Alayao Access Road Ok
Alayao Access Road Ok
Alayao Access Road Ok
Barangay Alayao
Municipality of Capalonga Grant
Province of Camarines Norte ###
B. Labor
Productivity Rate: 80.00 sq.m./man/day
Common Laborer 5.00 days 3.00 365.00 5,475.00
Sub-Total 5,475.00
TOTAL FOR ITEM 105 5,475.00
201 AGGREGATE BASE COURSE 133.90 cu.m.
A. Quantity Take-Off
STA 0+000 to 0+260
Base Course
Length 260.00 m
Width 3.00 m
Area 780.00 sq.m.
Thickness 0.10 m
Compacted Volume 78.00 cu.m
Road Shoulder
Width 0.50 m
Height 1 0.10 m
Height 2 0.33 m
Trapezoidal Cross Section Area 0.11 sq.m.
Length 260.00 m
No. of sides 2.00 sides
Compacted Volume 55.90 cu.m
B. Materials
Aggregate Base Course 154.00 cu.m. 1,300.00 200,200.00
Sub-Total 200,200.00
C. Labor
Productivity Rate: 10.00 cu.m/team/day (1 skilled and 3 common labor)
Skilled Laborer 16.00 days 1.00 550.00 8,800.00
###
Laborer 16.00 days 3.00 365.00 17,520.00
###
Sub-Total 26,320.00
D. Equipment Rentals
Productivity Rate: 10.00 cu.m/day
Portable Plate Compactor (FOL & Operator included) 16.00 days 1.00 2,800.00 44,800.00
Sub-Total 44,800.00
TOTAL FOR ITEM 201 271,320.00
311 PORTLAND CEMENT CONCRETE PAVEMENT 780.00 sq.m
A. Quantity Take-Off 179.40 cu.m.
###
Length 260.00 m
Width 3.00 m
Thickness 0.23 m
Area 780.00 sq.m
Volume 179.40 cu.m
Page 1 of 30
Target Length/Day 11.00 ln.m.
Number of Joints 24.00 joints ###
Number of RSB per Construction Joints @ 0.30m spacing 10.00 pcs. ###
Total Number of 16mm dia.RSB @ 0.6 m length 240.00 pcs.
Length of RSB for Construction Joints @ 0.6m each 144.00 m
B. Materials
Portland Cement (Type 1) 1,615.00 bags 310.00 500,650.00
Washed Sand 108.00 cu.m. 1,600.00 172,800.00
Crushed Gravel (3/4") 180.00 cu.m. 1,900.00 342,000.00
Nylon #80 4.00 kgs. 480.00 1,920.00
Flat bar 3" x ¼'' thk. x 6m 2.00 pcs. 1,250.00 2,500.00
Asphalt Filler 71.00 kgs. 350.00 24,850.00
2" x 6" x 12' Coco Lumber 92.00 pcs 360.00 33,120.00
2" x 3" x 12' Coco Lumber 92.00 pcs 180.00 16,560.00
10 mm dia x 6m RSB 12.00 pcs 265.00 3,180.00
16 mm dia x 6m RSB 24.00 pcs 585.00 14,040.00
Empty Cement Bags 500.00 pcs 8.00 4,000.00
8ft. Laminated Sack (40kg - 100m/roll) 36.00 m 100.00 3,600.00
4" CWN 8.00 kgs. 120.00 960.00
3" CWN 8.00 kgs. 120.00 960.00
Empty PVC Container (20 liters) 4.00 pcs. 250.00 1,000.00
Empty PVC Drum (200 liter capacity) 4.00 pcs 2,800.00 11,200.00
Sub-Total 1,133,340.00
C. Labor
For Formworks and Concrete Pouring
Productivity Rate: 7.5 cu.m./ Team/ day; 1 Team - 4 skilled and 14 laborer
(concrete pouring, bagging, hauling and water tendering,installation & dismantling, base corrections, and application of asphalt filler)
D. Equipment Rentals
Productivity Rate:
One-Bagger Concrete Mixer (FOL and Operator included) 24.00 days 1.00 3,000.00 72,000.00
Sub-Total 72,000.00
Note:
a. Temporary Facility is at the Barangay Hall
b. Dropsite for Aggregates is directly in the Project Site
c. For Other Remaining Materials it will be hauled by laborers
2" x 6" x 12' Coco Lumber Hauler 92.00 pcs 10.00 920.00
2" x 3" x 12' Coco Lumber 92.00 pcs 10.00 920.00
10 mm dia x 6m RSB 12.00 pcs 10.00 120.00
16 mm dia x 6m RSB 24.00 pcs 10.00 240.00
Sub-Total 28,040.00
TOTAL FOR ITEM 311 1,408,820.00
SPL- 1 PROJECT SIGNAGE 2.00 sets
A. Materials
2" x 3" x 12' Good Lumber 16.00 pcs 300.00 4,800.00
2" x 2" x 12' Good Lumber 2.00 pcs 200.00 400.00
4" CWN 3.00 kgs. 120.00 360.00
1" CWN 3.00 kgs. 120.00 360.00
1/4" thickness x 4' x 8' Marine Plywood 2.00 sheet 500.00 1,000.00
Quick Dry Enamel, White 2.00 liters 320.00 640.00
Tarpaulin w/ printed Information 4' x 8' 2.00 sheet 1,000.00 2,000.00
Sub-Total 9,560.00
B. Labor
Skilled Laborer 1.00 days 1.00 550.00 550.00
Laborer 1.00 days 1.00 365.00 365.00
Sub-Total 915.00
TOTAL FOR SPL-1 10,475.00
Page 2 of 30
SPL- 2 PROJECT MARKER 1.00 set
CHB
Height 1.20 m
Width 0.80 m
Thickness 0.125 m
Number of Markers 1.00 pcs
Total Surface Area 1.92 sq.m
Marker Footing
Length 1.00 m
Width 0.30 m
Thickness 0.10 m
Number of Markers 1.00 pcs
Volume 0.03 cu.m.
A. Materials
Portland Cement (Type 1) 8.00 bags 310.00 2,480.00
12 mm dia. X 6m RSB 2.00 pcs. 330.00 660.00
4" x 8" x 16" CHB 15.00 pcs 25.00 375.00
#16 GI Tie Wire 2.00 kg 100.00 200.00
Flat Latex (white) 1.00 liter 160.00 160.00
Semi-Gloss Latex (white) 1.00 liter 192.00 192.00
Concrete Neutralizer 1.00 liter 100.00 100.00
3" paint brush 2.00 pcs 75.00 150.00
Project Marker (45cm x 60cm x 5mm acrylic sheet marker with
1.00 set 12,000.00 12,000.00
info and 4 pcs wall spacer)
Sub-Total 16,317.00
B. Labor
(concrete works, masonry works and painting works)
Skilled Laborer 4.00 days 1.00 550.00 2,200.00
Laborer 4.00 days 1.00 365.00 1,460.00
Sub-Total 3,660.00
TOTAL FOR SPL-2 19,977.00
A DIRECT COST
Material Cost 1,359,417.00
Equipment Rental 116,800.00
Hauling Cost 28,040.00
Labor Cost:
a. Skilled 64,350.00
b. Unskilled 147,460.00
Sub-Total A 1,716,067.00
B INDIRECT COST
Project Supervision
Foreman 42.00 days 1.00 650.00 27,300.00
Warehouseman 42.00 days 1.00 365.00 15,330.00
TOTAL FOR PROJECT SUPERVISION 42,630.00
Temporary Facility Rental
Temporary Facility Rental (BLGU In-Kind) 3.00 months 3,000.00 9,000.00
TOTAL FOR TEMP. FACILITY 9,000.00
Additional Bond Premium
a. BDC-TWG Chairperson 1.00 lot 7,500.00 7,500.00
c. Barangay Treasurer (in-kind) 1.00 lot 7,500.00 7,500.00
TOTAL FOR ADDITIONAL BOND PREMIUM 15,000.00
Personal Protective Equipment
Page 3 of 30
Steel Filing Cabinet
Steel Filing Cabinet (Vertical Standing 4 layers with lock) 1.00 set 11,000.00 11,000.00
TOTAL FOR FILING CABINET 11,000.00
Material Testing
Fabricated Steel Beam Molds (6" x 6" x 21") 3.00 units 2,000.00 6,000.00
Delivery of Samples 1.00 lot 1,500.00 1,500.00
Flexural Strength on Concrete 3.00 pcs 650.00 1,950.00
TOTAL FOR MATERIAL TESTING 9,450.00
Administrative and Overhead Expenses 1.00 lot 42,655.00 42,655.00
TOTAL FOR ADMINISTRATIVE AND OVERHEAD EXPENSES 42,655.00
Sub-Total B 148,715.00
TOTAL (A+B) 1,864,782.00
ADD: Contingency
2.26% 38,775.00
TOTAL ESTIMATED COST 1,903,557.00
ADD: O&M (Other Amenities)
GRAND TOTAL 1,903,557.00
Page 4 of 30
KALAHI CIDSS NCDDP ADDITIONAL FINANCING
Barangay Alayao
Municipality of Capalonga
Province of Camarines Norte
Item no. Scope of Work ( Direct Cost ) % Weight Quantity Unit Unit Price Total
1,934,294.00 ###
###
ENGR. JOPHETH S. RELUCIO VERONICA R. PAMPAG
Technical Facilitator BDC-TWG Chairperson
###
Reviewed by: Concurred by: ###
###
###
ENGR. WILFREDO I. CALDIT JR. HON. SANTIAGO M. VALDEZ ###
Municipal Engineer Barangay Chairperson ###
###
###
Noted by: Noted by: ###
###
Barangay Alayao
Municipality of Capalonga
Province of Camarines Norte
SUNDAY
SUNDAY
SUNDAY
SUNDAY
SUNDAY
SUNDAY
SUNDAY
SUNDAY
82.10 Planned Review and 20.52 20.52 20.52 20.52
PORTLAND CEMENT
311 780.00 sq.m 1,408,820.00 Awarding of
CONCRETE PAVEMENT Actual Contract, PREPARATION OF
Delivery of SUBMISSION OF
0.61 Planned 0.61 2ND & FINAL
SPL- 1 PROJECT SIGNAGE 2.00 sets 10,475.00 Materials 2ND TRANCHE RFR
TRANCHE RFR
Actual ###
1.16 Planned 1.16
SPL- 2 PROJECT MARKER 1.00 set 19,977.00
Actual
TOTAL 1,716,067.00 100.00 0.00 1.92 5.93 26.45 20.52 20.52 20.52 4.13
ENGR. JOPHETH S. RELUCIO ENGR. WILFREDO I. CALDIT JR. VERONICA R. PAMPAG HON. SANTIAGO M. VALDEZ ENGR. DENVER A. BANLASAN
Technical Facilitator Municipal Engineer BDC-TWG Chairperson Barangay Chairperson PDO IV - Engineering Unit
Page 6
OFFICE OF THE BARANGAY SUB-PROJECT MANAGEMENT COMMITTE
Barangay San Francisco
Municipality of Talisay
Province of Camarines Norte
ITEM
ITEM DESCRIPTION QTY UNIT
NO.
A. Materials
Aggregate Base Course 242.00 cu.m.
Sub-Total
B. Labor
Productivity Rate: 10.00 cu.m/team/day (1 s
Skilled Laborer 13.00 days
Laborer 13.00 days
Sub-Total
C. Equipment Rentals
Productivity Rate: 10.00 cu.m/day
Portable Plate Compactor (FOL & Operator included) 13.00 days
Sub-Total
Length 700.00 m
Width 3.00 m
Thickness 0.20 m
Area 2,100.00 sq.m
Volume 420.00 cu.m
A. Materials
Portland Cement 3,780.00 bags
Washed Sand 252.00 cu.m.
Crushed Gravel (1") 420.00 cu.m.
CWN #3 3.00 kgs
CWN #4 4.00 kgs
Nylon #80 3.00 kgs.
Flat bar 2" x ¼'' thk. (Groove Liner) 4.00 pc.
Asphalt Filler 40.00 kgs.
2"x 6" C Purlins 32.00 pcs
2"x2" angle bar 10.00 pcs
12 mm dia. Def. Bars 5.00 pcs.
Empty Cement Bags 2,000.00 pcs
Trapal/saccoline 20.00 m
Water Drum ( 200 li) 5.00 pcs.
Empty Container 5.00 pcs.
Sub-Total
B. Labor
For Concrete Pouring
Productivity Rate: 7.50 cu.m/day/team
[Team: 4-Skilled Laborer, 12-Comm
Skilled Laborer 56.00 days
Laborer 56.00 days
Sub-Total
For Formworks (installation & dismantling, base corrections, and application of aphalt filler)
Productivity Rate: 30.00 sq.m/day/team
[Team: 2-Skilled Laborer, 2-Commo
Skilled Laborer 24.00 days
Laborer 24.00 days
Sub-Total
C. Equipment Rentals
Productivity Rate: 7.50 cu.m/day
One-Bagger Concrete Mixer (Operator & FOL included) 56.00 days
Sub-Total
I. Boulder Laying
Sta.0+000 to Sta. 0+77.7 77.7 m
Sta. 0+148.5 to 0+285.4 136.9 m
Sta. 0+289.3 to 0+ 382.7 236.9 m
Sta. 0+388.3 to 0+554.4 166.1 m
Sta. 0+592.3 to 0+700 257.7 m
Length 700.00 m
Cross sectional Area 0.28 sq.m.
Estimated Quantity 192.50 cu.m.
A. Materials
Boulders (0.1m - 0.2m dia.) 193.00 cu.m.
Portland Cement 809.00 bags
Washed Sand 77.00 cu.m.
ITEM
ITEM DESCRIPTION QTY UNIT
NO.
B. Labor
Productivity Rate: 6.00 cu.m/day/team
[Team: 2-Skilled Laborer, 10-Comm
II. Plastering
Length 700.00 m
Cross-sectional Length 0.28 m
Quantity (both sides) 1.00 side
Estimated Quantity 192.50 sq.m.
Thickness 0.016 m
Volume 3.080 cu.m.
A. Materials
Portland Cement 37.00 bags
Washed Sand 4.00 cu.m.
Sub-Total
B. Labor
Productivity Rate: 12.00 sq.m/day/team
[Team: 2-Skilled Laborer, 2-Commo
A DIRECT COST
Material Cost
Equipment Rental
Labor Cost:
a. Skilled
b. Unskilled
Sub-Total A
B INDIRECT COST
Pre-Engineering
Supervision
Mobilization/demobilization
Contractor's Profit
Taxes
ITEM
ITEM DESCRIPTION QTY UNIT
NO.
Personal Protective Equipments
First Aid Kit 1.00 set
Dust Mask 15.00 pcs.
Construction Gloves w/ rubber coating 60.00 pairs
Safety Rubber Boots 5.00 pairs
Sub-Total
Hand Tools
Shovel(construction use) 10.00 pcs.
Pick Mattock 4.00 pcs.
Sledge hammer 5.00 pcs.
Digging Bar 6.00 pcs.
Sub-Total
Material Testing
Temporary Facility Rental
Filing Cabinet
Bond Premium
Administrative and Overhead Expenses
Sub-Total B
TOTAL (A+B)
ADD: Contingency
≤ 5%
TOTAL ESTIMATED COST
ADD: O&M (Other Amenities)
GRAND TOTAL
Noted by:
D COST ESTIMATES
RATE PER
No. of Crew/
DAY/UNIT TOTAL
Labor
COST
700.00 169,400.00
169,400.00
255,200.00
265.00 1,001,700.00
750.00 189,000.00
1,000.00 420,000.00
65.00 195.00
65.00 260.00
320.00 960.00
530.00 2,120.00
155.00 6,200.00
750.00 24,000.00
550.00 5,500.00
250.00 1,250.00
7.00 14,000.00
70.00 1,400.00
1,500.00 7,500.00
150.00 750.00
1,674,835.00
cu.m/day/team
[Team: 4-Skilled Laborer, 12-Common Laborer ]
4.00 400.00 89,600.00
12.00 300.00 201,600.00
291,200.00
sq.m/day/team
[Team: 2-Skilled Laborer, 2-Common Laborer ]
6.00 400.00 57,600.00
6.00 300.00 43,200.00
100,800.00
2,178,835.00
800.00 154,400.00
265.00 214,385.00
750.00 57,750.00
RATE PER
No. of Crew/
DAY/UNIT TOTAL
Labor
COST
320.00 640.00
1,800.00 7,200.00
434,375.00
cu.m/day/team
[Team: 2-Skilled Laborer, 10-Common Laborer ]
265.00 9,805.00
750.00 3,000.00
12,805.00
sq.m/day/team
[Team: 2-Skilled Laborer, 2-Common Laborer ]
600,580.00
48,000.00
7,500.00 7,500.00
7,500.00
2,298,915.00
164,000.00
230,000.00
397,200.00
3,090,115.00
5,000.00
RATE PER
No. of Crew/
DAY/UNIT TOTAL
Labor
COST
1,500.00 1,500.00
50.00 750.00
50.00 3,000.00
350.00 1,750.00
7,000.00
490.00 4,900.00
500.00 2,000.00
500.00 2,500.00
530.00 3,180.00
12,580.00
5,000.00
5,000.00
5,000.00
5,000.00
30,000.00
74,580.00
3,164,695.00
75,305.00
3,240,000.00
3,240,000.00
BSPMC Chairperson
Barangay Chairperson
Prepared by : Approved by :
Noted:
Note: Costing to be used on the MIBF will be the Total Estimated Cost
KALAHI-CIDSS NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROJECT
COMMUNITY PROCUREMENT PLAN (CPP)
Name of Proposed Community Project: CONCRETING OF ACCESS ROAD Date Prepared: July 30, 2018
Barangay: SAN FRANCISCO Municipality TALISAY Province: CAMARINES NORTE
Total Estimates Cost: 3,240,000.00
Community Project Duration: 78 days 12-Jul-15
Items to be Procured Quantity Unit of Measures Unit Cost Total Cost Procurement Method Possible Supplier Schedule of Procurement Comments/Remarks
Package I
PROJECT SIGNAGE 1.00 lot 7,500.00 7,500.00
SUB-TOTAL 7,500.00 CSG 1st Tranch - 1st Month
Package II
AGGREGATES
Aggregates base course 194 cu.m. 700.00 135800.00
Washed Sand 267 cu.m. 750.00 200250.00 CSG 1st Tranch - 1st Month
Crushed Gravel (G-1") 336 cu.m. 1000.00 336000.00
Boulders (0.1m dia - 0.2m dia) 155 cu.m. 800.00 124000.00
SUB-TOTAL 796,050.00
Package III
HARDWARE MATERIALS
Portland Cement 3,700.00 bags 265.00 980,500.00
CWN #3 3.00 kgs 65.00 195.00
CWN #4 4.00 kgs 65.00 260.00
Nylon #80 5.00 kgs. 320.00 1,600.00
Flat bar 2" x ¼'' thk. (Groove Liner) 4.00 pc. 530.00 2,120.00
Asphalt Filler 40.00 kgs. 155.00 6,200.00
2"x 6" C Purlins 32.00 pcs 750.00 24,000.00
2"x2" angle bar 10.00 pcs 550.00 5,500.00
12 mm dia. Def. Bars 5.00 pcs. 250.00 1,250.00
Empty Cement Bags 2,000.00 pcs 7.00 14,000.00 C
Trapal/saccoline 20.00 m 70.00 1,400.00
Water Drum ( 200 li) 5.00 pcs. 1,500.00 7,500.00 B 1st Tranch - 1st Month
Empty Container 5.00 pcs. 150.00 750.00 G
Wheelbarrow (heavy duty) 4.00 units 1,800.00 7,200.00
PPE 0.00
Dust Mask 15.00 pcs. 50.00 750.00
Construction Gloves w/ rubber coating 60.00 pairs 50.00 3,000.00
Safety Rubber Boots 5.00 pairs 350.00 1,750.00
HANDTOOLS 0.00
Shovel(construction use) 10.00 pcs. 490.00 4,900.00
Pick Mattock 4.00 pcs. 500.00 2,000.00
Sledge hammer 5.00 pcs. 500.00 2,500.00
Digging Bar 6.00 pcs. 530.00 3,180.00
SUB-TOTAL 1,070,555.00
Package IV
EQUIPMENT
One (1) bagger mixer 56.00 days 2,000.00 112,000.00 CSG 1st Tranch - 1st Month
Two (2) unit Potable Plate Compactor 13.00 days 2,000.00 52,000.00
SUB-TOTAL 164,000.00
Package V
PERSONAL PROTECTIVE EQUIPMENT
First Aid Kit 1.00 set 1,500.00 1,500.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 1,500.00
Package VI
MATERIAL TESTING 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package VII
PROJECT SUPERVISION 1.00 lot 38,400.00 38,400.00 CFA 1st Tranch - 1st Month
SUB-TOTAL 38,400.00
Package VIII
Skilled Worker 1.00 lot 160,000.00 160,000.00
Labor 1.00 lot 303,360.00 303,360.00 CFA 1st Tranch - 1st Month
SUB-TOTAL 463,360.00
Package IX
PRE ENGINEERING 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package X
TEMPORARY FACILITY RENTAL 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package XI
FILING CABINET 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package XII
Administrative and Overhead Expense 1.00 lot 30,000.00 30,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 30,000.00
Package XIII
BOND PREMUIM 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
TOTAL 3,240,000.00
FINAL TRANCHING
TRANCHE TRANCHE AMOUNT %
1st Tranch 80.13% 1st Tranch 2,592,000.00 80.00%
2nd tranch 8.77% 2nd Tranch 324,000.00 10.00%
3rd Tranch 11.09% 3rd Tranch 324,000.00 10.00%
TOTAL 100.00% TOTAL 3,240,000.00 100.00%
Name of Proposed Community Project: CONCRETING OF ACCESS ROAD Date Prepared: July 30, 2018
Barangay: SAN FRANCISCO Municipality TALISAY Province: CAMARINES NORTE
Total Estimates Cost: 3,240,000.00
Community Project Duration: 78 days 12-Jul-15
Items to be Procured Quantity Unit of Measures Unit Cost Total Cost Procurement Method Possible Supplier Schedule of Procurement Comments/Remarks
Package I
PROJECT SIGNAGE 1.00 lot 7,500.00 7,500.00
SUB-TOTAL 7,500.00 CSG 1st Tranch - 1st Month
Package II
AGGREGATES
Aggregates base course 121.00 cu.m. 700.00 84700.00
Washed Sand 167.00 cu.m. 750.00 125250.00 CSG 1st Tranch - 1st Month
Crushed Gravel (G-1") 210.00 cu.m. 1000.00 210000.00
Boulders (0.1m dia - 0.2m dia) 97.00 cu.m. 800.00 77600.00
SUB-TOTAL 497,550.00
Package III
HARDWARE MATERIALS
Portland Cement 2,313.00 bags 265.00 612,945.00
CWN #3 3.00 kgs 65.00 195.00
CWN #4 4.00 kgs 65.00 260.00
Nylon #80 5.00 kgs. 320.00 1,600.00
Flat bar 2" x ¼'' thk. (Groove Liner) 4.00 pc. 530.00 2,120.00
Asphalt Filler 40.00 kgs. 155.00 6,200.00
2"x 6" C Purlins 32.00 pcs 750.00 24,000.00
2"x2" angle bar 10.00 pcs 550.00 5,500.00
12 mm dia. Def. Bars 5.00 pcs. 250.00 1,250.00
Empty Cement Bags 2,000.00 pcs 7.00 14,000.00 C
Trapal/saccoline 20.00 m 70.00 1,400.00
Water Drum ( 200 li) 5.00 pcs. 1,500.00 7,500.00 B 1st Tranch - 1st Month
Empty Container 5.00 pcs. 150.00 750.00 G
Wheelbarrow (heavy duty) 4.00 units 1,800.00 7,200.00
PPE 0.00
Dust Mask 15.00 pcs. 50.00 750.00
Construction Gloves w/ rubber coating 60.00 pairs 50.00 3,000.00
Safety Rubber Boots 5.00 pairs 350.00 1,750.00
HANDTOOLS 0.00
Shovel(construction use) 10.00 pcs. 490.00 4,900.00
Pick Mattock 4.00 pcs. 500.00 2,000.00
Sledge hammer 5.00 pcs. 500.00 2,500.00
Digging Bar 6.00 pcs. 530.00 3,180.00
SUB-TOTAL 703,000.00
Package IV
EQUIPMENT
One (1) bagger mixer 56.00 days 2,000.00 112,000.00 CSG 1st Tranch - 1st Month
Two (2) unit Potable Plate Compactor 13.00 days 2,000.00 52,000.00
SUB-TOTAL 164,000.00
Package V
PERSONAL PROTECTIVE EQUIPMENT
First Aid Kit 1.00 set 1,500.00 1,500.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 1,500.00
Package VI
MATERIAL TESTING 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package VII
PROJECT SUPERVISION 1.00 lot 24,000.00 24,000.00 CFA 1st Tranch - 1st Month
SUB-TOTAL 24,000.00
Package VIII
Skilled Worker 1.00 lot 100,000.00 100,000.00
Labor 1.00 lot 189,600.00 189,600.00 CFA 1st Tranch - 1st Month
SUB-TOTAL 289,600.00
Package IX
PRE ENGINEERING 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package X
TEMPORARY FACILITY RENTAL 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package XI
FILING CABINET 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
Package XII
Administrative and Overhead Expense 1.00 lot 30,000.00 30,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 30,000.00
Package XIII
BOND PREMUIM 1.00 lot 5,000.00 5,000.00 CSG 1st Tranch - 1st Month
SUB-TOTAL 5,000.00
TOTAL 3,240,000.00
FINAL TRANCHING
TRANCHE TRANCHE AMOUNT %
1st Tranch 53.77% 1st Tranch 2,592,000.00 80.00%
2nd tranch 35.14% 2nd Tranch 324,000.00 10.00%
3rd Tranch 11.09% 3rd Tranch 324,000.00 10.00%
TOTAL 100.00% TOTAL 3,240,000.00 100.00%
Temporary Facility
1 3.00 months 9,000.00 9,000.00 - 9,000.00
Rental
NA
Additional Bond
2 1 lot 7,500.00 7,500.00 - 7,500.00
Premium
TOTAL 16,500.00 16,500.00 - 16,500.00
MARJORETTE T. ROLL ENGR. JOPHETH S. RELUCIO VERONICA R. PAMPAG HON. SANTIAGO M. VALDEZ
PT Head Technical Facilitator BDC-TWG Chairperson Barangay Chairperson
OFFICE OF THE BARANGAY DEVELOPMENT COUNCIL- TECHNICAL WORKING GROUP
KALAHI-CIDSS NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROJECT - ADDITIONAL FINANCING
EMERGENCY COMMUNITY PROCUREMENT PLAN (ECPP)
Barangay: Alayao Name of Proposed Community Project: CONCRETING OF ACCESS ROAD Date Prepared: 24-Nov-22
Municipality: Capalonga Community Project Duration: 76 Calendar Days
Province: Camarines Norte Total Project Cost: PHP 1,903,557.00
d. Opening and Evaluation of Canvass (Provision for 1 lunch and 1 snack) 15 pax 80.00 1,200.00
e. Pre-Construction Conference (Provision for 1 lunch and 1 snack) 15 pax 80.00 1,200.00
f. Barangay Activity Reporting (Provision for 1 lunch and 1 snack) 17 pax 80.00 1,360.00
g. Barangay Sustainability Planning Workshop (Provision for 1 lunch and 1 snack) 17 pax 80.00 1,360.00
h. CM Planning (Provision for 1 lunch and 1 snack) 17 pax 80.00 1,360.00
i. O & M Planning (Provision for 1 lunch and 1 snack) 17 pax 80.00 1,360.00
VIII. Travel expenses for Bond application
Sending of Application in KC Office
1 CV x 100 Fare x 1 day 1 pax 100.00 100.00
Payment of Bond in Landbank
1 CV x 150 Meal Allowance x 200 Fare 1 pax 350.00 350.00
Prepared by:
2,400.00
2,900.00
5,060.00
8,400.00
5,905.00
400.00
17,140.00
450.00
42,655.00
KALAHI CIDSS NCDDP ADDITIONAL FINANCING
Barangay Alayao
Municipality of Capalonga
Province of Camarines Norte
Item no. Scope of Work ( Direct Cost ) % Weight Quantity Unit Unit Price Total
1,934,294.00 ###
###
ENGR. JOPHETH S. RELUCIO VERONICA R. PAMPAG
Technical Facilitator BDC-TWG Chairperson
###
Reviewed by: Concurred by: ###
###
###
ENGR. WILFREDO I. CALDIT JR. HON. SANTIAGO M. VALDEZ ###
Municipal Engineer Barangay Chairperson ###
###
###
Noted by: Noted by: ###
###