Pre-Post Energization List
Pre-Post Energization List
STANDARD
Form No. 8
Pre/POST Energization Check List
Sr Status Remark
Items
No Yes No N/A
Categorization of punch list (A, B) as per form # 7 should be available
1.
and Punch-list items having Status A must be cleared.
2. All equipment are properly labeled.
All Tests Results’ are available and signed by the contractor and
DEPARTMENT ENGINEERINGstaff for the following:-
3.1 GIS equipment (HV and EHV).
3.2 Power Transformers.
3.3 MV Switchgear.
3.4 Auxiliaries (AC & DC Panels, Battery & Battery Charger, Aux.
3. Transformers, and RMU).
3.5 SVC, Capacitor banks, and Reactors.
3.6 SAS (HMI, network switches, bay control devices, computers, GPS).
3.7 SCADA / Close Loop Test.
3.8 Under Ground Cables / Overhead Lines.
3.9 Protection Panels.
All Protection and Measuring CTs are normalized and tightness of CT
4. wiring is checked physically. Temporary shorting links are removed. Also
confirm single point earthing for Each CT circuit.
All VTs are Normalized and tightness of VT wiring is checked physically.
5. VT circuit MCBs are close and fuses are in place. Also Check VT HV
neutral is solidly grounded.
Check all power supplies to control, Protection, Alarm, and switchgear
6.
etc. are normal.
Check all control and protection devices are normal. No abnormal relay
7.
flag/alarms,
8. Marked up drawings have been Submitted.
All protection modifications and final setting corrections are approved
9.
from DEPARTMENT ENGINEERING.
All site test results are properly arranged at site with good manner and
10. colored soft copy of the same have been sent to DEPARTMENT
ENGINEERINGoffice.
Approved final setting confirmation have been completed and original
11. copy plus two scan copies of final setting review documents have been
sent to DEPARTMENT ENGINEERINGoffice.
12. Final Trip Tests are completed.
Issued By: