Sustainable Reservoir Management Through Sediment Flushing BKHEP
Sustainable Reservoir Management Through Sediment Flushing BKHEP
Sustainable Reservoir Management Through Sediment Flushing BKHEP
1. ABSTRACT:
Sediment deposition decreases the life of a reservoir and has adversely affected the sustainability
of many projects in the world. Along with reducing the benefits obtained from the project, it can
also have adverse long-term socio-economic impacts. Betan Karnali Hydroelectric Project is
designed as a PRoR project located in the western region of Nepal. It is geologically located in
the Himalayan region, a region with high sediment inflow (about 19.5 Million Ton/ year). Various
sediment management alternatives are being studied for this project. This paper presents the
sediment management of BKHEP reservoir by passing the sediment through the dam body via
hydraulic flushing with 1D HEC RAS 5.04 model. The result shows that the reservoir which
would have otherwise filled with sediment in 10 years is sustainable even at the end of 47 years
if hydraulic flushing with an average of 8.7 flush days per year and 1800 m3/sec flushing discharge
is introduced.
Key word: Sedimentation, Hydraulic Model (HEC-RAS), Reservoir Operation
2. INTRODUCTION:
Sedimentation is one of the major hurdles for reservoir sustainability. It causes loss of reservoir
capacity which affects the functionality of the system, especially for hydropower plants (Javed
2016).The declining storage reduces and eventually eliminates the capacity for flow regulation
and with it all water supply and flood control benefits, plus those hydropower, navigation,
recreation and environmental benefits that depend on releases from storage (Morris & Fan, 2010).
It is natural for a reservoir to continue accumulating sediments as it ages and with it there is
increase in the sediment related problems. Reservoir sediment management is essential for
ensuring life of the reservoir by protecting the storage capacity and decreasing the long-term
maintenance cost (Annandale, Morris & Karki, 2016). The twentieth century focused on the
construction of new dams but because of the lack of proper knowledge of the rate of sediment
deposition in the reservoir and the importance of proper sediment management, controlled
reservoir capacity reduction was not achieved and as a result reservoirs worldwide are losing
storage capacity as fast as 1 % per year. As it is not feasible to build new dams to replace the
reservoir volume and also not possible to sustain the projected levels of population and economic
activity if the storage reservoirs are lost to sedimentation, the 21st Century is focused on combating
sedimentation to extend the life of existing infrastructures (Morris & Fan, 2010)
If the land areas of the world are ranked according to their susceptibility to natural erosion, the
Himalayas will rank among the most vulnerable (Tejwani 1987). The sediment inflow rate is even
higher in the Himalayan region because of the fragile and complex geology, tectonic activities
and climate. In this region, the sediment concentration is relatively much higher in the monsoon
compared with the dry period. Landslides and mass wasting which are common during the
monsoon area also plays a major role in it. Because of the complex nature of sediment
concentration and deposition pattern, sediment management techniques vary widely from one site
to another and the suitable management technique can only be developed after studying and
analyzing the specific site
The most common methods of sediment management are sediment routing and removal of
sediment deposition. Sediment routing includes any method to manipulate reservoir hydraulics,
geometry or both to pass sediment through or around storage or intake areas while minimizing
objectionable depositions. Sediment routing commonly includes methods like drawdown sluicing
and sediment by-passing (Morris & Fan, 2010).
Removal of sediment deposition as the name suggests includes periodic removal of the
sediments that have been deposited in the reservoir either through mechanized efforts or natural
methods. The commonly used methods of sediment removal include flushing and dredging.
Because of the narrow size of the reservoir and its ability to be refilled quickly when the outlets
are closed, sediment flushing has been proposed and used as a method of sediment management
for this project.
Sediment flushing through reservoir may be the most economic strategy as compared to other
techniques. Atkinson presented a report on the flushing efficiencies of some of the successfully
flushed reservoir and the criteria for estimating the flushing efficiency (Atkinson, 1996). Flushing
is generally of two categories, free flow flushing, and pressure flushing. Free flow flushing is
more efficient compared to pressure flushing (Morris & Fan, 2010). Free flow flushing has been
used for this study. Different flushing rules can exist for any project depending upon the inflowing
sediment data and tradeoff between maximizing the generated energy and compromise of
reservoir storage capacity. Any flushing rules generated during the study, however, must be
optimized based on the data monitored during the operational period of the project (Morris & Fan,
2010).
3. STUDY AREA:
The Karnali River is a perennial trans-boundary river in the Western part of Nepal originating
in the Tibetan Plateau near lake Mansarovar. It cuts through the Himalayas in Nepal and
eventually joins the Ganges. The Betan Karnali Hydro Electric Project is located along the lower
limb of the Karnali River, in the mountainous region of Achham/Surkhet District.
Betan Karnali Hydroelectric Project (BKHEP) is a peaking run of river (PRoR) scheme project
on the Karnali river with 4 to 6 hours daily peaking depending on the inflowing discharge.
BKHEP is designed with a dam height of 80 m (from riverbed level.) with crest level at 477 masl
and having length of about 198 m. The reservoir has a total storage of about 161.5 MCM and
active storage of 36.19 MCM. The full supply level (FSL) of the project has been proposed at
473.30 masl and the minimum drawdown level (MDDL) of 466 masl has been provide. It is
designed with a design discharge of 536 m3/s and gross head of about 100 m producing 442 MW.
450
440
430
420 Volume Elevation Curve
410 Area Elevation Curve
400
390
0 50 100 150 200 250
Storage Volume (Mill. m3)
It produces a total average annual energy of about 2320.42 GWh with an average annual dry
season energy production of about 659.33 GWh and an average annual wet season energy of about
1624.09 GWh. The project area is estimated to have a flood of 8530 m 3/s, 11,548 m3/s, 14,560
m3/s and 22,604 m3/s for a return period of 100, 1000 and 10000 years respectively. The Probable
Maximum Flood (PMF) for the project has been estimated as 22604 m3/sec
The RCC dam is provided with 6 overflow spillway of size 10 m X 12 m (B x H) for water
level regulation, 1 overflow spillway of size 8 m x 8m ( B x H) for floating trash passage and 6
sluice spillway of size 8 m X8 m for sediment flushing. Combinedly, the spillways have been
designed to safely evacuate the probable maximum flood estimated for the project.
There are three hydrological stations set up and operated by the Department of Hydrology and
Meteorology (DHM), Nepal in the river reach relevant to the project area which have been
presented below:
Watershed River
Quality
Name Area Northing Easting Elevation Years of Data
of Data
(Km2) (m)
Lalighat 16,960 29˚9’32” 80˚33’23” 590 1977-2006 Fair
Asaraghat 20,860 28˚57’10” 81 ˚26’30” 629 1966-2012 Good
Benighat 22,664 28 ˚57’10” 81 ˚07’10” 320 1963-2015 Fair
Moreover, the consultants have established both manual and automatic gauge station near
headworks of BKHEP project and has been collecting stage, discharge and sediment data since
May 2018. Based on the manual gauge measurement of discharge at the project location, rating
curves for stage below and above 5 m have been prepared. The rating curves developed for
BKHEP are:
𝑄 = 72.7 ∗ (𝐻 − 1.542)1.615 ( 𝑓𝑜𝑟 𝑠𝑡𝑎𝑔𝑒 𝑏𝑒𝑙𝑜𝑤 5.00 𝑚) (1)
And
𝑄 = (𝐻/0.259)2.132 ( 𝑓𝑜𝑟 𝑠𝑡𝑎𝑔𝑒 𝑏𝑒𝑙𝑜𝑤 5.00 𝑚) (2)
12
10
8
Stage (m)
6
Rating Curve for Stage <5m
4
Rating Curve for Stage >5m
2 Measured Q wth Stage <5m
Measured Q with Stage >5m
0
0 500 1000 1500 2000 2500
Measured Q at BKHEP (m3/sec)
Except Asaragaht other gauging stations have discharge data only. As there is only two years
of measured data at the BKHEP headworks and since Asaraghat is close to BKHEP headworks,
discharge from Asaraghat has been used to generate the long-term hydrological data set at
BKHEP required for sediment modeling.
6. SEDIMENT CHARACTERISTIC AND LOAD ESTIMATION:
Till date 44 Particle Size Distribution (PSD) measurements at different time periods of the year
have been carried out and its results are shown in Figure 4. The sand predominately comprises of
quartz contributing to about 60 % of the total mineral composition, followed by mica and feldspar.
The heavy red dot line as seen in Figure 4 corresponds to the PSD of the inflowing sediment used
for modeling. There are two reasons for selecting the curve with higher sand contribution: (1)
suspended sediment load is measured from a trail bridge located at the site and there exist high
chance that the sand transported at the bed of the river gets under sampled the sand concentration
is underrepresented and (2) a higher sand load represents a more critical condition for modeling.
100
90
80
Percentage Finer
70
60
50
40
30
20
10
0
0.0001 0.001 0.01 0.1 1 10
Particle Size(mm)
The consultant is also designing another project (Phukot Karnali Hydroelectric Project
(PKHEP) on the upstream reach of Karnali. Based on the discharge derived at Headworks of
BKHEP and PKHEP and their corresponding concentrations monitored at the site, a rating
equation for estimating the sediment was developed for the project. Long term discharge data
prorated at BKHEP headworks using Asaraghat gauging station was used to estimate the total
sediment load for the Project. The suspended sediment load estimated at the headwork of the
project is 15.5 MT and the total average annual sediment load is estimated as 19.5 MT. Variation
of sediment concertation with discharge observed at site in relation to the Asaraghat gauging
station is shown in Figure 5
Sediment rating equation used for BKHEP:
1000
(mg/l)
Asaraghat
100 Phukot
Betan
10
100 1000 10000
Discharge (m3/s)
Figure 5. Concentration variation observed at PKHEP, BKHEP and historical data of various discharges
There are no bed load measurements carried out at the project site. The bed materials are very
coarse and flow velocity is very high making it impractical to measure the bed load by
conventional method. Hence to address the unmeasured bed load (primarily sand and gravels) bed
load correction factor of 25% has been added to compute the total load for the modeling purpose.
1600 9
1400 8
Discharge
Figure 6 : Average monthly discharge and sediment load variation at BKHEP headworks
Transport potential is calculated for each grain size at each cross section as if the sediment load
were comprised 100% of that material. Transport capacity for each grain size class is then
computed as the product of the transport potential and the fraction of that material in the active
layer. The total sediment capacity is the weighted average of the transport potentials computed
for each grain size in proportion to the relative abundance of each grain size in the active bed.
Once transport capacity is computed, the sediment continuity equation is solved over each
control volume. A control volume is represented as the distance from the midpoint between the
upstream cross section and the current one, to the midpoint between the downstream cross section
and the current section. Continuity principal is applied for each grain size as the capacity is
compared to the inflowing supply. If transport capacity exceeds supply, material is removed from
the control volume, while deposition results if supply is greater. This is quantified by the Exner
(sediment continuity) equation. (HEC, 2016)
∂n ∂Qs
(1-λp )B =-
∂t ∂x
Where n is the bed elevation, B is the width of the control volume, Qs is transported sediment
load, 𝜆𝑝 is bed porosity, x is a distance, t is the time.
Sediment transport capacity and after flush profiles were estimated using different transport
functions and compared. Out of various transport functions available, Engelund and Hansen
transport function along with Ruby Fall Velocity Method with Copeland (Exner 7) sorting method
was found to best represent the transport capabilities for BKHEP. As the contribution of sand
sized particles is dominant in BKHEP and Engelund and Hansen is a total load transport function
best suited for relatively uniform particles ranging from 0.19mm to 0.93 mm, it has been used for
the reservoir sediment modelling.
8. FLUSHING CONSIDERATIONS:
In BKHEP, discharge ranging from 1000 -2000 m3/sec contributes to almost 75% of the average
annual sediment inflowing into the reservoir as shown in Figure 7. Considering inflowing
discharge-sediment contribution, this paper presents one of the possible scenarios in BKHEP with
3-day flush duration (flushing discharge 1800 m3/sec) and minimal flush interval of 21 days. To
avoid the excessive sediment inflow and deposition into the reservoir, force flush is activated at
2400 m3/sec. To ensure evacuation of the deposited sediments by the end of monsoon, a force
flush on 15th September for 3-days duration has been set each year. With all these considerations,
this study has used average 8.7 days flush per year.
45 7
38.9 % of Average Annual
40 35.9 6
Suspended Load
485
475
Water Level (masl)
465
455
Water Level
445
MDDL (466 masl)
435 FSL (473.3 masl)
Fluhing Level at Dam
425
415
1 2 3 4 5 6 7 8 9 10 11 12
Months of Year
9. METHODOLOGY:
Sediment modeling needs various data sets namely, geometry data, flow data, sediment load,
flushing detailing and water levels, bed gradation and sediment concentrations and detailing of
inline structures etc.
To begin with, available data set for discharge and sediment was collected and analyzed to prepare
the discharge and sediment rating curves and estimate the total load. Geometric file of the reach
under consideration was prepared and physical attributes of the inline structures and reservoir
were provided to the HEC-RAS Model. Boundary conditions were set based on the available data
and the model was run under different transport function and sorting and armoring conditions to
get the satisfactory result. Figure 9 shows the sequential methodological approach adopted for the
study.
As the project is in study phase, there is no data for the proposed reservoir that can be used for
calibration. In absence of the calibrating data, two different procedures have been used for model
validation to check model behavior for reasonableness of the results. The first validation
procedure was to simulate the existing river profile in HEC-RAS. The profiles of the Himalayan
rivers are continuously influenced by the input of materials from landslide and debris flow, but
the reach under study does not have recent perturbations of this type and may be relatively stable
with respect to its longitudinal profile. The model was run for the river in normal scenario and
inflowing load of the coarse bed material was adjusted until the riverbed stabilized, neither
aggrading nor degrading to an appreciable degree.
Figure 10. Longitudinal profiles for Kulekhani reservoir (Shrestha 2012)
The second validation procedure was to confirm that the overall geometry of the delta
developed within the reservoir during the simulation is similar to the pattern observed in other
reservoirs subject to extensive annual drawdown (flushing). Reservoir sedimentation data of
Kulekhani-I (60 MW), one and only reservoir type project of Nepal, was referred to see the
resemblance of sedimentation considering temporal and spatial sediment deposition pattern.
(Shrestha, 2012)
11. RESULTS:
500
480 FSL
10 Year
Elevation (masl)
460
MDDL 20 Year
440 30 Year
420 40 Year
47 Year
400
Original
Bed
380
0 2500 5000 7500 10000 12500 15000 17500 20000 22500 25000
Distance from Dam Axis (Km)
Simulations were run for a total duration of 47 (1966-2012) years to observe the sediment
accumulation and effectiveness of the flushing operation with 6 sluice spillways of 8m x 8m
provided at an invert of 418 masl. Evolution of the bed profile over the simulation period (decadal
basis) is shown in Figure 11. Most of the sediment gets accumulated at the beginning of the
reservoir and tends to propagate toward the dam but with the flushing event the delta gets eroded
and flushed. Simulation results showed that, with the flushing strategy adopted, the live storage
capacity of the reservoir is retained even at the end of the simulation period (47 year). Moreover,
the dead storage capacity of the reservoir only gets reduced by 15% at the end of the simulation
ensuring the adequacy of the existing sediment flushing arrangements and strategy adopted.
12. CONCLUSION:
There might be various strategies and operational rules for sediment management in any project.
This study considers sediment management through the reservoir using only sluice spillways with
8.7 days of annual drawdown. It is seen that under the flushing consideration made for this case
study in BKHEP, the size and number of sluice spillway allocated to the project is adequate to
retain the live storage volume even at the end of simulation period. However, in absence of the
calibrating data for this numerical simulation, physical modeling must be carried out to support
and validate the simulation results. During operation phase the sediment deposition must be
monitored regularly to optimize the reservoir flushing. Bathymetric survey is recommended each
year before and after sediment flushing to determine the changes in the geometry of sediment
deposits over time.
REFERENCES
Annandale G.W., Morris G.L.& Karki P. 2012. Extending Life of Reservoirs: Sustainable Sediment
Management for Dams and Run of River Hydropower, World Bank
Engelund F. & Hansen E. 1967. A monograph on sediment transport in alluvial streams: Teknisk Forlag
Skelbrekgade 4 Copenhagen V, Denmark
Iqbal M. 2018. Modeling for sediment management of Gulpur HPP reservoir on Poonch river, In Science
International 2018, ISSN 1013-5316 Lahore: Pakistan
Javed W., T. T. November 2016. Sediment Flushing Statery for Reservoir Of Proposed Bhasha Dam ,
Pakistan. 2nd World Irrigation Forum, 6-8.
Laursen E. M. 1958. The total sediment load on streams. Journal of hydraulics Division, American society
of civil engineers, Volume 84 Issue 1 February 1958
Morris G. L.& Fan. J. 2010. Reservoir Sedimentation Handbook. V 1.04 2010. McGraw hill
Shrestha H. S. 2012. Sedimentation and sediment handling in Himalayan reservoirs, Norwegian Univ. of
Science & Technology, Trondheim, Norway
Tejwani, K. 1987. Sedimentation of reservoirs in the Himalayan Region. International Centre for Integrated
Mountain Development (ICIMOD), Volume-7, No. 3 ,323-327.
US Army Corps of Engineers.2016. HEC_RAS River Analysis System: User’s Manual ver. 5.0. Hydrologic
Engineering Center, Davis, California