Code of Practice Introduction 2010
Code of Practice Introduction 2010
(p.e. ≤ 10)
DISCLAIMER
Although every effort has been made to ensure the accuracy of the material contained in this
publication, complete accuracy cannot be guaranteed. Neither the Environmental Protection
Agency nor the author(s) accept any responsibility whatsoever for loss or damage occasioned or
claimed to have been occasioned, in part or in full, as a consequence of any person acting, or
refraining from acting, as a result of a matter contained in this publication. All or part of this
publication may be reproduced without further permission, provided the source is acknowledged.
CODE OF PRACTICE
The principal authors of this Code of Practice (CoP) are Ms Margaret Keegan, EPA, and Mr Frank
Clinton, EPA. Mr Laurence Gill, Trinity College Dublin (TCD), provided valuable technical input and
review during the drafting stages. Other personnel involved in the production and preparation of the
code were Mr John Mulqueen, National University of Ireland Galway (NUIG), Dr Michael Rodgers,
NUIG, Dr Cormac O’Suilleabhain, TCD, Mr Niall O’Luanaigh, TCD, Mr Gerard O’Leary, EPA, and Mr
Dermot Burke, EPA. The CoP builds on the EPA 2000 Guidance Manual (Mr John Mulqueen, Dr
Michael Rodgers, Mr Gerard O’Leary and Mr Gerry Carty), which provided a new approach to on-
site wastewater treatment assessment in Ireland.
In order to examine the position in relation to on-site systems (in Ireland and internationally) and to
produce draft guidelines for their future use, a research project in relation to on-site systems was
part-financed by the European Union through the European Regional Development Fund as part of
the Environmental Monitoring, R&D sub-programme of the Operational Programme for
Environmental Services, 1994–1999. The sub-programme was administered on behalf of the
Department of the Environment and Local Government by the Environmental Protection Agency,
which has the statutory function of co-ordinating and promoting environmental research. The study
Small Scale Wastewater Treatment Systems was co-ordinated by the Department of Civil
Engineering, NUIG, from 1995 to 1997.
In late 2000, as part of the Environmental Research, Technological Development and Innovation
(ERTDI) programme 2000–2006, the EPA approved a further research project to be undertaken by
the Department of Civil, Structural and Environmental Engineering at TCD. The Irish Government
under the National Development Plan 2000–2006 financed the ERTDI programme. This later
project was entitled Establishment of the Hydraulic Performance and Efficiencies of Different
Subsoils and the Effectiveness of Stratified Sand Filters (2000-MS-15-M1). This project was later
extended to examine the efficiencies of subsoils for on-site wastewater treatment and disposal with
respect to endocrine disrupting chemicals. A further research project by TCD on The Effective
Distribution of On-Site Wastewater Effluent into Percolation Areas via Distribution Boxes and
Treatment by Reed Beds Compared to Attenuation of Pollutants in Sandy Subsoils (2005–MS-15)
has recently been completed.
The NUIG and TCD researchers are internationally recognised for their work on wastewater
treatment systems and have published in peer-reviewed international journals and presented their
findings at international conferences. The findings of the research were used to inform the
requirements of the CoP.
The Agency also wishes to acknowledge the contribution of the various sections of the Department
of the Environment, Heritage and Local Government (DoEHLG), National Standards Authority of
Ireland (NSAI), Irish Agrément Board (IAB), An Bord Pleanála, Domestic Effluent Trade Association
(DETA), Geological Survey of Ireland (GSI), the County and City Managers Association, Local
Authority personnel, River Basin District Project co-ordinators, Fisheries Boards, Irish On-Site
Wastewater Association (IOWA) as well as the tutors and participants of the FÁS Site
Characterisation courses and comments by practitioners in the field and the numerous individual
contributors during the consultation period 20th July to 10th September 2007.
Finally, the authors would also like to acknowledge the assistance of EPA colleagues Dr Matthew
Crowe, Mr Donal Daly, Mr Brendan Wall and Mr Leo Sweeney.
Yellowstone Communications Design produced the graphics and its input is acknowledged.
BS British Standard
C Capacity
°C Degrees Celsius
Cu Uniformity co-efficient
DO Dissolved oxygen
g Gram
h Hour
K Hydraulic conductivity
kg Kilogram
l Litre
m Metre
m 3 Cubic metres
mg Milligram
mm Millimetre
s Second
SS Suspended solids
T/P The T-value (expressed as min/25 mm) is the time taken for the water level to drop a specified
distance in a percolation test hole. For shallow subsoils the test hole requirements are different
and hence the test results are called P-values. For further advice see Annex C.
WT Water table
assessment methodology set out in this systems used to treat and dispose of domestic
document should be used by planning wastewater from single houses. Guidance on
authorities to satisfy the requirements of good practice is included in Part Two and
Article 22 (c) of the Planning and Development informs the implementation of the requirements
Regulations, 2006. There is also an obligation of Part One.
on the proposed house builder/owner to ensure
that any planning application submitted should The figures and diagrams in this CoP are for
include an assessment of the site and illustration purposes to assist the users of this
recommendations in accordance with the code. They should not be considered as
guidance provided in this CoP. In addition, it is substitutes for detailed design drawings.
essential that the wastewater treatment system
installed on site complies with the conditions of The code will be subject to ongoing review. The
planning and that the system is properly Agency welcomes any suggestions, that users
installed and maintained in accordance with the of the CoP wish to make. These should be
guidance in Sections 11 and 12. returned to the Office of Environmental
Enforcement at the Environmental Protection
The CoP is divided into two parts: Part One Agency Regional Inspectorate, McCumiskey
sets out requirements for on-site wastewater House, Richview, Clonskeagh Rd, Dublin 14.
Disclaimer i
Acknowledgements ii
Abbreviations iii
Preface vi
List of Figures xi
1 Scope 1
2 References 2
3 Definitions 3
4 Wastewater Characteristics 6
6 Site Characterisation 10
11.4 Installation 48
12.1 Introduction 51
Figure 6.2 A general guide to the selection of an on-site wastewater treatment system
discharging to ground 12
Figure 7.2 Longitudinal section of a typical septic tank (all dimensions in mm) 21
Figure 8.4 Intermittent sand filter system with underlying sand/subsoil polishing filter 29
Figure C.3 Idealised cross section of the T-test holes and the proposed percolation trench 73
Figure C.4 Cross section of the P-test holes and the proposed percolation trench 75
Table 4.1 Range of raw domestic wastewater influent characteristics (I.S. EN 12566-3:2005) 6
Table 6.2 Depth requirements on-site for on-site systems discharging to ground 14
Table 7.1 Nominal septic tank capacity for various design populations 21
Table 8.3 Criteria for constructed wetland systems receiving septic tank effluent 35
Table 10.1 Minimum soil polishing filter areas and percolation trench lengths required
for a five-person house 44
Table B.3 Recommended minimum distance between a receptor and a percolation area or
polishing filter 62
Table C.3 Subsoil classification against T-values for 400 T-tests (Jackson, 2005) 68
Table C.7 Information obtained from desk study and on-site assessment 76