Supportdoc2 Minigridtechspecs v2
Supportdoc2 Minigridtechspecs v2
AC Alternating Current
BOS Balance of Systems
DRD Department of Rural Development
ELC Electronic Load Controller
ESE Electricity Supply Enterprise
FS Feasibility Study
HH Households
IEC International Electrotechnical Commission
IECEE IEC System for conformity testing and certification of electrotechnical
equipment and components
IFC International Finance Corporation
IGC Induction Generator Controller
kV Kilovolt
kW Kilowatt
kWh Kilowatt-hour
LED Light Emitting Diode
LV Low voltage (400V)
MoEE Ministry of Electricity and Energy
MV Medium voltage (11-33kV)
MW Megawatt
NEP National Electrification Project
PMO Project Management Office within DRD
Pre-FS Pre-Feasibility Study
PV Photovoltaic
RoR Run-of-River
VEC Village Electrification Committee
Wp Watt-peak
ii
Contents
1 INTRODUCTION ......................................................................................................... 1
1.1 Definition of Mini-grid Project ................................................................................................... 1
1.2 Purpose ........................................................................................................................................ 1
1.3 Structure of the Technical Specifications ................................................................................... 1
iii
7.3 Batteries .................................................................................................................................... 20
7.3.1 General requirements ............................................................................................................... 20
7.3.2 Standards.................................................................................................................... .............. 21
7.3.3 Design requirements ................................................................................................................ 22
7.3.4 Labelling and data ................................................................................................................... 22
7.4 Data-logging and Monitoring.................................................................................................... 22
7.4.1 Power generation side........................................................................................................ ....... 23
7.4.2 Utility network monitoring (QAF)........................................................................................... 25
7.4.3 Customer .................................................................................................................... .............. 25
7.4.4 Monthly reporting............................................................................................................ ......... 25
7.5 Balance of System (BOS) in solar mini-grid ............................................................................ 26
7.5.1 Cable in Solar PV Mini-grid: .................................................................................................. 26
7.5.2 Mounting structure: ................................................................................................................. 28
7.5.3 Module bonding to array structure .......................................................................................... 29
7.5.4 Distribution boards, bus-bar enclosures, switchgear and fuses ............................................... 29
7.5.5 System grounding.............................................................................................................. ....... 31
7.5.6 System electrical earth ............................................................................................................. 32
7.5.7 Lighting protection design .................................................................................................................. 33
8 GENERATION SYSTEM OF HYDRO MINI-GRID ................................................ 35
8.1 Micro / Mini Hydro Turbines .................................................................................................... 35
8.1.1 Turbine runner material: .......................................................................................................... 35
8.1.2 Adaptor / Manifold .......................................................................................................... ........ 35
8.1.3 Manifold valve ......................................................................................................................... 35
8.1.4 Hydro Turbines ........................................................................................................................ 36
8.1.5 Turbine runner material: .......................................................................................................... 36
8.1.6 Manifold .................................................................................................................................. 36
8.1.7 Manifold valve ........................................................................................................................ 36
8.1.8 Expansion section .................................................................................................................... 37
8.1.9 Turbine casing .............................................................................................................. ........... 37
8.1.10 Bearings and Water seals: …............................................................................................................ 37
8.1.11 Pressure gauge: ................................................................................................................................. 38
8.1.12 Base frame: ....................................................................................................................................... 38
8.1.13 Drive system and couplings: ............................................................................................................ 38
8.1.14 General aspects of hydro generating system: ................................................................................... 38
8.1.15 Tools and special equipment ............................................................................................................ 39
8.2 Generator (Alternator) of hydro mini grid: ............................................................................... 39
8.3 Cable size in Hydro Mini Grid: ................................................................................................. 39
iv
10.2.7 Material of distribution line conductor: .................................................................................... ........ 42
10.2.8 Types of distribution line conductor: ............................................................................................... 43
10.2.9 Span of the LV distribution line poles, ..................................................................................... ........ 43
10.2.10 Distribution line Clearance ............................................................................................................. 43
10.2.11 Insulators: ................................................................................................................. ...................... 43
10.2.12 Stay assembly ............................................................................................................... .................. 44
10.3 Load centers .............................................................................................................................. 44
10.3.1 Clustering .......................................................................................................................................... 44
10.3.2 Distribution board and load points ................................................................................................... 44
10.3.3 House wiring and Appliances ........................................................................................................... 44
10.3.4 Street lighting.................................................................................................................................... 44
10.3.5 House Energy meter and vending machines .................................................................................... 44
10.3.6 Earthing convention: conductor earthing conventions .................................................................... 44
11 Documentation and labelling ....................................................................................... 46
11.1 Documentation .......................................................................................................................... 46
11.2 Labelling SLD and equipment .................................................................................................. 46
11.3 Signage and safety equipment ................................................................................................... 46
11.4 Warranties ................................................................................................................................. 47
LIST OF TABLES
LIST OF FIGURES
v
NEP Mini Grid Technical Specifications – v. January 2019
1 INTRODUCTION
The Off-Grid Component of the National Electrification Project (NEP) is supporting the
development of mini-grids using one or a combination of energy generation technologies for
pre-electrification.
The generation source shall be decided based on assessment of various resources at the potential
site. Candidates include, but are not limited to, solar photovoltaic (PV), micro hydropower,
biomass, wind, diesel or any combination (hybrids) of these technologies. Mini-grids up to one
megawatt (MW) effective generation capacity are eligible for assistance through this program,
and larger systems may be considered on a case-by-case basis.
This document outlines the minimum technical specifications that must be followed in
development of mini-grid plants under the NEP framework.
1.2 Purpose
These technical guidelines are drafted with the purpose of maintaining acceptable quality
standards of the projects developed under the NEP mini-grid program in order to ensure the
safety and sustainability of projects.
The role of a mini-grid project developer is to ensure that contractors, equipment suppliers and
associated service providers involved in the mini-grid project development provide
components and services which meet or exceed the guidance and standards described in this
document.
1
Source: Mini-Grid Policy Toolkit
1
NEP Mini Grid Technical Specifications – v. January 2019
communities and/or project developers, new technologies may be added to this document
whenever it is required.
• General Requirements
• Civil works
• Power Generation systems
• Distribution system
Departure from specifications: If the developer believes that project can be developed in such
a way so as to perform better and safer than if a strict adherence of this document were followed,
prior approval from the NEP Project Management Office (PMO) at the Department of Rural
Development (DRD) may be sought to depart from these specifications. In the event that a
departure is approved and real-world findings validate the initial claims, a revision for these
specifications may be issued to ensure that the most cost-effective approach is followed for
future projects.
Disclaimer: Whilst the PMO has made every effort to ensure that information presented here
is correct and up-to-date for safe and effective performance of mini-grid projects, all parties
must rely upon their own skills and judgments when making use of this document.
The PMO shall review the technical design and equipment in proposal submissions and shall
reserve the right to modify specifications and/or requirements for any equipment or component
in order to improve reliability, functionality, longevity of a project design or to remove
ambiguity.
2
NEP Mini Grid Technical Specifications – v. January 2019
(b) Technical and operational aspects of the propose mini-grid project must comply with
prevailing statutory requirements at both the Union and State/Regional levels. At the Union
level, the 2014 Electricity Law 2 is the current governing legislation for the off-grid
electricity space.
(c) Prospective developers are required to utilize the standard documents such as demand
assessment forms (Support Doc. 13), instructions on selection of distribution line layout
and design (Support Doc. 7), bills of quantity formats and financial analysis formats
(Support Doc. 8), etc. provided on the DRD website3.
(b) Mini-grids in which the load demand growth is expected to mature slowly or only after
several years must be designed for phased implementation. Such project phasing may
entail installing smaller generation plant initially and designing a second phase as demand
increases. Mini-grid systems designed in a phased manner take full advantage of the
modular and expandable nature of different generation and distribution technologies.
(c) When designing the mini-grid distribution system, alternating current (AC) should be used
irrespective of generation technology or capacity of the system. Voltage, frequency and
other electrical parameters of the AC distribution network should be compatible with that
of the national electricity grid in Myanmar.
(d) Depending on the type and capacity of loads and/or depending on the plant capacity, a
system may require a 11kV medium voltage (MV) network in combination with a low
voltage (LV) network of either single-phase (230V) or three-phase (400V) configuration.
Special care must be exercised in the three-phase mini-grid systems so as to balance the
loads evenly across each phase.
2
Pyidaungsu Hluttaw Law no. 44/2014
3
http://drdmyanmar.org/index.php
3
NEP Mini Grid Technical Specifications – v. January 2019
(e) Additional studies such as geological analysis, environmental analysis, hydrological study,
test certificates from suppliers, etc. may be requested from the relevant authority by the
PMO.
(b) Full time plant operator is compulsory for the NEP mini-grid project. In addition, Developer
needs to appoint a project manager responsible for the mini-grid project, who is responsible
for the successful operation of the project and needs to communicate with VEC and DRD
regularly.
(c) As the engineering, procurement and construction representative of the mini-grid project,
the developer should also provide applicable warranty certificates from manufactures and
suppliers at the time of project commissioning.
(d) It is recommended that the developer and/or the Village Electrification Committee (VEC)
obtain suitable insurance coverage for the project, taking into account circumstances that
may lead to costly repair or replacement obligations within the project lifetime.
4
NEP Mini Grid Technical Specifications – v. January 2019
3.1 Durability
The design life of mini-grid civil structures should be 20 years. Adequate and safe structures
should be achieved while minimizing unnecessary costs for the community and other
stakeholders.
3.4 Formwork
Concrete formwork should be preferably done with metal sheets or with plywood of minimum
15 mm thickness or with similar wood sheeting. A lubricating layer of concrete form release
agent (typically oil) should be applied before casting with formwork in order to maintain good
quality of surface finish.
All structures made of steel should be galvanized appropriately or wire brushed to prevent
rusting. Wherever galvanization or wire brushing is not possible, two coats of anticorrosive
paint should be applied. Furthermore, it is advisable to sandblast any steel components in
contact with water before painting if they have not been adequately galvanized.
5
NEP Mini Grid Technical Specifications – v. January 2019
(b) Insulation and ventilation: Window areas of the powerhouse shall be equivalent to at least
10% of the powerhouse floor area to ensure adequate passive ventilation in the absence or
failure of automatic temperature control equipment. All metallic roof sheets must be
insulated from the inside using double size insulation glass wool or similar insulating
material of minimum 25mm thickness. Roof ventilation should be achieved through the use
of whirly-bird passive air extractors and ventilation gaps must be rodent resistant.
(c) Roofing: The minimum height between floor and ceiling should be 3 meters or 10 feet.
Roofing material should be made of fire-resistant materials such as tile or corrugated sheets.
In case of corrugated sheets, the minimum thickness should be 0.47mm. The roof should
be watertight and should extend at least 1 meter or 3 feet over walls to prevent water for
entering through window portals. The power house door shall be designed with adequate
spacing for easy installation and removal of equipment. For safety reasons, the door should
be outward-opening (i.e. able to open from the inside).
(d) An appropriate lifting mechanism such as a gantry crane should be provided for the
convenience of operation and maintenance in case the system components are unwieldy or
otherwise difficult to access safely.
(e) A toolbox including any required specialized tools should be available and upkept with any
consumables needed for routine maintenance. Operation and maintenance log books should
be regularly updated (i.e. on a daily basis) with accurate performance records.
(f) Workers’ room, an extension of the powerhouse, with basic facilities such as
bathroom/washroom and essential living furniture should accompany the powerhouse
design as it is necessary for an operator to be present all the times during normal system
operation.
(g) All exposed trenches such as the cable ways of solar projects and main valve pits of hydro
projects should be covered with checkered steel plates or another suitable cover made of
steel. Wherever it is impossible to cover these trenches, a safety railing should be affixed
during construction.
(h) Fencing & drainage: Proper fencing with foundations suitable for the slope of the land,
drainage system and main gate is compulsory for NEP mini-grid systems.
6
NEP Mini Grid Technical Specifications – v. January 2019
(b) Intake should be selected such that minimum debris will enter the system during
flooding period.
(c) In case the layout is long, a shorter headrace channel with higher slope connecting to
the settling tank and channel section with mild slope from there to the forebay should
be incorporated for efficient filtering purpose.
(d) Forebay and settling tank (if any), should be located near the natural gulley whenever
possible to facilitate safer and low-cost spillway arrangement of diverting spill water
back to the stream.
(b) Construction material of weir can be concrete or rubble and masonry or mixture (rubble
masonry interior jacketed with concrete layer). Selection of material will be based on
the weir height, flowrate and power output of the plant.
(c) Intake should be equipped with a trash rack to prevent clogging; a control gate to
control the water flow to the channel and flood barrier wall to make the control gate
operations possible during high flow periods. Trash rack should have preferably iron
rods or flat irons; welded with a gap decided based on the turbine supplier’s
recommendation; rod orienting upward (vertical) direction without cross bars, making
it easy for the plant personnel to clean efficiently with a rake. It should have a locking
mechanism to prevent unauthorized access. Rod spacing should not be too small which
can cause rapid blockage and resulting an operational problem.
(d) Flood barrier should be designed with consideration of 100-year flood level calculated
with hydrological model.
7
NEP Mini Grid Technical Specifications – v. January 2019
(e) Location of the intake, specially the intake gate should be done such that it can be
accessed during high flood period.
(f) Unregulated environmental flow releasing pipe, of which diameter and location
(height from the top of weir) determined by the National Environmental authority or
PMO, must be placed to release environmental flow (Eflow) to safeguard the downstream
ecosystem.
(g) Flush gate, designed based on the maximum silt load of the stream needs to place at the
lowest point of the weir with a proper controlling mechanism.
(h) Erosion and deepening of downstream riverbed (due to scouring action) of weir and
spillways should be considered in design phase and should be protected with suitable
mechanism/ structures incorporated in weir design.
5.3 Channel
(a) Rectangular concrete channel build with Grade 25 reinforced concrete is the prefer
selection for MHP projects. For extreme case like very low plant capacity with
relatively higher channel length, earth, rubble masonry, cement and mortar channels,
pipe or combination of different types can be considered.
(b) Freeboard allowance of 30% should be kept when designing the channel dimensions.
(c) Maximum channel velocity to avoid erosion, in different types of channel should be
conform to the specifications below. In case of silty water, channel velocity should be
maintained at the minimum velocity of 0.3 m/s to prevent clogging of the channel.
8
NEP Mini Grid Technical Specifications – v. January 2019
(d) Channel crossing and drain outlets underneath should be placed in appropriate
places (e.g. gulley crosses the channel path if it is not being diverted to the channel) at
intervals of at least 20m. This will ensure safe flow of water across the channel (i.e.
transverse flow across channel) from embankment to the river down. Interval of drain
outlets will depend on nature of surface water flow in the project area. Drain outlet can
be an embedded construction to a channel or a pipe line.
(a) Settling Tank section: Settling tank will settle the particles which otherwise could
damage the turbine casing and runner over a period of operation due to wear (abrasion)
and cavitation. MHP projects under NEP should settle and filter particles above 0.3
mm unless the turbine manufactures instructed to filter even finer particles.
(b) In reaction turbines, the manufacture will state the maximum sand particle allowed in
the water and same should be honored to get the cavitation guarantee offered by the
supplier.
(c) Flush gate (sluice gate) and spill way operating manually should be incorporated to
the settling section to flush the silt collected from time to time. In most instances, one
spillway is adequate to cover the safe passage of spill water in settling and forebay
sections.
(d) Trash rack is compulsory in the forebay section and the rod spacing can be decided to
match the weir intake trash rack.
9
NEP Mini Grid Technical Specifications – v. January 2019
Gantry (steel or concrete beam), climbing ladder and handrails should be fixed for the
safety of the operators during the cleaning of the forebay trash rack.
(e) A thumb rule which can be used during reconnaissance study for determining the
height of forebay section is to make it minimum four times of the penstock diameter
to prevent vortex formation in the full flow operation of the turbines. In detailed
engineering design this water height should be selected to be greater than [1.5 x
(Vpenstock)2/20]. V is the velocity of water in the penstock.
(f) Bell mouth (or penstock itself in smaller systems) should be positioned at least 150mm
above the forebay tank floor to prevent silt and small stones from entering the penstock.
(g) Vent pipe with a sufficient diameter should be fixed to the penstock or bell mouth
section to prevent damage due to surge. It will prevent inward collapse of penstock due
to surge pressure.
10
NEP Mini Grid Technical Specifications – v. January 2019
(a) Penstock should have constant gradient in each section; i.e. straight from one anchor to
the next. In some projects an air release valve should be fitted to highest point if air is
likely to trapped due to the layout of the penstock.
(b) Material that can be used in MHP projects and design characteristic which should be
followed in selection of different parameters are tabulated in the table below:
(d) Penstock loss due to internal friction and local losses like, bend losses, contractions
losses, expansion losses etc. calculated for 110% of the rated flow of the plant should
be below 5% of the gross head.
(e) If the steel pipes are fabricated locally, all the pipes should be pressure tested to the
150% of the static pressure of the system.
(f) Penstocks laid above ground should be supported at every 6m intervals with a slide
block or support block. In the event of support blocks, minimum of 120 deg of the
penstock circumference should be firmly in contact to the support block. These supports
11
NEP Mini Grid Technical Specifications – v. January 2019
and slide blocks can be made with concrete, rubble and masonry; if the height is less
than 2m a combination of concrete and rubble and masonry or steel.
(g) In all bends, an anchor block made of reinforced concrete and/or concrete with 20%
plums and/or rubble and masonry with concrete jacket should constructed to
counterbalance the forces occurs due to cause by change of momentum of water.
Possible penstock failing scenarios like toppling, sliding, sinking/lifting forces should
be considered when sizing the anchor blocks. Annexes 2 and 3 drawings of typical slide
block, anchor block and support block are provided for reference.
(h) Underground steel and PVC penstocks should be buried at least 300mm beneath the
ground and should be on a sand bed. No slide or supports blocks apart from anchor
blocks at the bends are required in underground penstocks. In GRP penstocks, even this
requirement of having anchors at bends can be minimized.
(i) Underground steel penstocks should be painted with epoxy liquid coal tar (bitumen) to
a minimum paint thickness of 150 um.
(j) Thermal expansion and Expansion joints: rubber sheets or tar sheets (graphite
asbestos sheet) of minimum thickness of 3mm must be placed between penstock and
supports to prevent abrasion due to thermal expansion and contraction.
Expansion joints are required in steel penstocks just below anchor blocks and forebay
tank to minimize the stress created due to thermal expansion and contraction.
In case of uPVC penstock pipes, spigot joint can accommodate the thermal
expansions. If glued socket connections are used in over ground uPVC penstocks, at
least one spigot joint is recommended between anchors or expansion joint can also be
used.
12
NEP Mini Grid Technical Specifications – v. January 2019
Frequency - 50Hz
(b) The power factor should not drop below 0.8 in synchronous generator systems, while
this should not drop below 0.95 in induction generator systems. 0.95 to retain frequency
control. If required, pf correction device must be added to achieve the pf specified
above.
(c) All major equipment such as generators, inverters, solar panels, batteries etc. should
have clear name plate; fitted by manufacture; which displays the manufactures name,
serial and model numbers, date of manufacture wherever required and technical
specification of the components etc.
(d) All electrical installation must comply to standards specifications of British Standards
Institution, Regulation for Electrical Installation issued by Institute of Electrical
Engineers, London (IEE Wiring Regulations) 17th edition or IEC 60364 Electrical
Installations for Buildings.
(e) Power cables which can be copper or aluminum shall comply to IEC60227 and IEC
60502 Power cables with extruded insulation; IEC 60228 Conductors of insulated
cables or BS 6004/BS 6346.
(f) Enclosures of electrical accessories, joint boxes should comply to BS 4662. Live
surfaces and points of cables and other parts should be shielded from human contact.
13
NEP Mini Grid Technical Specifications – v. January 2019
Proper jointing method which are durable, strong and serving the purpose must be used.
In case of joining conductors with different material, bi-metallic connectors must be
used.
(g) Distribution board in powerhouse: should have appropriately rated isolators, ELCB (or
RCD) and MCB for each line complying with IEC 61008: Residual current operated
circuit-breakers without integral overcurrent protection for household and similar uses
(RCCBs), IEC 60898: Electrical accessories - Circuit-breakers for overcurrent
protection for household and similar installations and/or IEC 60947: Low-voltage
switchgear and control gear, as applicable.
(h) Protection at powerhouse to safeguard end-users: Over and under voltage and frequency
protection should added to control panels at powerhouse if required to safeguard the
users and domestic and industrial equipment and appliances use.
(i) All metal enclosures including casing of electrical generators, casing of turbines, cable
trays etc. and surge protection devices (SPD), Residual current devices (RCD),
lightening arrestors at powerhouse and load points should have earthing system
complying to the relevant part of IEC 60364: Low-voltage electrical installations
standards. Each distribution line starting form powerhouse should have one ELCB with
a maximum leakage current rating of 300 mA.
(j) Copper rod with diameter not less than 35/50 sq.mm or copper strip of dimensions not
less than 20mm x 3mm or Cu conductor of minimum cross section of 25mm2 should
be used as earthing. Earth resistance of 2 Ω (ohm); on dry day, should be maintained at
the powerhouse and consumer points.
(k) Lighting arrestors: lighting protection installation in NEP mini-grid projects should be
comply with IEC 62305: Protection against lightning or British Standards C.P.326
standards. Roof conductor and down conductors shall be soft annealed copper type of
size not less than 20mm width and 3 mm in thickness. In case of bare conductor are is
for distribution line, spark gap type lightening arrestors and associated earthing system
should be installed to cover each 500 m radius of line and end user points.
(l) IT and Control cabling: All the control and IT cables should be appropriately laid and
conform to IEC 11801: Information technology - Generic cabling for customer
premises and IEC 14763-2: Information technology - Implementation and operation of
customer premises cabling standards to ensure proper control and monitoring of system.
(m) Monitoring and controlling: Irrespective of the technology used, following electrical
parameters should be monitored at powerhouse control panels.
14
NEP Mini Grid Technical Specifications – v. January 2019
Number
Electrical parameter/ panel meter Single phase Three phases
Frequency/ Frequency meter 1 No. 1 No.
Voltage/ Voltmeter (village) 1 No. 3 Nos.
Voltage/ Voltmeter (ballast) Depend on ballast partitions
Amperage/ Ammeter (village) 1 No. 3 Nos.
Amperage/ Ammeter (ballast) 1 No. 3 No.
Energy/ Energy meter (kWh) 1 No. 1 No.
Power factor One phase Each phase
(n) Labels and Diagrams: All electrical components should have labels describing their
function, in English and Myanmar language. Block diagram which shows overall
system and single line diagram (circuit diagrams) for each panel and controllers should
be included. Illustrated Warning signs in Myanmar language should be fixed at all
places which poses a threat for operators, community and/or end users.
15
NEP Mini Grid Technical Specifications – v. January 2019
• Assessment of the load demand characteristics, especially: initial uptake, load growth
and allowances for growth, seasonality of loads, day time loads versus nighttime loads.
• Variability of solar resource from day to day, and seasonally
• Solar mini-grid configuration options best suited to match load characteristics with
resource characteristics.
In general, solar mini-grids for rural villages will always comprise of at least the following
components, also illustrated in figure below.
• Distribution network
• Storage batteries
• DC-AC inverter or power conditioner for providing useful power to the loads
• Solar arrays
o DC-coupled charging batteries directly, or,
o AC-coupled providing power direct to AC day-time loads, and optionally
charging battery through the bi-directional inverter charger
• Optional back-up diesel generator
• Water supply arrangement for regular cleaning of PV arrays.
Solar PV or Solar PV Hybrid Mini-grids must follow IEC 62257, Recommendations for Small
Renewable Energy and Hybrid Systems for Rural Electrification, which provides guiding
principles for design and other system characteristics of such systems.
(a) Compulsory Standards: Solar modules shall conform to the following standards form
the International Electro-Technical Commission (IEC).
16
NEP Mini Grid Technical Specifications – v. January 2019
(b) Recommended standards: In special case of salty environment (installation near the
sea), additional standard of IEC 61701 Salt mist corrosion testing of photovoltaic
modules should satisfy.
(d) For the delivery of the solar modules the transport standard IEC 62759-1: Photovoltaic
(PV) modules - Transportation testing - Part 1: Transportation and shipping of module
package units (or equivalent) must be fulfilled.
(e) Warranties: All PV modules installed in the NEP mini-grid should have following
product warranty levels.
(d) Bypass diodes should be installed in each module to prevent hot-spots in modules,
which occur often because of partial shading of modules. The NEP mini-grid project
developer shall ensure that every module in a series string of more than 24V nominal
voltage, shall include bypass diodes in the module terminal-connection box. The diodes
should be replaceable without replacing the module or module junction-box.
(e) Modular junction box, cable and Connector: should have water and dust tight
junction (IP65) box mounted at the back of the panel with minimum of 1 m ;4 mm2
output cables connected with male and female (quick) connectors.
17
NEP Mini Grid Technical Specifications – v. January 2019
(f) Label of PV panel: label of the PV module should have the following details. Name of
the manufactures and website; model number, serial number, peak current, peak
voltage, power rating of panel at standards test condition; open circuit voltage, short
circuit current.
(g) Developer should provide I-V curve with the Feasibility at AM 1.5 and STC,
Temperature coefficients dV/dT, dI/dT, etc
• IEC 62109-1 (Safety of Power Converters for Use in Photovoltaic Power Systems –
Part 1: General Requirements).
• IEC 62109-2 (Safety of power converters for use in photovoltaic power systems
- Part 2: Particular requirements for inverters
• European Union (CE) or Underwriters Laboratory (UL 1741) for compliance
(b) Particular standards for PV inverters which must comply with the following or similar
• IEC 61727: Photovoltaic (PV) systems – Characteristics of the utility interface
• IEC 62116: Test procedure of islanding prevention measures for utility
interconnected photovoltaic inverters
• DIN VDE 126-1-1 or VDE 126 or similar (frequency and voltage disconnection
limits) Automatic disconnection device between grid parallel power generating
system and the public low voltage grid
18
NEP Mini Grid Technical Specifications – v. January 2019
(c) Particular standards for Bi-directional Battery inverters must in addition comply with
comply with
• IEC 61000-3-2, IEC 61000-3-3, IEC 61000-6-1, IEC 61000-6-2, IEC 61000-63:
Electromagnetic compatibility,
• IEC 60335-2-29: Household and similar electrical appliances - Safety - Part 229:
Particular requirements for battery chargers
(e) Warranties of inverters: Manufacturing and Performance warranty: must have five-
year warranty period and mini-grid project developer should be responsible for transporting
back and forth and get the inverter repaired or replaced in case such a claim is required.
7.2.2 Labelling and data
Each inverter device must be labelled with the minimum information:
o Manufacturer name and model
o Serial number
o Input and output voltage and rated power
o Battery type compatibility (if applicable lead-acid and type (OPzV etc.), or
Li-ion and type (LiCoO2 LCO, LMO, NMC, LFP, NCA, LTO)]
19
NEP Mini Grid Technical Specifications – v. January 2019
The supplier is required to provide for each conversion device offered the following data:
o System rating (kW/kVA) with temperature de-rating curves/tables o Input Voltage
(DC) range
o Output Voltage (AC)
o Efficiency versus Power output graph, for various input voltages o
Certificates and compatibility with country standards applicable o Warranty
o Product brochure
7.2.3 Guidelines for Inverter Selection
(a) Inverter should produce output electricity to match the quality requirement stated in 7.1
in this document.
(b) PV Inverters should have at least one maximum power point trackers (MPPT). If the
mini-grid capacity above 25 kW; multi string i.e. Inverter with multiple MPPTs is
preferred.
(c) In general, modular and expandable inverters / bi-directional inverter units are
preferred, which can be used in multiples in parallel to increase power. Centralized
systems which are not expandable to account for future load growth are not preferred.
(d) PV Inverter or charge controller should be able to handle 125% of array short circuit
current.
(e) Efficiency of PV inverter should be above 95% over 75% of the power range.
Efficiency of bi-directional inverter should be more than 90% over 75% of the power
range.
(g) Inverter should have protection for incorrect polarity; over temperature and excessive
DC voltage.
(h) Inverters located inside the powerhouse should operate between -25°C to 60°C with
derating and should have an Ingress Protection rating of at least IP 54.
7.3 Batteries
7.3.1 General requirements
(a) Batteries of the following types are allowed for the NEP solar mini-grid projects:
• Lead-acid: the following are acceptable:
20
NEP Mini Grid Technical Specifications – v. January 2019
7.3.2 Standards
(a) The standards Cycle life of lead acid batteries:
• IEC 60896-21 and 22 Ed 1(2004); Stationary lead-acid batteries - General
requirements and test methods: Valve regulated types (clauses 6.13 and 6.17)
• IEC 61427-1 (Secondary cells and batteries for renewable energy storage -
General requirements and methods of test - Part 1: Photovoltaic off-grid
application
(b) The safety standard for Valve Regulated lead acid batteries:
• IEC 60896-21 and 22 Ed 1(2004); Stationary lead-acid batteries - General
requirements and test methods: Valve regulated types
• IEC 61056-1 (2012): General purpose lead-acid batteries (valve-regulated
types) - Part 1: General requirements, functional characteristics - Methods of
test.
(c) Standards for Cycle life endurance for li-ion batteries:
• IEC 61960; Secondary cells and batteries containing alkaline or other non-acid
electrolytes – Secondary lithium cells and batteries for portable applications
OR
• IEC 62620; Secondary cells and batteries containing alkaline or other non-acid
electrolytes. Secondary lithium cells and batteries for use in industrial
applications
21
NEP Mini Grid Technical Specifications – v. January 2019
For each battery type, the battery must be labeled indicating at minimum o Manufacturer,
Model Number, Voltage and Capacity. o Type of the battery [lead-acid and type (OPzV
etc), or Li-ion and type (LiCoO2 LCO,
LMO, NMC, LFP, NCA, LTO)] o
Battery Voltage, Battery Capacity@C20
The supplier is required to provide for each Battery type the following general data
o Battery discharge performance versus Temperature
o Battery cycle life versus depth of discharge
o Battery cycle life versus battery temperature
o Product brochure
o Warranty information
The supplier is required to provide for each Battery type the following test data
o Battery discharge performance curves at C10 and C50, at a minimum
o Safety test compliance against IEC 60896-2 for VRLA batteries
o Battery cycling curves against IEC 60896-11 or IEC 60896-2, or against IEC 61427.
22
NEP Mini Grid Technical Specifications – v. January 2019
System Parameters such as solar PV electricity generated, diesel genset generation and run
hours, battery voltage and SoC, and energy sent-out from powerhouse, at a minimum shall be
recorded hourly with automated data logging equipment. This shall be retained in hourly data
format, but also cumulated into daily, weekly and monthly reports.
The logging system shall have capability to upload to internet via mobile carrier or other means.
Connection to internet for data upload must occur at least once per month to transfer if no
mobile network in available at site. All of the data for the previous month must be uploaded
but a more frequent upload interval is preferred.
A live-interactive online system which can see individual components is natural preferred (i.e.
each PV inverter, each battery inverter, each battery bank).
Time of occurrence and duration of service interruption events (power failures) to be logged
(either automatically or manually) and reported monthly;
All of the above shall be summarized into monthly performance report for the site.
Multiple meters must be installed in such a manner that all generation and outgoing energy is
effectively monitored for clear understanding of system performance.
23
NEP Mini Grid Technical Specifications – v. January 2019
Standards
IEC 62052-11: Electricity metering equipment (a.c.) - Particular requirements - Part 11:
Electromechanical meters for active energy (classes 0,5, 1and 2)
IEC 62053-21: Electricity metering equipment (a.c.) - Particular requirements - Part 21: Static
meters for active energy (classes 1 and 2)
IEC 62053-22: Electricity metering equipment (a.c.) - Particular Requirements - Part 22:
Static meters for active energy (classes 0,2 S and 0,5 S)
Note: More meters may be required and must be installed if multiple interface of generation or
outgoing point exist in the system, it is the responsibility of developer to install meters such
that a complete energy balance is effectively monitored.
Installation of household meters: household energy meters needs to have the ability to see at
least the remaining balance available & energy usage. Energy meter is expected to be installed
inside the house (or other load point) but if it is installed in the service pole due to any reason,
interface with display should be given to each load points to see the above minimum information
on their electricity usage and to facilitate the recharging, if applicable.
24
NEP Mini Grid Technical Specifications – v. January 2019
Time of occurrence and duration of service interruption events (power failures) to be logged
(preferably automatically or manually) and reported monthly.
7.4.3 Customer
Consumer level consumption data including average daily Watt-Hour consumption and peak
power demand (Watts or Amps) to be measured and recorded for inclusion in monthly
reporting. This shall cover individual usage and payments, as well as groups of consumers as
per monthly reporting.
All records are for inclusion in monthly reporting format for the same is described
separately.
4
Quality Assurance Framework for Mini-Grids, NREL, US DoE and Global
Leap (2016): https://www.nrel.gov/docs/fy17osti/67374.pdf
25
NEP Mini Grid Technical Specifications – v. January 2019
The Switches/Circuit Breakers /Connectors used must comply with IEC 60947 part I, II, III:
Low-voltage switchgear and control gear - ALL PARTS and EN 50521.
All the Junction Boxes /Enclosures for Inverters/Charge Controllers/Luminaries must have
ingress Protection of IP 54(for outdoor)/ IP 21(for indoor) as per IEC 60529: Degrees of
protection provided by enclosures (IP Code) standards.
SPD should be installed on both AC and DC side conforming to IEC 61643-11: Low-voltage
surge protective devices - Part 11: Surge protective devices connected to low-voltage power
systems - Requirements and test methods.
7.5.1.1 General
All external wiring, cabling, insulation material and junction boxes must be UV-resistant and
terminals protected against dust and moisture.
The wiring installation shall be both physically robust against bumping and tugging, and
electrically robust. All wiring and connectors should have a design lifetime of 20 years.
Double insulation (i.e. insulation comprising both basic and supplementary insulation, and
appropriate barriers and separation of parts must be applied to all systems with an open circuit
voltage of more than 120VDC Class II insulation on the DC part of PV system, even if less
than 120VDC is strongly recommended.
26
NEP Mini Grid Technical Specifications – v. January 2019
insulated cables or BS 6004/BS 6346. PVC insulated cables for working voltage up to and
including 1100 V and UV resistant for outdoor installation should be used wherever required.
PV1-F double-insulated cable UV resistant cable is to be used for high voltage DC PV arrays,
Flexible DC copper wiring of 4/6mm2 should use for inter-array cabling, up to
inverter/combiner box conforming to:
Relevant part of IEC 60332: Tests on electric and optical fiber cables under fire conditions,
IEC 60216-1: Electrical insulating materials - Thermal endurance properties
IEC 60811-403: Electric and optical fiber cables - Test methods for non-metallic materials -
IEC 61034 I, II: Measurement of smoke density of cables burning under defined conditions IEC
60754: Test on gases evolved during combustion of materials from cables
DC cable of appropriate size should be used for interconnecting all equipment at site including
but not limited to batteries, inverter, combiner box etc. to ensure AC and DC losses to less than
2% respectively. Calculations of the current rating of the cables should be according to IEC
60287: Electric cables - Calculation of the current rating
All wiring must be neatly done and secured by means of appropriate fasteners at regular
intervals.
Wiring lengths shall be sufficiently looped to allow ease of connection and disconnection in
the case of component replacement, and for maintenance.
Any wiring connections whether internal, external, high voltage or low voltage shall be inside
accessible junction boxes. No visible connections. The double insulation nature of the cables
shall be maintained.
Conductor lugs should be used to terminate all DC wiring. Lugs and connectors should be
crimped or soldered, and mechanically and electrically sound. No connections shall be made
using terminal blocks. DC connections shall be ferruled. All DC electrical connections to be
treated with corrosion inhibiting paste, substantially equivalent to DENSAL paste.
at each end. Cables crossing roads or driveways shall be protected by steel pipes buried in the
ground. Any underground cable interconnections shall be approved water-tight corrosion
resistant types.
In case of a welding structure, galvanization should be done after the fabrication work. All
aluminum shall be anodized any damage shall be treated. Any contact between unlike materials
shall be avoided by using insulation between any aluminum and galvanized sections. Any
surface damage to galvanizing shall be treated with approved cold-galvanizing treatments. Life
of the mounting structure to be 20 years.
The structure assembly shall accommodate such cable trucking and any array junction boxes
as may be required to meet the specification requirements for module interconnection in similar
corrosion resistant materials.
(a) Cleaning of PV panels: in the event where solar panels are mounted at a height where
a person cannot access safely for cleaning purpose, a gantry which can be permanently
fixed to ground or movable is required to include to the design.
(b) DC/AC Isolator, rated to suite the system should be installed between PV combiner
box and inverter. Suitable AC isolator is requiring after the inverter. They must follow
the appropriate standards mentioned above.
28
NEP Mini Grid Technical Specifications – v. January 2019
Notes
5
3
4
2
1
Note that the following methods are NOT considered acceptable in the corrosive salt
environment.
• Lugged cable between each module and array frame, with array frames providing earth
continuity: Combination of copper crimp lug, aluminum and zinc plated "tek" screws
are not acceptable
• Rely on metallic contact between module clamps and frames to provide earth contact,
with array structure providing earth continuity: Contact may be lost over time due to
corrosion
• Special earth clamps “bite” in to each module providing earth contact onto array
structure, with array structure providing earth continuity: Contact may be lost over time
due to corrosion
7.5.4 Distribution boards, bus-bar enclosures, switchgear and fuses
The general requirement for system configuration and enclosures is non-prescriptive. This
section elaborates on the various enclosures and switchgear recommendations.
29
NEP Mini Grid Technical Specifications – v. January 2019
All enclosures shall include standard din-rail mounting for breakers, isolators and meters.
Enclosures to be surface mount, with bottom cable entries, (with receptacle for module DC
connectors inlet and outlet) and gland seals. All unused slots to be blanked off to prevent access.
All external enclosures to be IP65. All DB’s and individual components within DB’s to be
clearly labeled. All external enclosures shall be made of corrosion resistant material.
Enclosures to be either dedicated either for AC or DC use. Mixed use enclosures are not
allowed unless there is clear physical separation between AC and DC compartments with
requisite labelling.
All junction boxes shall be rated to IP65 and Class II. Any junction boxes used externally shall
have bottom entry panel receptacles for string connector connections - glands/, and with drip
loop installed externally. They shall be located to facilitate inspections with sufficiently long
wiring loops internally.
7.5.4.2 Array DB
Usually located within the powerhouse, Array DB isolates high voltage DC-coupled arrays
from their respective DC MPPT charge controllers.
Array DB would also optionally isolate any AC-coupled DC arrays from grid tie inverter inputs,
if these inverters were located indoors. For array structure mounted grid-tie inverters this is not
necessary, or they would have in-built switch-gear.
7.5.4.3 DC DB / DC Busbar
DC Busbar Enclosure is required in systems with large battery banks and multiple parallel DC
coupled arrays and MPPT’s, and /or multiple parallel AC-DC battery chargers or parallel
DCAC inverters. The DC busbar provides safe and protected interface between the batteries
and these paralleled devices. The following are requirements for protection:
30
NEP Mini Grid Technical Specifications – v. January 2019
• Battery bank isolator for each battery bank, for both positive and negative poles and
negative. CB preferred, rated to maximum discharge capacity of battery or to enable
single battery bank to interface with all electronic devices. • Labelling of each
component as necessary • Safety covers.
All battery banks that are not physically inside the DC Busbar Enclosure shall have separate
battery fuses or circuit breakers on both positive and negative terminals, close to battery, to
protect against cable short circuits.
Each battery/cell shall be labelled with a unique number numbered from negative to positive.
Appropriate danger/caution signage shall be put in place, especially in the case of high voltage
banks (greater than 48Vdc).
7.5.4.5 Inverter AC DB
The inverter AC-CB is for paralleling of outputs of grid-tie inverters, and usually located inside
the powerhouse. The inverter AC DB shall normally contain the following
• AC over-current CB from each inverter, either 2 pole or 4 pole.
• Busbar of relevant rating and poles
• Outgoing overcurrent CB
7.5.4.6 Main AC DB or multi-cluster box
The purpose of this DB is to interconnect all AC connected devices. Typical inputs and outputs
include:
• Outgoing feeders to the load
• Feeder with CB from grid tie inverters (inverter AC DB)
• Feeders to each DC-AC inverter (off-grid inverters)
• Feeders with CB to each AC-DC charger (or bi-directional inverter charger
• Generator set change-over switch or interface panel, allowing parallel diesel generator
operation with inverter/chargers, or complete change-over to generator supply only to
load.
• Relevant lighting protection devices
• Metering and logging devices for power generation side.
31
NEP Mini Grid Technical Specifications – v. January 2019
practical direct route downwards that directs the cable away from sensitive electronic
equipment and shall not enter the building. In cases where the array structure is separate from
a metal roof, insulated stranded copper earth wire is connected to both the array and the roof
structure and terminated at the same earth electrode. The maximum allowable earth cable
resistance between array frame and earth electrode shall be 1.7 Ohms. See earth electrode for
its requirements.
System electrical grounding shall only occur on the AC side of a system, where the AC neutral
conductor is connected to the consumer earth conductor, at one and only location on the site
only. This would usually be within the Main AC DB or Multi-cluster. This requires an AC
side N-PE bridge, and is not negotiable! It shall be clearly labelled and also marked on SLD.
The maximum allowable earth fault impedance (Ze) between consumer and earth terminal to
earth electrode shall be 1.7 Ohms and shall use able of same size as the main conductors. See
earth electrode for its requirements.
• Virtually earthing bond is allowed only via AC side in one location, if particular equipment
is not galvanically isolated from AC side (i.e. certain transformer less Grid tie inverters).
This shall be clearly marked on SLD if relevant, and in the equipment.
32
NEP Mini Grid Technical Specifications – v. January 2019
The maximum earth electrode earth impedance target is 5 ohms on a dry day each electrode.
This figure is sufficient to fulfill functions of (i) array lightning surge earth path, (ii) system
bonding earth path and equipment protection, and (iii) system electrical earth if required, for
the entire system.
In sites with high earth contract resistances, then the following additional steps shall be taken
towards this target:
• All underground cables AC or DC cables: Class 2 protection at power house incomer JB,
on all conductors plus N, direct to earth electrode. In general, avoid underground cables
and use cable trays to keep cables above ground-induced surges.
• Class 2 protection lightning surge arrestors with visual fault indication, 40kA (8/20)
according to IEC 61643-1 for sensitive electronics, clamping voltage to less than 1,500V.
33
NEP Mini Grid Technical Specifications – v. January 2019
• Class 1 and 2 combined protection may be installed later if required for sites with direct
strike risk.
Note: For solar PV plant, it is generally advisable to install no lighting conductors on site or
near the site, to avoid bringing surges towards the site and to electronics. Lightning should be
rather directed away from the site.
34
NEP Mini Grid Technical Specifications – v. January 2019
Each category has number of turbine types. The site specific Head (Hn) and flowrate (Q) will
determine the suitable turbine type. Typically micro / mini hydropower projects implemented
under NEP will be owned and operated by the village community, therefore relatively simple
designs that rely on manual control and operation are more likely to ensure long term
sustainability of the project.
Minimum runaway speed of the turbine should be 1.8-time of the rated speed. It should be able
to operate at least 2 hours at this speed without mechanical failure.
The Main valve should be slow closing (operated via a gearbox if required) gate or butterfly
valve with a pressure rating exceeding the total pressure of system including a a satisfactory
safety factor. A bypass valve of (1.5”-2”) is required in parallel with the main valve to equalize
pressure on both sides to ensure easy opening.
35
NEP Mini Grid Technical Specifications – v. January 2019
Each category has number of turbine types. Head and flowrate will determine the suitable
turbine type. In NEP mini grid mini-grid projects, village community will ultimately owns and
will operate the project and hence manual or semi-automatic; less complicated designs will
ensure long term sustainability of the project.
Minimum runaway speed of the turbine should be 1.8-time of the rated speed. It should be able
to operate at least 2 hours in this speed without a mechanical failure.
8.1.6 Manifold
Manifold (which takes water from penstock and carries to the runner) and/or branch pipes must
maintain maximum velocity of 3 m/s in order to reduce the head loss due to pipe friction and
local losses.
Main valve should be slow closing (can be with a gearbox in some instances) gate or butterfly
valve with pressure rating satisfying total pressure of system. Bypass valve of (1.5”-2”) is
requires in parallel with the main valve to equalize pressure on both sides to ensure
effortlessness opening.
36
NEP Mini Grid Technical Specifications – v. January 2019
Where axial force is present, (e.g. turgo turbines or turbines with vertical shaft), angular contact
bearing or tapered bearing should be selected.
37
NEP Mini Grid Technical Specifications – v. January 2019
In configurations where the turbine is coupled directly to the alternator, a flexible coupling is
required. Taper lock couplings are easy to maintain and therefore preferred, however, not
mandatory. Couplings should be statically and dynamically balanced.
Guards: in case of belt drive system or direct coupling system, protection guards made of steel,
firmly fixed to the base frame or ground is a mandatory requirement.
All valves used in branch pipes used in Pelton turbines should be flanged typed gate valves or
spear valves. In case spear valves or in crossflow turbine guide vane mechanisms a hole for
38
NEP Mini Grid Technical Specifications – v. January 2019
cleaning and inspection should be provided to enable easy removal of debris without the need
to dismantle the entire turbine. Depending on the governing mechanism selected, these branch
valves can be operated manually or automatically.
Capacitor banks in this system should have an over current device (usually MCB) to disconnect
the excitation capacitor bank and stop the generation of excessive voltage and damage to the
alternator in the case of turbine overspeed / runaway speed.
Synchronous alternators with brushless excitation can be used for all the mini hydro projects
irrespective of capacity. The systems can either be controlled electronically using an Electronic
Load Controller (ELC) or with a more sophisticated flow control device. Flow control devises
are normally only viable for larger sized projects in excess of 50kW.
(For both IGC and ELC controlled schemes, a reliable ballast tank to absorb any excess power
is mandatory. Over/under voltage protection must also be included as function of the IGC or
ELC. Ballast tanks should be fitted with an overload protection (usually a bank of appropriately
rated MCBs).
Ballast tanks can be water or air and should be able to dissipate 100% plant capacity continually
(for example under full load rejection condition).
Flexible cables fulfilling BS 6004 and BS 6346 should be used for NEP mini grid projects. All
cables should be laid as per standards specified in clause 3.3 here. Maximum voltage of all
wires/ cables should be 600V.
Log books, Operations and Training manuals are to be provided and training is to be conducted
by the developer before commissioning of the project. One copy of these documents is to be
handed over to NEP PMO and DRD township office as per the agreement signed with DRD.
39
NEP Mini Grid Technical Specifications – v. January 2019
• Combustion based Rankine system: The combustion-based systems are most versatile and
can utilize all kinds of biomass resources including wastes. Biomass is fired in a boiler to
produce steam and the same is used in steam turbine for generation of power.
• Gasification and gas engine-based system: Biomass gasification is the process of partial
combustion of biomass under controlled air supply, thus producing a mixture of gases
generally called as producer gas which can be burnt in an engine to generate electricity.
Unlike Solar or hydro, vast number of technology configuration can be available in this sector
and NEP mini-grid developers are expected to use the latest technologies to ensure optimal
conversion.
Management of continuous energy supply and catering to low demand periods (like late night
street light illumination) are major challenges for such system and thus require innovative ideas.
No detailed specifications are outlined here due to the novelty of the sectors but developer is
expected to follow standards from International Finance Corporation (IFC). The IFC standards
should be satisfied for designing and operation of biomass projects under NEP assistance.
• IFC/World Bank: Environmental Health and Safety General Guidelines; 30 April 2007
40
NEP Mini Grid Technical Specifications – v. January 2019
In general, the size of the plant, extent of demand and distance to the load points will decide
whether medium voltage (MV) transmission line is feasible or not. In all cases losses are to be
fully considered.
In case of MV distribution line, 11m poles complying to ESE standards and an outdoor ONAN
hermetically sealed transformer; satisfying the IEC60076 specifications must be used.
41
NEP Mini Grid Technical Specifications – v. January 2019
2. Planting of poles next to roads or streets shall comply with the specifications of
the responsible road’s authority.
3. LV, MV and street lighting (i.e. electrical services) shall not share a pole with
telephone services.
4. Care must be taken so that the required clearances are adhered to as given in this
document.
10.2.4 Distribution line diagram:
NEP mini-grid proposal requires the developer to include a distribution line drawing (sketch)
with following details:
The spacing of poles shall be as indicated on the layout drawings. Distance of each segment of
line, conductor type and conductor size and number of conductors in each segment, location of
load points with load details, position of lightening arrestors, positions of poles and
disconnector poles (poles with jumpers), position of street lights and poles with cluster load
breakers and Residual Current Devises (RCD).
A table showing voltages and voltage drops i.e. distribution network Voltage Regulation
should be include with the proposal.
42
NEP Mini Grid Technical Specifications – v. January 2019
IEC 62420: Concentric lay stranded overhead electrical conductors containing one or
more gap(s)
IEC TR 61597: Overhead electrical conductors - Calculation methods for stranded
bare conductors
IEC 61395: Overhead electrical conductors - Creep test procedures for stranded
conductors
10.2.8 Types of distribution line conductor:
Bare conductors, Insulated conductors and Bundle conductors (insulated and bundled together)
can be used for the mini-grid transmission/ distributing lines but insulated conductor is
preferred due to safety concerns and less maintenance requirement. Additional safety in terms
of lightening protection (spark gap type; described in section 7.2.9) is required if bare
conductors are used. Service cables needs to insulated with additional protection sheath.
43
NEP Mini Grid Technical Specifications – v. January 2019
10.2.11 Insulators:
Nylon or ceramic bobbing insulators (larger: 96 mm diameter) and (small: 46mm diameter) are
to be used for all feeders and service line, in case of bare conductors.
For insulated conductors, nylon or ceramic bobbing insulators or suspension clamps (for
straight line section), small angles suspensions/ large angle suspensions (for bends) are to be
used. If nylon or ceramic bobbing insulators are used for insulation conductors, insulated wire
should be used for binding the cable to the insulator. All the accessories used should be
accredited to ESE requirement or international standards IEC 1109.
10.2.12Stay assembly
Stay support using stay assembly is required on first and last pole of feeder along with any pole
with distribution line bend of above 50. Stay assembly will include stay rod, plate, thimbles
and stay brackets and should be made with galvanized steel with a thickness of 80 um. It should
be accredited to ESE specifications or follow international standards.
Flexible wires 1/0.044 of brown color code (for phase) and blue color (for neutral) and a green
color earth wires of 1 mm2 should be used for house wiring. All wiring should be done inside
conduits, with a minimum of 20mm diameter; fixed firmly with brackets with maximum
spacing of 450 mm.
44
NEP Mini Grid Technical Specifications – v. January 2019
It must be capable of having progressive block-rate tariffs (increasing tariffs for increasing
consumption) or allow for variable pricing. It is not compulsory to have GSM (mobile data)
connection for operation and/or data logging but the same encouraged.
Position of energy meters: Energy meter is expected to be installed inside the house (or other
load point) but if it is installed in the service pole due to any reason, interface with display
should be given to each load points to see the above minimum information on their electricity
usage and to facilitate the recharging, if applicable.
The meters must have Class 1.0 accuracy and conform to IEC 62053-21, IEC 62052-11, EN
50470.
Note: All equipment used in mini-grids projects must meet required national standards
wherever available or, in the absence of the same, IEC standards mentioned in this document
or other similar document released by DRD. The equipment may follow another equivalent
standard such as BS, EN, DIN, ASTM or Australian etc.
For cost reason, mini-grids may consider following either TN-C-S or TT systems (2 conductor
for single phase, 4 conductors for 3 phase). Both these options require N-PEN bond at the
powerhouse. At consumer side, both require 3 cable wring in the household. TN-C-S is more
cost effective as it does not require an additional earth electrode at each consumer.
As a default condition, the developer should apply the prevailing earthing standards as set out
by ESE where such standards exist.
45
NEP Mini Grid Technical Specifications – v. January 2019
11.1 Documentation
• Single Line Diagram (SLD)
• Engineer sign-off
• User manual
• Operational manual
• ToC of each
11.2 Labelling SLD and equipment
All electrical components labels describing their function in English and Myanmar language.
• Quality
• Correspondence
• Circuit breakers and equipment
11.3 Signage and safety equipment
Illustrated Warning signs in Myanmar language should be fixed every place it poses a threat
for operators and users.
46
NEP Mini Grid Technical Specifications – v. January 2019
11.4 Warranties
Equipment supplied and installed originally at site with warranty details.
47
NEP Mini Grid Technical Specifications – v. September 2018
Annexure 1
48
NEP Mini Grid Technical Specifications – v. September 2018
Annexure 2
49
NEP Mini Grid Technical Specifications – v. September 2018
Annexure 3
50