damped or unstable (especially with regards to POD
being in operation or not). Unstable oscillation with the POD in operation will require appropriate tuning
of the control system and this shall be agreed between EirGrid and the HVDC system owner.
Check active and reactive power and terminal voltage of the HVDC system during the change of active
power simulation.
Success Criteria:
POD function of the HVDC system damps oscillations of the HVDC system (local mode) and/or damps or
does not make worse identified network oscillations (inter-area or global).
Change of active power transfer does not lead to undamped oscillations in active or reactive power of
the HVDC system.
Simulate:
Introduce 10% step change in active power during steady state operation for the following cases:
P=Pmax exporting with export station (connected to EirGrid system if it is providing a connection to a
different system) providing DC and AC voltage control and the remote end providing active and reactive
power control
P=Pmax importing with import station (connected to EirGrid system if it is providing a connection to a
different system) providing active power and AC voltage control and the remote end providing DC
voltage control and reactive power control
Repeat the same simulations under different pulse width modulation if that is within the HVDC system
functionality.
Page | 45
Simulation Studies and Modelling Requirements for Compliance Demonstration
Success Criteria:
Change in active power within given timeframe as defined by EirGrid on site-specific basis as per Gc
CC.7.5.8.5.
Use a model to represent the system such that it covers the topology leading to the conditions
necessitating the provision of fast active power reversal.
HVDC system operating at appropriate import or export configuration leading to the requirement of fast
active power reversal.
Simulate:
Apply system fault leading to transient instability (for example this could be a critical fault clearance
time issue) with appropriate signals to the HVDC system.
Other signals as appropriate (for example if it is associated with the critical clearance time of a
generator, rotor angle plot of the generator can be presented).
Success Criteria:
HVDC system remains connected and stable while meeting the capability requirements in CC.7.5.1.1.(k).
[GC clause that specifies the fast active power reversal Art 13-1-c within the specified time limit]
Page | 46
Simulation Studies and Modelling Requirements for Compliance Demonstration
When several HVDC converter stations or other plants and equipment are within close electrical
proximity, adverse control interactions may occur. EirGrid may request that a study is performed to
demonstrate that no adverse interaction will occur. If adverse interactions are identified, the studies
shall identify possible mitigating actions to be implemented to ensure compliance with the
requirements of the Grid Code.
The responsibility of these studies rests with the connecting HVDC system owner. All parties relevant to
the connection point as identified by EirGrid shall provide relevant data and models as reasonably
required to meet the scope of the studies.
The result of the studies shall be assessed by EirGrid and if deemed necessary, additional studies in line
with the scope may be requested.
All relevant data and models as part of the interaction study shall be provided to EirGrid such that the
studies can be replicated if required.
Any mitigation actions identified by the studies shall be carried out by the HVDC system owner as part of
the connection compliance process.
4.3.8. Sub-synchronous torsional interaction studies (Art 31 not within simulation study
part)
It is required that HVDC system shall not cause subsynchronous torsional interaction and that shall be
capable of contributing to electrical damping of torsional frequencies.
Simulation studies confirming the damping characteristics of the HVDC system with regards to SSTI shall
be submitted by the HVDC system owner. All parties relevant to the connection point as identified by
EirGrid shall provide relevant data and models as reasonably required to meet the scope of the studies.
The result of the studies shall be assessed by EirGrid and if deemed necessary, additional studies in line
with the scope may be requested.
All relevant data and models as part of the interaction study shall be provided to EirGrid such that the
studies can be replicated if required.
Any mitigation actions identified by the studies shall be carried out by the HVDC system owner as part of
the connection compliance process.
Page | 47
Simulation Studies and Modelling Requirements for Compliance Demonstration
High-Level Principles:
1. PPMs such as windfarms and solar farms generally operate in two distinct modes – normal
operation, and fault-ride through mode. In normal operation, the TSO is chiefly concerned with the
PPMs behaviour and characteristics at the HV connection point, such as P-Q capability, voltage
control modes, ramping behaviour, and frequency response. During faults, the behaviour of the
PPM is typically delegated to the individual PPM units, such as individual wind turbines or solar
modules. However the TSO does not have visibility down to the individual module level at present,
and so performance monitoring of PPMs is done at the connection point. From a simulation and
model compliance viewpoint, performance assessment should take into account behaviour at this
lower voltage level as well as at the connection point in order to capture the effects of depressed
voltages on cables and transformers and obtain a more holistic view of the PPM FRT response.
2. While PPMs are expected to ride through a variety of different fault types and durations, very short
faults (less than or equal to 150ms) can be difficult to assess, as a steady-state may not be reached
within such a short time frame. Accordingly, very short faults will be assessed to confirm overall
stability and direction of response, but not in a strictly quantitative way.
3. The Grid Code PPM1.4.2(c) states that the reactive current shall be supplied within the rating of the
PPM. By extension, this means that the maximum expected current at the connection point should
not exceed the current at full power output and 0.95 power factor. Similarly, at the PPM module
level, the current from an individual module is not expected to exceed the value when operating at
maximum power output and 0.95 power factor at the connection point. We note that the DS3
System Service products incentivise performance in excess of the Grid Code requirements to help
achieve high levels of non-synchronous generation, and so depending on the DS3 product
Page | 48
Simulation Studies and Modelling Requirements for Compliance Demonstration
definitions, reactive currents in excess of the Grid Code requirement could be warranted for those
services, but that assessment is separate from the normal Grid Code assessment.
4. The reactive current during a fault should be greater than zero as measured at the PPM element
terminals irrespective of pre-fault reactive current value. We understand that other jurisdictions
have different requirements but we have not seen stability issues in Ireland related to this
requirement. If stability issues are experienced in reality, the Grid Code empowers the TSO to
reduce the magnitude of the response from the PPM, in discussions with the PPM owner.
5. The Rise Time and Settling Time requirements are to be assessed by applying a step-change to 50%
retained voltage at the PPM connection point in the simulation, and plotting the reactive current,
reactive power, and voltage at the PPM element terminals, and also the reactive current, reactive
power, and voltage at the connection point. It is assumed by the TSO that the gains and time
constants in the PPM control systems do not change depending on the fault. If this is not the case,
the OEM or PPM must inform the TSO so that a wider suite of simulations are carried out.
6. In assessing the simulated reactive current response, a tolerance of +/-10% of the maximum reactive
current as measured at the connection point, will be allowed. Thus if the maximum current for a
PPM is 1kA (reactive), the tolerance will be +/-100A. If 500A was the expected response, a value
between 400-600A will be deemed acceptable. Ultimately, the response of the model should
accurately represent the behaviour of the physical unit under fault conditions. Deviations outside
the tolerance band will need to be explained and discussed with the TSO.
7. Once the voltage has recovered above 0.9pu, the PPM has 500ms to switch back into normal
operation (pre-fault control mode, and pre-fault reactive setpoint). It then has a further 1 second to
achieve those values based on PPM 1.6.2.4. The voltage droop should take into account the fact
that the transmission voltage may be different to what it was before the fault. We do not necessarily
expect the PPM to go back to the pre-fault MVAr value if system conditions have changed.
8. Accurate dynamic models are of utmost importance to the TSO for both system operations and
planning. Every device or PPM that connects to the grid should have an appropriate dynamic model.
As TSO we expect (and require through the Grid Code) that developers will supply us with models
that are good enough for carrying out transient simulations, and these should be in the form of
standard PSSE/WECC 2nd Generation models and DigSilent PowerFactory models, or customised
models with supporting documentation and Laplace diagrams. In summary, if the developer is able
to produce simulations to allow us to assess compliance, then they should also be in a position to
provide the TSO with the models used to carry out those simulations, so that the TSO can carry out
its own functions. We also now seek EMT models for PPMs to help us manage the power system as
the proportion of power electronic converter based devices increases significantly. These may be
supplied as “Black Box” models within PSCAD.
Page | 49
Simulation Studies and Modelling Requirements for Compliance Demonstration
“The reactive current response of the Controllable PPM shall attempt to control the Voltage back
towards the nominal Voltage, and should be at least proportional to the Voltage Dip.”
This means that the reactive current should be in a direction such as to tend to increase the voltage –
the PPM should not be absorbing reactive power during a fault as a rule, although there may be
particular cases where the reactive power at the connection point is effectively zero despite the best
efforts of the individual PPM modules.
All other things being equal, a voltage dip by 0.5pu should elicit a reactive current response
approximately twice that of a dip of 0.25pu. In other words, the reactive current response should be
proportionate – it should depend on the severity of the fault. However, the available reactive current
will also depend on the pre-fault MW output of the PPM. The following diagram illustrates the general
principle, where the reactive current should ideally be on or close to the diagonal line, with more severe
faults eliciting larger reactive responses from the PPM. Some examples are given of compliant and
incompliant responses. Note the diagrams are assuming that the available reactive current is constant
across the different voltage dips – this may not necessarily be true in reality.
Page | 50
Simulation Studies and Modelling Requirements for Compliance Demonstration
Voltage at
Connection Point
0.9pu
+10%
IQmax
-10%
IQmax
0.15pu Reactive
Current at
Connection Point
I Qavail
PPM reactive current IQavail I max
2
I P2
Figure A.1: Guideline on how much reactive current response a PPM should give, assuming I Qavail
is the same for each fault, and assuming the fault is long enough for a steady-state to be reached
Voltage at
Connection Point
0.9pu
0.15pu Reactive
Current at
Connection Point
I Qavail
PPM reactive current
Figure A.2: Incompliant response example – reactive current is not proportional to voltage dip;
Upper point shows too large a response for a slight voltage dip, and the middle voltage dip point
has less of a reactive response than the upper point.
Page | 51
Simulation Studies and Modelling Requirements for Compliance Demonstration
Voltage at
Connection Point
0.9pu
0.15pu Reactive
Current at
Connection Point
I Qavail
PPM reactive current
Figure A.3: Compliant response example - reactive current increases as voltage dip worsens
IQavail is the available reactive current (the active current being prioritized), with I max being the total
maximum current based on the rating of the PPM or on the prevailing wind/solar conditions at the time
of the fault. A voltage dip to 0.15pu elicits the maximum reactive response, and allowance is given for
over and under provision (see principles above). The TSO expects that the control systems of the PPM
would consider the difference between the nominal voltage and the fault voltage and provide a type of
fast-acting proportional response, although it is up to the PPM on how they actually implement this.
Under PPM1.4.2(e), the TSO can seek to change the slope of the line to elicit a smaller reactive response
if it is found that the reactive response is too great.
Note that for unbalanced faults, the response should be determined with respect to the positive
sequence voltage, but within the technical limits of the plant.
“The reactive current response shall be supplied within the rating of the Controllable PPM, with a Rise
Time no greater than 100ms and a Settling Time no greater than 300ms.”
As stated above, the normal maximum current within the rating of the PPM is the current at the
connection point when the PPM is operating at maximum MW output and 0.95 power factor, and this
current will consist of a real and a reactive component. The magnitude of the reactive component will
depend on the severity of the fault and the available reactive current. The rise time and settling time
are defined terms, but these can only be accurately assessed for long duration faults or application of a
step-change to the PPM controller.
“For the avoidance of doubt, the Controllable PPM may provide this reactive response directly from
individual Generation Units, or other additional dynamic reactive devices on the site, or a combination
of both.”
Some PPMs have installed statcoms, and these may be used to provide some of the necessary reactive
current during a fault in addition to the reactive current from the individual generation units (Wind
Turbines / Solar Modules etc.)
Page | 52