L1 Series Hybrid Inverter User Manual (Neutral) V1.3-20211125142830

Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

User Manual

Hybrid Inverter User Manual


Contents
1. Introduction 01
1.1 Important Safety Instructions 01
1.2 Explanation of Symbol 02
1.3 Basic features 03
1.4 Work Modes 04
1.5 Dimension 05

2. Interface definition and Technical Data 06


2.1 Interface definition 06
2.2 Technical Data 07
2.3 Basic Data 08
2.4 Safety and Protection 08

3. Installation 09
3.1 Check for Physical Damage 09
3.2 Packing List 09
3.3 Tools required for installation 09
3.4 Mounting 10

4. Electrical Connection 11
4.1 Grid connection and EPS connection 11
4.2 PV connection 13
4.3 Battery Connection 14
4.4 Communication interface definition 15
4.5 WiFi And GPRS Connection(optional) 16

5. Setting 17
5.1 Control Panel 17
5.2 Instructions for LED Indicator 17
5.3 Instructions for the use of three modes 18

6. Fault diagnosis and solutions 20


1. Introduction
1.1 Important Safety Instructions

Danger!
Danger to life due to high voltages in the inverter!
All work must be carried out by qualified electrician.
The appliance is not to be used by children or persons with reduced physical sensory or mental
capabilities, or lack of exrerience and knowledge, unless they have been given supervision or instruction.
Children should be supervised to ensure that they do not play with the appliance.

Caution!
Danger of burn injuries due to hot enclosure parts!
During operation, the upper lid of the enclosure and the enclosure body may become hot.
Only touch the lower enclosure lid during operation.

Caution!
Possible damage to health as a result of the effects of radiation!
Do not stay closer than 20 cm to inverter for any length of time.

Note!
Grounding the PV generator.
Comply with the local requirements for grounding the PV modules and the PV generator. It is
recommends connecting the generator frame and other electrically conductive surfaces in a manner
which ensures continuous conduction and ground these in order to have optimal protection of system
and persons.

Warning!
Ensure input DC voltage ≤Max. DC voltage .Over voltage may cause permanent damage to inverter or
other losses, which will not be included in warranty!

Warning!
Authorized service personnel must disconnect both AC and DC power from inverter before attempting
any maintenance or cleaning or working on any circuits connected to inverter.
Risk of electric shock!

Accesories only together with the inverter shipment are recommanded here.Other wise may result in a risk of fire,
electric shock, or injury to person.
Make sure that existing wiring is in good condition and that wire is not undersized.
Do not disassemble any parts of inverter which are not mentioned in installation guide. It contains no user-serviceable
parts. See Warranty for instructions on obtaining service. Attempting to service the inverter yourself may result in a
risk of electric shock or fire and will void your warranty.
Keep away from flammable, explosive materials to avoid fire disaster.
The installation place should be away from humid or corrosive substance.
Authorized service personnel must use insulated tools when installing or working with this equipment.
PV modules shall have an IEC 61730 class A rating.
Never touch either the positive or negative pole of PV connecting device. Strictly prohibit touching both of them at
the same time.
The unit contains capacitors that remain charged to a potentially lethal voltage after the MAINS , battery and PV
supply has been disconnected.
Hazardous voltage will present for up to 5 minutes after disconnection from power supply.
CAUTION-RISK of electric shock from energy stored in capacitor, Never operate on the inverter couplers, the MAINS
cables, Battery cables, PV cables or the PV generator when power is applied. After switching o ffthe PV , battery
and Mains, always wait for 5minutes to let the intermediate circuit capacitors discharge before unpluging DC , battery
inplug and MAINS couplers.
When accessing the internal circuit of inverter, it is very important to wait 5 minutes before operating the power
circuit or demounting the electrolyte capacitors inside the device. Do not open the device before hand since the
capacitors require time sufficiently discharge!

1
1.2 Explanation of Symbol

This section gives an explanation of all the symbols shown on the inverter and on the type label.

Symbols on the Type Label

Symbol Explanation
CE mark.
The inverter complies with the requirements of the applicable
CE guildlines.

TUV certified.

RCM remark.

SAA certification.

Beware of hot surface.


The inverter can become hot during operation. Avoid contact
during operation.

Danger of high voltages.


Danger to life due to high voltages in the inverter!

Danger.
Risk of electric shock!

Observe enclosed documentation.

The inverter can not be disposed together with the household waste.
Disposal information can be found in the enclosed documentation.

Do not operate this inverter until it is isolated from battery,mains and


on-site PV generation suppliers.

Danger to life due to high voltage.


There is residual voltage existing in the inverter after powering off,
which needs 5 min to discharge.
• Wait 5 min before you open the upper lid or the DC lid.

2
1.3 Basic features
Hybrid Inverter Seires is a high quality inverter which can convert solar energy to AC energy
and store energy into battery.
The inverter can be used to optimize self consumption, store in the battery for future use or
feedin to public grid. Work mode depends on PV energy and user’s preference. It can provide
power for emergency use during the grid lost by using the energy from battery and inverter
(generated from PV).In addition, the parallel function is available(off grid model).

System Diagram 1 (applies to most countires )

PV1+
PV1 -
Inverter
PV2+
PV2 -

Megarevo meter + -
Main switch CT

PE Battery

DPDT
RCD RCD

E-BAR

EPS
Load

System Diagram 2 (applies to wiring rules AS/NZS_3000:2012 for Australia and New Zealand )

PV1+
PV1 -
Inverter
PV2+
PV2 -

meter + -
Main switch
CT

Battery
RCD RCD
N-BAR

E-BAR

EPS
Loads Loads

3
1.4 Work Modes
Hybrid Inverter provides multiple work modes based on different requirements.
Work modes: Self-use
1.When PV, Grid, Battery is available:
A. Solar energy provides power to the loads as first priority, if solar energy is
PV Grid
Inverter sufficient to power all connected loads, solar energy excess power will
BAT EPS provides to charge battery, and then reduntant power will feed to grid.

B. Solar energy provides power to the loads as first priority ,if solar energy is
PV Grid
Inverter not sufficient to power all connected loads, battery energy will supply power to
BAT EPS the loads at the same time.

PV Grid C. Solar energy provides power to the loads as first priority ,if solar energy and
Inverter battery are not sufficient to power all connected loads, utility energy (Main
BAT EPS Grid) will supply power to the loads with solar energy at the same time.

2 .When PV, Grid is available(without battery):


PV Grid A. Solar energy provides power to the loads as first priority ,if solar energy is
Inverter
sufficient, the excess power will feed to grid.
EPS

B. Solar energy provides power to the loads as first priority, if solar energy is
PV Grid not sufficient to power all connected loads, Grid energy will supply power to
Inverter
EPS the loads at the same time.

3 .When PV, Battery is available(Grid is disconnected):


PV
Inverter A. Solar energy provides power to the loads as first priority ,if solar energy is
BAT EPS sufficient to power all connected loads, solar energy will provides to charge
battery.
PV
Inverter B. Solar energy provides power to the loads as first priority ,if solar energy is
BAT EPS not sufficient to power all connected loads, battery energy and solar energy
will supply power to the loads at the same time.

Work modes: Peak shift


1.When PV, Grid, Battery is available:
PV Grid A. On charge time, solar energy will charge battery as first priority. The excess
Inverter energy will supply power to the loads.If solar energy is sufficient to supply loads
BAT EPS and charge battery,and If there's still some extra energy, then the excess
power will feed the power to grid

PV Grid B. On charge time, solar energy will charge battery as first priority.then the
Inverter
BAT EPS excess solar energy will supply power to loads.If solar energy is not sufficient to
charge battery and supply loads, grid will supply all the connected loads with
solar energy together.

PV Grid C. On discharge time, solar energy provides power to the loads as first priority,
Inverter
BAT EPS if solar energy is sufficient to supply loads ,and if there's still some extra energy
from solar energy ,then the excess power and battery will deliver the power to
the grid at the same time.
PV Grid
Inverter D. In the period of no charge or discharge, the solar power supply loads at first
BAT EPS priority , excess energy to the grid.

Grid 2. When Grid, Battery is available(PV is disconnected):


Inverter A. On charge time, grid will charge battery and supply power to the connected
BAT EPS loads at the same time.

Grid
Inverter B. On discharge time, if load power is less than battery power, battery will
BAT EPS supply power to loads as first priority, the excess power will be feed to grid.

Grid
Inverter C. On discharge time, if load power is more than battery power, battery and grid
BAT EPS will supply power to the loads at the same time.

4
Work modes: Bat priority

1. When PV, Grid, Battery is available:


A. Solar energy will charge battery as first priority, if solar energy is excess,
PV Grid
Inverter the excess power will supply load. If there's still some extra energy, then the
BAT EPS excess power will feed the power to grid .

B. Solar energy will charge battery as first priority, if solar energy is excess,
PV Grid
Inverter the excess power will supply load.If solar energy is not sufficient to charge
BAT EPS battery and supply loads, grid will supply power to loads.

Grid 2. When Grid,Battery is available(PV is disconnected):


Inverter
BAT EPS Grid will supply power to load and charge battery at the same time.

Note!
If set anti-Reverse function allowable, Once on the work mode of Self-use , Peak
shift, battery priority, the system will not feed power to grid.

1.5 Dimension

5
2. Interface definition and Technical Data
2.1 Interface definition

A B C D E F G H I

com

J A
K L M N O P

Object Description
A/B Battery +/Battery -
C/D PV1+/PV1-
J/K PV2+/PV2-
E DC switch
F WiFi port for external WiFi
L Reserved port
G DRM/BMS
H Grid current / DRY IO
M USB port for upgrading
N POWER CAN /LEAD-NTC
I Pressure valve
O EPS output
P Grid output

6
2.2 Technical Data

Model
Model 3K 3K6 4K 4K6 5K 6K

DC input
Max. recommended DC power [W] 4600 4600 6000 6000 7000 7000
Max. DC voltage[V] 550 550 550 550 550 550
Norminal DC operating voltage[V] 360 360 360 360 360 360
MPPT voltage range [V] 125-500 125-500 125-500 125-500 125-500 125-500
MPPT voltage range@full load [V] 150-500 150-500 170-500 170-500 220-500 220-500
Max. input current [A] 14/14 14/14 14/14 14/14 14/14 14/14
Max. short circuit current [A] 17.5/17.5
14/14 17.5/17.5
14/14 14/14
17.5/17.5 17.5/17.5 17.5/17.5 17.5/17.5
Start input voltage [V] 125 125 125 125 125 125
No. of MPP trackers 2 2 2 2 2 2
Strings per MPP tracker 1 1 1 1 1 1
Max. inverter backfeed current to array 0 0 0 0 0 0
DC disconnection swtich /
AC output
Norminal AC power[VA] 3000 3600 4000 4600 5000 6000
Max. apparent AC power[VA] 3000 3600 4000 4600 5000 6000
Rated grid voltage(range)[V] 230 (176 to 270)
Rated grid frequency[Hz] 50/60
Norminal AC current[A] 13 16 17.4 20 21.7 26
Max.AC current[A] 13 16 17.4 20 21.7 26
Displacement power factor 0.99 leading...0.99 lagging
Total harmonic distortion(THDI) < 2%
Load control optional
AC input
Norminal AC power[VA] 3000 3600 4000 4600 5000 6000
Rated grid voltage(range)[V] 230(176 to 270)
Rated grid frequency[Hz] 50/60
Norminal AC current[A] 13 16 17.4 20 21.7 26
Max.AC current[A] 13 16 17.4 20 21.7 26
Displacement power factor 0.99 leading...0.99 lagging
AC inrush current 35 35 35 35 35 35
EPS output
EPS rated power[VA] 3000 3600 4000 4600 5000 6000
Max. EPS power[VA] 3000 3600 4000 4600 5000 6000
EPS rated voltage, Frequency 230VAC, 50/60Hz
EPS rated current[A] 13 16 17.4 20 21.7 26
Max. EPS current[A] 13 16 17.4 20 21.7 26
Switch time[s] <500ms
Total harmonic distortion(THDv) <2%
Parallel operation Yes
Compatible with the generator Yes(signal provided only)

Battery parameter
Battery type Lithium battery/Lead-ACID
Battery voltage range[V] 40-58
Recommended battery voltage[V] 48
Cut Off Voltage[V] 40

Max. charging Voltag[V] 58

Max. Protective Voltage[V] 59


Max. charge/discharge current[A] 95/62.5 95/75 95/83.3 95/95.8 95/104.2 95/110
Peak charge/discharge current[A] 95/62.5 95/75 95/83.3 95/95.8 95/104.2 95/110
Communication interfaces CAN/RS485/WIfI/LAN/DRM
Reverse connect protection Yes

Efficiency
MPPT efficiency 99.9%
Euro efficiency 97%
Max. efficiency 97.6%
Max. Battery charge efficiency 95%
Max. Battery discharge efficiency 95%

7
2.3 Basic Data

3K 4K 5K
Model
3K6 4K6 6K
Dimension [W/H/D](mm) 550*520*200
Dimension of packing [W/H/D](mm) 665*635*330
Net weight [kg] 25
Gross weight [kg] 31
Installation modularization
Operating temperature range[℃] -25~+60 (derating at 45)
Storage temperature [℃] -25~+60
Storage/Operation relative humidity 4%~100% (Condensing)
Altitude [m] <2000
Ingress Protection IP65(for outdoor use)
Protective Class Ⅰ
Night-time consumption <3W

Over Voltage Category lⅡ(MAINS),Ⅱ(PV,Battery)


Pollution Degree II
cooling Nautral
Noise level <40dB
Inverter Topology non-isolated
Active anti-islanding method Power variation
Communication interface CAN/RS485/WIfI/LAN/DRM

2.4 Safety and Protection

Safety & Protection


Over/under voltage protection YES
DC isolation protection YES
Monitoring ground fault protection YES
Grid protection YES
DC injection monitoring YES
Back feed current monitoring YES
Residual current detection YES
Anti-islanding protection YES
Over load protection YES
Over heat protection YES
Max. output fault current 55A
Max. output over current 28.7A

8
3. Installation
3.1 Check for Physical Damage

Make sure the inverter is intact during transportation. If there is any visible damage,such as cracks,
please contact your dealer immediately.

3.2 Packing List


Open the package and take out the product, please check the accessories first.
The packing list shown as below.

A B C D

E F G H I

Object Description
A Inverter
B Bracket
C Expansion screws and pan-head screws
D PV connectors (2*positive, 2*negative)
E AC terminals
F PV pin connectors (2*positive, 2*negative)
G Wi fimodule (optional)
H GPRS module (optional)
I User manual

3.3 Tools required for installation.


Installation tools : crimping pliers for binding post and RJ 45, screwdriver,manual wrench etc.

9
3.4 Mounting

Ø Space Requirement

300mm
Table Available Space Size
Position Min.size
300mm 300mm
Left 300mm
Right 300mm
Top 300mm
Bottom 300mm
Front 300mm

300mm

Step 1: Screw the wall bracket on the wall


1.1 Place the bracket on the wall and mark down the position of the 4 holes.
1.2 Drill holes with driller, make sure the holes are deep enough (at least 60mm) to support the inverter.
1.3 Install the expansion tubes in the holes, and tighten them. Then install the wall bracket with the
expansion screws.

Step 1

Step 2: Place the inverter on the wall mounted bracket by holding the handle on the side.

Step 2

Step 3: Tighten the fixing screws on both sides of the inverter.


Step 4: If necessary, costomer can install an anti-theft lock on the left-bottom of the inverter.

Step 3、Step 4

10
4. Electrical Connection
Ø Electrical connection diagram

BAT PV CT EPS Grid

PV Breaker
L
N
PE
PV Breaker GRID
Meter
- -
Grid side

+ + EPS CT
Main Breaker
- - Breaker
BAT Breaker

... .
. ...
+ +
Loads AC Breaker Home Load
Lithium BAT(48V) On Grid Breaker
Pv1 PV2
(PV MAX:500V)

4.1 Grid connection and EPS connection

Hybrid inverter are designed for single phase grid. Voltage is 220/230/240V, frequency is 50/60Hz.

Other technical requests should comply with the requirement of the local public grid.

Table 1 Cable and Micro-breaker recommended

Model 3K 3K6 4K 4K6 5K 6K

Cable 4-5 mm² 5-6mm²


Micro-breaker 20A 32A

Micro-breaker should be installed between inverter and grid, any load should not be connected with
inverter directly.

11
Step1. Check the grid voltage.
1.1 Check the grid voltage and compare with the permissive voltage range (Please refer to technical data).
1.2 Disconnect the circuit board from all the phases and secure against re-connection.

Step2. Remove the waterproof lid from the grid port on the inverter.

Step3. Make AC and EPS wires.


3.1 Choose the appropriate wire(Cable size: refer to Table 1).
3.2 Reserve about 60mm of conductor material sectional area and remove 10mm of insulation from the end of wire.
3.3 Separate the docking screw cap of the AC terminal from the housing portion and insert stripped wires into AC
terminal and tighten the screws with a hexagonal wrench.
3.4 Tighten the docking screw cap and housing portion of the AC terminal.

10mm

60mm

Step4. Connect the AC connector to the GRID port of the inverter and tighten the screw cap .
Connect the LOAD connector to the EPS port of the inverter and tighten the screw cap .

Note: Connect the AC connector to the GRID


into grid interface.

EPS
GRID

12
4.2 PV connection

Hybrid Inverter can be connected in series with 2-strings PV modules for 3KW,3.6KW,4KW,4.6KW,
5KW and 6KW.
Select PV modules with excellent function and reliable quality. Open-circuit voltage of module arrays
connected in series should be <Max. DC input voltage;operating voltage should be conformed to MPPT
voltage range.
Max.DC Voltage Limitation

Model 3K 3K6 4K 4K6 5K 6K

Max. DC Voltage (V) 550


MPPT Voltage Range(V) 125-500

Warning!
PV module voltage is very high, which already achieve dangerous voltage range, please comply
with electric safety rules when connecting.
Please do not make PV positive or negative ground!

Connection Steps:
Step1. Checking PV module to ensure PV is in open circuit state and ensure the PV+ and PV- ports of
the PV string are correct.
Step2. Separating the DC connector.

plug pin contact cable nut

Step3. Wiring
3.1 Choose the 12 AWG wire to connect with the cold-pressed terminal.
3.2 Remove 10mm of insulation from the end of wire.
3.3 Insert the insulation into pin contact and use crimping plier to clamp it.

12AWG
Crimp!

10 mm

Step4. Insert pin contact through the cable nut to assemble into back of the male or female plug. When
you feel or heard a “click” sound the pin contact assembly is seated correctly.

insert

13
Step5. Plug the PV conntector into the corresponding PV connector on inverter.

4.3 Battery Connection


Ø Note
1.Before choosing battery, please note the maximum voltage of battery can not exceed 59V and the
rated voltage of battery can not exceed 48V, and the battery communication should be compatible
with Hybrid inverter.
2.Before connecting to battey, please install a nonpolarized DC(125A) breaker to make sure inverter
can be securely disconnected during maintanance.
3.The connecting cable between the battery and the inverter shall be at least 4AWG.
4.The battery communication can only work when the battery BMS is compatible with the inverter.
5.To replace the battery, you need to turn off all switches and unplug the system
communication line.
6.All the above wiring and operations must be carried out after the whole machine is powered
down, and all of them need professional personnel to complete

Ø Power Connection Steps:


Step1. Choose the 2 AWG wire and strip the cable to 15mm.
Step2. Select two O-terminals with an aperture of M6.
Step3. Insert the stripping line into the O-terminal and clamp it with a crimping clamp.

Step1,2,3.

Step4. Remove waterproof cover plate.


Step5. Disassemble the waterproof connector and pass the cable through the waterproof connector.

Step4. Step5.

14
Step6.
. Connect the cable to the terminal of the inverter .
.Step7. Assemble waterproof connectors and waterproof covers plate.

Step6,7

BAT

Note!
Positive and negative lines are not allowed to reverse.
The positive pole on the left and the negative pole on the right.

4.4 Communication interface definition

Ø BMS PIN Definition


Communication interface bewteen inverter and battery is RS485 or CAN with a RJ45 connector.
The wiring sequence of the crystal head conforms to the 568B standard: orange white, orange,
green white, blue, blue white, green, brown white and brown.
1 8

PIN 1 2 3 4 5 6 7 8
CAN Definition X X X BMS_CANH BMS_CANL X X X
Rs485 Definition X X X X X GND BMS_485A BMS_485B

Ø DRY_IO (RJ45 PIN) Definition


Communication interface between inverter and meter is RS485 with a Rj45 connector.
1 8

1 2 3 4 5 6 7 8

DRYO_1A DROY_1B DRYO_1C DRYI_1 DRYI_1B DRYO_2A DRYO_2B DRYO_2C

Ø DRM Connection

DRM is provided to support several demand response modes by emitting control signals as below.
Note: Only PIN6(DRM0) is available now, and other PIN functions are being developed.
1 8

1 2 3 4 5 6 7 8
DRM1/5 DRM2/6 DRM3/7 DRM4/8 +5V DRM0 GND GND

15
4.5 WiFi And GPRS Connection(optional)

Inverter provides a WiFi port which can collect data from inverter and transmit it to
monitoring-website by WiFi.

Step1. Plug Wifi into “COM” port at the bottom of the inverter.
Step2. Build the connection between the inverter and router.
Step3. Create a user account online.( Please check the WiFi user manual for more details).

Ø Diagram
Could

Router

com

WiFi

1 2 3 4
+5V RS485_A RS485_B GND

Ø GPRS Connection :
GPRS connection interface is consistent with WIFI interface,Please refer to the GPRS user
manual for detailed connection steps.

Ø Diagram

Could

Router

AC

com GPRS
Grid

Meter

16
5 Setting
5.1 Control Panel
B C D E

F G H I

Object Name Description


A LCD
Display the information of the inverter.
Screen

lit in green: The inverter is in grid mode.


B
Off: The inverter is in not in grid mode.

Indicator lit in green: The inverter is in off-grid mode.


C
LED Off: The inverter is in not in off-grid mode.

lit in Yellow: The inverter is in Warning .


D
Off: The inverter has no Inverter Warning

lit in red: The inverter is in fault status.


E
Off: The inverter has no errors.
F Esc: Return from current interface or function.
G Function Up: Move cursor to upside or increase value.
H Button Down: Move cursor to downside or decrease value.
I Enter: Confirm the selection.

5.2 Instructions for LED Indicator


Grid EPS Alarm Fault
(Green) (Green) (Yellow) (Red)

Initialization off off off off

Stand-by off off off off

Grid mode on off off off

Off-Grid off on off off

Bypass of mains off on on off

Fault off off off on

17
5.3 Instructions for the use of three modes

W OR OD PEAK SHIFT

REMOTE CTRL

(Test mode)

(Test mode)

DC-SOURCE

Lithum-48V

18
For example,Before selecting the mode, you can set it up ac cording to the local power grid,
PV input mode and battery type.

Power grid:

Select 1:Set up
Press Esc button Press Enter button
Circular display
User Enter password
interface

Default password 00000


Press UP/DOWN button
Adjust the figure.

Circular display Press Enter button Choose Press Enter button


interface according to 3:GRID STD
local power grid

PVinput mode:

Enter password Press Enter button


Setting 1:SYS SETTING 6 PV INPUT
Press Enter button

Press Enter button

Select PV input
mode,Press
enter to confirm

Battery parameters:

Enter password Press Enter button


Setting 1:BAT TYPE Set corresponding battery
Press Enter button type,Press enter to confirm.

19
6. Fault diagnosis and solutions

The inverter is easy to maintain. When you encounter the following problems, please refer
to the Solutions below, and contact the local distributor if the problem remains unsolved.
The following table lists some of the basic problems that may occur during the actual
operation as well as their corresponding basic solutions.

Fault diagnosis table

Content Cause Solutions


1.Check whether the load is in compliance with the
maximum power of the machine.
The load power exceeds the inverter power or the
Over load 2. Cut off all the power and shut down all the machines;
output port is short-circuited.
disconnect the load and plug in to restart machines, then
check whether the load is short circuited if the fault has
been eliminated.
The battery is not connected to the inverter or the
Check whether there is voltage at BAT port of measuring
battery port has no output voltage.
Bat Disconnect inverter.

1.The battery charge is too low. 1. If the battery is too low, charge it in time.
Bat under vol 2.The battery BMS sends an instruction to prohibit 2. Check the battery communication protocol
discharging.

Bat low vol  The battery voltage is lower than the normal Charge the battery as soon as possible
working voltage value.

1. Check whether PV input voltage is within MPPT


1. The PV input voltage exceeds the MPPT voltage.
Bus over vol  voltage range.
2. The load port and the power grid port are
2. Power down the whole machine, and then power up
connected inversely.
after the display screen goes out.

There is no normal communication between the Check whether the communication between inverter and
BMS Comm.fail 
battery and the inverter. battery is normal.

Fan Fail  Poor contact of fan Power down the whole machine, and then power up
after the display screen goes out.

20
V1.3

You might also like