ANNEXURE - I

RESILIENT INFRATECH PVT LTD


Name of Work - Electrical Work including Erection, Testing and Commissioning of all electrical equipments with structure of
Outdoor Switchyard 11 KV / 6.6 KV Substation.
Sl.n
o. Item Specifications UOM QTY Unit Rate Amount Remarks

A SWITCHYARD EQUIPMENT

Lightning Erection, Testing and Commissioning with structure Set


1 of 9 KV - 10 KA; Station Class; Metal Oxide - (Set of 3 4 6500 26000.00
Arrestor Polymer type; complying to IS:3070; nos)

Erection, Testing and Commissioning with


structure of 12 KV - 800A; Rated Short Time
Withstanding current - 40 KA For 1 Sec;
Disconnect Outdoor; Horizontal Mounting; Manual operated;
2 Switch Double Break - Central Rotating With Earth Switch Nos. 10 12500 125000.00
along with Accessories viz., operating pipe, Handle,
connectors and Pad lock arrangement complying to
IS:9920;

Erection, Testing and Commissioning with structure


of 12KV - 800A, 40KA / 1 sec, 50Hz, VCB, Out door,
with mounting structure and along with C.T.
3 Vacuum Circuit mounting structure, complete with Porcelain
bushings, Manual / Motor operated with anti- Nos 3 37750 113250.00
Breaker pumping feature, Trip free operating mechanism
with all standard fittings and features; complying to
IS:13118; MS Structure - Hot dip galvanized,
Mechanism box- Protection Class: IP55;

Erection, Testing and Commissioning with structure


of Outdoor; Metering; 12 KV; 400 / 1A; 10VA; CL -
0.2S; Instrument Safety factor (ISF) - 5.0; Surge Set 1 7500 7500.00
Coefficient (for Rated Thermal Short Ckt current)
Ksi - 100; Live Tank design; Oil cooled; complying to
IS: 2705.

Erection, Testing and Commissioning with structure


of Outdoor; Dual Core - Metering & Protection; 12
KV;50 Hz; 400 / 1-1A, each core - 10VA; Core-1:
Metering- CL:0.5; Core-2:Protection -CL:5P20;
Instrument Safety factor (ISF) - 5.0; Surge Set 1 7500 7500.00
Current Coefficient (for Rated Thermal Short Ckt current)
4 Tranformer Ksi - 100;Live Tank design; Oil cooled; complying to
IS: 2705.

Erection, Testing and Commissioning with structure


of Oudoor; Three Core CT - Metering , protections
& Differential protection; 12 KV, 50 Hz; 200 / 1-1 A,
each Core- 10VA; Core-1: Metering - CL:0.5; Core- Set 2 7500 15000.00
2: Protection - CL:5P20; Instrument Safety factor
(ISF) - 5.0; Surge Coefficient (for Rated Thermal
Short Ckt current) Ksi - 100; Live Tank design; Oil
cooled; complying to IS: 2705.
Sl.n Item Specifications UOM QTY Unit Rate Amount Remarks
o.

Erection, Testing and Commissioning with structure


5 Potential
Transformer
of Outdoor; Two winding; 11 KV; 50 Hz, 15 VA;
Primary : 11 KV/√3 ; Secondary : 110V/√3 - CL-0.5; Set 3 7500 22500.00
Dead Tank Type, Oil filled, complying to IS:3156.

3.0 MVA; 3-Phase; 11KV /6.9 KV; Dyn 11; ONAN; Z=


6.00%; Two winding; Outdoor type; PRIMARY -
Power 11KV Bushings; SECONDARY - 6.9 KV Cable Box;
6 Transformer WTI / OTI / PRV / Buckholz Relay, Marshalling Box, Nos 2 87000 174000.00
Radiators and Bidirectional rollers; OFF-Load Tap
changer on 11 kv Wdg - +10% to -10% - steps of
2.5% ; standard fittings; Complying to IS-2026;

NGR with Erection, Testing and Commissioning of R - 80


7 Monitoring Ohms.; Current carrying capacity - 50 A for 10 sec. Nos 2 15500 31000.00
Relay

NGR with
8 Monitoring Erection, Testing and Commissioning of R - 50 Nos 2 15500 31000.00
Ohms.; Current carrying capacity - 5 A for 10 sec.
Relay

Erection, Testing and Commissioning of 200 KVA; 3-


Phase, 3-Winding; 11KV /0.440kV/0.230 kV
(Secondary Voltage 230 V Line to Line with Neutral
9 Station tapped Earthed; 440 V winding is for Control Loads Nos 1 26500 26500.00
Transformer Panel); Dyn11yn11; ONAN; Z= 4.5%; Outdoor
type;PRIMARY - 11 KV Bushings; SECONDARY -
Cable Box; WTI/ OTI, Radiators; Standard fittings;
Complying to IS-2026;

Erection, Testing and Commissioning of 1400 KVA;


3-Phase, 2-Winding; 6.9 KV /0.433 Kv; Dyn 11;
10 AUXILIARY TFR ONAN; Z= 4.5%; Outdoor type; PRIMARY - 6.9 KV Nos 2 45000 90000.00
Cable Box; SECONDAY - Cable Box; WTI/ OTI,
Radiators; Standard fittings; Complying to IS-1180.

11 Earthing Mesh Earthing including earthing of equipments Lot 1 135000 135000.00

2.5 M long, 40 mm dia GI Pipe, including digging of


soil / hard rock, and back fill by mixture of salt, Nos 82 5500 451000.00
Charcoal & Soil.

Qty may vary


Equipment Supply and Fabrication of Equipment Structure as per actual
12 Structure Lattice Type structure and 4 nos 15 mtr tower for MT 22 87000 1914000.00 drawing
Lattice Type shielding wire
received

HT Cable laying
13 & Termination HT Cable Laying Mtr 150 145 21750.00

Supply and termination of termination kit of Nos 12 9500 114000.00


11 KV grade Qty may vary
as per site
requirement
Sl.n Item Specifications UOM QTY Unit Rate Amount Remarks
o. Qty may vary
as per site
Control Cable requirement
14 laying & Control Cable Laying Lot 1 55000 55000.00
Termination

Glanding and termination Lot 1 25000 25000.00

15 Cable Tray & Fabrication & Installation of 65x65x65x6 mm ISA MT 1.5 24000 36000.00
Support for cable tray support Material to
be supplied
by PPTL
Erection of Cable tray Mtr 300 120 36000.00

Supply & Erection of IPS tube (0.5/1'') complete in


16 IPS tubing all respect including connectors and clamps for Lot 1 275000 275000.00
connection of equipments of outdoor swithyard

Supply and Installations of 100 watts LED light with


17 Switchyard 12 feet GI Pole with Junction Box, Cable and Other Lot 1 245000 245000.00
Illumination
accesories. (8 Nos)

18 Stringing of Supply and Erection of 7/8 SWG GI Wire Lot 1 65000 65000.00
shield wire

B SWITCHGEAR ROOM EQUIPMENT

6.6 KV Panel
I/C - 2 nos; BC- Erection, Testing and Commissioning of 6.6 KV
1 1; O/Gs - 14 nos Indoor VCB Panel Consisting of Two BUSes - 6.6kv-
600A-26.3KA/1s and

1. I/C FROM TFR-1 & TFR-2 - 2 nos. Nos 2 18500 37000.00

VCB - 12 KV - 800 A, 26.3 KA / 1 sec, Draw-Out Type

2. BUS COUPLER - 1 no. Nos 1 18500 18500.00

VCB - 12 KV - 800 A, 26.3 KA / 1 sec, Draw-Out Type

3. O/G FROM 6.6 KV PANEL - 14 nos. Nos 14 18500 259000.00

2 I/C CB C & R Erection, Testing and Commissioning of 11kV I/C Nos 1 18500 18500.00
Panel Feeder C & R Panel Consisting of :

Feeder Protection Relay - REF615, ABB With


Protections : with all necessary Feeder protections

Meters, Switches, Annunciator, Indication Lamps,


Push Buttons, Wires & Other Accessories; Further
details in GTP & Technical specifications.

TFR C & R Erection, Testing and Commissioning of


3 Panels for Transformer C & R Panels for TFR-1 & TFR-2 Nos 2 14500 29000.00
TFR-1 & TFR-2 Consisting of :
Sl.n Item Specifications UOM QTY Unit Rate Amount Remarks
o.

Erection, Testing and Commissioning of 6.6 kv


Capacitor Panel consisting of: 6.6 kv, 1200 KVAR
Capacitor Bank in a Panel in the configuration of
6.6 kv Capacitor 3*200 + 3*100 + 4*50 + 4*25) with APFC Relay in a
4 Panel - 2 nos single Star configuration without Earth connection. Nos 2 24000 48000.00
Steps changed to 2*300 + 2*200+2*100 - as per
vendor remarks - series reactor design is not
possble for 25 kvar

DG Panels - Erection, Testing and Commissioning of VCB - 12 KV


5 6.6kv-1000KVA - 800 A, 26.3 KA / 1 sec, Draw-Out Type with Nos 2 18500 37000.00
DG sets Protection Relay REG615

DG Erection, Testing and Commissioning of


Synchronising Breaker (Bus coupler BC)-VCB - 12 KV
6 Synchronisation - 400 A, 26.3 KA / 1 sec, Draw-Out Type with Nos 1 18500 18500.00
Panel Protection Relay REG615

Erection, Testing and Commissioning of Main LT


Panel - 0.415 KV consisting of
1. I/C FROM TFR-3 & TFR-4 - 2 nos. Nos 2 9300 18600.00

I/C-1 from TFR-3 - 1600 KVA - 6.6/0.433 kv - 3-P-


2500 A - 65 KA/1s ACB; I/C-2 from TFR-4 - 1600
Main LT Panel - KVA - 6.6/0.433 kv - 3-P- 2500 A - 65 KA/1s ACB
7
0.415 KV
2. BUS COUPLER - 1 no. Nos 1 9300 9300.00
ACB - 3-P - 2500 A - 65 KA/1s

3. O/G ACB / MCCBs from Main LT Panel - 14 nos;


Each O/G feeder is provided with CBCT + ELR - Nos 14 4750 66500.00
Test / Reset

Erection, Testing and Commissioning of 0.415 kv


0.415 kv Capacitor Panel consisting of: 0.415 kv, 850 KVAR
8 Capacitor Panel Capacitor Bank in a Panel in the configuration of Nos 2 13500 27000.00
-2 nos 2*250 + 2*100 + 2*50 + 2*25) with APFC Relay in a
single Delta configuration.

Erection, Testing and Commissioning of 110 V - 200


9 Battery Bank Ah, VRLA battery - 2.0 V /cell - 55 Cells in series Nos 1 35000 35000.00

Erection, Testing and Commissioning of 110 V - 35


Battery charger A , Battery charger - Fully automatic Thyristor
10 with DCDB controlled charger. DCDB, integral with Battery Nos 1 18500 18500.00
charger Panel - I/C - 63 A - 2P - 10 KA DC MCCB;
O/G - 12 nos - 2P -10 A - 6 KA -DC MCB
Sl.n Item Specifications UOM QTY Unit Rate Amount Remarks
o.

Erection, Testing and Commissioning of Control &


Lighting Panel consisting of: I/C - 3P-200 A - 10 KA
MCCB; from Station Transformer; O/G - 9 nos - 3P-
11 Control &
Lighting Panel 32 A - 10 KA MCBs; Tie CB to control & Lighting Nos 1 9500 9500.00
Panel - 100 A MCCB Floor Mounted; Meters;
Switches; Indication lamps; wires & other
Accessories;

Erection, Testing and Commissioning of Control


Control Supply Supply DB consisting of: I/C - 3P-63 A - 10 KA MCB;
12 DB O/G - 12 nos - 2P-16 A - 10 KA MCBs; Wall Nos 1 9500 9500.00
Mounted; Meters; Switches; Indication lamps;
wires & other Accessories;

Erection, Testing and Commissioning of Switchgear


Switchgear Room Lighting DB consisting of: I/C - 3P-63 A - 10
13 Room Lighting KA MCB; O/G - 12 nos - 2P-16 A - 10 KA MCBs; Wall Nos 1 9500 9500.00
DB Mounted; Meters; Switches; Indication lamps;
wires & other Accessories;

Erection, Testing and Commissioning of External


External
Lighting DB - Lighting DB consisting of: I/C - 3P-63 A - 10 KA
14 MCB; O/G - 12 nos - 2P-16 A - 10 KA MCBs; Wall Nos 1 9500 9500.00
Switchyard & Mounted; Meters; Switches; Indication lamps;
peropheral wires & other Accessories;

Erection, Testing and Commissioning of Office,


Office Lighting, Canteen & Street Ltg DB consisting of: I/C - 3P-63 A
15 Canteen, Street - 10 KA MCB; O/G - 12 nos - 2P-16 A - 10 KA MCBs; Nos 1 9500 9500.00
Ltg DB Wall Mounted; Meters; Switches; Indication lamps;
wires & other Accessories;

Emergency Erection, Testing and Commissioning of Emergency


Lighting DB - Lighting DB consisting of: I/C - 2P-63 A - 10 KA DC
16 Switchgear MCB; O/G - 12 nos - 2P-16 A - 10 KA DC MCBs; I/C Nos 1 9500 9500.00
from DCDB; Wall Mounted; Meters; Switches;
Room Indication lamps; wires & other Accessories;

Miscellaneous Miscellaneous work required to complete the job


17 Work that not mentioned in BOQ Lot 1 75000 75000.00

TOTAL = 4814400.00