Modern Railway Track
Modern Railway Track
Modern Railway Track
Coenraad Esveld
Coenraad Esveld
Emeritus Professor of Railway Engineering
Delft University of Technology
ISBN 978-1-326-05172-3
SISO 696.3 UDC 625.1
© Copyright 2001/2014 C. Esveld
This work is subject to copyright. All rights are reserved, whether the whole or part of the
material is concerned, specifically the right of translation, copying, reprinting, re-use of
illustrations, recitations, broadcastings, reproduction on microfilm or in other ways, and storage
in data banks. Duplication of this publication or parts thereof is only permitted under the Dutch
Copyright Law.
The digital version 3 can be bought via www.esveld.com. The paper version of the second
edition can also be ordered from www.esveld.com.
ii
Modern Railway Track PREFACE
It is my intension to update the book in the next couple of years to the actual state of
technology, with emphasis on weld treatment and slab track. But also contact mechanics, track
components and the new EN standards will be treated. That digital version will be published as
MRT-4
It would be very much appreciated if the readers of this book will suggest any improvements or
enhancements. Please don’t hesitate to contact me at [email protected]. Actual
information can be found on www.esved.com under the heading ‘Modern Railway Track’. At the
heading ‘Downloads’ and then ‘Additional Downloads’ you can find pdf files of my lectures,
conference presentations and a basic railway course in Dutch.
Autumn 2014,
Coenraad Esveld
iii
Modern Railway Track PREFACE
xv
Modern Railway Track 1 INTRODUCTION
7.02+ BS
5.50+ BS 5.50+ BS
Catenary system via portal structure: V ≤ 140 km/h Catenary system via rotating lever: V > 140 km/h
The contact line should be kept at a constant tension for a good and continuous contact with
the pantograph which is pushed against the wire by means of springs. The tension is obtained
by weights or by means of gas cylinders at the end of the wire. Given the material of the wire
(copper), the length of the wire (about 1500 m), and temperature fluctuations, length variations
appear of about 50 cm. It is therefore of importance that the suspension points of the wires are
able to move with the expanding and contracting wire.
a. fixed suspension: for instance portal structures (Figure 1.2, left picture),
With a. the portals and carrying cables are fixed to each other. Because of this the carrying
cables sag a little with warm weather and hence the contact wire as well. With b. the poles and
carrying cables are fastened to each other flexibly. The cantilevers of the poles are movable and
will change along with the carrying cables when temperature changes. The contact wire can
now stay completely flat. The single pole structure is used with speeds of 140 km/h and higher.
At lower speeds portal structures can be used.
Concerning metro systems the so-called third rail takes care of the supply of the current. This
rail is installed next to the two rails carrying and guiding the train. Because of this no catenary
system is necessary. This leads to a smaller clearance and therefore a smaller and cheaper
tunnel construction is possible. When crossing over metro lines, the required height under the
bridge can be lower. However, people should always be kept away from this third rail; the track
should be inaccessible and without level crossings.
8
Modern Railway Track 1 INTRODUCTION
When choosing a track system, the above-mentioned requirements must all be given due
consideration and it is clearly necessary to form some idea of the axle loads and maximum
speeds to be expected in the decades to come. After this the situation regarding the various
track components, such as rails, sleepers, fastenings, switches, and ballast should be examined
so that the optimum track design is obtained.
15
Modern Railway Track 2 WHEEL-RAIL INTERFACE
2 WHEEL-RAI L I NTERFACE
2.1 Wheel-rail guidance
A rail vehicle basically consists of a body supported by secondary suspension on bogies in which
the wheelsets are mounted and damped by means of primary suspension. Track guidance of
the wheel is achieved in principle by making the following two provisions:
− The tires are conical instead of cylindrical which means that in straight track a centering
force is exerted on the wheelset if there is slight lateral displacement. The centering
effect promotes a better radial adjustment of the wheelset in curves. This leads to more
rolling, less slipping and hence less wear.
− The tires have flanges on the inside of the track to prevent derailment. In case of more
considerable lateral displacement both in curves and on switches, the lateral clearance
between wheelset and track is often no longer sufficient to restrict lateral displacements
adequately by means of the restoring mechanism previously discussed. Should the
wheel flange touch the rail head face, this can result in high lateral forces and wear.
Track width 70 mm
14
1:20 (1:40)
Inclination
+3/–3
Flange gauge Inside gauge 1360
+0/–16
Track gauge Flange gauge 1426
+10/–3
Track gauge 1435
Figure 2.1: Wheelset and track dimensions for straight normal gauge track
17
Modern Railway Track 2 WHEEL-RAIL INTERFACE
With a conical profile the conicity is constant and (2.8) Conic profile
becomes (see also): y
∆ ( + )−( − ) ≈2γe
=½ = ½ = (2. 9)
y y
In the next paragraph the effects resulting from
progressive non-linear behavior of the effective conicity Flangeway clearance
and its influence on the running stability of vehicles and
rail wear are dealt with in greater detail.
2.6 Worn w heel profiles Figure 2.7: y-∆r curves. Difference between conical and
worn wheel profiles
22
Modern Railway Track 2 WHEEL-RAIL INTERFACE
give a stable equilibrium, but will instead induce a highly frequent jumping to and fro between
two points on the curve.
2.7.6 Spin
sin sin y
ɸ= = (2. 16) Slip
Adhesion
It should be noted that the spin ø has a
dimension [1/m].
30
Modern Railway Track 9 SLAB TRACK
After adjustment, the rail is made stress free by means of heating before the compound is
poured into the groove (Figure 9.52).
Many pilot tracks of embedded rail have been applied over the last 30 years, 246 m paved-in as
well as main-line track. Nearby Deurne (The Netherlands) in 1976, a pilot was constructed in
heavily used track with speeds up to 160 km/h. The track existed of a series of 6 meters of
prefabricated slabs containing the gullies supported underneath with old NP46 rails [201]. The
experiences were qualified as positive. In 1994, the rails were renewed, but the wear of those
rails was considerably less compared to the adjacent track.
Another large pilot concerned 3 km track nearby Best (The Netherlands) which came into
operation in October 1999 and is currently being monitored.
The superstructure consists of a 42 cm thick slab with longitudinal reinforcement providing the
slab with a high flexural strength. The slab lies on top of a concrete road bed and stabilized
subsoil. The cross section of this track structure is shown in Figure 9.48, while the construction
process of this test track is illustrated in Figure 9.49 up to and including Figure 9.54.
Embedded Rail
0.6 m
Concrete slab
Sand bed
2.5 m
Figure 9.48: Cross section of the embedded rail superstructure near Best
Figure 9.49: Installing of the rails Figure 9.50: Positioning of the rails by means of wedges
285
Modern Railway Track 10 THE RAIL
309
Modern Railway Track 11 SWITCHES AND CROSSINGS
It must be possible to run through switches and crossings in both directions. A normal or single
turnout, as shown in Figure 11.1, allows movement of traffic in a straight direction on the
through track or in a divergent direction. A picture of the right-hand turnout is given in Figure
11.2.
A B
R=... m
1:n
422
Modern Railway Track 16 INSPECTION AND DETECTION SYSTEMS
In addition to the dynamic signals, quasi-static signals are produced for cant, curvature, and
gauge. The measuring principles are presented schematically in Figure 16.84. Problems due to
drift and lack of initial conditions mean that the quasi-static cant is not determined by
integration of the rate gyro signal, but by making use of the lateral car body acceleration,
curvature, and recording speed as indicated in Figure 16.84.
Y ≅ Κv 2 − gφB 1 θ
Κ = ≈ YS = YL + YR + 1435 mm
R L
φ = φ B − Δφ
θ = θ1 + θ 2
g θ1 θ2
gφB L
Κv 2
Y″ R
φB θ YR
Δφ YL
φ
All signals low pass filtered with 3rd order Bessel filter
Two other transducers are, in addition to the two linear displacement transducers between car
body and bogie frame in the measuring bogie, installed in the second bogie to record curvature
according to the principle sketched in Figure 16.84. The quasi-static gauge is directly derived
from the line-scan camera signals.
All three quasi-static signals are low-pass filtered with a 3rd-order Bessel filter. The phase
relationship is linear and causes a distance delay of 27.5 m. As the curvature recorded in fact
corresponds to the car center, the delay of the signal in relation to the measuring bogie
amounts to 35 m or 20 m for forwards and backwards running respectively. With the
introduction of VRA this delay can be corrected.
The track parameters produced by the former BMS system of NS are derived from a
combination of signals provided by 16 transducers, i.e. 1 rate gyro, 2 accelerometers, 10
LVDTs, 2 line-scan cameras, and 1 tachometer. The location of the various transducers is
indicated in Figure 16.85. The track parameters are derived from the following expressions:
Level:
+
= − +∆ (16.6)
2
582
Modern Railway Track 16 INSPECTION AND DETECTION SYSTEMS
Dynamic components of the wheel rail contact force have a significant impact on track
deterioration and should therefore be kept as low as possible. Weld geometry plays an
important role as a main contributor to high-frequency loads. At TU Delft this aspect was given
high priority in the early beginning of the 21 century, with a study aiming at developing a
theory, with associating algorithm, to describe dynamic component of the vertical wheel rail
contact force. The algorithm should be such that it could be implemented in a PDA, or hand-
held computer, fast enough to make real time calculations within seconds.
The vertical wheel rail contact force is approximately proportional to the square of the speed. In
this way the standards are speed dependent. Furthermore the contact force is linearly related to
the inclination (first derivative dy/dx of the geometry).
= ∗ ∗ (16.43)
The inclination is determined from the versines measured with the RAILPROF on a base of 1 m,
sampled at an interval of 5 mm. During data processing the samples are averaged (low-pass
623