MRT-DN02-P2H-830026 (Commissioning Procedure) Damper Rev.1
MRT-DN02-P2H-830026 (Commissioning Procedure) Damper Rev.1
MRT-DN02-P2H-830026 (Commissioning Procedure) Damper Rev.1
Owner’s Engineer
Contractor
Sub-Supplier
Project
MRT-DN02-P2H-830026
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
RECORD OF REVISION
Rev. Date Page Affected Description of Revision
Rev.1 2 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
CONTENTS
3. COMMISSIONING .............................................................................................................. 8
3.1. COMMISSIONING REQUIREMENT ............................................................................... 8
3.2. SEAL AIR FAN COMMISSIONING .................................................................................. 8
3.3. HYDRAULIC COMMISSIONING ..................................................................................... 8
3.4. DAMPER COMMISSIONING ............................................................................................ 9
4. APPENDIX .......................................................................................................................... 10
4.1. P&ID FOR DAMPER ..........................................................................................................11
4.2. FUNCTION & INTERLOCK TEST RECORD SHEET..................................................11
4.3. MOTOR SOLO TEST RECORD SHEET .........................................................................11
4.4. LOAD TEST RECORD SHEET .........................................................................................11
Rev.1 3 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
1. GENERAL INFORMATION
1.1. OBJECTIVE
This document provides the commissioning guideline of Damper for MUARA TAWAR COMBINED
CYCLE POWER PLANT BLOCK 2,3 & 4 ADD-ON PROJECT.
1.2. SCOPE
The scope of commissioning covers the following activities and associated equipment list.
1) Checking the completeness of equipments required for commissioning.
2) Checking the integrity and readiness of all associated piping, valves, instrumentation, control
system and other fittings.
3) Checking completeness of all the electrical connections and associated protections.
4) Checking the various control loops and their response.
5) Checking the protection and functional interlocks of electrical / mechanical equipment in the
system.
6) Checking cleanliness of the entire system and it must be free of any foreign material or dirt, which
may damage the equipment or impair the system functionality.
1.3. SAFETY
At all times when conducting commissioning activities maintaining the Health and Safety of personnel
is of paramount importance. At all times the station safety regulations must be followed to ensure that
the health and safety of personnel (including those not directly involved in the commissioning activity)
is in no way put at risk.
It must be noted that commissioning activities may require equipment to be operated in an abnormal
manner or access to be gained to normally inaccessible areas. When conducting such activities extra
vigilance, caution and precautions are required to ensure that they are achieved in a safe manner.
Rev.1 4 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
1.4. REFERENCES
Temperature (Ambient) 35 °C
Accumulators 2 x 32L
Motor Power 22 kW
4) Guillotine damper
Gas path dimensions 6000x6000 mm (internal)
Rev.1 5 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
Rev.1 6 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
2. PRE - COMMISSIONING
1) The mechanical and electrical erection of the system or equipment concerned has been completed
and cold checks of cabling including I/O-tests have been performed.
2) The functional testing does not disturb the completion of the other systems.
3) The functional testing does not cause any risk to personal safety.
4) The preliminary lubrication works included in the works have been performed.
5) The Site has been cleaned off the works wastes impeding the cold test operation of the systems.
6) The electrical instruments being part of the equipment have been installed in compliance with the
valid regulations.
7) Moving parts as well as rotating and hot parts that may hazard the personal safety have been
protected properly.
8) The persons in charge for start-up have been appointed.
9) Supervisor for the pressure equipment operation appointed. (if required)
1) Proper communication facilities between various control stations and central control room have
been prepared.
2) Personal protection equipment is available for commissioning personnel.
3) Warning signs are placed in all concerned operating area.
4) Portable fire extinguishers or permanent fire fighting systems are available at critical location.
Rev.1 7 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
3. COMMISSIONING
3) Initial startup
- Start seal air fan
- Check that seal air MOV opens
- Check that seal air differential pressure
- Check rotation of fan. Correct at fan side if required.
- Stop system
- Check that seal air damper closes
- Check that seal air fan stops
- Repeat process with remaining fan
4) Load Test
- Start one (1) seal air fan.
- Record pump operationg data as per “Load Test Record Sheet” in Local.
- Stop the fan after recording finish and repeat remaining fan load test.
Rev.1 8 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
Watch the optical clogging indicator on top of the filling filter. If the indicator moves to the red
range of the display, stop the motor filling pump and change the filter element of the filling filter.
2) Check and fill up the nitrogen pressure at the accumulator
Never switch on the HPU without sufficient nitrogen pressure.
3) Select Local Control by key switch.
4) Run HPU system
5) Check that one pump starts, and charges the accumulators
6) Switch off pump and discharge accumulators
1) Check that blade stop bolts are set so that the blade stops before the blade seals are bent excessively
2) Visually check all hydraulic connections
3) Ensure the blade path is free of obstructions such as scaffolding
4) Confirm locking pins and links are removed from cylinders
5) Ensure that exclusion zones are empty
6) Start system
7) Once accumulators are charged, press slow open.
8) Check that the blade starts to move within 1 minute.
9) Stop the blade once it begins to move
10) Verify that the blade as moved in the correct direction
11) Isolate the HPU outlet valves
12) Check hydraulic pipes for leaks
13) Check hydraulic cylinders for leaks
14) Check hydraulic cylinder operating area for obstructions such as cabling, conduit etc.
15) Check that no personnel are in exclusion zones
16) Open HPU isolation valves and open blade using slow open
17) Check for smooth operation
18) When the blade is within 1m from the bypass blade stops, press stop
19) Close HPU isolation valves
20) Check that the blade stop bolts are installed
21) Check that the blade stop bolts are set so that the blade seals are not bent excessively
22) Open HPU Isolation valves
23) Slow open the blade fully
24) Close HPU isolation valves
25) Check blade sealing against landing bars. Blade seals should be making firm contact with the
landing bars
26) Adjust blade stops if necessary
Rev.1 9 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
DCS Test
1) With blade fully closed, check for blade closed indication
2) With blade fully closed, check for position feedback
3) Set system to remote mode
4) Check for remote mode feedback
5) Send full open signal to diverter
6) Verify that the diverter opens fully, and the blade position is indicated correctly by the position
feedback signal
7) Send a 50% position request signal and remove the full open signal
8) Check the blade stops at approximately 50%
9) Send a full close signal, and verify the blade closes fully
10) Ensure that it has been at least 1 hr since the last fan start. This is to prevent the fans from
overheating
11) With the blade fully open, switch on the circuit breaker for fan 1
12) Check that Fan1 running signal is present
13) Check that the seal air barrier safe signal is present
14) Switch off Fan1 circuit breaker and switch on Fan 2 circuit breaker
15) Check that Fan 2 running signal is present
16) Clear all faults and check that system healthy is present
4. APPENDIX
Rev.1 10 of 11
[COMMISSIONING PROCEDURE] DAMPER
MRT-DN02-P2H-830026
Rev.1 11 of 11
4.1. P&ID FOR DAMPER
MRT-DP00-P2LB-122106
MRT-DP00-P2LB-122106
MRT-DP00-P3LB-122106
MRT-DP00-P3LB-122106
4.2. FUNCTION & INTERLOCK TEST RECORD SHEET
FUNCTION & INTERLOCK TEST
COMMENT
Contractor
Owner
4.2. FUNCTION & INTERLOCK TEST RECORD SHEET
FUNCTION & INTERLOCK TEST
COMMENT
Contractor
Owner
4.2. FUNCTION & INTERLOCK TEST RECORD SHEET
FUNCTION & INTERLOCK TEST
COMMENT
Contractor
Owner
4.2. FUNCTION & INTERLOCK TEST RECORD SHEET
FUNCTION & INTERLOCK TEST
COMMENT
Contractor
Owner
4.3. MOTOR SOLO TEST RECORD SHEET
MUARA TAWAR COMBINED CYCLE
POWER PLANT BLOCK 2, 3 & 4 ADD-ON PROJECT
2. Fan Data Description Before Start After Start After 15 mins After 30 mins After 45 mins After 60 mins Remark
Manufacturer Sebco
Type Horizontal
Capacity 82.7 ㎥/min Vertical N/A
Head (rated) 634 mmAq ①
Rotation direction CW
Motor Vibration
(View from MTR NON DRIVE END) Horizontal N/A
Non Drive End
[mm/s or μm]
3. Motor insulation resistance Axial N/A
3.1 LV Motor (for 400V Motor) MΩ
3.2 MV Motor (for 11kV Motor) MΩ
Vertical N/A
7. Trial operation records ③
・JOG operation Motor Vibration
Horizontal N/A
Drive End
Rotation direction CW CCW
[mm/s or μm]
Abnormal noise Yes No Axial N/A
Contractor
Owner
4.4. LOAD TEST RECORD SHEET
MUARA TAWAR COMBINED CYCLE
POWER PLANT BLOCK 2, 3 & 4 ADD-ON PROJECT
LOAD TEST
6. Measurement point position sketch
System : Damper
4. Conditions Vibration Directional Measurement
1 2 3 4 5
▷ Enough Faning liquid for testing Yes No V
Equipment : Seal air fan
▷ Final allignment / coupling complete Yes No V=Vertical direction
▷ Fan lubrication condition OK Yes No H=Horizontal direction
Tag No.: HNE10AN001/002
▷ Sequence test completed Yes No MOTOR Fan A=Axial direction
1. Motor Data A
Manufacturer hyosung 5. Pre-cautions
Type TEFC ・Be cautious about the following item. Yes No H
Voltage 400 V Leakage, Vibration, Noise, Temperature, Others
Output 22 KW
Insulation Class F
Temp Rising (Max) 80 ℃ Description Before Start After 30 mins After 60 mins After 90 mins After 120 mins Remark
Hertz 50 HZ
Rated current 41.4 A
Vertical N/A
Speed 2950 rpm ①
Motor Vibration
Horizontal N/A
Non Drive End
2. Fan Data [mm/s or μm] Axial N/A
Manufacturer Sebco
Type Horizontal
Vertical N/A
Capacity 82.7 ㎥/min ③
Head (rated) 634 mmAq Motor Vibration
Horizontal N/A
Rotation direction CW Drive End
(FACING MTR NON DRIVE END) [mm/s or μm] Axial N/A
3. Fan Operation
Vertical N/A
Rotation direction CW CCW ④
Fan Vibration
Horizontal N/A
Drive End
[mm/s or μm]
Axial N/A
Abnormal noise Yes No
Vertical N/A
⑤
Fan Vibration
Horizontal N/A
Abnormal smell Yes No Non Drive End
[mm/s or μm]
Axial N/A
Ambient Temperature
Starting current A [°C]
Non drive end bearing ①
Motor
Temperature Stator Shell ②
Speed rpm
[°C]
Drive end bearing ③
U N/A
Finish Time
Motor
Current V N/A
[Ampere]
W N/A
Coast Down time Sec
Contractor
Owner