ENGINEERING TECHNICAL PRACTICES
25 April 2005 GP 31-02
Guidance on Practice for Analyser Validation
Foreword
This is the first issue of Engineering Technical Practice (ETP) GP 31-02. This Guidance on Practice
(GP) is based on parts of heritage documents from the merged BP companies as follows:
Amoco (ACES)
A AR-FBD-PA-P Architectural—Facility Buildings—Process Analyser Shelters—Supply
Specification
A PC-PA-00-E Process Control—Process Analysers—Engineering Specification
A PC-PA-00-G Process Control—Process Analysers—Guide
A PC-PA-00-P Process Control—Process Analysers—Supply Specification
ARCO (APCES)
Std 312-92 Analysers
Copyright 2005,
2004, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipient’s organization. None of the information
contained in this document shall be disclosed outside the recipient’s own organization
without the prior written permission of Manager,
Director ofStandards,
Engineering,
BP Group,
BP Group,
unless
unless
the terms
the of
such agreement
terms of such agreement
or contract
or expressly
contract expressly
allow. allow.
Table of Contents
Foreword .............................................................................................................................................. 2
1. Scope.......................................................................................................................................... 4
2. Terms and definitions ................................................................................................................. 4
3. Functional requirements of validation application...................................................................... 4
3.1. General............................................................................................................................ 4
3.2. Interfaces with other systems ......................................................................................... 5
3.3. Statistical calculations ..................................................................................................... 6
3.4. User interfaces ................................................................................................................ 6
3.5. Reports and key performance indicators........................................................................ 7
3.6. Operating systems .......................................................................................................... 7
3.7. Use of on-line analysers with validation facilities ........................................................... 8
4. People and processes associated with quality measurement................................................... 9
5. Pre-requisites.............................................................................................................................. 9
5.1. Review of on-line analysers ............................................................................................ 9
5.2. Sampling points............................................................................................................. 10
5.3. Validation of laboratory analysers................................................................................. 10
Bibliography ....................................................................................................................................... 12
1. Scope
This GP provides guidance for the validation process of on-line analyser systems.
For the purposes of this GP (GIS), the following terms and definitions apply:
On-line analyser
Field instruments or inferential calculations that provide real-time indications of process stream
properties.
Process information system is connected to the DCS and includes bi-directional communication. It
also acts as a process data historian and serves information to users and software applications.
Laboratory analyser
An instrument that is not connected to the process that can analyse discrete samples and provide
measurements that are traceable and compliant with international standards.
Inferential calculations
Calculations that utilise single or multiple on-line process measurements to estimate properties of
process streams. The calculation could include linear or non-linear models.
Process control applications use the results of on-line analysers and manipulate process variables in
real-time in order to achieve the desired process conditions and production targets.
Validation Sample
A sample injected into an analyser that is certified by a third party but does not calibrate the analyser
i.e. calibration gas cylinder. These samples shall be traceable and compliant with international
standards.
% Analyser availability
Analyser availability = %Time Analyser is available without errors and accurate and the plant requires
it.
Adcon Utilisation
Adcon Utilisation = % Time advance control loop used / %Analyser available.
3.1. General
a. The applications shall compare equivalent results from on-line and laboratory based
analyses and/or validation samples.
b. The application shall include facilities to ensure that the values being compared have been
adjusted to account for process, instrument and system dynamics and that sample time
Downloaded Date: 6/17/2008 10:42:53 PM
The latest update of this document is located in the BP ETP and Projects Library
Page 4 of 12
25 April 2005 GP 31-02
Guidance on Practice for Analyser Validation
stamps for on-line and lab sample results and/or validation samples fall within the time
validity range.
c. The application shall execute when a new result from a laboratory analyser and/or
validation sample becomes available.
d. The application shall have the ability to incorporate samples not entered in chronological
order to the lab reporting system up to a maximum time out period.
e. Each result shall be accompanied by status signals for automatic disqualification from the
statistical analysis process and a status signal that can be manually set to allow specified
results to be disregarded and not used to validate the equivalent on-line analyser result.
f. The application shall include a statistical analysis taking into consideration ASTM/IP
standards and analyser performance criteria.
g. The application shall generate an indication of status and the current bias.
h. The current bias may be automatically calculated or manually entered. This feature shall be
an option and defined during configuration of the specific application.
i. The status and current bias shall be archived by the process information system and made
available for use by the quality measurement team to determine the root cause of any
failures in the overall quality measurement system.
The role of this team is further defined in section 4.
j. The bias and status shall allow the automatic updating of biases within process control
applications. However, the bias updating mechanism within process control schemes
should normally be a manual process.
k. Automatic updating of biases shall be considered on a per application basis.
l. Automatic updating of biases shall not be allowed to mask systematic failures in quality
measurement systems.
m. Process control applications shall allow operators to manually override biases and confirm
acceptance of calculated biases via a DCS interface.
n. Process and operation performance monitoring tools.
o. When a status is changed a text message shall be generated that describes the reason for
the change.
p. The on-line analyser status and text message shall be archived.
q. The application shall include a steady-state indicator.
r. The indicator should be set according to the status of measurements that are indicative of
the dynamic stability of the process.
d. Numerical data entries shall be validated using standardised validation routines and
outliers removed.
4. Suggest possible error (either labs or analyser) when difference is outside control
limits.
5. Provide overview screens of all analysers (user configurable) and indication of their
status for each site area. E.g. Refinery, crude unit three.
6. Provide operators with a text description of analysis status and advise appropriate
action if difference is outside control limits.
b. Quality measurement team
1. Provide quality measurement team with all of the above plus:
2. Calculated number of outliers in the last n results
3. Calculated bias apparent in the last n results.
4. Calculated identification of bias drift.
5. Calculated identification of control limit increase/decrease.
6. Automated notification of analyser fault/inaccuracy via email.
7. Validation of both analyser and laboratory data
8. % of invalid lab and/or analyser data points
9. Calculated availability of analyser (on-line, accurate and required by process)
10. Calculated ADCON utilization while analyser is ‘ok’
11. Current and historical standard deviation of the difference between analyser and lab
results.
12. Validation of laboratory sample timings.
13. Calculated value of analyser’s mean time between failures and failure rate.
14. Calculated value of analyser’s mean down time
15. Calculated value of analyser’s mean time to repair .
16. Additional trending of process variables to identify links between process and
analyser changes.
17. Full reporting of above.
18. Fully configurable from web page to add/modify/delete analyser-lab comparisons
c. Management information system
1. All of above plus:
2. Full overview of site analysers
3. Overall reporting on availability, accuracy and reliability on an area by area basis.
a. Each business unit shall include a team responsible for the maintenance of the quality
measurement systems.
b. This team shall develop and lead the implementation of plans to maintain and improve the
performance of quality measurements.
c. Each business unit shall also include a quality measurement performance team. This team
shall include the following generic functions:
1. Leader/champion
2. Laboratory specialists, (chemist and technician)
3. On-line analyser specialists (engineer and technician)
4. Operations personnel
5. Production planning
6. Process control applications
7. Product quality specialist.
d. The following processes shall be in place and championed by the quality measurement
teams:
1. Procedures governing laboratory quality control
2. Analyser validation exception investigation
3. Root cause analysis and defect elimination
4. Laboratory and on-line analyser routine maintenance and calibration schedule
5. Process for identifying laboratory and on-line analyser maintenance frequency
6. On-line analyser performance criteria – on line certification and lab cover suitability
7. Laboratory analyser routine maintenance schedule
8. Analyser selection and implementation standards
9. MOC for analyser implementation
10. Sample techniques
11. Lab testing and data entry charter – elapsed time from sampling
12. Accurate time stamping of samples
13. Analyser central knowledge management
e. The quality measurement team and processes shall ensure that biases between laboratory
and on-line analysers are not tolerated and shall be eliminated.
5. Pre-requisites
Prior to any site implementing the software applications and people processes described above
the following activities shall be completed.
b. The end user of each on-line analyser measurement shall be identified and their
requirements evaluated.
c. Any known defects associated with the on-line analysers shall be eliminated.
Annex A
Statistical Calculation Methods
System capability calculations are based on the last “n” samples, using the current sample,
where all samples are not outliers. An outlier is anything that fails the UCL and LCL checks and
the system capability checks. The system capability is calculated by obtaining the standard
deviation of the sample set * confidence factor. The confidence factor would typically be 3.0
but shall be configured per on-line analyser.
The Calculations required for ASTM/IP repeatability, ASTM/IP reproducibility, total standard
deviation will be stored in a database.
The bias, standard deviation, means use the last n samples (n can vary between properties)
including the current sample.
Bias = mean (last n {lab – analyser samples})
T = (abs (((mean of the last n {lab – analyser samples})-bias)) * (sq root of sample set size)) /
StDev. UCL(upper control limit) and LCL (lower control limit)calculations use the last n
samples, not including the current sample
UCL = mean (last n {lab – analyser samples}) + ((t test critical value at 95%, 2 tailed using
sample set size-1) * St Deviation). This should not be greater than the reproducibility of the
tests being compared. For physical property analysers this should not be greater than the
reproducibility of the lab test.
LCL = mean (last n {lab – analyser samples}) - ((t test critical value at 95%, 2 tailed using
sample set size-1) * St Deviation). This should not be greater than the repeatability of the tests
being compared. For physical property analysers this should not be greater than the
reproducibility of the lab test.
UCL and LCL shall be initially set at the ASTM/IP standard reproducibility for the test being
undertaken. If no ASTM/IP reproducibility’s are available for the test in question then the UCL
and LCL shall be calculated using +/- the overall tolerance for the analyser system as shown
below:
Overall Tolerance = UC/LC where
UC = CU1*CU2
LC = CL1*CL2
CL1 = 1-(T1/100)
CU1 = 1+(T1/100)
CL2 = 1-(T2/100)
CU2 = 1+(T2/100)
T1 = Analyser repeatability for the particular test/range of analysis
T2 = Calibration standard tolerance
CL1 = Lower analyser confidence
CL2 = calibration standard lower confidence
CUI = Upper analyser confidence
CU2 = Upper calibration standard confidence
Bias only updated if T > t test critical value (at 95%, 2 tailed using sample set size “n”-1) for 2
consecutive sample times. Where “n” is at least 21 samples.
Bibliography
[1] ASTM D3764, Standard Practice for Validation of Process Stream Analyzer Systems
[2] ASTM D6122, Standard Practice for Validation of Multivariate Process Infrared Spectrophotometers
[3] ASTM D6299, Standard Practice for Applying Statistical Quality Assurance Techniques to Evaluate
Analytical Measurement System Performance
[4] ASTM D6300, Standard Practice for Determination of Precision and Bias Data for Use in Test
Methods for Petroleum Products and Lubricants
[5] ASTM D6621, Standard Practice for Performance Testing of Process Analysers for Aromatic
Hydrocarbon Materials
[6] ASTM E456, Standard Terminology for Relating to Quality and Statistics
[7] ASTM E1655, Standard Practices for Infrared Multivariate Quantitative Analysis