21dj0032 Pow
21dj0032 Pow
LOCAL PROGRAM,
Local Infrastructure Program, Local Roads and Bridges,
Local Roads, Construction of Road,
Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
(LIP 2021)
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City
EXECUTIVE SUMMARY
For THE DISTRICT ENGINEER
1. Project Profile
Project ID :
Project Name : LOCAL PROGRAM, Local Infrastructure Program,
Local Roads and Bridges, Local Roads,
Construction of Road, Barangay Kinatihan II,
Candelaria, Quezon
Location of Project : Candelaria, Quezon
2. Project Category : Construction of Local Road
3. Source of Fund : LIP 2021
4. Action Recommended : For Approval
5. Implementing Office : DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : P 6,000,000.00
8. ABC : P 5,940,000.00
9. Project Duration : 120 Calendar Days
10. Mode of Implementation : By Contract
PREPARED BY:
ISRAEL J. AFRICA
Engineer II
SUBMITTED BY:
Project : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Appropriation : (a) Road 375 m
: Barangay Kinatihan II, Candelaria, Quezon : (c) Others
Project ID : Target Start Date :
Location : Candelaria, Quezon Total Project Duration : 120 CD
Station Limits STA. 0+000.00 - STA. 0+375.00
: No. of Pre-determined :
Appropriation : P 6,000,000.00 Unworkable Days :
Source of Fund : LIP 2021
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A: Facilities for the Engineer 1.63% 77,665.71 1.63% 77,665.71
B: Other General Requirements 5.61% 266,309.42 5.61% 266,309.42
C: Earthworks 7.56% 359,182.04 7.56% 359,182.04
D: Subbase and Base Course 12.02% 571,171.34 12.02% 571,171.34
E: Surface Courses (PLS. SEE FORM POW-2015-01C-00) 73.17% 3,475,943.25 73.17% 3,475,943.25
F: Bridge Construction 0.00% - 0.00% -
G: Drainage and Slope Protection Structures 0.00% 0.00 0.00% -
H: Miscellaneous Structures 0.00% 0.00 0.00% -
I: Provisional Sum 0.00% - 0.00% -
J: Daywork 0.00% - 0.00% -
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
ISRAEL J. AFRICA FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 l.s. 75,865.71 75,865.71 75,865.71 75,865.71 86,031.72 86,031.72 1.60% 1.60%
A.1.4(1) Provision of Progress Photographs 120.00 120.00 each 1,800.00 1,800.00 15.00 15.00 17.01 17.01 0.04% 0.04%
TOTAL OF PART A 77,665.71 77,665.71
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 2.00 ea. 10,781.28 10,781.28 5,390.64 5,390.64 6,792.21 6,792.21 0.23% 0.23%
B.7(2) Occupational Safety and Health Program 1.00 1.00 l.s 142,865.67 142,865.67 142,865.67 142,865.67 162,009.67 162,009.67 3.01% 3.01%
B.8(2) Traffic Management 1.00 1.00 l.s 72,662.47 72,662.47 72,662.47 72,662.47 82,399.24 82,399.24 1.53% 1.53%
B.9 Mobilization / Demobilization 1.00 1.00 l.s. 40,000.00 40,000.00 40,000.00 40,000.00 42,000.00 42,000.00 0.84% 0.84%
TOTAL OF PART B 266,309.42 266,309.42
PART C EARTHWORKS
100(3)a1 Individual Removal of Trees (small, 150 mm Ø up to 300 mm Ø) 73.00 73.00 ea 154,624.15 154,624.15 2,118.14 2,118.14 2,668.86 2,668.86 3.26% 3.26%
101(1) Removal of Structures and Obstructions 1.00 1.00 l.s. 116,575.51 116,575.51 116,575.51 116,575.51 146,885.14 146,885.14 2.45% 2.45%
102(2) Surplus Common Excavation 129.84 129.84 cu.m. 17,996.00 17,996.00 138.60 138.60 174.63 174.63 0.38% 0.38%
104(1)a Embankment from Roadway Excavation (Common Soil) 118.63 118.63 cu.m. 23,950.61 23,950.61 201.90 201.90 254.40 254.40 0.50% 0.50%
105(1)a Subgrade Preparation (Common Material) 2,850.00 2,850.00 sq.m. 46,035.77 46,035.77 16.15 16.15 20.35 20.35 0.97% 0.97%
TOTAL OF PART C 359,182.04 359,182.04
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 594.00 594.00 cu.m 571,171.34 571,171.34 961.57 961.57 1,211.58 1,211.58 12.02% 12.02%
TOTAL OF PART D 571,171.34 571,171.34
PART E SURFACE COURSES
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days 2,287.50 2,287.50 sq.m. 3,475,943.25 3,475,943.25 1,519.54 1,519.54 1,914.62 1,914.62 73.17% 73.17%
TOTAL OF PART E 3,475,943.25 3,475,943.25
PART F BRIDGE CONSTRUCTION
TOTAL OF PART F -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
TOTAL OF PART G - -
PART H MISCELLANEOUS STRUCTURES
TOTAL OF PART H - -
PART I PROVISIONAL SUM
TOTAL OF PART I
PART J DAYWORK
TOTAL OF PART J
GRAND TOTAL 4,750,271.76 4,750,271.76 100.00% 100.00%
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
3
2 Dump Truck 12 yd 1 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Payloader 1 35
6 Water Truck 16,000 L, 360 hp 1 36
7 Vibratory Roller 10 m.t., SD100DC 1 37
8 Concrete Saw 1 38
9 Concrete Screeder 1 39
10 Transit Mixer 1 40
11 Motorized Road Grader 1 41
12 Chain Saw 1 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-
12 SUB-TOTAL 0
TOTAL
TOTAL 12
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
As Submitted 1.60% 1.00 l.s. 56,549.87 19,315.84 - 75,865.71 75,865.71 8% 6,069.26 4,096.75 86,031.72
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated 1.60% 1.00 l.s. 56,549.87 19,315.84 - 75,865.71 8% 6,069.26 4,096.75 86,031.72
As Submitted 0.04% 120.00 each 1,800.00 - - 15.00 1,800.00 8% 144.00 97.20 2,041.20
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.04% 120.00 each 1,800.00 - - 1,800.00 8% 144.00 97.20 2,041.20
As Submitted 1.63% 58,349.87 19,315.84 77,665.71 6,213.26 4,193.95 88,072.92
TOTAL OF PART A
As Evaluated 1.63% 58,349.87 19,315.84 - 77,665.71 6,213.26 4,193.95 88,072.92
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.23% 2.00 ea. 8,480.00 2,301.28 - 5,390.64 10,781.28 20% 2,156.26 646.88 13,584.41
B.5 Project Billboard / Signboard
As Evaluated 0.23% 2.00 ea. 8,480.00 2,301.28 - 10,781.28 20% 2,156.26 646.88 13,584.41
As Submitted 3.01% 1.00 l.s 55,335.27 76,500.00 11,030.40 142,865.67 142,865.67 8% 11,429.25 7,714.75 162,009.67
B.7(2) Occupational Safety and Health Program
As Evaluated 3.01% 1.00 l.s 55,335.27 76,500.00 11,030.40 142,865.67 8% 11,429.25 7,714.75 162,009.67
As Submitted 1.53% 1.00 l.s 47,131.59 7,226.88 18,304.00 72,662.47 72,662.47 8% 5,813.00 3,923.77 82,399.24
B.8(2) Traffic Management
As Evaluated 1.53% 1.00 l.s 47,131.59 7,226.88 18,304.00 72,662.47 8% 5,813.00 3,923.77 82,399.24
As Submitted 0.84% 1.00 l.s. - - 40,000.00 40,000.00 40,000.00 0% - 2,000.00 42,000.00
B.9 Mobilization / Demobilization
As Evaluated 0.84% 1.00 l.s. - - 40,000.00 40,000.00 0% - 2,000.00 42,000.00
As Submitted 5.61% 110,946.86 86,028.16 69,334.40 266,309.42 19,398.51 14,285.40 299,993.32
TOTAL OF PART B
As Evaluated 5.61% 110,946.86 86,028.16 69,334.40 266,309.42 19,398.51 14,285.40 299,993.32
PART C EARTHWORKS
As Submitted 3.26% 73.00 ea 100,740.00 6,929.73 46,954.42 2,118.14 154,624.15 20% 30,924.83 9,277.45 194,826.43
100(3)a1 Individual Removal of Trees (small, 150 mm Ø up to 300 mm Ø)
As Evaluated 3.26% 73.00 ea 100,740.00 6,929.73 46,954.42 154,624.15 20% 30,924.83 9,277.45 194,826.43
As Submitted 2.45% 1.00 l.s. - 19,955.92 96,619.59 116,575.51 116,575.51 20% 23,315.10 6,994.53 146,885.14
101(1) Removal of Structures and Obstructions
As Evaluated 2.45% 1.00 l.s. - 19,955.92 96,619.59 116,575.51 20% 23,315.10 6,994.53 146,885.14
As Submitted 0.38% 129.84 cu.m. - 463.91 17,532.09 138.60 17,996.00 20% 3,599.20 1,079.76 22,674.96
102(2) Surplus Common Excavation
As Evaluated 0.38% 129.84 cu.m. - 463.91 17,532.09 17,996.00 20% 3,599.20 1,079.76 22,674.96
As Submitted 0.50% 118.63 cu.m. - 930.72 23,019.89 201.90 23,950.61 20% 4,790.12 1,437.04 30,177.77
104(1)a Embankment from Roadway Excavation (Common Soil)
As Evaluated 0.50% 118.63 cu.m. - 930.72 23,019.89 23,950.61 20% 4,790.12 1,437.04 30,177.77
As Submitted 0.97% 2,850.00 sq.m. - 2,036.52 43,999.25 16.15 46,035.77 20% 9,207.15 2,762.15 58,005.07
105(1)a Subgrade Preparation (Common Material)
As Evaluated 0.97% 2,850.00 sq.m. - 2,036.52 43,999.25 46,035.77 20% 9,207.15 2,762.15 58,005.07
As Submitted 7.56% 100,740.00 30,316.80 228,125.24 359,182.04 71,836.40 21,550.93 452,569.37
TOTAL OF PART C
As Evaluated 7.56% 100,740.00 30,316.80 228,125.24 359,182.04 71,836.40 21,550.93 452,569.37
PART D SUBBASE AND BASE COURSE
As Submitted 12.02% 594.00 cu.m 513,602.40 2,546.72 55,022.22 961.57 571,171.34 20% 114,234.27 34,270.28 719,675.89
200(1) Aggregate Subbase Course
As Evaluated 12.02% 594.00 cu.m 513,602.40 2,546.72 55,022.22 571,171.34 20% 114,234.27 34,270.28 719,675.89
As Submitted 12.02% 513,602.40 2,546.72 55,022.22 571,171.34 114,234.27 34,270.28 719,675.89
TOTAL OF PART D
As Evaluated 12.02% 513,602.40 2,546.72 55,022.22 571,171.34 114,234.27 34,270.28 719,675.89
PART E SURFACE COURSES
As Submitted 73.17% 2,287.50 sq.m. 3,413,597.55 35,035.68 27,310.02 1,519.54 3,475,943.25 20% 695,188.65 208,556.60 4,379,688.50
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
As Evaluated 73.17% 2,287.50 sq.m. 3,413,597.55 35,035.68 27,310.02 3,475,943.25 20% 695,188.65 208,556.60 4,379,688.50
As Submitted 73.17% 3,413,597.55 35,035.68 27,310.02 3,475,943.25 695,188.65 208,556.60 4,379,688.50
TOTAL OF PART E
As Evaluated 73.17% 3,413,597.55 35,035.68 27,310.02 3,475,943.25 695,188.65 208,556.60 4,379,688.50
PART F BRIDGE CONSTRUCTION
As Submitted
As Evaluated
As Submitted 0.00% - - - - - - -
TOTAL OF PART F
As Evaluated 0.00% - - - - - - -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
As Submitted
As Evaluated
As Submitted 0.00% - - - - - - -
TOTAL OF PART G
As Evaluated 0.00% - - - - - - -
PART H MISCELLANEOUS STRUCTURES
As Submitted
As Evaluated
As Submitted 0.00% - - - - - - -
TOTAL OF PART H
As Evaluated 0.00% - - - - - - -
PART I PROVISIONAL SUM
As Submitted
As Evaluated
As Submitted 0.00% - - - - - - -
TOTAL OF PART I
As Evaluated 0.00% - - - - - - -
PART J DAYWORK
As Submitted
As Evaluated
As Submitted 0.00% - - - - - - -
TOTAL OF PART J
As Evaluated 0.00% - - - - - - -
As Submitted 100.00% 4,197,236.68 173,243.20 379,791.88 4,750,271.76 906,871.09 282,857.16 5,940,000.00
GRAND TOTAL
As Evaluated
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02-00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
ISRAEL J. AFRICA FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
Portland Cement Concrete Pavement (Unreinforced) - 0.23 m AS SUBMITTED 2,287.50 sq.m. 3,475,943.25 20% 695,188.65 208,556.60 903,745.25 4,379,688.50 1,914.62
311(1)c1
thick, 14 days AS EVALUATED 2,287.50 sq.m. 3,475,943.25 20% 695,188.65 208,556.60 903,745.25 4,379,688.50 1,914.62
AS SUBMITTED 3,475,943.25 695,188.65 208,556.60 903,745.25 4,379,688.50
TOTAL OF PART E
AS EVALUATED 3,475,943.25 695,188.65 208,556.60 903,745.25 4,379,688.50
PART F BRIDGE CONSTRUCTION
AS SUBMITTED
AS EVALUATED
AS SUBMITTED - - - - -
TOTAL OF PART F
AS EVALUATED
AS EVALUATED
AS SUBMITTED - - - - -
TOTAL OF PART G
AS EVALUATED - - - - -
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
AS EVALUATED
AS SUBMITTED - - - - -
TOTAL OF PART H
AS EVALUATED - - - - -
PART I PROVISIONAL SUM
AS SUBMITTED
AS EVALUATED
AS SUBMITTED - - - - -
TOTAL OF PART I
AS EVALUATED
PART J DAYWORK
AS SUBMITTED
AS EVALUATED
AS SUBMITTED - - - - -
TOTAL OF PART J
AS EVALUATED
AS SUBMITTED 4,750,271.76 906,871.09 282,857.16 1,189,728.24 5,940,000.00
GRAND TOTAL
AS EVALUATED 4,750,271.76 906,871.09 282,857.16 1,189,728.24 5,940,000.00
Project : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay
Kinatihan II, Candelaria, Quezon
Location : Candelaria, Quezon
PART C EARTHWORKS
PART D
SUBBASE AND BASE COURSE
PART E
SURFACE COURSE
Prepared by:
ISRAEL J. AFRICA
Engineer II
BACK UP COMPUTATION
PROJECT : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
LOCATION : Candelaria, Quezon
ITEM NO. : 105(1)a, 200(1), 311(1)c1
375.00
SUB-TOTAL 1,143.75 1,143.75 1,425.00 1,425.00 297.00 297.00
TOTAL 2,287.50 2,850.00 594.00
Prepared by:
ISRAEL J. AFRICA
Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road,
Barangay Kinatihan II, Candelaria, Quezon
AREA VOLUME
DIST.
STATION Cut Fill Cut Fill
LEFT RIGHT LEFT RIGHT M LEFT RIGHT LEFT RIGHT
0 + 0 1.960 1.580 - -
20 36.900 31.600 0.000 0.000
+ 20 1.730 1.580 - -
20 23.300 21.300 0.000 0.000
+ 40 0.600 0.550 - -
20 15.500 15.700 0.000 0.000
+ 60 0.950 1.020 - -
20 15.500 17.900 0.000 0.000
+ 80 0.600 0.770 - -
20 9.000 12.700 0.000 0.000
+ 100 0.300 0.500 - -
20 3.700 8.700 0.000 0.000
+ 120 0.070 0.370 - -
20 0.700 5.700 1.200 0.000
+ 140 - 0.200 0.120 -
20 0.000 2.700 4.000 0.500
+ 160 - 0.070 0.280 0.050
20 0.000 0.700 7.400 2.400
+ 180 - - 0.460 0.190
20 0.000 0.000 11.800 8.200
+ 200 - - 0.720 0.630
20 0.000 0.000 15.600 11.700
+ 220 - - 0.840 0.540
20 0.000 0.000 16.600 9.000
+ 240 - - 0.820 0.360
20 0.000 0.000 11.800 4.200
+ 260 - - 0.360 0.060
20 3.200 3.000 4.200 0.600
+ 280 0.320 0.300 0.060 -
20 7.500 7.400 0.600 0.000
+ 300 0.430 0.440 - -
20 4.300 4.400 2.000 1.700
+ 320 - - 0.200 0.170
20 4.500 2.300 2.100 1.700
+ 340 0.450 0.230 0.010 -
20 5.300 7.800 0.200 0.000
+ 360 0.080 0.550 0.010 -
15 0.675 6.150 1.125 0.000
+ 375 0.010 0.270 0.140 -
375
-( / )
278.13 118.63 0.80
Prepared by:
ISRAEL J. AFRICA
Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Kinatihan II, Candelaria, Quezon
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
(Rental Basis)
a. Portable Mist-Based Sanitation Tent 1 720.00 9.79 7,048.80
b. Thermal Scanner (w/ rechargeable battery) 2 720.00 1.03 1,483.20
c. Power Sprayer w/ complete accessories 1 720.00 3.47 2,498.40
(Rental Basis)
a. Portable Mist-Based Sanitation Tent 1 720.00 9.79 7048.8
b. Thermal Scanner (w/ rechargeable battery) 2 720.00 1.03 1483.2
c. Power Sprayer w/ complete accessories 1 720.00 3.47 2498.4
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Rental Basis (Based on D.O 13 series of 2018) Unit Cost for 210 C.D.
Speed Restriction (R4-1) each 2.00 993.30 1,986.60
Roadwork Ahead (T1-1) each 2.00 2,299.50 4,599.00
End Speed Restriction (R4-2) each 2.00 993.30 1,986.60
Workmen Ahead (T1-5) each 2.00 1,184.40 2,368.80
Road Machinery (T1-3) each 2.00 1,373.40 2,746.80
Prepare to Stop (T1-18) each 2.00 1,184.40 2,368.80
Temporary Hazard Marker (Chevron, T5-5) each 1.00 1,209.60 1,209.60
* Traffic Cones (@ 5 meters apart) each 23.00 388.50 8,935.50
Rental Basis (Based on D.O 13 series of 2018) Unit Cost for 210 C.D.
Speed Restriction (R4-1) each 2.00 993.30 1,986.60
Roadwork Ahead (T1-1) each 2.00 2,299.50 4,599.00
End Speed Restriction (R4-2) each 2.00 993.30 1,986.60
Workmen Ahead (T1-5) each 2.00 1,184.40 2,368.80
Road Machinery (T1-3) each 2.00 1,373.40 2,746.80
Prepare to Stop (T1-18) each 2.00 1,184.40 2,368.80
Temporary Hazard Marker (Chevron, T5-5) each 1.00 1,209.60 1,209.60
* Traffic Cones (@ 5 meters apart) each 23.00 388.50 8,935.50
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Candelaria, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item no./Description : 311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
MAP SHOWING DPWH QUEZON II DEO OFFICE TO THE POINT OF REFERENCE (PROJECT SITE) L= 50.6 KM
Prepared by:
ISRAEL J. AFRICA
Engineer II
UNIT COST ANALYSIS FOR AGGREGATES (SAND and GRAVEL)
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads,
Project :
Construction of Road, Barangay Kinatihan II, Candelaria, Quezon