Checklist No.:GBPPL/SE/UM01,Rev 00
Effective Date :-
Project :
Project Number : Building Name / No :
Responsibility:
Inspection Stage : After Reaching of Trailer / Truck No. ______________________
Observation Extra
Sl. No. Check Point Remarks
Require
Yes No ment
Whenever Truck / Trailer reached at
3 Side
1 site, three Side Photos of Truck / Trailer
Photo
to be send to HO
Whether cranes / Hydra, slings, etc are
2 available of required capacity ? Photo
Safety
Whether Slings, clamping jaws are in
3 Officer
good working condition?
Sign
Whether ground is compact for crane /
4 hydra movement ?
Whether space for material unloading /
5 stacking has been identified?
Whether Handling of material has been 3
6 Photos
done with proper care?
Whether physical material has been
7
verified with the packing list?