Thermal Management Solutions - Vertiv
Thermal Management Solutions - Vertiv
Thermal Management Solutions - Vertiv
MANAGEMENT
SOLUTIONS - DX
İlke CAKABEY
Thermal Sales Manager
07.04.2021
TARGET OF THE PRESENTATION
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 2
PRINCIPLES OF PRECISION
COOLING APPLICATIONS
3
4
TECH-BYTE SEMINARS - Module 1.1 – V3
EVERYTHING STARTS FROM THE SERVER…
We can consider that every kW of Electric energy brought into the datacenter
is transferred into Heat
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 5
IDEAL CONDITIONS
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 6
WHEN IT WORKS, IT MAKES HEAT
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 7
AIR DISTRIBUTION IN THE DATA CENTER
q1
Servers Airflow
qservers = q1 + q2 + ...qn
q2
• High Temperature
Increased Server Power Consumption
Decreased Server Performance
Decreased Server Lifetime
Increased Server Noise
In Extreme Cases Shutdown of System
• High Humidity
Condensation
Server Corrosion
• Low Humidity
Static Electrical Discharge
• Dust
Electrical Short Circuits
START STRONG FINISH STRONG 8.11.16 • Malta • 9
WHERE DOES A HEAT LOAD COME FROM? IN A GENERAL
WORKING ENVIRONMENT
❑ People
❑ Ventilation Requirements
❑ Electronic/Electric Devices
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 10
SENSIBLE HEAT RATIO (SHR)
Latent
Capacity
Latent
Capacity
Sensible
Sensible Capacity
Capacity
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 13
OPEN ARCHITECTURE: HOT AISLE / COLD AISLE APPROACH
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 14
IF AIRFLOW IS NOT ENOUGH…
Hot Aisle
Recirculation!
Cold Aisle
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 15
PATENTED: SMARTAISLETM DYNAMIC CONTROL
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 16
SMARTAISLETM DYNAMIC CONTROL: SENSORBOX
18
COOLING PRODUCT TOPOLOGY
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 19
PUE : POWER USAGE EFFECTİVENESS
PUE is a Measure of Data Center Efficiency is needed to help drive the right
behavior for improving efficiency
PUE
Energy for IT
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 20
MECHANICAL PUE - SIMPLIFYING THE COMPARISON
Fan
Scalable
Best Fit to
Expansion
Expansion Valve
Scenario
Less
Floor Mount
Unit Evaporator Complexity
Easy
Air Cooled
Condenser Maintenance
Best Day 1
Compressor
Efficiency
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 22
23
LIEBERT® PDX – INDOOR UNIT: MAIN FEATURES
5 kW 165 kW
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 23
LIEBERT® PDX – INDOOR UNIT: MAIN FEATURES
iCOM®
Control
TXV or EEV
5 Cooling
Versions and
Economizer
(Digital) Scroll
Compressor
3 Humidifiers
Liebert EC
Fan 2.0
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 24
Liebert® Humidifiers
Product Range – Humidifiers
. .
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 26
LIEBERT® WITH AN OPTIMAL SOLUTION:
WHEREVER YOU WANT YOUR DATA CENTER TO BE
. .
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 27
LIEBERT® HPM-S
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 28
IN-ROW COOLING
CRV-DCL
29
LIEBERT® CRV – IN ROW COOLING
Range:
DX 14-35kW CW 30-50kW
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 30
LIEBERT CRV – ROW BASED COOLING
▪ DX and CW Version
▪ 300 and 600 mm wide frame
▪ Wide Range: 4 basic capacities in DX and 5 in CW version
▪ High Efficiency:
▪ EC Fans
▪ Inverter driven scroll compressor on the 300mm frame
▪ Digital Scroll on the 600 mm frame
▪ High Density Applications: up to 10kW/Rack in open architecture
▪ Rich features: Humidifier, Re-heat, ATS, and more…
Direct Expansion (DX) Chilled Water (CW)
New New New New
2019 2019 2019 2019
CR012RA CR025RA CR020RA/W CR035RA/W CR030RC CR052RC CR060RC CR040RC CR050RC
kW 13,6 22,2 23.4 36.4 39,2 54 57.0 46.6 58.0
Humidity
No Yes Yes Yes Yes No Yes Yes No
Control
Width 300 mm Frame 600 mm Frame 300 mm Frame 600 mm Frame
Rating Conditions: DX – 38 °C, 22% RH, 35 °C Outdoor temperature; CW – 38 °C, 22% RH, 7/12 °C CW Temperature
38
39
*Additional Notes
COOLING CAPACITY
• Since comfort cooling units have been designed for comfort application, a significant part of their
cooling capacity (approx. 35%) is Latent Capacity
• Data centers however require mainly SENSIBLE CAPACITY
• Therefore Thermal Management units have been designed to maximize the Sensible Cooling
Capacity
10
Cooling Capacity (kW)
Latent
In this comparison we can see
Capacity
that 10 kW comfort unit behaves
6.5
in datacenter applications as only
5 Sensible a 6.5 kW unit.
Capacity
Sensible
Capacity
1. 10 kW Comfort Cooling Unit is not equal to 10 kW Thermal Management unit in Data Center
application
2. For 10 kW of heat load in data center you would need a 15 kW Comfort Cooling unit
15
Latent
To cool 10 kW of data center heat
Cooling Capacity (kW)
Capacity
load you would need a 15 kW
10
Comfort Cooling unit or a 10 kW
Thermal Management unit
Sensible
Sensible
Capacity
Capacity
5
Comfort Cooling
START STRONG FINISH STRONG 8.11.16 • Malta • 40
*Additional Notes
41
OPERATION
Operation Cost COSTS
• As we have previously seen, to cool 10 kW of heat load in a data center we need a 15 kW comfort
cooling air conditioner
• 15 kW comfort unit has approx 50% higher power input than 10 kW Thermal Management unit
15 kW unit 10 kW unit
Power Input
Power Input
4.5 kW 3 kW
Customers can save up to 50% of their operating costs on cooling by installing a Thermal
Management unit instead of a comfort air conditioner
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 42
LIEBERT® HPW– HOW FREECOOLING WORKS?
Room Outside
Room Outside
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 43
LIEBERT® HPF– OVERVIEW
Cooling Type:
– Indoor Package Solutions
Mounting:
– Floormount
Cooling Range:
– From 5 to 15 kW
Versions:
– Under, Over and Displacement
Options:
– Freecooling,
– Emergency 48V DC
– EC fan
Colours:
– Charcoal grey
– Light grey RAL7035
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 44
LIEBERT HPF – WITH FLEXIBLE CIRCULAR CHANNEL
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 45
LIEBERT® HPS: MAIN FEATURES
- Air Filtration
- Indoor ventilation Liebert SE
- Fresh Air or Emergency freecooling
HPSC
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 46
LIEBERT® HPS: AIR DELIVERY TYPES
START STRONG FINISH STRONG Preliminary planning document, subject to consultation, negotiation or other local legal requirements. 8.11.16 • Malta • 47