Mangan Report
Mangan Report
Mangan Report
Steve Mangan
Corbett & Co
International
Users’ Conference,
Construction Lawyers,
London
There are new definitions, terminology and upgrade a project’s facilities. Get that right, he
approaches not found in other books within the argued, and the rest will follow easily.
FIDIC ‘rainbow suite’. October 2011 also saw the publication of the
Gold Book clauses concerning risk, insurance first edition of the subcontract intended for use
and force majeure, for example, were new. Force with the FIDIC 1999 Red Book. Siobhan Fahey
majeure is dealt with by a new clause dealing with of the drafting task group gave a presentation of
exceptional risk. Unlike the existing Yellow the new subcontract following feedback on the
Book, the Gold Book has a standing Dispute test edition released in 2009.
Adjudication Board (DAB). It has also softened The subcontract is intended to be used ‘back
the 28-day time bar for contractors’ claims to back’ with the 1999 Red Book, which it
notices by providing for the DAB to permit late incorporates by reference. There are important
submission where it is fair and reasonable to do differences, however, if the main contract is in
so. Sub-Clause 20.5 permits the parties by the MDB form. The subcontract is drafted with
agreement to request informal assistance from flexibility in mind and is appropriate for
the DAB in resolving any disagreement between subcontracts both large and small. There are
them – an important dispute avoidance facility. numerous alternative clauses for the parties to
An interim binding decision of the DAB may consider using, dealing with, for example,
also now be enforced, closing the ‘gap’ that has taking over of the subcontract works and issue
been the subject of much recent debate in the of the performance certificate. Extensive
industry (see below). guidance notes are provided within the
We therefore expect to see a similar ‘Gold document. Unless an alternative is required for
Book approach’ in the forthcoming new edition countries where such clauses are unenforceable,
of the Yellow Book. the default payment position is
The Gold Book has been ‘pay-when-paid’ and not ‘pay-if-
followed in 2011 by publication of ‘We expect to see paid’. Generally, the subcontract
its own guide – the FIDIC DBO a “Gold Book adopts the same balanced
Contract Guide. Michael approach to risk allocation as is
Mortimer-Hawkins, its principal approach” in the found in the Red Book main
author, spoke to the Conference
on the thinking behind this
forthcoming new contract and other FIDIC 1999
rainbow contracts.
document and on the Gold Book edition of the Of particular interest is the
itself. As well as providing its clause- disputes resolution clause. Chris
by-clause commentary, the Guide Yellow Book.’ Seppälä gave a presentation of the
sets out to inform readers of why three alternative options. These
the wording and provisions of the contract are may result in a very complex procedure for the
as they are. Although it has no contractual resolution of subcontract disputes given the
weight, users of the Guide say they find the back-to-back nature of the subcontract and
guidance particularly helpful and that it does main contract obligations and therefore the
avoid disputes. potential for related disputes to arise on a
As to the new editions of the Red and Silver project. The simplest option involves no
Books, these will be released in 2013, subcontract DAB and direct recourse to ICC
appropriately enough coinciding with the 100th arbitration if disputes cannot be resolved
anniversary of FIDIC itself. amicably within a 56-day timetable. The main
FIDIC has also appointed a task group to contractor may, however, require the
consider the introduction of a ‘brownfield’ subcontractor to attend and provide information
(Operate, Design & Build (ODB)) form of in an upstream dispute with the employer.
contract. With this in mind, Andrew Brickell, A second option requires an ad hoc
Director of Project Management MWH New subcontract DAB and if the dispute between
Zealand Ltd, gave an interesting presentation of subcontractor and main contractor involves a
his experience in the preparation and use of main contract issue, the main contractor must
bespoke brownfield ODB contracts in New notify the subcontractor and refer that dispute
Zealand. He recommended that, instead of first to the main contract DAB. The
FIDIC rewriting the Gold Book, a simpler and subcontractor is not bound by the result or by
more helpful approach might be to focus on any later arbitral award.
producing an enhanced operation and A third complex option binds the
maintenance contract, useable whether or not subcontractor to a related decision of the
any future capital works would be required to DAB and any arbitral award under the main
viewed instead as a project management tool the decision remains binding only and not
that ultimately leads to lower project costs and final and binding. If a party then fails to
higher quality infrastructure. At least one comply with that decision, the Red, Yellow
speaker expressed the wish to see FIDIC engage and Silver Books do not expressly permit an
with the EU on the point. aggrieved party to enforce the decision by
Evgeni Smirnov of the European Bank for referring the failure to arbitration, as it may
Reconstruction and Development (EBRD) was do under Sub-Clause 20.7 of the Red Book in
able to offer the Conference some good news the case of a final and binding decision.
on this front. He said that the EBRD is very There have, however, been a couple of
much in favour of standing DABs, and sees the examples where such binding DAB decisions
ad hoc DAB as the fall-back option when dispute have been enforced. There is, however, no
resolution is being considered. uniform ‘international’ policy on this issue.
Conference consensus therefore favoured There was continued discussion of the
leaving the FIDIC standard forms unamended ‘gap’ at the Conference. Nael Bunni advised
wherever possible. ‘If it ain’t broke, don’t fix it!’, that it had never been FIDIC’s intention to
they say! create a situation where the decision of a
DAB could simply be ignored. Compliance
was assumed and expected of the parties,
Developments and challenges of DABs
failing which, enforcement should be
The Conference heard from a panel of experienced available in the form of an arbitral award.
DAB members regarding recent developments The gap had now been closed by Sub-Clause
and challenges of DABs. Members included 20.9 of the new Gold Book. All DAB decisions
Nael Bunni, Nick were now
Henchie, Peter ‘There are now moves to try and enforceable and
Chapman and this policy should
David Loosemore. convince the EU that, instead be continued by
Nick Henchie the drafting task
expressed a strong
of simply seeing the DAB as an groups in their
note of caution unnecessary additional project preparation of
regarding the forthcoming
effectiveness of cost, it should be viewed instead editions of the
DABs. A DAB is as a project management tool that FIDIC contracts,
required actually to he said. In the
make a decision and ultimately leads to lower project costs meantime, he
thereby resolve the thought FIDIC
dispute before it. In
and higher quality infrastructure.’ should publish an
his experience, all errata sheet for
too often the board wrongly saw itself as a other contracts introducing both the Gold
Dispute Review Board with a dispute avoidance Book’s Sub-Clause 20.5 dispute avoidance
mission that paid little heed to the contract. As a facility and Sub-Clause 20.9 regarding
result, he considered that DABs only created enforcement. Alternatively, the parties could
further disputes rather than resolved them. themselves amend, for example, the Red
Nael Bunni reminded delegates that Sub- Book’s Sub-Clause 20.7 by replacing it with
Clause 20.2 of the Red Book has always contained the wording of Sub-Clause 20.9 of the new
a facility whereby the parties could jointly Gold Book.
approach the DAB and request its opinion on a The Conference also debated the motion that
matter. In his experience parties often did not the Silver Book was the 1999 form best suited to
often take advantage of this very valuable dispute design-build projects. Despite the best efforts of
avoidance service. It was a facility now given the proposers, the motion was soundly defeated.
more prominence by its own dedicated Sub- All in all, the 180 delegates, the content of the
Clause 20.5 of new Gold Book. Conference and the lively discussion from the
The pages of CLInt, the International floor show that the FIDIC project is in robust
Construction Law Review and other industry good health.
publications have seen much discussion
recently of the ‘gap’ in the enforceability of
Steve Mangan is a Director of Corbett & Co International
DAB decisions. Where notice of dissatisfaction
Construction Lawyers Ltd in London.
has been given following a DAB’s decision,