Lecture-4 Print
Lecture-4 Print
1.3.3.3 Vane Shear Test … cont’d 1.3.3.3 Vane Shear Test … cont’d
• The applied torque, T is resisted by the vertical cylindrical • The shear strength so obtained is the undrained –
surface of area ----, which contributes a torque of ----- and the unconsolidated shear strength of the soil.
horizontal circular at the top and bottom ends of the blades, • For a fully saturated, pure cohesive soil, this stress is also equal
which contributes a torque at T1 each. to the undrained cohesion, Cu.
• We can thus have two cases: • This test result is much superior to that of lab test results like
– Top of the blade just on the surface of the soil to be tested. unconfined compressive strength or UU – triaxal tests on
sensitive class.
• The following correlation exists in the literature:
– Top of blade well with in soil.
•
5 6
9 10
1.4 Layout, Number and Depth of Boreholes 1.4 Layout, Number and Depth of Boreholes
1.4.1 Layout and Number of boreholes
• Whenever possible locations of boreholes should be close to
the location of the future foundation element.
• Trial pits for small foundations such as strip footings for Fig.**
residential houses should not be located close to the position 1.4.2 Depth of Boreholes
of the foundation. • The depth of investigation is mainly governed by the depth of
• It is recommended (Bowels, 1995) that any project should have the soil affected by the foundation-soil contact pressure.
at least three boreholes where the surface is more or less level • The influence depth is commonly considered as that depth up
and the stratification is sufficiently uniform. to which the vertical stress is only 5 to 10% of the contact
• For sites of somewhat uneven stratification five borings are pressure.
recommended.
• For foundations with rectangular layout four of them may be
located at each corner and the remaining one at the center.
13 14
Fig. **
1.4 Layout, Number and Depth of Boreholes 1.4 Layout, Number and Depth of Boreholes
• Tomilson (1996) gave the following guidelines • For important construction, it may be necessary to sink two or
• a) isolated footing b) Raft //mat found three boreholes to deeper depth than the other.
• When foundations are taken down to ‘’bed rock’ it is important
to prove that there really is the bed rock at that level. In order
not misinterpret a possible big boulder for the bedrock, for
example, the boring must be continued to a depth of at least
3m below the surface of the rock.
Fig.**
• c) Closely spaced footings d)Largely piled foundation
Fig.** 15 16
1.4 Layout, Number and Depth of Boreholes 1.4 Layout, Number and Depth of Boreholes
• EBCS-7 Recommendations Depth, D
• Buildings:
– For structures on footings: D=3B, but = 1.5
3
– For structures on mat: =
2
– For structure on piles; ≥ ′ + 3 (D’=pile length)
• Roads:
– 2 to 3m below subgrade level
1.5 The Site Investigation Report • The report should be divided under at least the following
• Generally the report should include any pertinent data from headings
historical records, site observations, trial tests, boreholes, lab • It should have at least an introduction with like:
tests and field tests. – for whom the project is done
– the reason as to why the investigation is needed
• Two classes of report: a report possessing factual data and – how the investigation is run
interpretative data. – time and year of the investigation
– terms of reference (TOR)
– The former is what is normally reported by our local institutions • General description of the site
rendering geotechnical investigation service (case Ethiopia). – general configuration of the site/topography and important
surface features
– The latter is prepared by the design engineer who ordered the – types and density of vegetation
investigation .
– old building
– quarries, mine shafts, marshy grounds, ponds, water courses,
19 filled areas, roads and their types… etc 20
• Any useful information extracted from historical records on Laboratory Test Results
previous use of site. • A brief mention of the different lab tests under taken
• Other peculiar features: flooding, erosion, subsidence, • An account of unusual results should be included.
seismicity, slope instability, important features on existing
• Non-standard tests, the test procedure must be described
buildings like cracks.
• For detailed results, it is enough to make reference to pertinent
• General geology of the area: springs, location of quarries, like
forms like tables, charts, graphs, curves…etc.
faults, folds …etc if projects are big like dams.
• Discussion of results (in relation to foundation design and
• Description of soil conditions in Borings.
construction)
– various strata indicated
• Possible type(s) of foundation(s) is/are recommended based on
– ground water level,
the investigation results.
– good practice to show/ draw soil profile along selected lines of – Depth of foundation
borings
– Possible bearing capacity
21 22