July 8, 2014

GE MULTILIN
650 MARKLAND ST
MARKHAM, ON
L6C 0M1

Subject: UL Project Number 1867462.371414

Dear Mr. Raponi,

I have completed your project plan and this letter outlines important project information about the UL
service(s) you requested.

UL has received enough information to start the product evaluation, however additional items and/or
samples may be needed to complete the evaluation. Details regarding the investigation items and/or
samples required are included below under the heading of Required Investigation Items and Required
Samples. Providing the items and samples requested below will avoid unnecessary delays in your
project.

Product Service Description:

Revise E57838 Volume 5 Section 1

Standard(s) Referenced for this Evaluation:

CSA C22.2 NO. 14-13 INDUSTRIAL CONTROL EQUIPMENT - Edition 12 - Issue Date 2013/03/01
UL 508 STANDARD FOR INDUSTRIAL CONTROL EQUIPMENT - Edition 17 - Revision Date
2013/10/16

Product Category:

 NKCR - AUXILIARY DEVICES

Required Investigation Item(s) for Evaluation:

None Required

Required Sample(s) for Evaluation:

No Samples Required

Project Plan Estimated Completion Date Letter - Service Request Number Page 1 of 2
1867462.371414
Assumption(s):

 All safety critical components, enclosures and materials are UL Listed/Recognized and
suitable for the intended application.

Proposed Test Plan:

No Tests Specified

Timeline Assessment:

Customer Requested Completion Date: Not Provided


Estimated Project Completion Date: Jul 15, 2014

Project Phase Product Evaluation Process


Quote Completed
Project Plan Completed
Project
Initial Assessment and/or
1 Weeks Completion
Construction Review
& Final
Testing, Final Report
Processing
Preparation, and 1 Weeks
Technical Review

Any proposed project plan and timeline included in this communication is based on the received
information and on the above assumptions. The test program and other aspects of the project plan
will be finalized following a comprehensive construction review of your specific product.

A project handler from our engineering staff will begin the investigation shortly. The project handler
will keep you informed of the progress of your project. If you have any questions or need additional
information, you can contact me or customer service.

Regards,

Dana VanEvery
Engineering Coordinator
ICE
UL
T: 360-817-5762
E: [email protected]

Any information and documentation involving UL Mark services are provided on behalf of UL LLC
(UL) or any authorized licensee of UL.

Project Plan Estimated Completion Date Letter - Service Request Number Page 2 of 2