Gantt Chart Output

This document outlines the tasks, timeline, and team for a project to develop an LTO Appointment System over 4 weeks. It includes tasks for project initiation, requirements gathering, system design, backend and UI development, deployment, and documentation. Each task is assigned a lead and estimated start and end dates. The project lead is Mel Angelo Cortes.

Uploaded by

Rewky
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
78 views2 pages

Gantt Chart Output

This document outlines the tasks, timeline, and team for a project to develop an LTO Appointment System over 4 weeks. It includes tasks for project initiation, requirements gathering, system design, backend and UI development, deployment, and documentation. Each task is assigned a lead and estimated start and end dates. The project lead is Mel Angelo Cortes.

Uploaded by

Rewky
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

LTO Appointment System 08/08/23 - 08/28/23

Project Start Date 8/8/2023 (Tuesday) Display Week 1 Week 1 Week 2 Week 3 Week 4
Project Lead Mel Angelo Cortes 7 Aug 2023 14 Aug 2023 21 Aug 2023 28 Aug 2023
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
Gantt Chart - -

1 Project Initiation: LTO Appointment System -


❘ Define project scope
1.1
and objectives 8-Aug-23 9-Aug-23 2 100% 2 Gail Christney Duarte

❘ Identify project team


1.2
members
8-Aug-23 9-Aug-23 2 100% 2 Mel Angelo Cortes

1.3   ❘ Set up 8-Aug-23 9-Aug-23 2 100% 2 April Marie Rosales


communication channels
2 Requirements Gathering:
❘ Document functional
2.1 and non-functional 10-Aug-23 12-Aug-23 3 100% 3 April Marie Rosales
requirements

2.2 ❘ Prioritize requirements 10-Aug-23 12-Aug-23 3 100% 3 Louis Andre Sarino


and create user stories
❘ Create high-level
2.3
system architecture
10-Aug-23 12-Aug-23 3 100% 3 Mel Angelo Cortes

3 System Design: - -
■ Design user interface
3.1
wireframes
13-Aug-23 19-Aug-23 7 50% 5 Xymmer James Nadera

3.2 ■ Define database 13-Aug-23 19-Aug-23 7 50% 5 Louis Andre Sarino


schema and relationships
■ Install and configure
3.3
database server
13-Aug-23 19-Aug-23 7 50% 5 Mel Angelo Cortes

 ■ Create necessary
3.4
tables and indexes
13-Aug-23 19-Aug-23 7 50% 5 Louis Andre Sarino

■ Implement appointment
3.6
scheduling logic 13-Aug-23 19-Aug-23 7 50% 5 Rigie Rosal

4 Backend Development:
■ Develop user
4.1 registration and 20-Aug-23 25-Aug-23 6 50% 6 Mel Angelo Cortes
authentication 
Project Start Date 8/8/2023 (Tuesday) Display Week 1 Week 1 Week 2 Week 3 Week 4
Project Lead Mel Angelo Cortes 7 Aug 2023 14 Aug 2023 21 Aug 2023 28 Aug 2023
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
■ Integrate database
4.2
operations
20-Aug-23 25-Aug-23 6 50% 6 April Marie Rosales

■ Develop user interface


4.3
components
20-Aug-23 25-Aug-23 6 50% 6 April Marie Rosales

5 UI Development:
■ Implement responsive
5.1
design
20-Aug-23 26-Aug-23 7 50% 4 Gail Christney Duarte

5.2 ■ Integrate UI elements 20-Aug-23 26-Aug-23 7 50% 4 Mel Angelo Cortes


with backend functionality
■ Conduct unit testing of
5.3 UI components and 20-Aug-23 26-Aug-23 7 50% 4 Chrysler Mc Alon
backend
■ Perform integration
5.4
testing
20-Aug-23 26-Aug-23 7 50% 4 Rigie Rosal

6 Deployment:

6.1 □ Deploy system to 26-Aug-23 28-Aug-23 3 0% 1 Mel Angelo Cortes


production environment  

6.2  □ Perform initial system 26-Aug-23 28-Aug-23 3 0% 1 Gail Christney Duarte


checks and monitoring
7 Documentation:
7.1
□ Create user manuals
and technical 27-Aug-23 28-Aug-23 2 0% 2 Chrysler Mc Alon
documentation

7.2
□ Review and finalize all 27-Aug-23 28-Aug-23 2 0% 2 Mel Angelo Cortes
project documentation