Method Statement For Installationtesting Commissioning of Sprinkler System
Method Statement For Installationtesting Commissioning of Sprinkler System
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 3 of 15
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENTS
7.0 PROCEDURE
8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 4 of 15
1.0 PURPOSE
This method statement is applicable for the Installation, Testing & Commissioning of Fire fighting
Sprinkler System for the project as mentioned in the Specifications & Approved Shop Drawings.
2.0 SCOPE
This method Statement shall cover the Supply, Installation, Testing & Commissioning of
Sprinkler System in line with project requirements as indicated in the Approved Shop
Drawings, specifications & manufacturer’s instructions.
3.0 REFERENCE
3.1 Latest Approved shop drawings intended for Fire Fighting System
3.2 Specifications
3.3 Project Quality Plan
3.4 Project HSE Plan
3.5 Material Approval
4.0 DEFINITIONS
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
Project Manager
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 5 of 15
Construction manager
QA/QC Engineer
Site Engineer
HSE officer
SK
The work progress shall be carried out as per planned program and all the equipment’s required
to execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
Provision of all necessary information and distribution of responsibilities to his Construction
team.
The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
The constant coordination with the Safety Engineer to ensure that the works are carried out in
safe working atmosphere.
The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
He will ensure the implementation of any request that might be raised by the Consultant.
Efficient daily progress shall be obtained for all the equipment and manpower.
He will engage in the work and check the same against the daily report received from the
Foremen.
The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
He will follow and carries out all the relevant tests as per project specifications.
Obtain the required clearance prior to Consultant’s inspections.
Should acquire any necessary civil works clearances and coordination.
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 6 of 15
QA/QC Engineer will assist the Consultant Engineer/ Inspector during Inspection.
Check & ensure work is completed prior to offer consultant for inspection.
Coordination with site construction team.
He will assist the Consultant Engineer/ Inspector during the inspection.
Ensure all works have been completed prior to raise inspection to the consultant.
5.5 Site Foreman
The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on
the work activity.
Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure adequate lighting is provided in the working area at night time.
Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
Ensure safe access to site work at all times.
Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
One who will acknowledge the receiving of materials at site in coordination with QA/QC &
concerned Engineer.
6.0 EQUIPMENTS
d. Spirit Level
e. Electric Drill Machine
f. Step Ladders
g. Threading Machine
h. Solvent Cement
i. Electric welding machine. (if required)
j. Torque Wrench
k. Pipe Cutting Machine
l. Grinding Machine
m. Pressure Gauge
n. Hammer
o. Water Level Marker
p. Mobile Scaffolds
q. Staging Platforms
7.0 PROCEDURE
Work Sequence/Procedure
During transportation ensure that the equipment & its components (if any) are delivered in
a shipping package and or shall be at least in a box covered with plastic. Extra care in
unloading the equipment is required to avoid scratching or denting.
Where ever possible the loading and offloading of the Sprinkler Equipment shall be
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 8 of 15
7.3 Storage
To ensure that deterioration of the Sprinkler Equipment does not occur during storage, it is
recommended to store the equipment in sheltered conditions that are protected from weather
elements and accidental damage.
Sprinkler Equipment shall be protected with plastic/ tarpaulin or shall not be removed from
the shipping package unless otherwise instructed to do so.
All packages for the equipment reaching the site shall be identified as per package list.
contractor.
All relevant Shop drawings for the installation of the equipment shall be available &
approved by the consultant. No installation shall be done without Approved Shop
Drawings.
Installation activities shall only commence when all associated works by the Civil such as
clearing of work place, water proofing, etc. have been verified & completed.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination
with the Safety in charge at site.
Inspect the relevant area for any possible clashes with other services.
Check for other services, making sure that there is no interference between each service &
adequate access to work and for future maintenance can be maintained.
* A wet sprinkler system is used for Fire Protection purposes and it is an integral part of the
Installation of Fire Fighting System & Accessories as mentioned in the Approved Method
Statement. The system is designed in accordance to the Fire Protection Engineering Standards. The
system is a portion of the aboveground network of specially sized and pipes are hydraulically
designed which will be installed inside the building, structure or areas as indicated in the Approved
Fire Fighting System Approved Shop Drawings for which sprinklers are installed & fix in a
systematic pattern. The valve controlling the each system is located in the system riser or its supply
piping. Each sprinkler riser includes a device for actuating an alarm when the system is in
operation. The system is actually activated by heat from fire and discharges water over the fire
area.
* The sprinkler is fire suppression & control device that operates automatically when heat-
activated element is heated to its thermal rating or above, allowing water to discharge over a
specified area. The characteristics of a sprinkler that define its ability to control or extinguish a fire
are thermal sensitivity, temperature rating, orifice size, and installation orientation & water
distribution characteristics.
* The sprinkler system is designed as per NFPA 13 “Standard for the Installation of Sprinklers”.
The location & spacing of sprinklers and pipe sizes are designed in conformance with the
applicable clauses of NFPA 13. This standard provides the minimum requirements for the design &
installation of automatic Fire Sprinkler Systems and exposure protection sprinkler systems,
including the character and adequacy of water supplies and selection of sprinklers, fittings, piping,
valves & all materials and accessories.
Refer to Approved Method Statement in which the Installation Procedures for Sprinkler
Pipes, Valves & other Accessories have been discussed. However, Installation procedure
for Sprinkler Heads, Butterfly Valves, & Flow Switches are as follows:
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 10 of 15
Drill the hole in the pipe, as per product manufacturers’ recommended hole size for
insertion of the vane of the flow switch.
Clean the inside surfaces of the pipe, where the hole was made for a distance equal
to the pipe diameter on either side of the hole.
Roll the vane so that the arrow on the saddle points in the direction of the water
flow.
Install the saddle strap and tighten the bolts alternately.
Ascertain that the vane does not rub the inside surfaces of the pipe.
Fire alarm provision has to be provided to connect with the fire alarm control panel.
After completion of installation of the entire sprinkler heads, butterfly valves &
Flow Switches & raise inspection for Consultant Approval.
Once installation has been accepted & approved by the Consultant, provide
covering material to the Installed Sprinkler Heads to avoid entry of dirt, dust and
damage.
Testing & Commissioning shall commence after final approval by the consultant.
Prior to commissioning, ensure that all instruments (if any) to be used during the
commissioning shall be calibrated. Calibration certificates shall be available.
Ensure that all installed Fire Fighting Equipment & its components have been
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 12 of 15
8.0. ATTACHMENTS