Method Statement For Precast Concrete Works
Method Statement For Precast Concrete Works
No.:
00 15-12-2020
Initial Release
For Approval
TABLE OF CONTENT
1.0 PURPOSE................................................................................................................................................4
1.0.2 SCOPE.................................................................................................................................................4
1.0.3 LOCATION MAP..................................................................................................................................4
2.0 References.............................................................................................................................................5
2.1 Terms and Definitions.........................................................................................................................5
3.0 Materials and Equipment......................................................................................................................6
3.1 Materials................................................................................................................................................6
3.2 Machinery and Equipment....................................................................................................................6
4.0 Duties and Responsibilities....................................................................................................................7
4.1 Project Manager....................................................................................................................................7
4.2 Construction Manager:..........................................................................................................................7
4.3 Lean Implementation Leads:.................................................................................................................7
4.4 HSE Manager:........................................................................................................................................7
4.5 Technical Manager:...............................................................................................................................7
4.6 QA/QC Manager:...................................................................................................................................8
4.7 Site Engineer:.........................................................................................................................................8
4.8 QA/QC Engineer, Inspector:...................................................................................................................8
4.9 Land Surveyor:.......................................................................................................................................8
4.10.2 Operators:........................................................................................................................................8
4.10 HSE Officer:..........................................................................................................................................8
4.10.1 Concrete foreman:............................................................................................................................8
5.0 LEAN implementation Plan....................................................................................................................8
5.0.1 SORT...................................................................................................................................................8
5.02 SET IN ORDER......................................................................................................................................9
5.03 SHINE...................................................................................................................................................9
Method Statement for Precast Concrete Works, Page 2 of 21
Document
No.:
5.04 STANDARDIZE....................................................................................................................................10
5.05 SUSTAIN.............................................................................................................................................10
6.0 Methodology.......................................................................................................................................11
6.1 Fabrication of Precast Moulds.............................................................................................................11
6.2 Mould Preparation for Casting............................................................................................................11
6.3 Assembly of Reinforcement Cages......................................................................................................11
6.4 Placement of Reinforcement cages.....................................................................................................12
6.5 Embedded Items..................................................................................................................................13
6.6 Precast Concreting.............................................................................................................................13
6.7 Precast Curing......................................................................................................................................14
6.8 Precast De-moulding and stripping......................................................................................................14
6.9 Handling, Storage and Transportation of precast Elements................................................................14
6.10 Loading and Delivery.........................................................................................................................15
6.11 Quality Controls.................................................................................................................................15
6.12 Health, Safety and Environment........................................................................................................15
6.13 DOCUMENTATION / RECORDS...........................................................................................................17
6.14 Manpower.........................................................................................................................................17
10.1.1 Key Personnel.................................................................................................................................17
10.1.2 Survey Teams..................................................................................................................................17
10.1.3 Operators/Drivers...........................................................................................................................17
10.1.4 QA/QC Teams.................................................................................................................................17
10.1.5 Laboratory Technician....................................................................................................................17
10.1.6 Skilled & Unskilled Workers............................................................................................................17
10.1.7 Helpers...........................................................................................................................................17
6.15 Document References:...................................................................................................................17
6.16 Project Specification.......................................................................................................................17
6.17 QCS 2014..........................................................................................................................................17
6.18 IFC Drawing......................................................................................................................................17
7.0 Attachments........................................................................................................................................18
7.1 Inspection & Test Plan (ITP).................................................................................................................18
1.0 PURPOSE
The Purpose of this method statement is to provide guidelines and to describe the procedure to
produce precast Concrete Items at the precast site yards of Design & Build of External Works for
Landscape, Irrigation Network, Car Parking & Services At Lusail (Al-Daayan Area)
This Method Statement covers the general procedures to be followed for Production of Precast
Concrete Item as described in QCS-2014.
1.0.2 SCOPE
The scope of this document is to lay down the systematic procedures for the Production and Delivery of
Precast Concrete Item and to ensure that all works are carried out in accordance with the approved
shop drawings, and to full compliance with the project specification.
Zone 06 Zone 07
ZONE 05
Zone 03
Zone 01
Zone 02
Zone 04
2.0 References
● Approved Material Submittal
● Project Specification
● QCS 2014
● BOQ Specifications
● HSE Plan
● Quality Plan
Term Definitions
Client ASHGHAL
Contractor UCC-INFRA JV
PS Project Specifications
PE Project Engineer
Generators 1no.
Forklift 1no.
4.10.2 Operators:
To operate equipment and machines in line with HSE & traffic rules and regulations.
5.0.1 SORT
Goals:
Implementation:
Refer Method Statement to plan requirements of equipment and materials prior to starting the work.
Avoid unnecessary equipment, materials not necessary for the work.
All the Equipment’s should be checked before using if there is any Error.
Responsibilities:
● Construction Manager.
● Site Engineer
● Sr. Surveyor
Goals:
Implementation:
● Arrange all necessary items in site so that they can be easily selected when required to use it.
● All the Equipment’s should be set in order and to be Calibrated.
Responsibilities:
● Sr. Surveyor
● Site Engineer.
● QAQC Engineer/ Inspector.
● Safety Officers
5.03 SHINE
GOAL:
To improve the construction process efficiency and safety, reduce waste, prev ent errors and
defects.
IMPLEMENTATION:
Method Statement for Precast Concrete Works, Page 10 of 21
Document
No.:
● Carry out safety inspections during construction to confirm the safety requirements
Responsibilities:
● Sr. Surveyor
● Site Engineer.
● QAQC Engineer/ Inspector.
● Safety Officers
5.04 STANDARDIZE
GOAL:
● Establish procedures and schedules to ensure the first three 5S are in place.
IMPLEMENTATION
● Review the implementation of above three 5S in the weekly lean construction meetings for
compliance.
● Ensure everyone knows their responsibilities and they are doing it.
RESPONSIBILITIES:
5.05 SUSTAIN
● Ensure 5S approach is followed
IMPLEMENTATION:
RESPONSIBILITIES:
6.0 Methodology
6.1 Fabrication of Precast Moulds
● The precast moulds shall be fabricated at UIV Workshop located at the laydown area of UIV Site
offices.
● Upon completion of set up, the mould shall be checked for accordance with workshop drawing and
fabrication drawing regarding dimensional requirements and provisions of other accessories.
● The QC, PE and the Foreman are responsible to check the conformity of the mould to the approved
workshop drawing and fabrication drawing.
● Make sure pump has the right pressure and produce a fine mist.
● All the reinforced steel bar shall be factory cut and bend from an approved manufacturer through an
approved supplier.
● UIV shall submit a material delivery inspection request to ARAB ARCHITECTS for approval for all
deliver of steel bars.
● Testing of samples of rebars shall be carried out with TPL as per the frequency stated in QCS 2014.
● The diameter, length, and bending shall be as per approved shop drawing.
● The reinforcement cage shall be constructed at the fabrication yards of laydown area.
● The rebars shall be tied with approved tie wire and spacing of rebars shall be carried out as per
approved shop drawing.
● After completion of reinforcement installation, QC and Site Engineer shall verify the completeness of
the fabrication and shall verify the correctness of installation as per approved shop drawing.
● Reinforcement cage Inspection shall be carried out prior to placing into mould.
● Make sure the spacers are in the right position, maybe add some spacers to fix the cage properly in
the mould to prevent dislocation.
● Upon completion of installation the whole set up shall be checked for accordance with approved
workshop drawing regarding dimensional requirements and provisions of inserts.
Method Statement for Precast Concrete Works, Page 13 of 21
Document
No.:
● The QC, PE and the Foreman are responsible to check the conformity of the set up to the approved
workshop drawing
● Make sure no debris, tie wire cut offs etc. are left in the set up.
● Only Approved mix designs are to be used for production of precast elements.
● The Production Engineer is responsible to order the right mix design in accordance with approved
mix design list and workshop drawings.
● Concreting must be planned as complete operation without any breaks to avoid the occurrence of
cold joints.
● The concrete will be delivered via the concrete hopper from batch plant to a designated position.
● Concrete will be discharged into the bucket of the pouring bridge or a pouring bucket.
● During pouring make sure the outlet of the pouring bridge or pouring bucket is as close as
● The QC and 3rd party Laboratory Technician shall check the type of mix design, slump, and
temperature and take sample cubes in accordance with approved concrete design mix.
● For compacting the concrete use provision of fix installed vibrators, temporary installed vibrators or
poker vibrators.
● When using poker vibrators make sure the correct diameter related to mould set up will be used.
● Special attention shall be given to difficult areas like heavy reinforcement areas, difficult mould
geometry etc. to honeycombing, voids etc.
● In some cases, after consultant approval, an approved curing compound can be sprayed onto the
surface of the concrete in accordance with specification of supplier.
● During de-moulding and lifting the element shall be checked visually for any defects or damages.
● The element shall be directly marked / labelled with casting dates as specified in the workshop
drawing.
● In case of defects or damages the QC shall be informed immediately prior transferring to the stock
yard.
● Post pour Inspection shall be carried out to check the surface damages and repairing shall be done as
per approved Method Statement.
● Positions and type of provisions shall be identified in the workshop drawings ensure lifting forces are
equally distributed.
● Lifting of precast elements are not allowed until the achieved strength and age are notified to the
consultants.
● Lift the precast elements only on their designated lifting positions and with suitable approved lifting
equipment.
● Precast elements shall be preferably stored in erection position to avoid over handling.
● Precast elements shall be preferably transport in proper position and used suitable lifting devices to
avoid any damage and rejection of the transport elements in the erection.
● Wooden palette will be provided for the proper seating of the precast concrete item on the trailer
and precast concrete item directly to the flat bed.
● All the precast concrete item in the trailer are secured with the belt slings tightened to the trailer
hooks.
● The tightened belt meeting precast concrete item will be protected to avoid damages.
● QC inspector visually confirms on site the condition of the goods received is on well condition or not,
before releasing for installation.
Only approved materials will be used. Inspection and testing will be done in compliance with the
approved Test Plan. Control of the material will be in full adherence and compliance with project specific
specifications and conditions of the contract.
a) All workers in the factory will be instructed to wear Personal Protective Equipment (PPE).
● Safety Hard Hats
● Safety Gloves
● Dust Mask
● Safety Glass
● Hi-visibility jackets
● Tension Belts
● All workers in the factory must have inducted properly, received the required
training / competencies prior to proceed the works. All safety equipment must
be inspected and approved by the factory supervisor or safety officer.
● All workers in the factory must have inducted properly, received the required
training / competencies prior to proceed the works. All safety equipment must
be inspected and approved by the factory supervisor or safety officer.
● All lifting and binding tools are to be mark with a valid safety seal to ensure
their safe workability and use.
● Use adequate and visible signage, posters and board to promote awareness.
● Ensure adequate resting areas, toilet and drinking water are accessible to all.
● Ensure enough lightings are provided when working at night times. In addition
to fixed lightings, portable lights must be kept on standby.
● Any accident or near miss must be reported to Safety Officer immediately and
with a written report to UIV Head Office within 24 hours.
6.14 Manpower
10.1.3 Operators/Drivers
10.1.7 Helpers
7.0 Attachments
7.1 Inspection & Test Plan (ITP)