Method Statement For Installationtesting Commissioning of Sprinkler System

This document provides a method statement for installing, testing, and commissioning a sprinkler system. It outlines the purpose, scope, responsibilities of roles like the project manager and QA engineer, required equipment, and procedures to be followed.

Uploaded by

Ahamed Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views13 pages

Method Statement For Installationtesting Commissioning of Sprinkler System

This document provides a method statement for installing, testing, and commissioning a sprinkler system. It outlines the purpose, scope, responsibilities of roles like the project manager and QA engineer, required equipment, and procedures to be followed.

Uploaded by

Ahamed Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

PROJECT NAME

TITLE Ref. No. : S-6012-0085


METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 1 of 15

METHOD STATEMENT FOR

INSTALLATION,TESTING & COMMISSIONING OF SPRINKLER SYSTEM


PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 2 of 15

REVISION RECORD

This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.

Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 3 of 15

CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENTS

7.0 PROCEDURE

8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 4 of 15

1.0 PURPOSE

 This method statement is applicable for the Installation, Testing & Commissioning of Fire fighting
Sprinkler System for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE

 This method Statement shall cover the Supply, Installation, Testing & Commissioning of
Sprinkler System in line with project requirements as indicated in the Approved Shop
Drawings, specifications & manufacturer’s instructions.

3.0 REFERENCE

3.1 Latest Approved shop drawings intended for Fire Fighting System
3.2 Specifications
3.3 Project Quality Plan
3.4 Project HSE Plan
3.5 Material Approval

4.0 DEFINITIONS

PQP : Project Quality Plan


PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Work Inspection Request
MIR : Material Inspection Request
UPVC Class E : Ultra polyvinyl chloride
UPVC : Ultra polyvinyl chloride
HDPE : High density polyethylene
PEX PIPE : Cross-linked Polyethylene
G.I. Pipe : Galvanized Iron Pipe

5.0 RESPONSIBILITIES:

 Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
 Project Manager
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 5 of 15

 Construction manager
 QA/QC Engineer
 Site Engineer
 HSE officer
 SK

5.1 Project Manager

 The work progress shall be carried out as per planned program and all the equipment’s required
to execute the works shall be available and in good condition as per project planned.
 Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.

5.2 Construction Manager

 Construction Manager is responsible to supervise and control the work on site.


 Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
 Control and sign all WIRs before issuing to Consultant approval.

5.3 Site Engineer

 The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
 Provision of all necessary information and distribution of responsibilities to his Construction
team.
 The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
 The constant coordination with the Safety Engineer to ensure that the works are carried out in
safe working atmosphere.
 The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
 He will ensure the implementation of any request that might be raised by the Consultant.
 Efficient daily progress shall be obtained for all the equipment and manpower.
 He will engage in the work and check the same against the daily report received from the
Foremen.
 The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.

5.4 QA/QC Engineer (MEP):

 The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
 Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
 He will follow and carries out all the relevant tests as per project specifications.
 Obtain the required clearance prior to Consultant’s inspections.
 Should acquire any necessary civil works clearances and coordination.
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 6 of 15

 QA/QC Engineer will assist the Consultant Engineer/ Inspector during Inspection.
 Check & ensure work is completed prior to offer consultant for inspection.
 Coordination with site construction team.
 He will assist the Consultant Engineer/ Inspector during the inspection.
 Ensure all works have been completed prior to raise inspection to the consultant.
5.5 Site Foreman

 The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
 Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
 Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
 Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.

5.6 Safety Officer

 The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
 The implementation of safety measures is adequate to maintain a safe working environment on
the work activity.
 Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
 The site is maintained in a clean and tidy manner.
 Ensure only trained persons shall operate the power tools.
 Ensure all concerned personals shall use PPE and all other items as required.
 Ensure adequate lighting is provided in the working area at night time.
 Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
 Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
 Ensure safe access to site work at all times.

5.7 Store Keeper (SK)

 Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
 One who will acknowledge the receiving of materials at site in coordination with QA/QC &
concerned Engineer.

6.0 EQUIPMENTS

Following tools shall be arranged before starting the job.


a. Tool Box.
b. Measuring Tape.
c. Hack Saw Blade
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 7 of 15

d. Spirit Level
e. Electric Drill Machine
f. Step Ladders
g. Threading Machine
h. Solvent Cement
i. Electric welding machine. (if required)
j. Torque Wrench
k. Pipe Cutting Machine
l. Grinding Machine
m. Pressure Gauge
n. Hammer
o. Water Level Marker
p. Mobile Scaffolds
q. Staging Platforms

7.0 PROCEDURE

 Work Sequence/Procedure

7.1 General Requirements


 All the materials received at site shall be as per the approved technical material submittal
for Wet Pipe Sprinkler System and to be inspected upon receipt & approved by the engineer
prior in proceeding with the installation through MIR. Any discrepancies, damages etc.,
should be reported to the supplier for rectification or replacement & to be removed from
site immediately.
 All construction/inspection/testing works shall be carried out in accordance with the
specifications & to be done by qualified Mechanical Engineers and shall be checked and
approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
 Contractor has to clarify the procedure for material delivery to the site through consultant
Engineer at site.

7.2 Delivery & Storage

7.2.1 Material Transport/ Delivery

 During transportation ensure that the equipment & its components (if any) are delivered in
a shipping package and or shall be at least in a box covered with plastic. Extra care in
unloading the equipment is required to avoid scratching or denting.
 Where ever possible the loading and offloading of the Sprinkler Equipment shall be
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 8 of 15

carried out by hand.


 Equipment shall not be dropped onto hard surfaces & should not be dragged along the
ground.
 All the received units shall be checked & inspected to ensure that it is complying with the
approved material submittals prior to site storage.

7.3 Storage

7.3.1 Storage on Site Store

 To ensure that deterioration of the Sprinkler Equipment does not occur during storage, it is
recommended to store the equipment in sheltered conditions that are protected from weather
elements and accidental damage.
 Sprinkler Equipment shall be protected with plastic/ tarpaulin or shall not be removed from
the shipping package unless otherwise instructed to do so.
 All packages for the equipment reaching the site shall be identified as per package list.

7.4 Sequence of Installation for the Sprinkler System


7.4.1 Safety
 All site safety rules & regulations shall be complied with.
 Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in
the installation, testing & commissioning and shall be recorded.
 All operatives will be equipped with minimum personnel protective equipment; hard hat,
coveralls, safety boots, safety glasses.
 The persons using cleaning fluid and solvent cement have to wear hand gloves.
 Ensure only qualified personnel shall install, test & commissioned the equipment.
 During Testing & Commissioning, display warning sign boards necessarily provided and
barricade the area whenever necessary.
 Ensure that all operatives fully understand the method of these activities.
7.4.2 Pre- Installation Procedure
 Before commencement of installation activity, the supervisor must ensure that:
 Delivered Sprinkler Equipment shall have been inspected & approved via MIR by the
consultant prior to installation at site.
 All Installations & Pressure Testing of Fire Fighting Pipe works have been completed &
approved by the consultant.
 Relevant documents or certificates shall be presented at the time of inspection if required
by the Consultant.
 Permission to start or Civil Clearances prior to installation has been given by the main
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 9 of 15

contractor.
 All relevant Shop drawings for the installation of the equipment shall be available &
approved by the consultant. No installation shall be done without Approved Shop
Drawings.
 Installation activities shall only commence when all associated works by the Civil such as
clearing of work place, water proofing, etc. have been verified & completed.
 Safe access shall be provided by the Main Contractor thru Work Permit in coordination
with the Safety in charge at site.
 Inspect the relevant area for any possible clashes with other services.
 Check for other services, making sure that there is no interference between each service &
adequate access to work and for future maintenance can be maintained.

7.4.3 Installation Procedure for the Sprinkler System

7.4.3.1General Notes on the System:

* A wet sprinkler system is used for Fire Protection purposes and it is an integral part of the
Installation of Fire Fighting System & Accessories as mentioned in the Approved Method
Statement. The system is designed in accordance to the Fire Protection Engineering Standards. The
system is a portion of the aboveground network of specially sized and pipes are hydraulically
designed which will be installed inside the building, structure or areas as indicated in the Approved
Fire Fighting System Approved Shop Drawings for which sprinklers are installed & fix in a
systematic pattern. The valve controlling the each system is located in the system riser or its supply
piping. Each sprinkler riser includes a device for actuating an alarm when the system is in
operation. The system is actually activated by heat from fire and discharges water over the fire
area.

* The sprinkler is fire suppression & control device that operates automatically when heat-
activated element is heated to its thermal rating or above, allowing water to discharge over a
specified area. The characteristics of a sprinkler that define its ability to control or extinguish a fire
are thermal sensitivity, temperature rating, orifice size, and installation orientation & water
distribution characteristics.

* The sprinkler system is designed as per NFPA 13 “Standard for the Installation of Sprinklers”.
The location & spacing of sprinklers and pipe sizes are designed in conformance with the
applicable clauses of NFPA 13. This standard provides the minimum requirements for the design &
installation of automatic Fire Sprinkler Systems and exposure protection sprinkler systems,
including the character and adequacy of water supplies and selection of sprinklers, fittings, piping,
valves & all materials and accessories.

7.4.3.2 Installation Procedure:

 Refer to Approved Method Statement in which the Installation Procedures for Sprinkler
Pipes, Valves & other Accessories have been discussed. However, Installation procedure
for Sprinkler Heads, Butterfly Valves, & Flow Switches are as follows:
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 10 of 15

7.4.3.2.1 Sprinkler Heads:


 Prior to installation, ensure that all the Sprinkler Equipment is equipped with
associated appurtenances as per manufacturer standard & supply according to the
approved material submittal.
 All Sprinkler Equipment shall be covered & protected for moisture, corrosion, dust
& any deterioration before & after the installation.
 Ensure that the installations (with or without ceiling) whichever is applicable shall
be on the exact locations as mentioned on the Approved Shop drawings.
 Mark the final location of the Sprinkler System. It is much recommended to check
physically & measure the actual dimensions on site.
 Installation of sprinkler heads shall be as per manufacturer’s instructions and
requirements of NFPA-13.
 Make sure hangers & supports are aligned & secured.
 Pipe sizes shall be as per the approved & shall be initially tested.
 Hand tight the sprinkler heads into the fittings to avoid mechanical damage and
gradually tighten it with appropriate size & type of wrench.
 A nominal clearance of 3/8” to 1” from the finished ceiling line. Adjustment can be
made through the push-on Escutcheon plate to compensate for the variation in the
fittings.
 To install the Escutcheon plate, align and press it over the Sprinkler body, until the
outer edge of the Escutcheon meets the mounting surface.
 Ensure that the concealed pendant sprinklers are installed and inspected prior to
fixing of the cover.

7.4.3.2.2 Installation Procedure of Butterfly Valves:


 Install butterfly valves as per the approved drawings. Ensure that it is readily
accessible for operation & maintenance.
 Ensure valve disc does not interface with the operation of other system components
adjacent to the butterfly valve.
 If the valve is hard to close, it may be due to debris lodge in the sealing area. This
can be corrected by backing-off the hand wheel and closing it again several times if
necessary. Don’t force the valve to seat by applying a wrench to hand wheel. This
may distort the valve components or scratch the sealing surfaces.
 The inlet & outlet piping of the valve shall be properly supported to prevent
excessive stress to the valve body. Do not use the valve body to support pipeline
position as it may result in distortion of the valve body.
 Fire alarm provision has to be provided on the valve to connect with the fire alarm
panel.

7.4.3.2.3 Installation Procedure of Flow Switches


 Install the flow switch as per the approved drawings. Ensure that it is readily
accessible for operation, inspection & maintenance.
 Mount the flow switch either on horizontal or vertical pipes. On horizontal pipe, it
shall be installed on the top portion of the pipe for easier accessibility and service.
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 11 of 15

 Drill the hole in the pipe, as per product manufacturers’ recommended hole size for
insertion of the vane of the flow switch.
 Clean the inside surfaces of the pipe, where the hole was made for a distance equal
to the pipe diameter on either side of the hole.
 Roll the vane so that the arrow on the saddle points in the direction of the water
flow.
 Install the saddle strap and tighten the bolts alternately.
 Ascertain that the vane does not rub the inside surfaces of the pipe.
 Fire alarm provision has to be provided to connect with the fire alarm control panel.
 After completion of installation of the entire sprinkler heads, butterfly valves &
Flow Switches & raise inspection for Consultant Approval.
 Once installation has been accepted & approved by the Consultant, provide
covering material to the Installed Sprinkler Heads to avoid entry of dirt, dust and
damage.
 Testing & Commissioning shall commence after final approval by the consultant.

7.4.4. Testing & Commissioning Procedures


7.4.4.1 Visual Inspection & Testing Procedure

 After documentations & visual checks, Testing shall proceed further.


 Ensure all pipe works has been hydrostatically tested & completed.
 All supporting system has been completed, properly installed & fixed.
 Ensure all instruments (if required) to be used during the testing shall be calibrated
& records shall be available.
 Ensure that the all Equipment is in their proper location as mentioned on the
Approved Shop Drawings.
7.4.4.1.1 Flushing Procedure
 All main risers including Sprinkler & Fire Hose Reels shall be thoroughly flushed
before connection of Sprinkler Heads.
 Close all branch lines for initial flushing.
 Fill complete system with clean water and initially carry out the flushing manually.
 Refill the system with clean water & run the pumps for 2 hours.
 Open Drain valves in the main lines and drain the water.
 The flushing operation shall be continued until satisfactory cleaning is ensured.
 Water used during the flushing shall be drained or disposed to a safe place using
flexible pipes to the nearest drain point.
 Hydrostatic Testing for the Sprinkler Piping System shall commence after flushing.
 Record all test & take consultant approval to proceed with the Commissioning
Process.

7.4.4.2 Commissioning Procedure for the Sprinkler System

 Prior to commissioning, ensure that all instruments (if any) to be used during the
commissioning shall be calibrated. Calibration certificates shall be available.
 Ensure that all installed Fire Fighting Equipment & its components have been
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 12 of 15

installed as per the approved shop drawings, manufacturers’ recommendation &


piping system have been tested for leaks. Approval for all preliminary inspections
shall be available during the commissioning stage.
 Ensure all Fire Fighting System pipe works has been completed, tested & approved
by the Consultant.
 Ensure all sprinkler heads have been installed & fix properly with the correct
alignment & spacing.
 Ensure firmness & tightness of supports prior to Commissioning of the equipment.
 After satisfactorily verification of installation & testing records & visual checks for
the Fire Fighting Equipment, commissioning shall commence.
 Close the gate valves after all the PRV station in the building.
 Start pressurizing the high pressure lines using the fire pumps up to the required
system pressure.
 Adjust the PRV to reduce the pressure after the PRV Valve to the required system
pressure.
 Maintain the pipes pressurized & re-check visually if there are any leaks for about 2
hours.
 Close all the zone control valves, landing valves inside the cabinets & lock shield
valves of the hose reels.
 Open the gate valve after the PRV valve & start pressurizing the riser pipes &
cabinets using the fire pumps.
 Check pressure in all floors by using special adapter with calibrated pressure gauge.
Record the reading.
 Start opening the zone control valves for each floor & check for any leaks for about
2 hours.
 After pressurizing the whole system. Keep it for 24 hours for observation.
 Open the drain valves of the zone control valves floor by floor. Alarm system
should indicate fire signal in the building.
 Close the zone control valves floor by floor & alarm system should give fault
signal.
 Commission the alarm check valve in the pump room by opening its drain line &
check the mechanical bell performance.
 Open the lock shield valves for each hose reel & adjust its pressure to 3-4 bar
through the PRV using special nozzles with pressure gauge. The water flow should
be at least 6 meters. (Hose reel should be open outside the building to avoid any
damages to other services).
 After completing all the above steps, keep fire pumps in auto position & keep under
observation.

8.0. ATTACHMENTS

8.1. Quality Control Procedure


8.2. Inspection & Test Plan
8.3. Installation Check Sheet
8.4. Testing Check Sheet for Fire Fighting Piping System
8.5. Testing & Commissioning Check Sheet
PROJECT NAME
TITLE Ref. No. : S-6012-0085
METHOD STATEMENT FOR REV. No. 0
INSTALLATION, TESTING & COMMISSIONING OF SPRINKLER SYSTEM Date :
Page 13 of 15

8.6. Risk Assessment