TECHNICAL PROPOSAL

FOR
SEWAGE TREATMENT PLANT

BASED ON

MBBR TECHNOLOGY

PRODUCT 20 KLD STP BASED ON MBBR TECHNOLOY UPGREATION


PROJECT M/c GMCPL Nimrani
Kind Attn. Mr. Sunil Patel Sir

BY:
SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION

SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ
SE-MP-215
Aug. 19, 2021

Dear Sir,
This refers to the visit and discussion at your site regarding Sewage Treatment Plant, Based on
the discussion please find below our offer for same.

STP UPGFRE ATION ON MBBR TECHNOLOGY


CAPACITY – 20 KLD (CIVIL)
This includes following annexure:

ANNEXURE – I DESIGN BASIS

ANNEXURE – II TREATMENT PHILOSOPHY & PROCESS DETAILS

ANNEXURE – III BLOCK DIAGRAM

ANNEXURE – IV TECHNICAL DETAIL & SCOPE OF SUPPLY

ANNEXURE – V SCHEDULE OF EXCLUSION

ANNEXURE – VI PRICE AND COMMERCIAL TERMS

Thanking you,
For SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Sapna Tomar
Operation Manager
GSM - 8643008895

SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ
ANNEXURE – I

DESIGN BASIS
Nature of wastewater: Combined Sewage
Design Capacity 20 m3 per day

Sewage Characteristics Inlet Outlet

BOD (ppm) <300 <30

COD (ppm) <600 <150

TSS (ppm) <150 < 30

Oil and Grease < 10 <5

PH 6.5 - 8.5
Note: Treated water quality is subject to inlet raw sewage parameters. Any change in inlet
parameters will change treated sewage quality accordingly.
*Mode of disposal of treated water:- Recycling in irrigation, flushing, horticulture, landscaping, etc.

ANNEXURE - II

TREATMENT PHILOSHPHY & PROCESS DETAILS

Bar Screen: The Bar Screen of MSEP material is considered in the scope for better life. Bar screen of 10 mm
spacing is considered. The screen can be easily removed & cleaned as required.

Oil & Grease Removal: We have proposed manually cleaned oil & grease trap with baffle arrangement for
removal of oil & grease coming from kitchen/cafeteria for better & smell free biological process.

Equalization Tank: We have proposed collection cum equalization tank in RCC below the ground level. All
other tanks of STP in RCC can be built fully/partly above the ground as required. The tanks can be covered
from the top, if required and access manholes can be provided. The tank is provided with air distribution
piping with adequate number of Coarse Bubble diffusers.

MBBR Reactor: Aeration is provided through air blowers for decomposition of organic compounds in
presence of aerobic bacteria.

Settlement Phase
Immediately after the aeration, settlement/clarification occurs. Once aeration has stopped, the sludge
settles. The conditions in the basin become anoxic. Further carbonaceous oxidation and denitrification occur
during this phase.
Carbonaceous oxidation and denitrification continue to occur during this phase. Surplus sludge is wasted to
the sludge thickener during this phase. This is accomplished using desludge pump with proper flow control.
SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ
Media Filtration & Carbon Filtration System: The clarified & chlorinated water is pumped to Media Filter
followed by Carbon Filter to further polish the treated effluent. The Sand filter removes the suspended solids
and the Carbon Filter removes color & odor.

ANNEXURE - III

BLOCK DIAGRAM

Raw effluent Incoming from various points

Bar Screen
Separation of physical
Impurities

Oil & Grease Remove Oil & grease contain

Equalization Tank
Mixing Of Sludge and Water
To form Slurry

MBBR Nitrogen fixation, COD &


BOD Reduction, Clarification

Settling Tank Sludge Sedimentation

Multi Grade Sand


Filter Reduction in Suspended solids from 25
ppm to < 5ppm

Reduction in Color, Odor & De-


Activated Carbon
Chlorination
Filter

Treated water Tank

SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ
ANNEXURE – IV
SUMMARY OF SUPPLY :-

S. No. DESCRIPTION Qty.


1 Air Blowers 2 nos.(1W+1S)
2 Air Diffusion Grid with Diffusers for Aeration Tank 1 lot.
3 Pressure Sand Filter Media Replace 1 lot
4 Activated Carbon Filter Media Replace 1 lot
5 Electric panel 1 no.
6 Pipe fitting 1 lot

TERMINATION POINTS:
 From the inlet of Sewage Feed Pumps
 From the backwash line of MGF
 From the outlet & Back wash of Activated carbon filter

Civil Items which have to be in Scope of Client

S. No. Description Qty. Size


Bar screen cum oil skimmer chamber 1.5 m3 RCC – By Client
1.
Equalization/Collection Tank 10.0 m3 RCC – By Client
3.
MBBR Tank 7.0 m3 RCC – By Client
4.
Settling Tank 7.0 m3 RCC – By Client
5.
Filter Feed Tank 5.0 m3 RCC – By Client
6.

ANNEXURE - V

SCHEDULE OF EXCLUSIONS OR CLIENTS SCOPE:


 All Civil work.
 Treated water tank.
 Earthing, Power connection up to panel.
 All civil work including drains, drain sump, neutralization sump, supports of all
types, platforms, drain channel. We shall provide load data.
 Laboratory facilities including necessary instruments, chemicals and staff.
 Lubricants, oils, grease wherever required including the first charge.

SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ
 Relevant connections from termination points given in our offer.
 Unloading and protection/security of material.
 Scope of supply and services not specifically mentioned as forming a part of
our offer.

ANNEXURE - VI
PRICE & COMMERCIAL TERMS
Basic Price: Rs. 2,20,000/- (Two lac Twenty thousand only)
Freight : Extra at actual.
Payment : 40% advance along with order,
: 50% against Performa invoice before dispatch of material,
: 10% at time of Installation,
Taxes : @ 18% GST Extra.
Delivery : The plant would be dispatched within 3-4 weeks from date of P.O.
Guaranty : one year against manufacturing defects.

Validity : our offer is valid for a period of 30 days from the date of this proposal and is subject to variation thereafter.

Thanking you,
For SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Sapna Tomar
OperationManager
GSM - 8643008895

SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ
SHIBU ENTERPRISES
TOTAL WATER & WASTE WATER SOLUTION
Office Add.- 7, Gokul Nagar, Indore (M.P.)
e-mail. Shibuenterprises0@gmail.com
contact no. +91-8223886598, 8643008895
GST No. 23EPNPK8767Q1ZQ

You might also like