Gantt

The document outlines a project timeline spanning from May 2021 to January 2022. It is divided into phases including creating scope and requirements documents, developing 9 modules, conducting evaluations at 40%, 70%, and 100% completion, testing, and final submission. The longest module takes 28 days while evaluations and testing periods are generally 3-6 days.

Uploaded by

Hassan Shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views3 pages

Gantt

The document outlines a project timeline spanning from May 2021 to January 2022. It is divided into phases including creating scope and requirements documents, developing 9 modules, conducting evaluations at 40%, 70%, and 100% completion, testing, and final submission. The longest module takes 28 days while evaluations and testing periods are generally 3-6 days.

Uploaded by

Hassan Shah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Name Start Date Duration(days) 20-May

Scope Document
Scope Document 20-May-21 10
SRS Document
SRS Document 30-May-21 8
Evaluation of Scope and SRS
Evaluation of Scope and SRS 6/8/2021 3
Module 1: User Profile Management
Module 1: User Profile Management 11-Jun-21 9
Module 2: Admin Panel
Module 2: Admin Panel 20-Jun-21 25
Module 3: Job Platform
Module 3: Job Platform 15-Jul-21 28
SDS Document
SDS Document 13-Aug-21 8
Evaluation of SDS and 40% Evaluation
Evaluation of SDS and 40% Evaluation 21-Sep-21 3
Module 4: Freelance Platform
Module 4: Freelance Platform 24-Sep-21 20
Module 5: Chat Bot
Module 5: Chat Bot 14-Oct-21 9
Module 6: Payment Gateway
Module 6: Payment Gateway 23-Oct-21 16
Evaluation of 70% implimentation
Evaluation of 70% implimentation 9-Nov-21 3
Module 7: Market Trends
Module 7: Market Trends 12-Nov-21 19
Module 8: Blog Posting Platform
Module 8: Blog Posting Platform 1-Dec-21 9
Module 9: Mobile App
Module 9: Mobile App 20-Dec-21 12 Testing
Testing 26-Dec-21 6100% Evaluation and System Testing
100% Evaluation and System Testing 2-Jan-22 6 Submission
Submission 3-Jan-22 1
20-May-21 9-Jul-21 28-Aug-21 17-Oct-21 6-Dec-21
Scope Document
SRS Document
Evaluation of Scope and SRS
Module 1: User Profile Management
Module 2: Admin Panel
Module 3: Job Platform
SDS Document
Evaluation of SDS and 40% Evaluation
Module 4: Freelance Platform
Module 5: Chat Bot
Module 6: Payment Gateway
Evaluation of 70% implimentation
Module 7: Market Trends
Module 8: Blog Posting Platform
Module 9: Mobile App
Testing
100% Evaluation and System Testing
Submission
1 6-Dec-21 25-Jan-22