Pemeliharaan Rutin PLTG Tello WEEK-35 (28 AGUSTUS - 1 SEPTEMBER 2023) Pip Updk Tello

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PEMELIHARAAN RUTIN PLTG TELLO NO DOK :

WEEK-35 (28 AGUSTUS - 1 SEPTEMBER 2023) REV :

PIP UPDK TELLO

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL SENIN SELASA RABU KAMIS JUMAT FEEDBACK

HME 28 29 30 31 1

1 GT02-PM-RTN-HME-MBV-BR004 202313554 PM GT02 PENGECEKAN VISUAL PIPING MISS ELIMINATOR HME 28/08/23 Asmar, Burhanudin 2 01:30 03:00 Asmar, Burhanudin

2 GT02-PM-RTN-HME-MBV-BR001 202313553 PM GT02 PENGECEKAN VISUAL PIPING MAIN OIL SYSTEM HME 28/08/23 Asmar, Burhanudin 2 01:30 03:00 Asmar, Burhanudin

MAN HOUR REQUARED 24:00


MAN HOUR AVAILABLE 80
% UTILITY 30%

NO PM NUMBER WORK ORDER NUMBER DESCRIPTION WORK TYPE DUE DATE LABOR JUMLAH LABOR DURASI TOTAL SENIN SELASA RABU KAMIS JUMAT FEEDBACK

HKI & HLI 28 29 30 31 1

1 GT02-PM-RTN-HKI-MBK-GX001 202313608 PM GT02 PENGECEKAN INSTRUMENT DAN CONTROL HYDRAULIC SELF SEQUENCING VALVE
HLI-GT RATCHET & CLUTCH VH14-1
28/08/23 Ahmad, Rahmanda 2 01:00 02:00 Ahmad, Rahmanda

2 GT02-PM-RTN-HKI-MBK-AA002 202313606 PM GT02 PENGECEKAN INSTRUMENT DAN CONTROL HYDRAULIC RACHET VALVE VR5-1)
HLI-GT 28/08/23 Ahmad, Rahmanda 2 01:00 02:00 Ahmad, Rahmanda

3 GT02-PM-RTN-HLI-MBV-GH005 202313470 PM GT02 PENGECEKAN KELISTRIKAN EVAC PUMP MOTOR HLI-GT 28/08/23 Ahmad, Rahmanda 2 01:00 02:00 Ahmad, Rahmanda

4 GT02-PM-RTN-HKI-MBK-AU001 202313607 PM GT02 PENGECEKAN INSTRUMENT DAN CONTROL SELF CLUTCH CSA-1 HLI-GT 28/08/23 Ahmad, Rahmanda 2 01:00 02:00 Ahmad, Rahmanda

MAN HOUR REQUARED 40:00


MAN HOUR AVAILABLE 80
% UTILITY 50%