We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 9
3. SUCTION AND DISCHARGE LINES
3.1 Suction Line
‘The gas velocity in the common
suction line between evaporators
and the suction header must be
minimum 4 mis in horizontal
lines and minimum 8 ms in
vertical lines (recommendation
8 to 12 m/s). Gas velocities
greater than 12 m/s will create
high noise levels and high suction
line pressure drop which will
decrease system capacity
The suction line diameter
should be calculated according
to the minimum refrigerant
flow (at minimum evaporating
temperature and maximum
condensing temperature).
The common suction line
‘when horizontal shall be sloping
down toward the suction header
(0.5% slope, Smm rise for every
Im of run). if the suction line
must rise over 6 meters, multiple
suction risers must be created
‘every 4 meters as shown
in fig3.1
This is necessary to increase
the velocity of returning gas and
therefore insure proper oil return.
To avoid large quantities of oil
accumulation, create U-trap(s)
as short as possible.
Icis important to note that
standard size suction rotolock
valves ordered through Danfoss
Maneurop are designed for
general-purpose applications. It
is important to select rotolock
valve sizes according to the gas.
flow and not only according to
pipe size. Gas velocity in suction
lines of parallel systems may vary
considerably due to fluctuations
in load and the number of
SU. aps shores pose
Figure 3.1 Suction lie design
Figure 3.2 Double suction riser with Uraps
compressors running. It is
important to ensure sufficient
oil return under any load. In
general this means that double
Suction risers with U-traps are
imperative. See figure 3.2.
Marevroe (TSDavfets
3.2 Suction Header
The suction header must be
placed as close as possible to
the compressors.
The lines between the suction
header and the compressor
suction connection must be
flexible, ie. equipped with
vibration absorbers.
The suction lines from
the header towards each
individual compressor must be
fitted into the suction header
and the end tube cut at an angle
of 60° (see figures 3.4 & 3.5).
This configuration will result in
higher gas velocity at pick up
‘ube inlet and proper oil return
when the cil level in the suction
header rises. The compressor
suction lines must always enter
the suction header on the topside.
‘A recommended suction header
design is shown in figure 3.3.
To insure ideal pressure
equalization with an oil equalization
line system, the header must be
symmetrical and the lines from
the suction header to each
compressor must be short &
identical. These precautions are
not as critical when an oil level
regulator is used.
The following recommendations
are necessary for secure
installation:
+The suction line "A" and
‘the suction header "B” must
Figure 3.3 Suction header conguration with header below the compressor suction connections.
wr 0°
Figure 3.4 Detai of suction line inside Figure 3.5 Construction of suction header above the compressor suction
the suction header connections
9 ST MeaneuroeDavfits
be horizontal to avoid
unbalanced oil distribution.
+The gas velocity in the suction
header must be a maximum
of 4 mis.
+The suction line and the suction
header must be insulated to
limit the suction gas superheat.
Note: An alternative to
the construction of a suction
header is to purchase a pre-made
multiple compressor suction
accumulators.
3.3 Discharge Header
A properly constructed
discharge header will not allow
liquid flood back or migration of
the oil back to the compressor.
Furthermore it must restrict hot
discharge gas from returning to
switch off compressors where it
will condense and cause liquid
hammering at compressor
start up.
Therefore the following
construction details are of
importance:
+ Whenever possible, mount
the discharge header below
the compressor discharge
connections (see figure 3.6).
‘The compressor discharge lines
are below the compressors
and enter the discharge header
from above. This design
eliminates the risk of liquid
flood back. Check valves
(or non return valves), such
as Danfoss’ NRV, located
between the compressor
discharge connection and
the discharge header must
be installed to prevent liquid
condensation
the discharge lines enter
the discharge header from
the top. (See figure 3.7).
+ To avoid operational noise
the check valve dimension
must always be selected
according to the compressor
capacity and not the pipe size.
Contact your check valve
supplier for correct selection.
+The discharge header cross
section must be the sum of each
discharge tube cross section.
In an effort to avoid oil traps
never oversize the discharge
header.
In non-running compressors.
+ fit is impossible to mount
the discharge header below
the discharge connections
a special construction is
required. The key is to ensure
“cps NRV
[EEE Vibration absorber
Figure 3.6 Discharge header below compressor dscharge connections.
Meoewce ET
10—
L KR &
op: NV SEEDS Vibration sorter
Figure 3.7 Discharge header above compressor dcharge connections.
4. COMPRESSOR CONTROL
By starting only one compressor
ata time the peak load on the
power supply will be reduced.
Parallel installations also offer
many possibilities for efficient
capacity control.
For example, three compressors
of different capacity mounted in
parallel offer 7 different rated
‘capacities. The control system
should be designed to match
the cooling demand of the system
by staging compressors on and
off, thus reducing the amount
cof wasted energy in a system.
A secondary function of
the control system is to ensure
the compressors have an equal
number of running hours and
SEQUENCE
reduce the risk of refrigerant
migration in compressors stopped
over long periods of time.
(One example of a compressor
control sequence:
+ First start: Start compressors
in order 1,2,3 and also stop in
order 1,2,3
* Second start: Start
‘compressors in order 2,3, |
and also stop in order 2,3, |
+ Third start: Start compressors
in order 3, 1,2 and also stop in
order 3,1,2
Repeat sequence to balance each
compressors number of running
hours. Recommendations for
proper control:
* There shall be no more
than 12 starts per hour per
compressor.A higher number
reduces the service life of
the compressor. It is necessary
‘to use an anti-short cycle timer
in the control circuit to limit
the number of starts.
Ifa risk of long minimum load
‘operation exists it is recommend
10 install a timer which will force
run the entire system at 100%
capacity for 5 minutes every
5 hours. This will insure proper
oil return.
CSE Morera5. SYSTEM COMPONENTS
‘Typical system requirements and
recommendations for parallel
installations are listed below:
5.1 Suction line
accumulator
For parallel installations, it is
recommended to always use
a suction line accumulator. Be sure
to select the proper size suction
line accumulator according to
manufacturer recommendations.
In systems with an oil level
regulator itis best to use either
‘one suction line accumulator
per compressor or a multiline
accumulator having a connection
for each compressor.
5.2 Suction filter
Ics strongly recommended
to install a large suction filter
just before the suction header
for suction accumulator: This will
filter all foreign particles out
of the installation to protect,
the compressors. Danfoss DCR
filters with interchangeable strainer
type 48-F are recommended.
These filter shells provide the
possibilty to instal filter drier
cartridges (type 48-DN), or burn
cout cartridges (cype 48-DA),
while allowing easy after sales
service
5.3 Crankcase heater
Compressors must be installed
with continuously energized
self-regulating crankcase heaters
(PTC elements). These heaters
are to be installed with heat
conductive paste. The use of
an additional bele crankcase heater
may be necessary in some cases.
That belt crankcase heaters
must be switched on only when
the compressor is not running
The compressors should be
installed in a room of moderate
‘temperature to avoid refrigerant
condensation in non-running
compressors
References of crankcase heaters
are given in the selection and
Application Guidelines"
for MTIMTZ or LTZ
compressors. Contact
your local Danfoss Maneurop
Danfoss
‘organization for further
information.
5.4 Thermostatic
Expansion Valve
‘When the parallel installation
is serving a single evaporator
system the dimensioning of
the thermostatic expansion valve
(TEV) becomes critical and must
be made in relation to both
minimum and maximum capacity.
This will ensure correct superheat
control in all situations,
5.5 Condensing pressure
control
‘A condensing pressure control
should be installed to maintain
‘the minimum condensing pressure
according to the application
range published for each
compressor / refrigerant
‘combination. This condensing
pressure control will also allow
for an ideal liquid distribution in
the system (expansion valve
operation).
Marewer (SENT edInstallation and service
procedures for a parallel system
are similar to basic system
installations. The selection of
additional system components
for parallel installations follows
the basic system common rules.
‘Therefore refer to the "Selection
and Application Guidelines" of
the compressor for detailed
installation and service
procedures.
6.1 Compressor mounting
Individual compressors must
always be mounted using
the provided mounting
grommets. If this is not done
the system will transmit
vibration and in turn reduce
compressor life. common base
frame, rigid enough to support
the weight of the compressors,
must be used for installation
The common frame may be
mounted on grommets to reduce
transmission of vibration to
the floor. It is recommended to
install all control and safety
devices on an independent
frame. These devices should
be connected to the common
frame using flexible tubing
Davfets
6. INSTALLATION & SERVICE
Suction and discharge lines must
have adequate 3 dimensional
flexibility. For parallel systems
the simplest means of acquiring
this is by the use of vibration
absorbers.
The connecting suction and
discharge header pipes must be
as short as possible. Therefore it
isa benefit to mount compressors
as close together as possible. All
compressors must be mounted
‘on the same level.
6.2 Rotation direction
Compressors should run with
the same rotation direction.
This can be achieved by having
the same phase sequence on
each compressor motor
terminal (LI-T1,L2-T2, L3-T3)
6.3 Total capacity and
application envelope
The total cooling capacity of
4 parallel installation is slightly
less that the sum of the cooling
capacities of the individual
compressors. This is due to
the extra pressure drop in suction
and discharge headers. In general
this loss is about 1% of the total
capacity. The application envelope
ofa parallel installation is
the same as for the individual
compressors.
6.4 Pressure switch settings
The pump down pressure switch
(for example Danfoss type KP!)
must have a set point slightly
higher than the lowest
compressor safety pressure
switch set point. The high-
pressure safety switch shall
stop all compressors.
6.5 Failure analysis
‘When one compressor in
a parallel system fails the chance
of foreign particles entering other
compressors is greatly increased
Therefore a failure analysis must
be done quickly to insure further
proper running conditions for
the overall installation (ie.:oil
analysis).7, MANEUROP COMPRESSOR
CHARACTERISTICS
All Maneurop reciprocating
‘compressors MT, MTZ, LT &
LTZ are available in VE version,
specially designed for parallel
installation,
‘These compressors are provided
with an oil equalization connection
and a threaded oll sight glass
(see figure 7.1).
‘The standard compressors are
not suitable for parallel mounting
7.1 Oil level regulator and
oil sight glass
An il level regulator can be
mounted on the compressor oil
sight glass connection
7.2 Oil equalization
connection
‘A.3/8" oil equalization line can
be connected to the 3/8” flare
connection (see figure 7.2)
Recommended torque is 30
Nm.Note that older Maneurop
mpressors (until 1988) had a
1/4 rotolock connection for
this purpose (see figure 7.3).
For compressor replacement in
a parallel system with
compressors fitted with this
rotolock connection, an adapter
is available through Danfoss
Maneurop (ref. 7754010).
The position of the 3/8” flare oil
equalization fitting has recently
been modified so that equalization
only occurs when the oil level in
the compressor reaches the
maximum,
Further, to prevent oil drainage
from the non-running compressors
during part load operation,
the flare connector protrudes
into the compressor shell
(see figure 7.2)
FSA adapter (023 U 8014) is
available to convert the flare
connection to a brazed
connection design,
Figure 7.1 Correct oll level
insight glass
Compressor
Shel
159201
o1
sump
Figure 7.2 Oil equalization connection 318° flare connection
Figure 7.3 Former rotalock
with adaptor accessory.The Danfoss Maneurop
facilities
Tel. 04 74 00 28 29 - (33) 4 74 00 28 29
Fax 04 74 00 52 44 - (33) 4 74 00 52 44
SS ee nena nan newer
Danfoss Danfoss Maneurop
BP 331 F-01603 Trévoux France