Internship Report FINAL

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 22

RIFT VALLEY UNIVERSITY

Labu Lafto Compose


Department of Construction Technology and Management

Hosting Company: MCG Construction plc

Final Internship Report


Internship duration (March- June) 2023 G,C

Nam Of Instructor MATIAS A.


Nam of Hosting Company

MCG Construction
plc
Name of student

Kebede Challa
ID No

0065/18

DATE OF SUBMISSION: 08/07/2023 G.C

ADDIS ABABA, ETHIOPIA

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
Acknowledgement
First and foremost, I would like to thank the almighty GOD for giving me all the things I
deserved in my lives. I would like to thank university of Rift Valley University Labu Lafto
Campus, department of construction technology and management for giving me the
chance to have experience on the practical work and better skills with theoretical knowledge
on this internship program, I would like to give my sincere thanks for my academic advisor
Instructor Matias for his valuable advice. I am thankful to all the people within MCG
CONSTRUCTION PLC, but most of all to my supervisors for giving me kind guidance, gentle
supervision and encouragement throughout my internship period. The success and
accomplishment of this report stems from the efforts and dedication offered by MCG
construction staff members, whose support was either direct or indirect during my internship.
I thank all of them.

Executive summary
This report is a report about the internship experience that I have under taken during the last
months. In this report I have tried to list the overall aspects of the internship experience. I
have briefly summarized what is expected in the next chapters in this report. This report
includes the overall of my internship program categorized into four main chapters. The first
chapter discuss the background of the hosting company including its brief history, its main
products or services, its main customers or end users, its overall organization and work flow
as well as its vision, mission, core value, goals and strategic direction.in the second chapter I
have tried to give a brief review of structural elements of a building and the steps we have
followed to construct these structures, challenges we have faced while performing my tasks
and measures taken to overcome this challenges. The third chapter includes my project that
I have done at Addis Ababa Small and Medium Industry Cluster project includes overall
benefits I have gained in the program followed by a chapter of conclusion and personal
recommendation.

LIST OF ACRONYMS

PLC…………….….… private limited company

GC ………………………. General Contractors

BOQ……………………… Bill of Quantity

PPC……………………… Portland Pozzolana Cement

OPC……………….……. Ordinary Portland cement

i
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
LIST OF TABLEY Table

Project Holdings................................................................................................3

LIST OF FIGURES

Figure 1 Organizational Chart..........................................................................4


Figure 2 Project work flow chart………............................................................6
Figure 3 AASMIC Mega Project Progress……………………………..............................7
Figure 4 AASMIC Mega Project Progress…............................................................8
Figure 5 AASMIC Mega Project Progress................................................................8
Figure 6 Gada Especial Economic Zone Project on Progress………………...................9
Figure 7 Gada Especial Economic Zone Project on Progress…..................................9
Figure 8 Shop Drawing of Borana University Project on.............................................10
Figure 9 Shop Drawing of Borana University Project on.............................................10
Figure 10 Shop Drawing of Borana University Project on…........................................10
Figure 11 My Site Visit Report @Borana University Project Identifying gaps……..……….11

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
ii
Table of Contents
Acknowledgement .............................................................................................................i
Executive summary ...........................................................................................................i
List of Acronyms...............................................................................................................i
List of figures .....................................................................................................................ii
List of tables .......................................................................................................................ii

CHAPRER ONE............................................................................................................... 1

1, Background of the Company……… .............................................................................. 1


1.1, Company profile ......................................................................................................... 1
1.2, Vision .......................................................................................................................... 1
1.3, Mission........................................................................................................................ 1
1.4 Values of the company ................................................................................................ 2
1.5 Objective of the company ............................................................................................ 2
1.6 Ongoing Projects (holding project) .............................................................................. 3
1.7 Accomplished Projects....................................................................................... 3
1.8 Organizational structure .............................................................................................. 4

CHAPTER TWO................................................................................................................ 5

2. Overall Internship Experience………............................................................................ 5


2.1 Work flows of the Projects...........................................................................................6
2.2 Work task I have been executing & Procedures I followed .........................................7
2.3 Construction prosses on the projects.....................................................................11
2.4 Challenges I have been facing during performing my work task ................................12

CHAPTER THREE ........................................................................................................ 12


3. Overall Benefits of the internship Program ................................................................. 12 .

3.1 In terms of improving practical knowledge………………………………………...……13

3.2 In terms of improving industrial problem-solving capability …….…………………….………14


3.3 In terms of upgrading our theoretical knowledge …………………….…..……14
3.4 Team playing skills acquired …………………………………………….………14
3.5 Leadership Skills Acquired ………………………………………………………15
3.6 The benefits acquired in terms of understanding work Ethics……….....…....15
3.7 The benefits I acquired in terms of entrepreneurship……………….…..…….16
3.8 Interpersonal communication skills………………………………….……….….16

CHAPTER FOUR………………………………………………………………………17

4.1 Conclusion …………………………………………………………………………17

4.2 Recommendation………………………………………………………………….18

4.2 Reference ..................................................................................................................18

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023 iii
CHAPTER ONE
1 BACKGROUND OF THE COMPANY

1.1 Company profile


The company (MCG Construction plc) was first established in August 2013
G.C. as Class 5 General Contractor and has been showing diligence and
dedication as a prime contractor in executing construction of various building,
road & water supply projects since its establishment. In December 2017 G.C.,
the company advanced itself to Grade 1 General Contractor in order to comply
with the ever-growing construction industry of the country. The company is
registered under Ethiopian law. The owner of the company is JAGAMA KANANI who is
the owner and director of the company. Ever since its establishment accomplished
different construction works estimated at tenth of billions of Birrs for the federal
government, regional governments of Ethiopia. MCG construction is a category GC-I
general contractor. General Contractors who are qualified to undertake a variety of
construction work such as building, roads railways bridges, airports, dams, water
works… etc. MCG Construction has the skill, the potential and the experience to
construct.
 Roads
 Industry
 High rising buildings
 Water works and power locally and internationally.

1.2 Vision
To be a world class construction company which could undertake any kind of
construction works in Ethiopia and internationally. To become one of the strongest,
reliable and competitive contractors in the country transforming the nation integrated
application of skills, labor and opportunities in area of construction industries.

1.3 Mission
 To participate on the countries social-economic development without reservation
by delivering ethical, reliable and quality construction service in a timely and cost-
effective manner there by giving maximum satisfaction for all stokeholds. MCG
construction PLC is fully committed to establish ISO based quality and
environmental management system and conduct all activities in conformity with
established international standards and legal requirements so as to:
 Achieve maximum customer satisfaction;
 Become the industry leader in delivering quality, timely and cost-effective
construction
Service;
 Ensure continual improvement of the service, the process and the management
system;
 Create environmentally friendly working condition by reducing and gradually
eliminating
 Activities a waste having adverse effect on the environment and thus contribute
its shave in the global towards combating environmental degradation;

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023 Page-1
 Ensure the safety and security of the company employees and project
neighborhoods by
Creating a working environment which is free from danger and professional
hazards;
 Ensure that the quality and environmental objectives set by the company are met.

1.4 Values of the company

MCG Construction plc. Have the following values


 Team work
 Competent
 Innovative
 Reliability
 Qualitative
 Flexibility
 Honest and integrity
1.5 Objective of the company
A. To ensure that 95% the projects executed by the company and accomplished with in
the contract time.
B. To ensure that all non-recyclable and non-disposable (by selling) wastes are
disposed without causing adverse effect to the environment.
C. To assess our customer satisfaction level once per year to ensure continual
improvement of the service and delivery performance.
D. To build the capacity of our employees through training at demand
E. On quality and environmental management and on other training identifying
according to competence check list.

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023 Page-2
Projects Under Going (Holding Projects)
MCG Construction private limited company as explained before focuses mainly on
conducting construction of building and roads. Some of the project listed below in the
table.

No Name of the project Location Clients


1 Addis Ababa Small and Medium Industry Addis Ababa Mega Project
Cluster (Mega Project)

2 Gada Especial Economic Zone (Mega Project) East Shagar Zone Gada
Especial
Economic
Zone

3 Charati Road Project Somale Reginal State ERA

4 Waldahane Road Project Southern Reginal State ERA

5 Borana University Infrastructure Project Ya’abalo Borana


University

6 Federal Customs Office and Residencia Moyale Federal


Project Customs

7 Galan Mental Rehabilitation Hospital Project Galan-Shagar City

8 Negelle Borana Road Project Negelle Borana ORA

9 Olenchiti Rural Transformation Center (Industry Olenchiti OIP


park)

10 Ambo University Ambo


University

11 Adama Cultural Center Complex Project Adama City Adama City


Administration

Table 1. holding projects


1.7 Accomplished Projects
As explained the previous table, the company has many customers list as the following:
 Edi-Sololo Road Construction project ……. (ORA) Borana Zone
 Teltelle Road Construction project ……. (ORA) Borana Zone
 Negelle Borana Road Construction project ……... (ORA) Borana Zone
 Mizan Tepi University Project ………… (Ministry of Education)
 Meki Rural Transformation Center project …… (Oromia Industry park) Meki Town
 Jima National Pallas Renovation Project………... (National Pallas) Jima City
 Addis Ababa National Pallas Renovation Project………. (National Pallas) Addis Ababa
City
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
Page-3
1.8 Organizational structure
The man power of the construction can be ground to two major area different as
technical expert and support staffs. The technical expert has direct relative with the
overall construction activity of the construction. Therefore, the construction owned and
hired qualified expert of various describe line including civil Engineering sanitary
engineers, electrical, extra which posse different level of education ranging from
Diploma to second degree. At present, the company employs many professionals as
shown in table. These professionals are involved in different civil work activities where
they proved their competence in the field before and after joining our company, the
variety of exposure and back ground of these technical crews enables the company to
handle wide scope of construction project.

General
Manager

Deputy G/Manager Legal General


Construction Service Auditor

Finance Supply Plant & Equip. Property Human


Operation
Manager Manager Manager Manager Resource
Manager

Purchasers
Drivers Store
Contract Personnel
Accountants Keepers
Administration
Machinery
Cashers Operators Stock General
Planning
Control Service
Division
Mechanics
Project
Coordinators

Project
Managers Figure 1. 1 organizational structure
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023

Page-4
CHAPTER TWO
2.1 OVERALL INTERNSHIP EXPERIENCE
In this report I have tried to show all activities that I have experienced during my
internship period in the hosting company, MCG construction plc. And all the activities
which I have experienced during my internship regarding to the process are presented
below and I have tried to summarize all the training I got.
Section of the Company I have been working In MCG construction plc, I have been
working in different sections of the company both in the

 Office work

page-5

2.2 Work flows of the Projects

The work flow of the site seems like this:

Project Manager

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
Construction Project HR
Office Engineer Project Finance
Engineer Administration

Quantity
Personnel
Surveyors Surveyors Accountant

Time Keepers
Data Collectors
Site Engineers
Casher

Purchaser

Project Equipment
Administrator Gard’s
Forman’s

Drivers
Skilled Gang
Laborer’s Chiefs
Operators

Daily Mechanics
Helpers Laborer’s
Figure 1. 2 Project work flow chart

2.3 Work task I have been executing & Procedures I followed Page-6

2.3.1 Office work

The main task of the Section under which I have been working is Project
coordinating.
 Design review
 Preparation of shop drawings
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
 Identifying gaps on design, BOQ and specification
 Resource allocation
 Payments follow-up
 Materials approval processing
 Progress follow-up of project crew

During my Internship placement I have been assigned to perform above summarized


activities regarding under mentioned projects.

1) Addis Ababa Small and Medium Industry Cluster (Mega Project)


2) Gada Especial Economic Zone (Mega Project)
3) Borana University Infrastructure Project
The first project is a construction of four buildings with Basement + Ground + 4 +4
mezzanines every floor. Each building is intended to occupy 4 medium manufacturing
companies including their offices on mezzanines.

Figure 1. 3 AASMIC Mega Project Progress

Page-7

Figure 1. 4 AASMIC Mega Project Progress

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
Figure 1. 5 AASMIC Mega Project Progress

Where the second Third project is an infrastructure project Comprising Roads


construction, Water Supply systems, Fire Fighting System, waste water drainage
systems, Electrical and Data systems.

Page-8

we serve
by supp

Figure 1. 6 Gada Especial Economic Zone Project on Progress


.

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
Figure 1. 7 Gada Especial Economic Zone Project on Progress

Page-9

Figure 1. 8 Shop Drawing of Borana University Project on

Figure 1. 9 Shop Drawing of Borana University Project on

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
Figure 1. 10 Shop Drawing of Borana University Project on

Page-10

..\..\..\..\MCG Construction\Borana university\site visit report.docx Gage-10

Figure 1. 11 My Site Visit Report @Borana University Project Identifying gaps.

During my journey to the work sites/ Projects for work evaluation’s and supervision, I
have got some remarkable knowledge on undermentioned activities.

2.3. Construction prosses on the projects


FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
2.3.1. Sub structure

2.3.1.1. Earth work and excavation

2.3.1.2. Different type footing pad

2.1.2.3 Foundation column

2.3.1.4 Grade beams

2.3.1.5. Masonry wall

2.3.1.6 Hard core

2.3.1.7 Water Prof application

2.3.2. Superstructure

2.3.2.1. Beams

2.3.2.2. Column

2.3.2.3. Slab Page-11

2.3.2.4. Stairs

2.3.2.5. Formwork

2.3.2.6. Wall

2.3.2.7 Sanitary Installation

2.3.2.8 Electrical Installation

2.3.2.8 Electrical Installation

3. Site Work

3.1 Road And culverts construction

3.2 Site Sanitary installation

3.3 Site Electrical installation

3.4 Landscaping and Gardening (plantation)

2.4 The Challenges I Faced While Performing Tasks

Every activity has got its own problems while striving to achieve the works at hand.
In a construction industry there are many problems that arise while performing the
tasks and needs a solution in order to proceed in executing. During the course of the
four-month internship program at the company, it is expected that I faced some sort
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
of difficulties. Indeed, I were challenged to some extent. These challenges were not
due to lack of initiation towards performing the task I were given instead it was
simply a matter of experience in the field. And that was something that could be
solved by continually engaging one’s self to the activities in the course of time of the
challenges that I faced, some of them that worth mentioning are:-

 Weather condition

 Transportation

CHAPTER THREE

3.1 Over all benefit gained from internship

An internship was beneficial in terms of interpreting theoretical knowledge’s to


practical and actual skill.

I have been performing my work tasks well. At each section of work tasks, I have
tried to do my work effectively and efficiently. All peoples in the sector were
Page-12
appreciating my activities. I were practicing to fulfil all the work tasks in collaboration
with the help and advice of my supervisor. As much as possible I have tried best to
handle the activities assigned to me responsibly.

 I tried to accomplish my task as soon as possible


 Go and check other construction site to learn new things
Especially, I focused on the accuracy of works and in finding them quickly. Polite
way of treating everybody in the site as well as in the office is crucial thing in order to
have a good link of work with all stake holders of the company. Because of this I
make a smooth relationship with all of our staff members to avoid interruption of work
flow.

3.1. In terms of improving practical skill

The main goal of the internship program is to allow students to incorporate skill and
knowledge on the lessons learned in the classroom into a real-world experience.
Two words that describe person’s competencies are knowledge and skill. Knowledge
refers to the learning concept, principles and information regarding a particular
subject. Skill refers to the ability of using that information and applying it in context.
Practical skill is important that in workplace, what matters is not the amount of
practical experience or theoretical background that an individual has. What matters
is how much an individual is able to deal to effectively with the realities around him.
Through this internship program, I try to develop this theoretical skill into practical
skill. Practical skill I have gained from the program:

 Familiar with the procedures of every work tasks


FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
 Management of resources and time and taking risk

 The ability to analyze and interpret diverse, complex data, time, human power

 Critical thinking and the ability to evaluate designs, plans and projects

 Awareness of professional and ethical issues

 Use of materials, equipment, machines and human power effectively

 Constructing formwork for different structure

 Rebar works: bending, cutting, overlapping and its arrangement.

 Care for drawings, documents and resources

3.2 In terms of improving industrial problem-solving capability


Page-13
In order to solve problems, there should be effective communication in every direction within the
organization. Good communication with others. I have tried to Specify problems by in quantifiable
terms like who, what, where, when, why and how

 improving interpersonal communication

 How to resolve conflicts that arise during work

 How to compromise problems that arise in intrapersonal relationships

 How to explain situations in ways most understandable.

 use team to solve problems

 choose permanent correction for problems

3.3 In terms of upgrading our theoretical knowledge

The time that I spent at internship tries to gather practical knowledge regarding of
construction project, has also upgrades my theoretical knowledge that I obtained
from education or class room. In class room we only know what is done on papers,
but after I joined construction industries I view how class room work is real to
practical world. Thus it implies that internship upgrades my theoretical knowledge.
Since practical work is developed from theoretical, I upgraded my theoretical
knowledge by revising what I learned at class during internship time as well

3.4 Team playing skills acquired

The ability to work in team is a skill set in its own. It is clear that team work has a
great advantage in development of any work. In site, it is very important to play as a
team. If there are disagreements between any parties which are participated in the
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
project, it is very difficult to go ahead with the construction works. Knowing this I
have developed team work playing skill both by practicing and observing during my
internship. During my internship I worked hard to participate on team works. This
time was completely wonder full in developing my team playing skills, and much
more all the tasks I have been handling were team works. Skills that I developed for
being good team player:

 Functions as an active participant and team.

 Develop friendship among the teams and others.

 Develop knowledge through many sharing different ideas openly.

 I learned that how team works create trust between team members.

 I learned how team works create collaboration among team members

 Team members must know how to examine team and individual errors without
Page-14
making personal attacks.

 The team member should respect other.

 The team members should express their opinion without any fear.

 They must be good information gather about the work

3.5 Leadership Skills Acquired

Leadership is a process of influencing individual or groups to accomplish an


organizational goal. COTM Engineers need to be effective leaders. When asking and
communicating the Engineers, supervisors, and Foreman and General managers; I
have collected too much information and basic concepts on how to manage the
available labor, material, and property also the Engineer help me to develop my
leadership concept by applying practical activity. As a result I knew more than what I
had before in terms of leadership skills from the experience and more skilled peoples
in the company. Leadership skill required

 Sense of responsibility

 Positive expectation about team members

 Self confidence

 Make sound and timely decisions.

 Ensure that tasks are understood, supervised, and accomplished.

 Know your people and look out for their well-being. From this what I understand is
becoming a leader is not easy because it takes a conscious commitment and

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
consistent effort to develop one’s leadership skills. But it is possible for anyone who
is willing to make the effort, can become a good leader.

3. 6 the benefits acquired in terms of understanding work Ethics

Work ethics is one of the regulations that the workers follows on the job task. Work
ethics such as honesty (not lying, chatting and stealing), doing a job well, valuing
what one does having a sense of purpose and filling /being a greater vision or plan is
vital. The company that I have internship program have put with a document the right
and regulation of workers. During the job I follow every work ethics for good forward
of the projects. If the workers environment well connected on their work they put
positive progress on the project activity. Because of these any company by following
all the regulation of work ethics they get positive regulation their project progress.
These are one of the important skills that every worker knows in every day to day
work activities in the construction industries. In every activity I follow all the
regulation of the company because of these I improve my work ethics skills on my
work tasks, I always try to exercise: -
Page-15
 Cooperation: being interactive and cooperate with the others

 Office discipline: in work place don’t have to disturb the working condition.

 Punctuality: means keeping the companies work beginning time to complete the
given task on the given period.

 Accountability: accountability is a key requirement of good engineers.

 Open mindedness: I have to be open minded since it makes the work to be done
understandably.

 Friendly (well relation) with the workers.

3.7 The benefits I acquired in terms of entrepreneurship

Entrepreneurship is the process of involving the creation of new enterprises and that
the entrepreneur is the founder. It is the process of starting a business, a startup
company or organization. The entrepreneur develops a business plan acquires the
human and other required resources and is fully responsible for its success or
failure. Entrepreneurial activities differ substantially depending on the type of
organization and creativity involved. Working as an intern on the company gave me
an idea how my future career looks like. Site supervision work was good experience
in terms of understanding how the work is done. In terms of entrepreneurship skill,
we obtained some knowledge how to be a contractor or a consultant on construction
sector and how to be profitable and how attract customer towards our company. In
addition to this we acquire

 Look for new information

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
 Be active in technical knowledge and speaking ability.

 Be ready to win (get) small contracts (as sub-contractor)

 Providing better way for the work flow and project duration.

 The ability to solving conflict that create between labors

 The ability to perform multi work at the same time (ability to orders the workers in
different work)

3.8 Interpersonal communication skills

During the internship I know that every task in site and office is very difficult do
individually and to do the work based on the schedule it needs a team of different
professionals or it needs a network of skilled persons. Interpersonal communication
skill plays a vital role in daily activities of the society in the site work and office works
and also whatever job. Good communications are the connection bridge of any Page-16
profession for doing task peacefully and do on time and economically. It has also the
following advantages:

 To share ideas between colleagues

 To upgrade good habits, like to help each other’s

 To exchange skills and knowledge

 To create agreement by listening others idea

 To handle information

 To respect and tolerate peoples

 To facilitate work task

CHAPTER FIVE
CONCLUSION AND RECOMMENDATION

4.1 Conclusion

The internship program has been an enlightening me in exposing to the real


engineering work and put theoretical knowledge into practice. This helps the
students to carry out their job easily after their graduation as experts. It had
challenges but, in the end, it left me with knowledge that I would not acquire if I spent
the time learning in the university. Internship covers all attachment of students to the
practical implementation of the theory that was covered in school. I have been
involved in the internship program for the last four months in MCG Construction plc.
During the internship period I have got relevant practical experiences, professional
and entrepreneurial skills which are very important for the rest of my life. When
FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
theoretical knowledge is supported by practical activities, it become crucial power for
performing some activities and enables us to take part in production. Since skill is a
power and an important machine for production, it is important to participate in
practical activities to gain these different skills. This internship program helps me to
apply what I have been learning in theory. It also helps me to observe & practice a
real work of discipline and to deal with different problems and their solving methods.
The work ethics & principles as well as the management of site and the way of
performing a given tasks are the main benefits I have gained from the internship. It
was the deterministic period in which I decide my future life in the real world.
Generally, from this internship program I have gained Learn Practical consideration
for building and Road construction & design, upgrade my theoretical knowledge &
visualizations, knowing about work ethics, to improve problem solving skills,
managing of human power & different section skills, allows me to develop
professional contacts with different working teams, for my future job searching
process, to know my own strength & weakness, the Work flow of a given company
etc.

4.2 Recommendation

During the stay I had in head Office and on site, I were able to see the construction
of substructure and super structure structural elements. The followings are some of
my recommendation for both the company and university.

Final Report For the university

 The university should help the students to easily understand what they have learn
in laboratory. In this internship we saw how it is easy to understand on practical
work.

 To make the students more professional in the field of study, the learning process
should be more practical than theoretical.

For the company

 The hosting company must give priority for the health and safety of its all workers.
Helmets for the Foreman, Carpenter, and workers of dismantle formwork and the site
engineers and Hat for the workers (plastering, bar bending).

 The concrete worker must wear hand glove, safety shoes & uniform cloth

 Steel reinforcement is not stored on the wood bed prepared so that this causes the
reinforcement to corrosion. So, you have to store at some height above the ground
using the wood bedding materials.

REFERENCES

 Ethiopian Building Code Standard (EBCS- 2) 1995

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023
 Standard Handbook of Civil Engineering (Standard Publishers
Distributors)
 Handbook of Construction Management. Second edition. P K Joy 2014
 INTERNSHIP FINAL REPORT of ELSA GETU, EMEBET TEREFE and
HAILE KUMELA. 2014

Page-18

Gage-18

FINAL INTERNSHIP REPORT BY KEBEDE CHALLA @ RVU LABU LAFTO CAMPUSE 2023

You might also like