CH 5 Risk
CH 5 Risk
Managing Risk
Risk: is an uncertain condition that, if it occurs has positive or negative
effect on project objectives.
Some potential risk events can be identified before the project starts such
as equipment or change in technical requirements.
Risk Management: attempts to recognize and manage potential and
unforeseen trouble spots that may occur when the project implemented.
Risk management identifies as many risk events as possible (what can
go wrong), minimizes their impact (what can be done about the event
before the project begins), manages responses to those events that
materialize (contingency plans), and provides contingency funds to
cover risk events.
The focused at the beginning should be on risks that can affect the whole
project as opposed to a specific section of the project or network.
Scenario analysis is the easiest and most commonly used technique for
analyzing risks. Team members assess the significance of each risk event
in terms of:
1- Probability of the event
2- Impact of the event
Risks need to be evaluated in terms of the likelihood the event is going to
occur and the impact. The risk of a project manager being struck by
lightning at work site would have major negative impact on the project,
but the likelihood is so low it is not worthy of consideration.
The quality and credibility of the risk analysis process requires that
different level of risk probabilities and impacts be defined. These
definitions should be tailored to the specific nature and needs of the
project.
Some of the most common methods for handling risk are discussed here
1- Technical Risks: are problematic; they can ofen be the kind that
case the project to be shut down. What if the system or process
does not work? Contingency or backup plans are made for those
possibilities that are foreseen. In addition to backup strategies or
contingency plan, project managers need to develop methods to
quickly assess whether technical uncertainties can be resolved.
2- Schedule Risks: here contingency funds are set aside to crash the
project to get it back on track. Crashing or reducing project
duration, is accomplished by shortening (compressing) one or more
activities on critical path.