05 - FIDIC and NEC3
05 - FIDIC and NEC3
05 - FIDIC and NEC3
Contracts
1
International Standard Forms of Contract
FIDIC:
FIDIC Conditions of Contract: 4th Edition of the
Red Book. Prepared by the Fédération
Internationale des Ingénieurs Conseils (the
International Federation of Consulting Engineers).
Since its introduction in 1963, this standard form
has been used on a large number of international
civil engineering and building contracts worldwide
and most international development and financial
institutions, including the World Bank, has
endorsed its use. use FIDIC to apply funding
from World Bank
2
International Standard Forms of Contract
3
International Standard Forms of Contract
4
International Standard Forms of Contract
UNIDO standard form of conditions for
construction contracts.
Prepared by the United Nations Industrial
Development Organization is the specialist United
Nations agency, established in 1966
ENAA Turnkey Contract Conditions.
Prepared by the Engineering Advancement
Association of Japan.
SAA General Conditions of Contract.
Published by the Standards Association of Australia
There are different contract formed by
different parties. e.g. Hospital Authority 5
Main Areas Dealt with in the General
Conditions of Most cContracts
• The main areas dealt with in the general
conditions of most contracts are:
assignment and sub-letting,
bills of quantities, North American countries
may not have BQ
6
insurance, sureties,
liquidated damages,
variations,
provisional and prime cost sums,
sectional completion,
superintendent (Engineer/Architect), determination,
extension of time,
and dispute resolution.
7
Focus Today
8
FIDIC Conditions of Contracts
9
FIDIC Conditions of Contract
• In 1999, FIDIC published four new forms of contract.
The forms, which are identified by their colours of the
covers of the publication, are as follows:
10
Conditions of Contract for EPC Turnkey Projects
(Silver Book) – for situations where one entity
carries out all of the engineering, procurement and
construction to provide a facility ready for operation.
EPC is the abbreviation for Engineer Procurement
Contract.
Short Form of Contract (Green Book) – for building
or engineering work of relatively small capital value,
of short duration or of repetitive work.
The Test Edition of the FIDIC Form of Contract for
Dredging and Reclamation Works (Blue Book)
published in 2001, similar to the Green Book
11
General Remarks for 1999 Edition
12
Further readings:
Totterdill, B.W. (2006) FIDIC users’
guide: A practical guide to the 1999
red and yellow books, UK: Thomas
Telford
Bunni, N.G. (1997). The FIDIC Form
of Contract: The Fourth Edition of
the Red Book. Blackwell Science.
FIDIC Conditions of Contract for
Construction, UK: Thomas Telford
13
New Engineering Contracts (NEC3)
14
Agenda
1. Background of NEC
2. Aims and Objectives of NEC3
3. Overview of ECC – an introduction
4. Key Features of NEC3 ECC
5. Concluding Remarks
19
Background to the NEC
Clients using the NEC in Hong Kong
Highways Department
Noise Barriers on Fanling Highway between MTR Fanling Station and
Wo Hing Road: Option C: target cost with activity schedule
Drainage Services Department
Improvement of Fuk Man Road Nullah in Sai Kung: Option C: target cost
with activity schedule
Architectural Services Department
a few pilot projects, including Tin Shui Wai Hospital:
http://www.neccontract.com/news/article.asp?NEWS_ID=776
20
Aims and objectives of the NEC
Drafted with 3 clear objectives to improve:-
1. Flexibility
2. Clarity
3. Project management
Encourage trust, collaboration and early risk
identification
Requires a change in culture from all
21
Aims and objectives of the NEC
Flexibility
Multi-disciplinary (building/civil works)
Design & build or traditional procurement
Flexible risk allocation
International application (UK, France, India,
UAE, South Africa, New Zealand etc. )
22
Aims and Objectives of the NEC
Clarity
Ordinary language
Present tense defines actions of parties precisely
Minimal subjective judgments (fair, reasonable)
Minimal legal jargon
Difference between italicised terms and those with capital
letters
Procedural logic backed up by flow charts
23
Aims and Objectives of the NEC
Stimulus to good project management –
two principles
Foresight applied collaboratively mitigates problems and
reduces risk
Clear division of function and responsibility helps
accountability and motivates people to play their part
The role of the Project Manager (PM)
Proactive
PM is placed a great deal of authority under ECC
24
The NEC Family
Engineering & Construction Contract (ECC)
between an Employer and a Contractor
Engineering & Construction Subcontract
between a Contractor and a Subcontractor
Today’s focus
Professional Services Contract
between an Employer or a Contractor and a Consultant
(not just on an NEC project)
Adjudicator’s Contract
between two contracting parties and an Adjudicator
(not just on an NEC project)
25
The NEC Family
Engineering & Construction Short Contract
for “simple” work
(not necessarily low value)
Engineering & Construction Short Subcontract
for use with the ECC or EC Short Contract
Term Services Contract
where the contract is for a period of time rather than a single project
Framework Contract
Guidance Notes and Procurement and Contract Strategies
Guide
(including flow charts)
26
Parties named in the ECC
1. The Employer
2. The Contractor
3. The Project Manager – administers the contract
4. The Supervisor – administers testing, inspection
& defects (sim. Clerk of Works)
5. The Adjudicator (appointed jointly by the
Employer and the Contractor)
6. Others - people or organisations (e.g. design team
and cost manager) who are not the above, or any
employee, Subcontractor or supplier of the
Contractor 27
Overview of the ECC - Main Options
Option A - Priced Contract with Activity Schedule
Option B - Priced Contract with Bill of Quantities
Contracts priced by the Contractors for
undertaking the works (risk largely taken by the
Contractors)
Option C - Target Contract with Activity Schedule
Option D - Target Contract with Bill of Quantities
Target cost contracts in which the out-turn
financial risk is shared by the Client and the
Contractor with a pre-agreed sharing ratio (i.e.
pain-share/gain-share approach)
Option E - Cost Reimbursable Contract
Option F - Management Contract
Cost reimbursement contracts with financial risks
largely taken by the Client 28
29
Selected Hong Kong Projects using NEC3 :
Contract Contract Title Contract Nature Start / Option
No. Sum Comp.
DC/2008/02 Improvement of Fuk Man Road nullah in Sai $76M Flood Aug 2009 / C
Kung (Completed) prevention May 2012
Consultant-managed / DP
HY/2009/04 Retrofitting noise barriers on Fanling Highway $138M Noise Barrier Nov 2010 / C
between MTR Fanling Station and Wo Hing End 2013
Road
HY/2010/10 Retrofitting of noise barriers on Tai Po Tai Wo $72.853M Noise Barrier Mar 2012 / C
Road Mid 2014
DC/2012/09 Pak Hok Lam trunk sewer and Sha Tau Kok $203M Village June 2012 / B
village sewerage sewerage Aug 2016
Consultant-managed / CM
DC/2012/05 Yuen Long Kau Hui and Shap Pat Heung $160M Village Sept 2012 / D
sewerage Sept 2016
DC/2012/03 Happy Valley underground stormwater storage $680M Flood Sept 2012 / C
scheme prevention Apr 2018
In-house / DP
30
Selected Hong Kong Projects using NEC3 :
Contract Contract Title Contract Nature Start / Option
No. Sum Comp.
DC/2012/01 Building and Civil Maintenance and Minor TBC Maintenance TBC A
Works to DSD Plants and Facilities
ArchSD Design and Construction of Tin Shui Wai $2,968M D&B Feb 2013 / A
SSA502 Hospital May 2016
IS/2013/02 IS/2013/02 – Improvement Works at Mui Wo, TBC Civil July 2014 C
Phase 1
HY/2013/19 Retrofitting of Noise Barriers on Tuen Mun PTE Noise Barrier 2015 A
Road – Town Centre Section $546M
31
Overview of the ECC – Core Clauses
Core Clauses
1. General
2. The Contractor’s main responsibilities
3. Time
4. Testing and Defects
5. Payment
6. Compensation events (19 CEs: EOT + Direct Loss and
Expenses)
7. Title
8. Risks and insurance
9. Termination
32
Overview of the ECC - Secondary
Optional Clauses
Secondary Optional Clauses
X1. Price adjustment for inflation (used only with Options
A, B, C & D) (sim. “Fluctuation Clause”)
X2. Changes in the law
X3. Multiple currencies (used only with Options A & B)
X4. Parent Company Guarantee
X5. Sectional Completion
X6. Bonus for Early Completion
X7. Delay Damages (sim. Liquidated and Ascertained
Damages)
X12. Partnering
X13. Performance bond
33
Overview of the ECC - Secondary
Optional Clauses
Secondary Optional Clauses
X14.Advanced payment to the Contractor
X15.Limitation of the Contractor’s liability for his design to
reasonable skill and care
X16.Retention (not used with Option F)
X17.Low performance damages
X18.Limitation of liability
X20.Key Performance Indicators (not used with
Option X12)
Y(UK)2. The housing grants, Construction and
Regeneration Act 1996
Y (UK)3. The Contracts (Rights of Third Parties) Act
1999
Z. Additional Conditions of Contract (amendments)
34
Overview of the ECC – Dispute
Resolution Clauses
35
Main Option + DR Option (W1) (for HK) + Secondary Option
36
Contract Formation
The contract is formed by combining :
1. Contract Data Part One (Information provided by the
Employer) (sim Appendix to Form of Tender)
2. Contract Data Part Two (Information provided by the
Contractor)
3. Articles of Agreement (incl. contract amendments – z
clauses)
4. Contract Prices (Activity Schedule/BQ)
5. Works Information including
1. Drawings
2. Works Information document (PS, GS)
6. Site Information, Programme and Risk Register 37
Key Features of NEC3 ECC – Risk
Management
Risk Management
Early warning procedures: The Project Manager and the
Contractor may notify each other upon becoming aware of any
matter which could have an impact on cost, time or quality .
The Contractor may give an early warning by notifying the Project
Manager of any other matter which could increase his cost. The
Project Manager enters early warning matters in the risk register.
Risk reduction meeting: seek solutions together to bring advantage
to all those who will be affected
Risk register revised by the Project Manager to record the
decisions made.
41
Key Features of NEC3 ECC –
Relationship Management
Relationship Management
Introduction of Partnering clause (Option X12)
Contractual partnering approached adopted
Further encourage collaboration between the Employer
43
Main challenges of Application of NEC3
Cultural change
Adversarial relationship vs Partnering approach
Provide more training and guidance on the contract
philosophy and mechanisms of the NEC3 to the
supply chain
Choice of main option
HK: traditional lump sum fixed price vs target cost,
cost reimbursement contracts in NEC3
44
Main Challenges of Application of
NEC3
Secondary Options
Necessary to introduce additional conditions of
contract and perhaps amendments of contract to
standard form of contract to take account of
local law
Drafting secondary options to meet the requirements
of legislations in New Zealand
45
Main Challenges of Application of
NEC3
Dispute Resolution
W1: used in places other than UK
W2: used in UK
Adjudication is not commonly applied, not
supported by any form of legislation in HK
Results of adjudication can be enforced by
mutual agreement
If one side not accept the adjudicator’s
decision, can go for arbitration and litigation
46
Points to Note
1. The contract imposes heavy administrative burden to
parties (also with timebar provisions for CEs)
more human resources
47
Points to Note
3. Wide range of alternatives: care should be taken
in selecting appropriate options and allocating
responsibilities
4. Clause 10.1: “The Employer, the Contractor, the
Project Manager and the Supervisor shall act as
stated in this contract and in a spirit of mutual
trust and co-operation”
What is the remedy if breaching this clause?
Enforceability in question
48
Drainage Services Department
Improvement of Fuk Man Road Nullah in Sai Kung
Commenced in 2009, Completed in 2012
49
Improvement of Fuk Man Road Nullah
in Sai Kung
KPIs Target Outturn Performance
1. User Satisfactions 7 out of 10 8 out of 10 by Leisure and
Cultural Services
Department (LCSD) and
by DSD
8 letters of commendation
2. Time 24 weeks early Completed in 141 weeks
against an extended
contract period of 165
weeks
3. Cost 5% gain share Agreed target cost
HK$76M less actual cost
HK$73M = gain share of
HK$3M
4. Quality No major rework Minor defects on non
critical items. Handover to
LCSD within 10 days of
completion
5. Safety and Environment Zero accident No recorded incidents of
safety or environmental
infringements and 4 valid
public complaints
3 safety awards
50
Performance of NEC3 vs GCC
(Chan et al., 2014)
51
Performance of NEC3 vs GCC
(Chan et al., 2014)
52
Concluding Remarks
The NEC is a new kind of family of contract endorsed by
the OGC as best procurement.
Objectives of NEC are to improve:
1. Flexibility
2. Clarity
3. Stimulus to good project management
Growing in popularity in different places of the globe,
delivering benefits of driving proactive management and
collaborative working
In order to deliver the real benefits, the parties concerned
must understand: NEC is a fundamentally different form
of contract, requiring intensive contract management and
a different approach by the parties in terms of
documentation and management requirements
53
Thank you very much!
54
Further Readings
http://www.neccontract.com/
NEC conditions of contracts
Chan, J.H.L., Chan, D.W.M. and Clifford,
Bryan (2014). "New Engineering Contracts
(NECs) in Practice - Empirical Evidence
from a Pilot Case Study in Hong
Kong" Construction Law Journal, UK, 30(4),
June, 217-235
55