Mining Projects Valuation Using Real Options Analysis
Mining Projects Valuation Using Real Options Analysis
2022
D6519113
September 2022
Akita University
Akita University
Acknowledgment
Professor Tsuyoshi Adachi, as supervisor, deserves special thanks for his patience,
support, and academic counsel during this project. The author also expresses gratitude to
Professor Youhei Kawamura, Professor Atsushi Shibayama, and Professor Tadao Imai for
advising to make this research better.
The author would like to thank the Ministry of Education, Culture, Sports, Science, and
Technology Japan for financial support during the study, namely MEXT scholarship program.
His sincere thanks also go out to Akita University's Academic Affairs Division and
International Affairs Division employees. The author also appreciates his comrades at the
Mineral Economics Laboratory for their warm smiles, assistance, support, and general
camaraderie.
The writer's thankfulness is also to the Faculty of Mining and Petroleum Engineering of
Institut Teknologi Bandung for recommending and being accepted at this study level and
Universitas Islam Bandung for allowing him to take higher education at Akita University. In
addition, the author is sincerely grateful to PT Timah, Tbk, who gave him a permit to do
research on their mining area and the exploration and related economic data.
This thesis is dedicated to author's wife, Alfi Rachmawati, for her undying support,
unwavering patience, and bountiful love, enough to last a lifetime and a bit more. Nevertheless,
the author's special gratitude extends to his parents for their everlasting love and support.
i
Akita University
Table of Contents
Acknowledgment .................................................................................................................. i
Table of Contents................................................................................................................. ii
List of Tables ...................................................................................................................... iv
List of Figures .......................................................................................................................v
Abstract............................................................................................................................. viii
ii
Akita University
APPENDIX ...................................................................................................................... 87
A. Price Modelling ........................................................................................................ 87
B. Resource Summary ................................................................................................... 90
C. Reserve Summary ..................................................................................................... 92
D. Cost Calculation........................................................................................................ 95
iii
Akita University
List of Tables
Table 2.1 Resource Summary ............................................................................................... 15
Table 3.1 Empirical Example of the ROV and DCF for Commodities................................... 32
Table 3.3 Project Volatility Estimation Based on Historical Tin Price ................................... 39
Table 4.7 Present Value of Reserve and Price Relative Changing ......................................... 76
Table 4.8 Option Value of Reserve and Price Relative Changing ..........................................76
iv
Akita University
List of Figures
Figure 2.8 Ultimate Pit Limit Design for Mid Reserve .......................................................... 20
Figure 2.9 Ultimate Pit Limit Design for South Reserve ....................................................... 21
Figure 4.18 Generated Cells with Three Uncertainties Driver (Random Cells Picked) ..........65
Figure 4.19 Exercise Value with Three Uncertainties Driver (Random Cells Picked) ............ 66
Figure 4.20 Waiting Value with Three Uncertainties Driver (Random Cells Picked).............66
Figure 4.23 Project Value with Initial Total Reserve Changing .............................................69
Figure 4.24 Project Value with Initial Total Cost Changing .................................................. 69
Figure 4.26 Initial Price and Unit Cost Decision Map ........................................................... 72
vi
Akita University
Figure 4.31 Real Option (RO) Value with Price and Reserve Uncertainties Alteration ..........78
vii
Akita University
Abstract
The selling of examined metal is the only mining company revenue generator. It implies
a certain amount of metal and selling price would grow their revenue. Before mining, the
company should estimate the reserves with tremendous uncertainty. In addition, fluctuation of
the metal price as economic uncertainty forces the company to deal with an advanced strategy
to gain optimum value because profit is very sensitive to the selling price. Nevertheless, the
cost of mining operations is unstable due to both local and global economic conditions. Cost
instability represents the technical uncertainty of the process that consists of mining and
processing-related expenditure.
Geology and mining operations need excessive capital expenditure to run the project.
In contrast, finance has to press the expense to guarantee profit. A balance between them is the
crucial success of mining. Exploration is necessary to estimate the resource. The estimation is
detailed with core drilling at a considerable cost and yielded a certain confidence level of
reserves with inherent uncertainty. Sales prices and expenses are commonly assumed in
constant or constant growth without compromising their fluctuation. However, project
evaluation cannot ignore those uncertainties to get the project value.
A standard method to evaluate a project value, Discounted Cash Flow (DCF), could not
adequately account for the future risk. Net Present Value (NPV) as the decision parameter of
the DCF method theoretically only generates two decision areas that are accepted and declined.
While in reality, management commonly takes no action to wait for a reasonable commodity
price, stable cost and ensure the number of reserves by collecting more exploration data. As a
result, recent study dedicated to accounting for uncertainty, real options (RO) valuation, adapt
financial option theory to be practiced in a real business. On the other hand, uncertainty in
reserves is modelled by geostatistics methodology, kriging, and conditional simulation, which
captures the spatial variability of the deposits.
mining project evaluation through the simulation approach, namely Multistage Stratified Stage
Aggregation (MSSA), which would be the study's originality. Conditional simulation methods
in geostatistics will be utilized to account for grade uncertainty. Thus, the expected reserve and
the deviation are incorporated with commodity price and cost uncertainties.
ix
Akita University
x
Akita University
Chapter 1 Introduction
1.1. Background
1
Akita University
After exploration, a mining company obtains reserve estimation in a particular area with
inherited uncertainty. Then, the reserve is evaluated in a feasibility study, including mine
planning to extract the expected amount of metal. Once the reserve is extracted, the company
invests in equipment, processing plant, and other expenditure. The investment should be
assessed in detail, including the uncertainty. Practically, the evaluation method used by a
company is the traditional Discounted Cash Flow (DCF) methodology. However, the method
employed by common mining companies does not account for risk and uncertainty. Decision-
makers frequently modify the discount rate to account for risk and integrate technical risk
premium. Aside from that, they conducted a sensitivity analysis to forecast the impact of
changing cash flow parameters. In some circumstances, this method might be a significant
limitation in adoption; and an improper valuation technique (Nicholas, 2014).
Geology, mine plan, and finance departments forecast the DCF return of a typical
mining project based on significant assumptions about price, reserves, and cost. These profit
determinants come with risk and uncertainty. To date, the best method for modelling the
resource beneath the surface is to use a coring drill. A significant geological uncertainty, grade
uncertainty, will be assessed in this study through conditional simulation (CS) methodology.
CS resulted in resource estimation and inherited geological uncertainty (Dowd, 1994). The CS
method developed further kriging method, particularly generation of grade uncertainty. The
study considered geological uncertainty which is typically not identified in economic evaluation
instead of estimation.
With the confirmation of modifying factors, the resource was transformed into reserves.
Operating costs, including mining, processing, and metallurgical operations, represent technical
uncertainty. Furthermore, price uncertainty is a mining project's most significant profit
determinant. Failure to respond to those risks and uncertainties will cause a significant mistake
in evaluating the future worth of the project. Risk refers to the possibility of an undesirable
occurrence occurring. In contrast, uncertainty refers to the future outlook of the project being
unpredictable (Mun, 2006).
Researchers devised the Real Option (RO) to replace the DCF technique to account for
risk and uncertainty. An option is a financial derivative whose value depends on the price of a
stock. Option holders have the right but no obligation to execute their option by the maturity
date. These alternatives are quantified by option calculation to justify option value. The
adaptation of option calculation in the actual project is called real options (RO) (Hull, 2015).
2
Akita University
To date, three approaches are used to calculate the value of an option: Black-Scholes
Formulation, Lattice Valuation and Simulation Method. The Black Scholes Formula employed
a closed mathematical approach (Black & Scholes, 1973). On the other hand, lattice valuation
(Cox et al., 1979) used risk-neutral probability, which simplified the Black Scholes method's
mathematical equation.
The simulation technique has similarities with lattice valuation. However, based on the
Monte Carlo simulation methodology, the simulation method is designed to calculate high
dimensional risk and uncertainty (Barraquand & Martineau, 1995; Hull, 2015). By optimizing
the exercise and waiting for the value of the project, the lattice and simulation methods consider
management flexibility. A temporal stochastic model and theoretical computation for natural
resource project appraisal are introduced in the study of RO in natural resources (Brennan &
Schwartz, 1985). Furthermore, the RO technique considers the managerial flexibility to amend
a future choice if the ambiguity is exposed. The Black Scholes method (Black & Scholes, 1973)
and lattice valuation (Cox et al., 1979), two common RO approaches, become complicated
when accounting for more than one uncertainty. Nonetheless, the mathematical complexity
(Haque et al., 2014) and usability (Ajak & Topal, 2015) of RO in the industry are still limiting
factors. As a result, the simulation technique is vital to be developed further to solve the
limitation.
A case study is conducted on tin mining projects at PT Timah Tbk, a mining company
in Indonesia, particularly on monthly mine planning for underwater mining and using dredge
as the primary equipment. Economic, geological, and technical factors of uncertainties are
represented by price, grade, and cost, respectively. The application of RO in the mining industry
could be improved by incorporating these uncertainties. However, modelling those
uncertainties is challenging. Therefore, we proposed a modelling method to be applied in the
3
Akita University
mining industry. The model can be applied to other mining with adaptation to assumptions
relating to mineral properties, mining methods and global economic conditions. In addition, CS
methodology should increase RO application, particularly in analyzing geological uncertainties
in a multi-stage of a short-term mining project. Multi-stage terminology refers to the total
amount of mining locations as more than one. Our model covered resource estimation through
the geostatistics method to mine plan on a monthly basis and economic valuation of two areas
simultaneously. The option type is the waiting to operate option based on the data availability.
The company has the right to operate, wait for the uncertainty to be resolved, or abandon the
mining projects.
Metal prices have been fluctuating remarkably in recent years. Fluctuation of the price
certainly affects mining company value. On the other hand, total available reserves are always
uncertain until the deposit is depleted. The company should optimize the cost and obtain
exploration data to estimate the reserves. Moreover, the history of mine operational cost
indicated significant volatility that gives the most considerable risk to the tin mining company.
These three uncertainties are calculated in this research through real options methodology,
particularly Multi-stage SSA.
4
Akita University
In this study, there are five main problems regarding measuring project value. As a case
study, we demonstrated the case of the Indonesian tin company, PT Timah Tbk. They are as
follows:
1. How do a mining company quantify geological uncertainty and use it to calculate project
value?
2. How can a mining project value be calculated simultaneously considering economic,
technical, and geological uncertainties?
3. How to evaluate the multi-project mining using RO methodology?
4. What is the advantage and disadvantage of the simulation method compared with Black-
Scholes and lattice valuation?
5. What are the practical consequences of risk and uncertainty caused by price, cost, and
reserve in the mining industry?
The mining industry faced uncertainties, particularly price fluctuation, the geological
presence of the reserves, and technical-cost uncertainty. A developed evaluation method of a
project is required considering the three most significant problems in mining. In addition,
decision-making in a mining company practically needs coordination of geological, the finance
and the mining engineering department. The finance department urges to decide the cheapest
operating cost at the highest price. In contrast, the geological and mining engineering
department wants to minimize the uncertainty of the existence of the ore and easy operation
(Crundwell, 2009).
This research tried to meet their need using geostatistics and real options methodology.
It resolved the price fluctuation that directly affected the project value and assessed the
exploration step to account for grade volatility. Moreover, the fluctuation of the historical cost
was measured through statistical method. The proposed method calculated the consequence of
uncertainties to the project value. The assessment was conducted in a monthly time frame to
describe how the real option worked.
5
Akita University
To date, researchers developed methods to measure and mitigate the risk embedded in
a business. They made parameters to calculate the return of a project and the inherited risk.
Principally, a higher risk of a project should give the investor the best return. Furthermore, the
most popular method was discounted cash flow analysis, which decided to either accept or
decline to start. However, it had assumption that the risk would be constant during the project
life. The developed risk assessment methodology, namely real options analysis, was adapted
from financial option theory and practiced in real projects. It figured out the risk based on the
potential growth of the project and the probability embedded.
The uncertainties are assessed in short-term mining design or monthly mine planning
incorporating economic, technology, and geological uncertainties. Additionally, the utilization
of conditional simulation, which is typically an estimation tool, was first performed to assess
grade uncertainty which would be the significance of this study. By examining the research, the
project's decision-making was resulted in optimizing the project value. The methodology was
a pilot demonstration to improve the applicability of RO methodology by capturing several
uncertainties in a single evaluation. We developed the path generation in the MSSA method
and applied specific model in uncertainties measurement. Nevertheless, technical issues such
as geotechnical, weather, recovery, and other modifying factors (JORC, 2012) could be
6
Akita University
calculated in the future using RO Methodology, particularly simulation method with MSSA
approach.
Chapter 1 introduced the background of this research and set the purposes we intend to
achieve. A brief explanation of recent studies regarding project evaluation, notably RO
Analysis, and the gap of recent research is described in the chapter. In addition, we explained
the significance of the studies that would be the originality and contribution to current research.
Chapter 2 consisted of explaining the case study using the typical traditional evaluation
method. It covered exploration, mine planning, and project evaluation. Moreover, it contained
collected data and how the project valuation was carried out. This chapter also assessed the
positive and negative points of current practice. The drawback of the traditional method relied
on a lack of uncertainty consideration in the evaluation. Brief analysis, namely sensitivity
analysis, is conducted which has been standard practice in the industry.
The main focus of the research, Real Options Analysis, was described in Chapter 3.
After summarizing previous literature regarding real options analysis, we calculated the project
value of our case study. The recent three approaches are explained and demonstrated in this
chapter. Real options analysis was conducted to get the optimal decision of the monthly mine
planning whether go mine, get more data by doing next exploration, or waiting for more
information regarding the price change and cost prediction.
analyzed the result of project value through traditional DCF and real options using the MSSA
method. It contained a decision map and further analysis when the cost uncertainty was
eliminated. This assumption was based on the ability of the company to control the expense in
their project.
8
Akita University
1.6. References
Adachi, T., Mogi, G., & Adachi, T. (2008). Real Option Analysis of Multi-Stage Investment
on Resources Development Project by Improved SSA Method. Mining and Materials
Processing Institute of Japan, 124(9), 576–582.
Ajak, A. D., & Topal, E. (2015). Real option in action: An example of flexible decision making
at a mine operational level. Resources Policy, 45, 109–120.
https://doi.org/10.1016/j.resourpol.2015.04.001
Black, F., & Scholes, M. (1973). The pricing of options and corporate. The Journal of Political
Economy, 81(3), 637–654.
Brennan, M. J., & Schwartz, E. S. (1985). Evaluating Natural Resource Investments. The
Journal of Business, 58(2), 135. https://doi.org/10.1086/296288
Cortazar, G., Schwartz, E. S., & Casassus, J. (2001). Optimal exploration investments under
price and geological-technical uncertainty: A real options model. R and D Management,
31(2), 181–189. https://doi.org/10.1111/1467-9310.00208
Cox, J. C., Ross, S. A., & Rubinstein, M. (1979). Option pricing: A simplified approach. Journal
of Financial Economics, 7(3), 229–263. https://doi.org/10.1016/0304-405X(79)90015-1
Dowd, P. A. (1994). Risk assessment in reserve estimation and open-pit planning. Transactions
- Institution of Mining & Metallurgy, Section A, 103. https://doi.org/10.1016/0148-
9062(95)97056-o
Haque, M. A., Topal, E., & Lilford, E. (2014). A numerical study for a mining project using
real options valuation under commodity price uncertainty. Resources Policy, 39(1), 115–
123. https://doi.org/10.1016/j.resourpol.2013.12.004
Mun, J. (2006). Real options analysis: tools and techniques for valuing strategic investments
and decisions. In John Wiley & Sons, Inc (2nd ed.). John Wiley & Sons, Inc.
Nicholas, G. (2014). An Integrated Risk Evaluation Model for Mineral Deposits [The
University of Adelaide]. https://hdl.handle.net/2440/86234
9
Akita University
Savolainen, J. (2016). Real options in metal mining project valuation: Review of literature.
Resources Policy, 50, 49–65. https://doi.org/10.1016/j.resourpol.2016.08.007
JORC. (2012). Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves (The JORC Code).
10
Akita University
2.1. Exploration
11
Akita University
measured, indicated, and inferred. Furthermore, the reserve is a fraction of a resource that meets
minimum product specifications and may be reasonably expected to be profitably and
technically produced at the time of determination. It is classified into two categories which are
proven and probable (Hustrulid et al., 2013). As a result, the exploration stage, namely the
feasibility study, has a critical role in transforming resources into reserves.
Predicting rock characteristics at unknown locations and anticipating the future flow
behavior of complicated geological and engineering systems are the main problematic in
resource exploration. Addressing this complex situation requires a variety of theories and
assumptions (Pyrcz & Deutsch, 2014). A presumed orebody is a starting point for examination
in exploration. Tonnage, grades, elevation, and physical address are used to define the potential
deposit. Additionally, exploring a known orebody is carried out to discover new reserves and
better understand current deposits to assure their dependability. Additional reserves almost
always result in increased value straightforwardly (Runge, 1998). The last exploration step,
feasibility study, provides technical, environmental, and commercial base for an investment
decision. Iterative processes to optimize all critical elements of the project will be a procedure
in feasibility study. The ultimate aim of the stage is identifying the production capacity,
technology, investment and production costs, sales revenues, and return on investment.
Two standards of importance in the exploration can be defined for mines, i.e. (1) a
minimum ore reserve equal to that required for all the years that the cash flows are projected in
the feasibility report must be known with accuracy and confidence and (2) an ultimate tonnage
potential, projected generously and optimistically, should be calculated to define the area
adversely affected by the mining and within which dumps and plant buildings must not
encroach (Hustrulid et al., 2013). Those expected exploration results can be generated after
conducting drill hole surveys, sampling, splitting, assaying, logging drill holes, plotting, cross-
sectioning, drill hole spacing, cutoff grade estimation, geostatistical analysis, and finally
making reserve categories.
12
Akita University
holes with a total depth of 1459.6 meters. They were ranged from 4.8 meters under sea level
(MUSL) to 47.3 MUSL. Additionally, tin content data were ranged from 0.008 kg/m3 to 1.599
kg/m3. The company have right to extract as well as abandon the resources. This research
evaluated further the resource with its inherited uncertainties. The evaluation was started with
modeling the resources using GEOVIA Surpac 6.8.1. After plotting the drill hole data, we
composited it with its statistic (Figure 2.1) and variogram modeling (Figure 2.2) using the
geostatistical methodology.
Statistics is the collection, organization, and interpretation of data and the conclusion
and decision-making process. While geostatistics is a subfield of applied statistics. It
encompasses the following concepts: spatial context (geological), spatial connections,
volumetric support/scale, and uncertainty. The branch of knowledge was first developed by
Krige (1951) and followed by Matheron (1963), which generated a statistical framework to
resolve the relationship between vein width, the efficiency of exploration data in terms of
sampling, measuring, and assaying. Geostatistics consists of three main concepts: regionalized
variables, random function, and random variables. The regionalized variable is a function that
takes a value at every point in the space of regionalization. However, the function varies
irregularly from point to point in the space of regionalization. The random function is the set of
random variables at all possible locations. The unique outcome that exists at every location
realizes the random function. The grade may be considered a random variable that assumes a
series of outcome values at unsampled locations. The series of possible outcome values for the
random variable at each location is determined by a probability distribution (Nicholas, 2014).
13
Akita University
𝑛(ℎ)
1 Equation 2.1
𝛾 (ℎ ) = ∑[𝑍(𝑥𝑖 ) − 𝑍(𝑥𝑖+ℎ )]2
2𝑛(ℎ)
𝑖=1
Estimation is process of determining the best single value for a spatial attribute in an
unsampled area. Kriging is a phrase coined by G. Matheron in 1963 in tribute to Danie Krige.
It produces an interpolation function based on a covariance or variogram model derived from
the data. Kriging method is defined as optimal regression of observed Z values of surrounding
14
Akita University
(real) data and weighted according to covariance values from semivariogram results. Local
scale of kriging model is accurate and it takes local priority over global geographical variability.
The value of estimation can be formulated as Equation 2.2 for simple kriging type.
𝑛
𝑍 ∗ = ∑ 𝜆𝑖 𝑍𝑖 Equation 2.2
𝑖=1
Inputting parameters of compositing data and variogram model resulted kriging model
(Figure 2.3, and 2.4) and conditional simulation model (Figure 2.5 and 2.6). The resource
estimation through Kriging and Conditional simulation method is described at Appendix A and
summarized at Table 2.1.
15
Akita University
16
Akita University
17
Akita University
18
Akita University
In this research, monthly mine planning is conducted for underwater mining with dredge
as main equipment. We developed a mine planning simulation using GEOVIA Surpac 6.8.1
and utilized GEOVIA Whittle 4.6 mining software to optimize the mine design. Optimizer
software can reduce the iterative activity of mine planning. It employed Lerch - Grossman
algorithm to get the maximum NPV. The algorithm pit limit based on fixed slope angles
governed by block dimensions. The parameter we used to develop the mine plan is described
in Table 2.2. The cost parameter is obtained from averaging historical cost with similar mining
method and equipment. We simulated for two reserve locations using the Kriging model or
Conditional Simulation model (Table 2.3 and Appendix B). The design result of mine planning
is shown at Figure 2.8 and Figure 2.9.
Location Volume Tones Grade (Kg/ M3) Tin (Ton) NPV (USD)
Ordinary Kriging Model
mid 748,000 2,244,000 0.36 269.28 1,147,183.00
south 172,000 516,000 0.17 28.896 -279,926.00
Conditional Simulation Model
mid 3,680,500 11,041,500 0.39 1,428.03 7,294,826.00
south 580,875 1,742,625 0.36 208.53 882,590.00
19
Akita University
20
Akita University
21
Akita University
The Discounted Cash Flow (DCF) approach is one of the most frequent methods for
evaluating a mining project. For most mining prospects, DCF methodologies are used to make
investment decisions (Fig. 2.10). This strategy has been a popular tool for numerous decades
for completing appraisals and allocating scarce funds. It is based on cash flow and is simple to
comprehend. The DCF method assesses the entire project by modifying or discounting the
project net cash flow to account for risk and time. The bigger the investment risk, the higher
the discount rate. DCF approaches do not allow for management flexibility and it assures
parameters throughout the project. Decisions must be taken "now or never," and the use of an
appropriate discount rate is critical.
Evaluating a project is a multidisciplinary task and is not solely the domain of any
profession or management. It involves engineering economics, capital budgeting, financial
management, and strategic planning (Crundwell, 2008). The key concept of the resource
22
Akita University
Well-known economic theory, the time value of money, explained that the current value
of money is bigger than the future and less than the past (Equation 2.3). There are three reasons
for this: inflation, risk, and liquidity (Crundwell, 2008). The Net Present Value (NPV), as
expressed in Equation 2.4. is the total of all cash flows discounted at present using the time
value of the money. The investor's value is increased when the net present value is positive. If
it is less than zero, the investor's interest is expected to be lost.
Traditional DCF techniques do not account for decisional flexibility in project capital
planning. DCF analysis fails to account for the value of genuine alternatives inherent in capital
budgeting, which explains why it does not consider the true worth of an investment (Trigeorgis,
1993). Misuses of DCF methods include discounting real flows with nominal interest rates,
failing to implement inflation correctly; applying unnecessary risk-adjustment factors, failing
125
120
115
Present Value (K USD)
110
105
100
95
90
85
80
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
39
41
43
45
47
49
51
53
55
57
59
Production Month
17
16
15
Present Value (K USD)
14
13
12
11
10
8
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
39
41
43
45
47
49
51
53
55
57
59
Production Month
24
Akita University
to recognize that risk diversification should not be considered; using unsuitable criteria in
measuring profitability, such as internal rate of return, which frequently yield erroneous
conclusions; and frequently gauging cash flows using standardized accounting principles.
In the case study, the evaluation was conducted in February 2021. Therefore, the used
price was flat on January 2021. While for the operating cost was resumed from the company
with a similar operation method and similar location. The overall operation did not cause initial
capital expenditure. The research evaluated the reserve that had been explored before. The
company had the right to execute or abandon the project. As we assumed the production was
flat in 5 years of operation, the cash flow and cash flow models are shown in Table 2.4, Table
2.5, Figure 2.11, and Figure 2.12. It resulted in Net Present Value of 6.6 MUSD and 0.9 MUSD
for mid and south reserve, respectively.
25
Akita University
Unit Total
Component Unit 1 2 3 … 58 59 60
value value
Production Ore 1000 ton 7,204 120 120 120 … 120 120 120
Grade kg/m3 0.594 0.594 0.594 0.594 … 0.594 0.594 0.594
Tin Got ton 1,426 23.77 23.77 23.77 … 23.77 23.77 23.77
Selling Price usd/ton 23,199 23,199 23,199 23,199 … 23,199 23,199 23,199
Gross Revenue 1000 usd 551.51 551.51 551.51 … 551.51 551.51 551.51
Mining Cost 12,785 213.08 213.08 213.08 … 213.08 213.08 213.08
Processing Cost 6,738 112.30 112.30 112.30 … 112.30 112.30 112.30
Operating Cost 1000 usd 19,523 325.38 325.38 325.38 … 325.38 325.38 325.38
Net Income Before
1000 usd 226.13 226.13 226.13 … 226.13 226.13 226.13
Tax
Tax 1000 usd 28% 63.32 63.32 63.32 … 63.32 63.32 63.32
Cash Flow 1000 usd 118.69 118.69 118.69 … 118.69 118.69 118.69
Discounted value 1000 usd 0.25% $118.40 $118.10 $117.81 … $102.69 $102.43 $102.18
Net Present Value = 6.605 Million USD
26
Akita University
27
Akita University
The risks related to mining are diverse and complicated, with the orebody constituting
the primary source of risk. Mining is distinct from most other industries in that product
knowledge relies primarily on estimations that carry a degree of uncertainty. World commodity
prices heavily influence possible income fluctuations and, hence, the amount of the commercial
mineral inventory (Dominy, 2016).
Sensitivity analysis is the process of changing one or more elements to examine how
the variation affects the project's value. While sensitivity analysis helps to understand the
implications of uncertainty, it does not provide a project value adjusted for the uncertainty. One
of the most important benefits of sensitivity analysis is that it identifies the elements that have
the greatest impact on the economics of a project. The analysis enables assessors to collect more
information more effectively.
12,000
11,000
10,000
Net Present Value (1000 USD)
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
-20 -10 0 10 20
Relative Changing (%)
We conducted a sensitivity analysis on price, reserve, and cost variables on our case
study (Figure 2.13). Price and production were the most sensitive parameters, followed by total
cost, mining cost, processing cost, tax, and discount rate. However, because sensitivity analyses
are usually conducted on a single ‘best estimate’ of the resource model, it should reflect that
level of local inaccuracy and could be misleading decision-making. Therefore, combining more
28
Akita University
than one uncertainties evaluation is necessary and analysis based on simulation should be
conducted to anticipate an unpredictable situation in the future.
Sensitivity analysis can understand project risk straight forward. In addition, all
stochastic variables need to be considered in a single evaluation model with all possible
permutations (Nicholas, 2014). Practically, general mining companies conduct sensitivity
analysis to measure the effect of parameter changing. It runs analyses that reflect various
commodity prices, reserve amount, and operating and capital costs to determine the effect of
such variations. In very simplistic terms, sensitivity analysis is 'what if' analysis, which is an
important notion at the core of any application of decision tools and may be applied to a wide
range of uses. One-way sensitivity analysis is the simplest form of sensitivity analysis where a
given amount varies one value in the model to examine the impact of the change on the model's
results (Taylor, 2009).
29
Akita University
2.5. References
Runge, I. C. (1998). Mining Economics and Strategy. Society for Mining, Metallurgy, and
Exploration, Inc.
Dyas. K. E. (2002). Project Evaluation. In Mining Reference Handbook (pp. 1–9). Society for
Mining, Metallurgy, and Exploration, Inc.
Hustrulid, W., Kuchta, M., & Martin, R. K. (2013). Open Pit Mine Planning & Design (3rd
ed.). CRC Press.
Stermole, F. J., & Stermole, J. M. (2000). Economic Evaluation and Investment Decision
Methods (10th ed.). Investment Evaluations Corporation.
Krige, D. G. (1951). A Statistical Approach to some Basic Mine Valuation Problems on the
Withwatersrand. J. South. Afr. Inst. Min. Metall., 52(6), 119–139.
Crundwell, F. (2008). Finance for Engineers: Evaluation and Funding of Capital Projects.
Springer-Verlag London Limited.
Rimélé, A., Dimitrakopoulos, R., & Gamache, M. (2020). A dynamic stochastic programming
approach for open-pit mine planning with geological and commodity price uncertainty.
Resources Policy, 65(December 2019). https://doi.org/10.1016/j.resourpol.2019.101570
Newman, C., Newman, D., & Dupuy, R. (2020). Development of a multiple level underground
limestone mine from geology through mine planning. International Journal of Mining
Science and Technology, 30(1), 63–67. https://doi.org/10.1016/j.ijmst.2019.12.007
Trigeorgis, L. (1993). The Nature of Option Interactions and the Valuation of Investments with
Multiple Real Options Author. Journal of Financial and Quantitative Analysis, 28(1), 1–
20.
Whittle, D., Whittle, J., Wharton, C., & Hall, G. (2005). Strategic Mine Planning (Issue
January). Gemcom Software International Inc.
30
Akita University
An option is a financial derivative whose value depends on the price of a stock. Option
holders have rights but no obligation to execute their option in the maturity date. These
alternatives are quantified by option calculation to justify option value. The adaptation of option
calculation in the actual project is called real options (RO). For instance, if a company decides
to invest in a mine, they exercise right. They lose the right, but they earn the asset. Discounted
Cash Flow (DCF) method theoretically assumed static decision over project life time without
ability to change decision. In contrast, RO assumed dynamic future decisions when the
uncertainties resolved. That managerial flexibility is not accommodated in the traditional DCF
methodology. For instance, the operation of a project can be contracted, delayed, or abandoned
and real options discount uncertain cash flows at the correct rate (Crundwell, 2008).
The analysis of options was introduced by Fisher Black and Myron Scholes to analyze
a derivative market product (Black and Scholes, 1973). It had been popular with the lattice
method, which was developed further. The real options theory was largely accepted in the
financial literature, and many scholars sought to alter it (Table 4.1). Cox, Ross, and Rubinstein
developed a basic economic concept of option pricing under the non-arbitrage assumption in
1979 and a simple and efficient numerical approach for valuing options (Cox et al., 1979).
Myers (1977) stated real option first time in the study of corporate debt policies, which account
for the flexibility of the company management. Mun (2006) added that a real option is a
systematic approach and integrated solution using financial theory, economic analysis,
management, decision science, statistic, and econometrics to evaluate real asset dynamic and
uncertain.
Brennan and Schwartz (1985) used an option pricing model to analyze a natural resource
project for the first time. Natural resources, they said, contain much unpredictability in terms
of resources and cost. According to the Brennan and Schwartz model, continuous-time non-
arbitrage methods and stochastic control theory may be used to assess such enterprises and find
31
Akita University
the best strategies for creating, managing, and abandoning them. Trigeorgis offered examples
of applied actual options valuation (Trigeorgis, 1993). They demonstrated how to postpone,
enlarge, and shut a variety of investment project decisions, particularly in the natural resource
sector. They indicated that commodity price changes have a major impact on natural resource
investment decisions. All prior empirical research on ROV and DCF in mining operations is
included in Table 3.1. This thesis employed ROV in a mining project with a combination of
uncertainties which will be the originality of the research.
Table 3.1 Empirical Example of the ROV and DCF for Commodities
32
Akita University
31 2005 V Blais, R Poulin, M Samis DCF.ROV Copper, gold Not available Canada
32 2006 M Samis, G A Davis, D Laughton DCF.ROV Copper Not available Not available
33 2007 J Hall, S Nicholls DCF.ROV Coal Hypothetical Not available
S Dessureault, V N Kazakidis, Z Sudbury, Western
34 2007 DCF.ROV Nickel, copper Canada, USA
Mayer Arizona
35 2007 P Guj, R Garzon DCF.ROV Nickle Not available Not available
G Dogbe, S Frimpong, J
36 2007 DCF.ROV Copper Hypothetical Not available
Szymanski
37 2008 S Shafiee, E Topal DCF.ROV Gold Hypothetical Australia
38 2009 Li Shu-xing, Knights Peter DCF ROV Not available Hypothetical Not available
39 2009 S.A. Abdel Sabour and G. Wood DCF ROV Copper, Gold Not available Canada
Akbari Afshin Dehkharghani,
40 2009 Osanloo Morteza, Shirazi Mohsen DCF ROV Copper Not available Not available
Akbarpour
S. A. Abdel Sabour and R.
41 2011 DCF ROV Copper Not available Canada
Dimitrakopoulos
Hesam Dehghani, Majid Ataee-
42 2014 DCF ROV Gold, Copper Grasberg Indonesia
pour, Akbar Esfahanipour
Snehamoy Chatterjee, Manas
43 2015 Ranjan Sethi, Mohammad Waqar DCF ROV Iron Not available India
Ali Asad
44 2015 Ajak Duany Ajak, Erkan Topal ROV Iron Not available Australia
45 2017 Jyrki Savolainen ROV Not available 170 mines Not available
Oscar Miranda, Luiz E. Brandao,
46 2017 DCF ROV Silver Not available Peru
Juan Lazo Lazo
Renewable
47 2018 Xiaoran Liu and Ehud I. Ronn ROV Not available China
Energy
48 2019 Aldin Ardian and Mustafa Kumral DCF ROV Gold Not available Canada, Indonesia
Shiwei Yu, Zhenxi Li, Yi-Ming
49 2019 DCF ROV Geothermal Xiong New Area China
Wei, Lancui Liu
Giorgio Locatelli, Mauro Mancini,
50 2020 DCF ROV Energy Not available Not available
Giovanni Lotti
Result of a project or underlying asset will remain uncertain until the end of the project
period. Therefore, the owner of the right does not know whether their choice will be profitable
at the option's maturity. The strike cost for real option is making the production facility to start
the project. Real option valuation parameter is resumed at Table 3.2. Option value can be
measured in various ways, such as path-dependent simulation, closed-form formulas, partial
differential equations, and lattice methods. Real option concept based on the manager's
flexibility to take action when information is obtained. The method implies that the manager
should defer or abandon the mine project when the project will not profitable respecting
uncertainty model.
The option evaluation in the mining project is divided into each mining stage. It
contained exploration, development, extraction, and abandonment. For instance, delay option
type is put option with the time maturity from acquisition to closing. The other option type is
the call option with the mature period, which is acquisition to the next stages. In the extraction
stage, the partition came to mine design, mine planning, temporary close, expansion, defer
33
Akita University
building, and switch option. Every type of options analysis has its particular framework, as
calculating option value is various. In this thesis, the calculation of option is focus on the wait
to operate option which the manager has right to delay operation considering uncertainty of the
project.
34
Akita University
Financial Option
Real Option Parameter Definition
Parameter
Strike Price Capital Cost The price to get the option
Maturity Project period Length of the option
Underlying Asset Present Value The asset value
Call Option Invest option Right to buy an asset
Put Option Abandon option Right to sell an asset
Long Position Investor Owner of an option
Short Position - The writer who buy the option
The option can only be exercised at
European Option -
maturity
The option can be exercised at any time
American Option American Option
before the option expires
Cortazar has provided a case study of real options in mining exploration which
accounted for geological and economical uncertainties (Cortazar et al., 2001). In line with this
research, there were three sources of uncertainties: geological, technical and price uncertainties.
Recently, the evidence of uncertainty in mining project valuation has been highlighted. Their
sources are recovery, grade, commodity price, discount rate, and mining cost. They drive the
successes of mining projects when the company is accurate in predicting. However, simulating
multiple uncertainty parameters can overcome the difficulty of prediction (Ardian & Kumral,
2020). Theoretically, the ultimate result of the option value can be described in Figure 3.1. It
consist of option value, strike price, Net Present Value and the option premium. The asset value
will be varied as uncertainty parameter is changed.
Inputs of cash flow are sources of uncertainty. Technical parameters refer to production
uncertainty which consists of the reserve, mining, and metallurgical uncertainty. While selling
price, capital cost, and variable cost lead to economic uncertainty. Real option foundation relies
on the flexibility of management to take action when uncertainty is resolved in the future time.
35
Akita University
Black and Scholes model employed the capital asset pricing model to derive a link
between the market's necessary return on the option and the required return on the stock. Black
Scholes method is based on the potential underlying asset, and the cost expensed during the
project (Hull, 2015).
1. The stock price follows the Geometric Brownian Model process with growth (µ) and
volatility (σ) constant (Equation 3.1),
2. The short-selling of securities with full use of proceeds is permitted,
3. There are no transaction costs or taxes. All securities are perfectly divisible,
4. No dividends during the life of the product,
5. There are no riskless arbitrage opportunities,
6. Security trading is continuous, and
7. The risk-free rate, r, is constant and identical for all periods.
where:
𝛿𝑆
= Percent change of variable
𝑆
36
Akita University
Where:
𝑆 𝜎2
ln ( 𝐾0 ) + (𝑟 + 2 ) 𝑇 Equation 3.3
𝑑1 =
𝜎 √𝑇
𝑆 𝜎2 Equation 3.4
ln ( 𝐾0 ) + (𝑟 − 2 ) 𝑇
𝑑2 = = 𝑑1 − 𝜎√𝑇
𝜎 √𝑇
c : call option value
𝑆0 : underlying asset
K : strike price
𝜎 : asset volatility
r : continuously compounded risk free rate
T : time to maturity of the option
The normal distribution N(x) is a likelihood of a call option being executed in a risk-
free environment. It is the cumulative probability distribution function for a variable or the
probability of a variable will be less than a constant (x). In a risk-neutral universe, where stock
prices less than the strike price are treated as zero. Furthermore, the expression S0N(d1)ert is the
predicted stock price at time T. The strike price is only paid if the stock price is greater than K,
which has a chance of N(d2).
In the case study the option is defined as waiting to operate option. The company has
right to operate, delay and abandon the project when the project is unprofitable. Respecting the
multi uncertainty of cash flow, Black Scholes formula could not explain it. Under no investment
assumption (K=0), Equation 3.2 will be error. However, the uncertainty is existing over project
period. Therefore, the important of simulation method is to identify and assess the project value
and the uncertainty when empirical approach cannot resolve it.
Then, we model the asset uncertainty by measuring the volatility of the asset. We
calculated the asset volatility as indicated by its standard deviation (Equation 3.5).
37
Akita University
1 𝑛
𝜎=√ ∑ (𝑢𝑖 − 𝑢̅)2 Equation 3.5
𝑛 − 1 𝑖=1
Where:
𝜎 : standard deviation
𝑃𝑖
𝑢𝑖 ∶ present value growth = ln ( )
𝑃𝑖−1
𝑢̅ : mean of 𝑢𝑖
n+1 : number of observation
The calculation conducted further by applying price into cash flow model periodically
(Figure 3.2). In Table 3.3, the calculated volatility of the project relating to price uncertainty
was 29% in a monthly time frame.
1
𝜎𝑝𝑟𝑜𝑗𝑒𝑐𝑡 = √ (5.11) = 0.29
60 − 1
38
Akita University
39
Akita University
25,000 8,000
7,000
6,000
15,000 5,000
4,000
10,000 3,000
2,000
5,000
1,000
0 -
Jan-16 Jul-16 Feb-17 Aug-17 Mar-18 Sep-18 Apr-19 Nov-19 May-20 Dec-20
Period
𝑆 𝜎2
ln ( 𝐾0 ) + (𝑟 + 2 ) 𝑇
𝑑1 =
𝜎 √𝑇
7.514 0.292
ln( )+(0.25%+ )·60
1 2
=
0.29√60
= 2.022
𝑆 𝜎2
ln ( 𝐾0 ) + (𝑟 − 2 ) 𝑇
𝑑2 =
𝜎 √𝑇
= 𝑑1 − 𝜎√𝑇
= 2.022 − 0.29√60
= -0.224
40
Akita University
Lattice valuation was founded by Cox et al., (1979) which simplified Black Scholes
methodology. It started from the assumption that an asset follows a random walk. In each step,
the asset has a certain probability of increasing and decreasing by a certain percentage amount.
The approach followed a very important principle, namely risk-neutral valuation. When the
time of lattice simulation is limited to zero, the value is equal to the result of the Black Scholes
method. Recently, the lattice method has been popular in the academic research of real options
analysis (Crundwell, 2008). Johnathan Mun described that the initial lattice approach of real
option is the Brownian motion (Mun, 2006). The uncertainty in the future is explained by
simulation. A likelihood distribution may be built at an increasing period based on all the virtual
paths. The simulation pathways were developed using a Geometric Brownian Motion with set
volatility defined at Equation 3.1.
𝛿𝑆
= 𝑒 𝜇(𝛿𝑡)+𝜎𝜀√𝛿𝑡 Equation 3.6
𝑆
The upside factor (u) is when the simulated parameter generates a positive value or
𝑒 𝜎√𝛿𝑡 . At the same time, down factor (d) is obtained when a negative value is produced or
41
Akita University
𝑒 −𝜎√𝛿𝑡 . A manager should decide which maximizes the project value whether execution, delay
or abandonment, to get the option value. Executing the project resulted company should pay
the investing expenditure. In contrast, delaying and abandoning projects resulted the company
expense or producing nothing. Furthermore, the probability of each way is calculated using
risk-neutral probability. For instance, if the probability of upside is denoted as P, the expected
value of a project is expressed at Equation 3.7. However, the project is conducted over time.
Thus, the discount factor will be added in the exponential formula and generate Equation 3.8.
The Lattice method is a simplification of Black Scholes formulation. Similar with Black
Scholes formulation, the three uncertainty drivers cannot be accounted for by lattice valuation
methodology. They adapted from financial option which written on an asset with certain
exercise price with single uncertainty driver. The underlying asset for real option is the present
value of cash flow while strike price is the initial investment. However, when the methodology
applied to ongoing project which has no investment needed, they cannot calculate the
uncertainty although uncertainty is always existing.
42
Akita University
Period (month) 0 1 2 3 … 60
project value (KUSD) 7,514 10,042 13,420 17,935 … 270,762,143,780
5,622 7,514 10,042 … 151,599,282,030
4,207 5,622 … 84,880,190,381
3,148 … 47,524,279,948
Then, we subtract with the initial investment of 1 Million USD and we obtain Table 3.5.
Period (month) 0 1 2 3 … 60
NPV (KUSD) 6,514 9,042 12,420 16,935 … 270,762,142,780
4,622 6,514 9,042 … 151,599,281,030
3,207 4,622 … 84,880,189,381
2,148 … 47,524,278,948
Last step is backward calculation by applying Equation 3.8 and we got Table 3.6.
Period (month) 0 1 2 3 … 60
Option Value (KUSD) 6,961 9,479 12,811 17,282 … 270,762,142,780
5,074 6,984 9,464 … 151,599,281,030
3,641 5,127 … 84,880,189,381
2,526 … 47,524,278,948
The simulation or numerical method is used when the analytic approach does not exist.
It follows a stochastic process to predict the future. A stochastic process is defined as a variable
whose value fluctuates unpredictably over time. Theoretically, stochastic modeling should
satisfy Markov properties, Wiener, and Ito process. Markov properties is a form of a stochastic
process explain that the present value is all that matters when forecasting the future. Since they
are uncertain, future predictions must be described in terms of probability distributions. The
Markov property states that the probability distribution of the price at any given future time is
independent of the past price's path. At the same time, Wiener Process is a particular type of
Markov stochastic process with a mean change of zero and a constant variance rate. The last
property, the Ito process, is a generalized Wiener process. The parameters a and b are functions
of the value of the underlying variable x and time t (Equation 3.10). Incorporating the three
processes result in Equation 3.11.
43
Akita University
Monte Carlo simulation employs the risk-neutral valuation outcome when valuing an
option. The steps are:
44
Akita University
(Adachi et al., 2008). However, none of them is applied in the mining project, which has
different calculation methods on uncertainties calculation. The considerable risk and
uncertainties in this study are economic, technical, and geological factors represented by price,
cost, and reserve, respectively. However, modeling the uncertainty is unique, and we developed
it through this research. Nevertheless, integration of those uncertainties will improve the
applicability of RO in the mining industry. Detail work of simulation approach is explained at
Chapter 4.
45
Akita University
3.5. References
Adachi, T., Mogi, G., & Adachi, T. (2008). Real Option Analysis of Multi-Stage Investment
on Resources Development Project by Improved SSA Method. Mining and Materials
Processing Institute of Japan, 124(9), 576–582.
Black, F., & Scholes, M. (1973). The pricing of options and corporate. The Journal of Political
Economy, 81(3), 637–654.
Brennan, M. J., & Schwartz, E. S. (1985). Evaluating Natural Resource Investments. The
Journal of Business, 58(2), 135. https://doi.org/10.1086/296288
Crundwell, F. (2008). Finance for Engineers: Evaluation and Funding of Capital Projects.
Springer-Verlag London Limited. https://doi.org/10.1007/978-1-84800-033-9
Cox, J. C., Ross, S. A., & Rubinstein, M. (1979). Option pricing: A simplified approach. Journal
of Financial Economics, 7(3), 229–263. https://doi.org/10.1016/0304-405X(79)90015-1
Hull, J. C. (2015). Options, futures, and other derivatives. In Asset Pricing (Ninth, Vol. 59,
Issue 2). Pearson Education, Inc.
Mun, J. (2006). Real options analysis: tools and techniques for valuing strategic investments
and decisions. In John Wiley & Sons, Inc (2nd ed.). John Wiley & Sons, Inc.
Nicholas, G. (2014). An Integrated Risk Evaluation Model for Mineral Deposits [The
University of Adelaide]. https://doi.org/https://hdl.handle.net/2440/86234
Shafiee, S., Topal, E., & Nehring, M. (2009). Adjusted real option valuation to maximise
mining project value - A case study using century mine. Australasian Institute of Mining
and Metallurgy Publication Series, 3, 125–134.
Trigeorgis, L. (1993). The Nature of Option Interactions and the Valuation of Investments with
Multiple Real Options Author. Journal of Financial and Quantitative Analysis, 28(1), 1–
20.
46
Akita University
This research performed identical Java scripts in mining areas which has different
properties with the oil industry, especially uncertainty modeling. We practiced on developed
mining site, especially underwater tin mine planning. The company has the right to extract the
mineral considering the uncertainty of selling price, operating cost, and the amount of mineral
itself. Regarding the limited number of dredges as main equipment, every mining location is
47
Akita University
treated as stage extraction. Therefore, MSSA is an alternative method to compute the real value
of multi project with multi uncertainties driver.
MSSA method started with building stratification map, which represents a partition or
state-space path traveled by the asset's value. It was separated into thin layers along with the
maps like the optimal stochastic control path shown in Figure 4.1. The controlling path was
price, grade, and cost uncertainty.
(MUSD)
(Month)
The algorithm simulates project value 100,000 times considering three uncertainties.
The method is an alternative to combine three uncertainties and more than one project. In the
case study, the option type calculation is delay option of two mining project. The company has
the right to mine, wait or abandon the project considering the three uncertainties.
48
Akita University
Figure 4.2. detailed the steps of the MSSA algorithm. The algorithm was started by
building 400 cells as a state-space of the project value. The multi-stage development was
defined according to the parameters S.
𝑎
𝑆ℎ,𝑗 (i) : the value of the asset a (a=1,….A) at time 𝑡𝑗 to maturity in the ith path of stage h
1 2 𝐴
𝑆ℎ,𝑗 = ( 𝑠ℎ,𝑗 (i), 𝑆ℎ,𝑗 (i),….𝑆ℎ,𝑗 (i) ): the ith mapped path of multiple assets in stage h
The state-space path was divided to run through several cells (cell division stage)
corresponding to the average expected payout of the total number of pathways.
𝑘
Then, whole range of 𝑆ℎ,𝑗 was divided into intervals 𝐶ℎ,𝑗
𝑘 𝑘 𝑘+1
𝐶ℎ,𝑗 = [𝑐ℎ,𝑗 ,𝑐ℎ,𝑗 ] (k = 1,…K)
𝑘
𝑆ℎ,𝑗 = in the state k when 𝑆𝑗 ∈ 𝐶ℎ,𝑗
𝑉ℎ,𝑗 (k) = the continuation value when the option is not exercised at 𝑡𝑗 in stage h
49
Akita University
Furthermore, the division path of project value was generated using Monte Carlo
simulation to model uncertain parameters. Generated the mapped paths of the asset 𝑆ℎ,𝑗 (i) and
𝑘
counted the number of paths 𝑎ℎ,𝑗 (k) such that 𝑆ℎ,𝑗 ∈ 𝐶ℎ,𝑗 (Equation 4.1).
𝑘
𝑆ℎ,𝑗 (i) ∈ 𝐶ℎ,𝑗 ∩ 𝑆ℎ,𝑗+1
𝑓ℎ.𝑗 (k) = ∑𝑆 𝑘
ℎ.𝑗 ∈ 𝐶ℎ,𝑗
(𝑒 −𝑟𝑈ℎ 𝑃ℎ+1,𝑗+𝑈ℎ (m) -𝐼𝑜 ) Equation 4.1
∑𝑆 (𝑒 −𝑟𝑈ℎ 𝑆ℎ,𝑗+𝑈𝐻 -𝐼𝑜 )
ℎ,𝑗 ∈𝐶𝑘
ℎ,𝑗
Where
𝑚
𝑆ℎ,𝑗+ 𝑈ℎ = 𝑆ℎ+1,𝑗+𝑈ℎ ∈ 𝐶ℎ+1,𝑗+𝑈ℎ
when h = 1,……,H-1
𝑘 𝑚
Next step was calculating transition probabilities from 𝐶ℎ,𝑗 to 𝐶ℎ,𝑗+1 and forward
𝑓ℎ,𝑗 (𝑘)
exercise value 𝑒ℎ,𝑗 (𝑘) = (Equation 4.2). Finally, we maximized exercise value and
𝑎ℎ,𝑗 (𝑘)
k k+1
Number of paths from Ch,j to Ch,j+1
∏h,j (k. k + 1) = Equation 4.2
k
Number of paths through Ch,j
Ph,j (k) = max[Eh,j (k), Vh,j (k)]
Where: 𝑉ℎ,𝑗 (𝑘) = 𝑒 −𝑟(𝑡𝑗+1−𝑡𝑗 ) ∑𝐾
𝐼=1 ∏ℎ,𝑗 (𝑘, 𝑙 )𝑃ℎ,𝑗+1 (𝑙) Equation 4.3
𝑓ℎ,𝑗 (𝑘)
𝐸ℎ,𝑗 (𝑘 ) =
𝑎ℎ,𝑗 (𝑘)
As long as the value of waiting to invest is higher than the value of investing
immediately, the company should defer the investment decision (Mun J., 2006). Otherwise,
they do not need to wait to decide to invest or abandon the project.
50
Akita University
Price is a time series variable in the cash flow parameter. Therefore, forecasting price
and modelling the uncertainty should be started by statistical analysis of historical price. One
of the analyses is unit root test to check the stationary data. The most popular one, and the one
that we used, is the Augmented Dickey–Fuller (ADF) test. This test is based on the process yt
= ϼyt-1+vt is stationary when ϼ < 1, but when ϼ=1, it becomes the nonstationary random walk
process yt = ϼyt-1+vt. Hence, one way to test for stationarity is to examine the value of ϼ. In other
words, we test whether ϼ is equal to one or significantly less than one. where the vt are
independent random errors with zero mean and constant variance δ2. Non stationary data can be
modelled using random walk model or Geometric Brownian Motion (GBM) model (Hill et al.,
2011).
The tin price is collected from January 2016 to December 2020 to model the price in 5
years’ production. The ADF test resulted the data was not stationary (Table 4.1). The null
hypothesis that tin price has a unit root can be rejected because the error probability was 27%
or more than 5% threshold. Therefore, we used Geometric Brownian Motion (GBM) model to
simulate SSA. Brownian motion model is a continuous-time stochastic process with three
important properties: Markov process, Wiener process (probability distribution is independent
of any other time interval), and normally distributed with increasing variance over time.
Table 4.1 ADF test on Tin Price data (2016-2020)
t-Statistic Prob.*
51
Akita University
Further uncertainty modelling stage is measuring the volatility of the asset. Thus, we
analyze the price volatility as indicated by its standard deviation (Equation 4.4). The price is
frequently watched at defined periods to assess the volatility of a price experimentally.
1 𝑛
𝑠=√ ∑ (𝑢𝑖 − 𝑢̅)2 Equation 4.4
𝑛 − 1 𝑖=1
Where:
s : standard deviation
𝑃𝑖
𝑢𝑖 ∶ price growth = ln ( )
𝑃𝑖−1
𝑢̅ : mean of 𝑢𝑖
n+1 : number of observation
The standard deviation of the 𝑢𝑖 is 𝜎 √𝜏, where τ is the length of time, thus, σ=s/√τ. It is
not easy to pick a fair value for n. More data typically leads to greater accuracy, although
accuracy varies with time, and too old data for predicting future volatility may be irrelevant.
Alternatively, n can be specified as the number of days to which volatility will be applied as a
rule of thumb (Hull, 2015).
Mining project revenue depends on the price of sold material. In the case study,
historical price sourced from S&P data from January 2016 to December 2020. The unit root
analysis through Augmented Dickey Fuller test resulted a nonstationary data with probability
27%. Therefore, we used GBM assumption to model the price in the project life. Application
of Equation 4.4 to tin price (Table 4.2) resulted standard deviation of 4.7%. The fluctuation was
based on 60 monthly data. The volatility will be used to predict 5 years later.
1
𝑠𝑝𝑟𝑖𝑐𝑒 = √ (0.1373)
60 − 1
𝑠𝑝𝑟𝑖𝑐𝑒 = 0.047
52
Akita University
53
Akita University
𝑑𝑃
= (r-δ)𝑑𝑡 + 𝜎𝑃 𝑑𝑧𝑃 Equation 4.5
𝑃
Where P = price,
r = risk free rate,
δ = convenience yield,
𝜎𝑃 = price volatility,
𝑑𝑧𝑃 = Wiener Process.
The variability of real option value can only be captured when we simulated varies of
the initial investment in either Black Scholes or lattice valuation. An ongoing project can only
54
Akita University
be evaluated through the simulation method. The underlying asset represented by present value
could not capture permutation between cash flow variable which MSSA approach could do.
10
8 -10%
-20%
6
Project Value (MUSD)
-30%
4
-40%
2 -75% -50%
0
Initial
-2 Assumption
-4 Critical Value
-6
-8
-10
5 10 15 17.4 20 23 25
Price ($/Ton) Thousands
55
Akita University
The valuation of mining projects is based on conditional simulation (CS) of ore body
parameters. CS is a geostatistical tool that can generate punctually or block ‘realizations’ of
mineral grades. Each realization is intended to honor the histogram and semivariogram of the
true grade distribution and honor known data points (Nicholas, 2014). It is a technique to
measure spatial uncertainty based on spatial Monte Carlo Analysis (MCS). CS reproduces the
properties of an ore body and quantifies the variability, which we call “spatial uncertainty.” The
realization of CS methodology on our case study is figured at Figure 4.5. The utilization of
MCS is for the NPV probability distribution function and the variability of the projected cash
flow (Jurdziak L and Wiktorowicz, 2008).
56
Akita University
57
Akita University
58
Akita University
10
8 -10%
Project Value (MUSD)
6
4 -30%
-50% -20%
2 -75% -40%
0
-2 Current
Critical Assumption
-4 Value
-6
-8
-10
2 4 6 6.2 8 8.3 10
Total Reserve (M Ton) Thousands
Present Value Option Value
60
Akita University
We measure the technical uncertainty represented by cost volatility. The cost consisted
of mining, processing and metallurgical cost. Unit cost of production model construction was
based on historical cost given by the company with a similar location and production technique
(Figure 4.13). Similar ADF methodology was applied to the summarized historical unit cost
data (Figure 4.14). The unit root test concluded that the cost data is stationer (Table 4.4).
Therefore, the construction of the technical uncertainty model was used the Mean Reverting
(MR) model (Dixit A.K. and Pindyck R.S, 1993) instead of the GBM model. We used the
simplest mean-reverting process-also known as the Ornstein-Uhlenbeck process (Equation 4.8).
The process follows Markov property and does not have independent increments.
800
Thousands
700
Operating Cost (USD)
600
500
400
300
200
100
-
Jul-17
Jul-15
Oct-18
Oct-15
Jul-16
Oct-16
Oct-17
Jul-18
Jul-19
Oct-19
Jul-20
Oct-20
Jan-15
Apr-16
Apr-15
Jan-16
Jan-17
Apr-17
Jan-18
Apr-18
Jan-19
Jan-20
Apr-19
Apr-20
Period
Fuel Cost Employee Cost Material Cost Depreciation Others Total (USD)
61
Akita University
4.00
Sep-15
Jan-16
Sep-16
Jan-17
Sep-17
Jan-18
Sep-18
Jan-19
Sep-19
Jan-20
Sep-20
May-15
May-16
May-17
May-18
May-19
May-20
Period
cost
t-Statistic Prob.*
Then, we calculated x = -a/b, and η = −log(1 + b), and finally, we calculated the
standard error of the regression using equation 4.7.
log(1 + 𝑏)
𝜎 = 𝜎𝜀 √ Equation 4.7
(1 + 𝑏)2 − 1
62
Akita University
2.5
1.5
0.5
X(t)-X(t-1)
0 Y
0 0.5 1 1.5 2 2.5 3 3.5 4 Predicted Y
-0.5
-1
-1.5
-2
-2.5
X(t-1)
The regression model in Figure 4.15 resulted in intercept (b) 1,33 and variable (a) (-
0.88). In addition, it has an R squared error of 44%. Although the accuracy is quite low, the
simulation shows similarity with the historical data. It has better results than the GBM model
(Figure 4.16). In the Figure 4.16, the data was real historical value before January 2021and
followed by the prediction. In summary, the linear regression cost model tends to be back to its
mean in 92% rate (η). Nevertheless, the volatility σc rate is very high, reaching 39%.
dC
= η(x̄ − x)dt + σc dz𝑐 Equation 4.8
C
63
Akita University
In our research, technical uncertainty is related to the cost of operation, which consists
of mining cost, processing cost, and metallurgical cost. The purpose is to compare with other
uncertainty and the strategy to hedge the uncertainty. Historical data analysis showed that the
uncertainty is very high, reaching 39%. Additionally, the model had a different approach with
other uncertainties, which used the Mean Reverting Process and affected the expense side of
the project. Increasing cost decreased project value and vice versa. With the cost uncertainty
being the only driver as assumptions, the project is recommended to be delayed with Net Present
Value (NPV) 7.5 MUSD and Real Option Value (ROV) 15 MUSD (Figure 4.17). It had an
option premium of 100% far beyond our assumed threshold. The option premium can be
pressed below our threshold when either the cost dropped 75% or the volatility decreased to
5%.
64
Akita University
20
-75% -50%
-25%
+25%
15 +50% +75%
Current assumption
0
0 100 200 300 400 500 600 700
-5
Total monthly cost (*1000 USD)
Price, grade, and cost uncertainties were the driver of project risk assessment. The
mining project resulted in net present value output with SSA method in Java was 7.5 MUSD
and real option value 17.6 MUSD. Generated, exercise, and waiting cells values as illustrated
in Figure 4.18, Figure 4.19, and Figure 4.20., respectively. They were randomly picked
simulations from both locations of mining. The exercise values were the overall payoff if one
decides to invest. The waiting values were the expected overall payoff if one decides not to
100
80
Project Value (MUSD)
60
40
20
0
0 10 20 30 40 50 60
-20
-40
Month
65
Akita University
120
100
80
Project Value (MUSD)
60
40
20
0
0 10 20 30 40 50 60
-20
-40
-60
Month
Figure 4.19 Exercise Value with Three Uncertainties Driver (Random Cells
Picked)
60
50
Project Value (MUSD)
40
30
20
10
0
0 10 20 30 40 50 60
-10
Month
Figure 4.20 Waiting Value with Three Uncertainties Driver (Random Cells
Picked)
invest and wait to invest in future time. Furthermore, the project value will be the maximum
values between the exercise option computation and wait-to-operate value computations in each
cell at each time.
66
Akita University
Combination of the three uncertainties is aimed to evaluate the project with the
uncertainties. The exercise and waiting values are compared at each period to decide whether
to proceed with expansion or wait for more favorable economic conditions. These are computed
in the backward calculation. Each cell's exercise and waiting value will always be compared to
obtain the project value for each cell.
The exercise, waiting, and project value computations indicated that the project values
can take any value when deciding to exercise now or in the future. These results showed the
impact uncertainties effects on the mining project. However, the decision-making from the java
results can be made from the frequency distribution, probability distribution, and most
importantly, on the output net present value and real option value with its sensitivity analysis.
A total of 100,000 paths were simulated to calculate the expansion option payoff, and 84,433
were output from the payoff frequency distribution in Figure 4.21. It showed that the largest
number (16,000) of paths remained at payoff range 0, implying the computation recommended
to wait for the project. However, other simulations yielded positive values with most
probabilities at 7 MUSD and normally distributed to 23 MUSD.
18000
16000
14000
Number of simulation
12000
10000
8000
6000
4000
2000
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Payoff Value
67
Akita University
Our assumed MSSA simulation with price, grade, and cost uncertainty consideration
resulted in a project real option value of 17.6 MUSD compared to 7.5 MUSD when using the
traditional DCF Method. We simulated for changes in the critical parameter, which are initial
price (Figure 4.22), initial total reserve (Figure 4.23), and initial total cost (Figure 4.24). With
the determined uncertainty parameter, changing price and reserve gave a similar project value
(Figure 4.22 and 4.23). These results showed a delaying decision recommendation with option
premium reached, 135% which is far beyond our 5% threshold. Moreover, the decision
recommendation shifted into abandoning the project when the project value decreased 90% due
to the option value approaching zero.
40
30
Current Assumption
Project Value (MUSD)
20 +90%
+75%
10 +50%
+25%
0
-15 -10 -5 0 -25% 5 10 15 20 25 30
-50%
-10
-75%
-90%
-20
Present Value (MUSD)
68
Akita University
40
30
20
+75%
+50%
10
+25%
0 -25%
-15 -10 -5 0 5 10 15 20 25 30
-50%
-75% -10
-90%
-20
Present Value (MUSD)
20
15 -90%
-75%
10 -50%
-25%
Project Value (MUSD)
5
Current Assumption
+25%
0
-25 -20 -15 -10 -5 0 +50% 5 10 15 20
-5
+75%
-10
-15
-20
+200%
-25
Present Value (MUSD)
option value. Therefore, we studied further about the contribution of the uncertainty. The
dominant uncertainty was cost uncertainty (39%), followed by geological (9% and 16%) and
price uncertainty (5%). The simulation recommended waiting for the project to be stable
because of the huge option premium which is the differences between present value and option
value.
-25% (13.33) (10.43) (5.62) (0.86) 2.90 6.38 9.85 13.31 15.41
0 (12.68) (8.83) (2.40) 2.90 7.52 12.16 16.78 21.43 24.22
25% (12.04) (7.21) 0.50 6.37 12.16 17.92 23.72 29.52 32.98
50% (11.39) (5.61) 2.90 9.85 16.79 23.76 30.67 37.62 41.79
75% (10.76) (4.00) 5.22 13.32 21.42 29.52 37.63 45.73 50.54
90% (10.37) (3.04) 6.62 15.40 24.19 32.99 41.81 50.60 55.84
70
Akita University
MSSA methodology (Table 4.5 and Figure 4.25) opposed the results of the traditional method,
which recommends immediate exercising of the project. The traditional method recommended
exercising the project when the present value exceeds zero. The present value becomes negative
when the price or reserve drops by 50%. The overall result in both traditional and real option
method is symmetrical because both affect the income value of the cash flow. Discounted Cash
Flow methodology only views the projected income to determine the decision. The assumed
project cash flow is sensitive to income and outcome parameters (Table 4.5). Price and reserve
parameters are the income side of the project. Both parameters will be revealed when the
company decides to exercise the project.
15,821
14,572
INITIAL TOTAL RESERVE (K TON)
12,491
10,409 Assumption
8,327
6,245
4,164
Wait to Operate
2,082
Abandon
833
71
Akita University
4.73
Abandon
3.38 Assumption
2.70
2.03
Execute
1.35 Wait
0.68
5,800 11,600 17,399 23,199 28,999 34,799 40,598
Initial Price (USD/ton)
Price and reserve uncertainties had similar properties related to the shift in present and
option values. However, cost shifting had different outcome patern. Increasing cost definitely
decreasing value of the project. The option premium as determinant of decision
recommendation can be decreased by increasing the profit or decreasing the uncertainties driver.
We have simulated further for the uncertainties driver at Figure 4.27.
72
Akita University
Figure 4.27 showed that project uncertainties accounted for option premium in the real
options methodology. Price and reserve volatility is combined regarding their similar properties
of affecting income side of the project, while cost uncertainty separated to assess the result. The
figure explained that cost uncertainty was the most dominant factor of the option premium
compared to other uncertainties. For instance, if the company decides to have a 10% maximum
risk, they should decrease the cost volatility below 5%, and so on. Otherwise, the project is
delayed.
Nevertheless, the uncertainty alteration does not change the decision using a traditional
methodology represented by the present value. The simulation has proven that cost uncertainty
assurance is the key to project value using MSSA methodology. Additionally, the changing
price and reserve are related to the present and option value shift. However, it made a pattern
with the constant of option premium. Therefore, we simulated further for the no-cost
uncertainty case.
73
Akita University
Notating the distinction of cost parameters, we investigated the project value with no
cost uncertainty (Figure 4.28, and Figure 4.29). The assumption is the company can control the
cost to secure the profit. Our multi-stage SSA simulation with no cost uncertainty case yielded
an RO value of 7.8 MUSD, compared to the corresponding net present value (NPV) of 7.5
MUSD obtained from the standard DCF method. The simulation resulted in a significant
waiting value decreasing from 17.6 MUSD. The magnitude of the cost uncertainty parameter
affected the decision recommendation significantly. In addition, we modeled the changes using
important parameters: initial price and initial reserves (Figure 4.28, and Figure 4.29). They were
treated as if their positive and negative values fluctuated. Nonetheless, the critical value of
changing decision recommendation was specified when the option value approached the present
value and was close to zero.
10
-10%
8
-20%
6
-30%
Project Value (MUSD)
4
-40%
-75% -50%
2
0
Initial
-2 Critical Value Assumption
-4
-6
-8
-10
20.8
5 7 9 11 13 15 17 19 21 23 25
Price ($/Ton) Thousands
74
Akita University
10
8
-20%
6
-30%
Project Value (MUSD)
-10%
4
-40%
-75% -50%
2
-2 Critical Current
Value Assumption
-4
-6
-8
-10
2 3 4 5 6 7 7.5 8 8.3 9 10
Total Reserve (Ton) Thousands
When the price dropped by more than 10% from our assumption, the option premium
value surpassed the assumed 5% threshold (Figure 4.28). Because the trend of option premium
was increasing, the wait to execute decision was recommended to delay the execution of the
project. When the price dropped by 45% and the RO value was almost zero, the decision was
changed to "abandon the project."
The changing reserves parameter (Figure 4.29) had a similar result to the price alteration
(Figure 4.28). A decrease of 10% reserve from our expected CS shifted the decision from
execution to wait until the uncertainty was resolved. Moreover, when the reserves dropped by
45% from the estimated value in CS, the recommendation was changed from waiting to execute
the project to abandon it as the threshold exceeded 5%.
Scenario analysis was performed to map the decision recommendation and spread from
the original assumption shift in price and reserve grade. Table 4.7 and Table 4.8 represent the
project's present value and option value, respectively. Recommending a decision through RO
was performed by comparing the present and option values. In contrast, the traditional method
produced the present value as the only decision parameter.
75
Akita University
-5%
0 (12.68) (8.83) (2.40) 2.90 7.54 12.18 16.80 21.38 24.20
5% (12.55) (8.51) (1.77) 3.59 8.47 13.31 18.18 23.04 25.95
10% (12.43) (8.18) (1.16) 4.30 9.39 14.49 19.57 24.67 27.69
15% (12.30) (7.86) (0.58) 4.99 10.31 15.64 20.95 26.30 29.48
20% (12.17) (7.54) (0.02) 5.68 11.26 16.79 22.32 27.89 31.24
25% (12.04) (7.22) 0.50 6.38 12.17 17.96 23.73 29.52 32.99
The colored blocks in Table 4.7 represent the decision recommendation through the
traditional DCF method. A positive present value would be reached if the price exceeded 12,000
dollars per ton ore or drops 50% from our initial assumption. With option premium due to the
parameter's wait-to-operate value resulting from uncertainty, the RO methodology and the SSA
approach improved the decision to neither execute (green color) nor reject (red color) the mine
project. Instead, it provided waiting recommendations for specific cases, as shown by the
yellow color in Table 4.8 and Figure 4.30.
76
Akita University
12490.5
Execute
11657.8
9992.4
9159.7
8327 Wait
Wait
7494.3
6661.6
Abandon
5828.9
4996.2 Abandon
4163.5
3330.8
Uncertainties were not accounted for in the traditional method; therefore, they did not
affect the present value and remained constant at 7.5 MUSD either using manual-based DCF
calculations or SSA through the JAVA program language. These calculations summarized the
cash flow model with the additional time value of money. Figure 4.31 displays the option value
alteration where the uncertainty was changed in increments of 5%. The value of waiting implied
that the project had to be delayed when the option value was far from the calculated present
77
Akita University
value. A shift in the price uncertainty had an almost symmetrical effect with the reserves
uncertainty to the option value. When the parameter was altered below the critical value of 8.3
MUSD, the decision recommendation was changed from execution to wait-to-operate or to
abandon the project. The price and reserves parameters presented the income side of the project;
therefore, both parameters were incorporated when the company decided to exercise the project.
The two uncertainties had similar properties, implying future decisions based on future
conditions.
Figure 4.31 Real Option (RO) Value with Price and Reserve Uncertainties Alteration
A mining company does not have control over price and reserve. Price will always
fluctuate in the future, which depends on the supply and demand of the commodity. On the
other hand, the reserve is a spatial base parameter. It will be known when mining the reserve.
Otherwise, the company should increase the exploration drilling to assure the reserve. The
spacing between drill holes determines the volatility. It can be additional data to confirm the
reserve amount and decrease the geological uncertainty. However, the geological uncertainty
will never be eliminated caused by the nugget effect. The term "nugget" is borrowed from
geostatistics, referring to the unexpected nugget of minerals founding a mining process (Yin J
et al., 2011). Cressie (1993) concluded that the nugget effect in geostatistics is caused by two
factors: micro-scale variation and measurement error.
The critical value was calculated to secure the project profitability. Dixit and Pindyck
emphasized that this critical value is reached when the waiting value is identical to or less than
78
Akita University
the executing value (Dixit & Pindyck, 1993). However, the uncertainties created distance
between the two values. Mun stated that the company's behavior determined the risk of a project
(Mun, 2006). Therefore, the critical value may vary among decision-makers. Although both
methods recommended immediate execution of the project, SSA improved the results of the
traditional method. The traditional method recommended executing the project when the
present value exceeded zero. This improvement caused the RO methodology to recommend the
delay option under several other conditions.
79
Akita University
4.7. References
Adachi, T., Mogi, G., & Adachi, T. (2008). Real Option Analysis of Multi-Stage Investment
on Resources Development Project by Improved SSA Method. Mining and Materials
Processing Institute of Japan, 124(9), 576–582.
Taylor, M. (2009). What is sensitivity analysis. Consortium YHE: University of York, April
2009, 1–8.
Dixit, A. K., & Pindyck, R. S. (1993). Investment under uncertainty. Princeton University Press.
Jurdziak, L., & Wiktorowicz, J. (2008). Conditional and Monte Carlo Simulation - the Tools
for Risk Identification in Mining Projects. In E. J. Sobczyk & J. Kicki (Eds.), Economic
Evaluation and Risk Analysis of Mineral Projects (pp. 61–72). Taylor & Francis.
Dowd, P. A. (1994). Risk assessment in reserve estimation and open-pit planning. Transactions
- Institution of Mining & Metallurgy, Section A, 103. https://doi.org/10.1016/0148-
9062(95)97056-o
Cortazar, G., Schwartz, E. S., & Casassus, J. (2001). Optimal exploration investments under
price and geological-technical uncertainty: A real options model. R and D Management,
31(2), 181–189. https://doi.org/10.1111/1467-9310.00208
Deutsch, C. V., & Journel, A. G. (1997). GSLIB: geostatistical software library and user’s
guide. Second edition. In GSLIB: geostatistical software library and user’s guide. Second
edition (Second Edi). Oxford University Press.
Dominy, S. C. (2016). Errors and Uncertainty in Mineral Resource and Ore Reserve Estimation
: The Importance of Getting it Right Errors and Uncertainty in Mineral Resource and Ore
Reserve Estimation : The Importance of Getting it Right. January 2002.
https://doi.org/10.2113/11.1-4.77
Hill, R. C., Griffiths, W. E., & Lim, G. C. (2011). Principles of Econometrics (4th ed.). John
Wiley & Sons, Inc.
Nicholas, G. (2014). An Integrated Risk Evaluation Model for Mineral Deposits. The
University of Adelaide.
80
Akita University
Adachi, T., Mogi, G., & Adachi, T. (2008). Real Option Analysis of Multi-Stage Investment
on Resources Development Project by Improved SSA Method. Mining and Materials
Processing Institute of Japan, 124(9), 576–582.
Mun, J. (2006). Real options analysis: tools and techniques for valuing strategic investments
and decisions. In John Wiley & Sons, Inc (2nd ed.). John Wiley & Sons, Inc.
Sefemo, D. F., & Adachi, T. (2015). Management Flexibility and Its Real Option Pricing in
Expansion Project of a Metal Mine: Actual Case Study in Selibe Phikwe Mine , Botswana ,
Africa. April, 922069.
Crundwell, F. (2008). Finance for Engineers: Evaluation and Funding of Capital Projects.
Springer-Verlag London Limited. https://doi.org/10.1007/978-1-84800-033-9
Yin, J., Ng, S. H., & Ng, K. M. (2011). Kriging metamodel with modified nugget-effect: The
heteroscedastic variance case. Computers and Industrial Engineering, 61(3), 760–777.
https://doi.org/10.1016/j.cie.2011.05.008
Cressie, N. A. C. (1993). Statistics for spatial data revised edition. In John Wiley & Sons, Inc.
John Wiley & Sons, Inc.
Mun, J. (2006). Real options analysis: tools and techniques for valuing strategic investments
and decisions. In John Wiley & Sons, Inc (2nd ed.). John Wiley & Sons, Inc.
Dixit, A. K., & Pindyck, R. S. (1993). Investment under uncertainty. Princeton University Press.
Haque, M. A., Topal, E., & Lilford, E. (2014). A numerical study for a mining project using
real options valuation under commodity price uncertainty. Resources Policy, 39(1), 115–
123. https://doi.org/10.1016/j.resourpol.2013.12.004
81
Akita University
82
Akita University
Chapter 5 Conclusions
The mining project had been planned using GEOVIA Surpac and Whittle Mining
Software based on real tin exploration data. The assumed price was at January 2020 while cost
is calculated at the average historical data in 5 years with similar mining method and equipment
when the project was planned. The obtained present value for twos mining areas was 7.5 million
USD. Uncertainty in mining could be modeled using the real option and our result was 17.6
million USD with price, grade and cost uncertainties driver. Thus, the MSSA approach in real
option methodology evaluated multi-uncertainty and multi-stage mining (rainbow option). Our
developed algorithm could produce real option value using JAVA Programming as a simulation
tool.
83
Akita University
Generally, a mining company could not control the price and reserve uncertainties. We
used the Geometric Brownian model to account for price and reserve uncertainties. While for
cost uncertainty, the Mean Reverting model gave a better result. Price would be revealed when
the company decided to mine. At the same time, the reserve will be proven by the production.
The increasing of exploration drill data theoretically could decrease the uncertainty. However,
a huge exploration expenditure would be the consequence.
Logarithmic natural growth analysis based on historical data resulted in the price has an
average monthly growth rate (α) of 0.74%. However, to be applied at our evaluation method,
we assumed the price growth would follow the stochastic differential equation model,
particularly the one-factor constant convenience yield model for risk-neutral prices. Assumed
parameters were risk-free rate of 0.25%, convenience yield 0.17% and calculated price
volatility of 4.7%.
This research started to utilize the CS method to quantify the reserve uncertainty in real
options valuation. CS is a geostatistical tool that can generate punctually or block ‘realizations’
of mineral grades. Each realization is intended to honor the histogram and semivariogram of
the true grade distribution and honor known data points. It is a technique to measure spatial
uncertainty based on spatial Monte Carlo Analysis (MCS). CS reproduces the properties of an
ore body and quantifies the variability, which we call “spatial uncertainty.” We incorporated
the advanced geostatistical application as well as advanced economic valuation methodology.
We measure the technical uncertainty represented by cost volatility. The cost consisted
of mining, processing and metallurgical cost. Unit cost of production model construction was
based on historical cost given by the company with a similar location and production technique.
Similar ADF methodology was applied to the summarized historical unit cost data. The unit
root test concluded that the cost data is stationer. Therefore, the construction of the technical
uncertainty model was used the Mean Reverting (MR) model. We used the simplest mean-
reverting process-also known as the Ornstein-Uhlenbeck process.
A mining company does not have control over price and reserve. Price will always
fluctuate in the future, which depends on the supply and demand of the commodity. On the
other hand, the reserve is a spatial base parameter. It will be known when mining the reserve.
We simulated the combination relative shifting and volatility of price, reserve and cost. The
real option result opposed traditional Discounted Cash Flow in several condition particularly in
the waiting decision condition. In real option method, option premium is the decision
84
Akita University
determinant. Our 5% threshold assumption recommended to execute the project when the
company can eliminate cost volatility. The condition resulted option premium 3.8% which
dropped from 135% when cost uncertainty is existing. The simulation revealed that cost
uncertainty of 39% was the dominant factor of project valuation using real options methodology
comparing to price uncertainty (4.7%) and grade uncertainty (9% and 16%). The company
should ensure cost planning before executing the project to make the project profitable.
There are many uncertainties in the mining industry. The most significant uncertainties
are economical, geological, and technical, represented by price, grade, and cost. The traditional
method could not explain those uncertainties, and the previous real options method did not
incorporate the uncertainties. This research is a pilot project for combining uncertainties
simultaneously through the MSSA approach. Practically, a mining company can execute at
calculated risk or wait to resolve uncertainty or abandon the project to save from loss.
Additionally, we cannot perform standard real options approaches Black-Scholes and lattice
method to evaluate multi uncertainties. These methodologies resulted only in price risk
measurement by project. They cannot assess an ongoing project and multi uncertainties. In
contrast, the MSSA could capture more permutation of the cash flow parameters. Nonetheless,
the MSSA needed adaptation to model each uncertainty faced by the mining company and high
computation power to simulate.
We simulated further for changing parameter of uncertainty. Price, grade and cost is
assumed as control variable to get critical value. Moreover, those uncertainty is shifted to obtain
profitable project. The uncertainty alteration does not change the decision using a traditional
methodology represented by the present value. The simulation has proven that cost uncertainty
assurance is the key to project value using MSSA methodology. Additionally, the changing
price and reserve are related to the present and option value shift identically. However, it made
a pattern with the constant of option premium.
The current limitation for RO, including mathematical complexity and applicability, is
solved using our methodology. SSA simulation solves the mathematical problem while
incorporating grade uncertainty in the simulation to determine the project value and risk.
However, the SSA methodology needs optimization on number of simulation and modeling
methods. Balancing calculation time and consistency of result is the key of method limitation.
Furthermore, comparing to Black-Scholes and Binomial Lattice method, only SSA can be
performed on the case study. Adding capital assumption and eliminating grade uncertainty, they
85
Akita University
have similar result with difference less than 1%. Nonetheless, capturing additional uncertainty
increases the future applicability of the RO. Each modifying factor in the conversion resource
to be reserved and from geological confidence is supposed to be modeled further to obtain
proper project value and ultimately guarantee a successful project with calculated risk.
This study presented a project that combined uncertainties and multi projects in mining
ventures. We considered pricing and geological factors in two mining locations, whereas other
modifying factors were assumed to be stable. Owing to its ability to capture real-world
parameters, the utilization of the proposed RO methodology in the mining industry is expected
to increase in future. In terms of future development, the valuation method could be further
enhanced to combine additional uncertainties, project valuation, and stages of investment. The
outcome parameter in cash flow in terms of mining expenditure may present an additional
application of the proposed methodology. The method can be developed further to combine
more uncertainties, project valuation, and more stages of investment. The utilization of real
options methodology in the mining industry is expected to increase by capturing the real
uncertainty as stated at modifying factor to convert resource to be reserve. Finally, uncertainties
could be overcome by management's flexibility to either hold or abandon the project.
86
Akita University
APPENDIX
A. Price Modelling
88
Akita University
89
Akita University
B. Resource Summary
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Tonnes Cummulative Volume (m3) Tonnes
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
0.0 -> 0.1 0.01 0.138 0.03 0.01 1,205,250 128,375 385,125
0.1 -> 0.2 0.01 0.627 0.143 0.08 820,125 35,000 105,000
0.2 -> 0.3 0.01 1.084 0.253 0.16 715,125 8,000 24,000
0.3 -> 0.4 0.06 1.825 0.357 0.19 691,125 11,625 34,875
0.4 -> 0.5 0.09 1.144 0.449 0.17 656,250 14,625 43,875
0.5 -> 0.6 0.15 1.239 0.555 0.17 612,375 29,000 87,000
0.6 -> 0.7 0.22 1.436 0.645 0.20 525,375 33,625 100,875
0.7 -> 0.8 0.23 1.597 0.749 0.24 424,500 18,625 55,875
0.8 -> 0.9 0.23 2.244 0.846 0.34 368,625 13,750 41,250
0.9 -> 1.0 0.23 2.614 0.949 0.36 327,375 10,750 32,250
1.0 -> 1.1 0.28 2.518 1.052 0.34 295,125 11,750 35,250
1.1 -> 1.2 0.36 2.423 1.155 0.34 259,875 13,375 40,125
1.2 -> 1.3 0.36 2.605 1.246 0.37 219,750 13,875 41,625
1.3 -> 1.4 0.26 2.845 1.351 0.39 178,125 15,625 46,875
1.4 -> 1.5 0.48 2.952 1.444 0.42 131,250 12,625 37,875
1.5 -> 1.6 0.35 3.15 1.549 0.45 93,375 9,625 28,875
1.6 -> 1.7 0.39 3.642 1.646 0.50 64,500 9,000 27,000
1.7 -> 1.8 0.20 4.308 1.747 0.67 37,500 4,500 13,500
1.8 -> 1.9 0.11 5.757 1.84 0.86 24,000 4,625 13,875
1.9 -> 2.0 0.04 5.908 1.947 1.11 10,125 2,875 8,625
2.0 -> 2.1 0.02 7 2.031 1.28 1,500 500 1,500
Grand Total 0.328 0.905 0.578 0.09 401,750 1,205,250
90
Akita University
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Tonnes Cummulative Volume (m3) Tonnes
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
0.0 -> 0.1 0.02 0.08 0.04 0.01 11,503,500 964,500 2,893,500
0.1 -> 0.2 0.06 0.28 0.15 0.03 8,610,000 484,500 1,453,500
0.2 -> 0.3 0.10 0.46 0.25 0.05 7,156,500 332,000 996,000
0.3 -> 0.4 0.18 0.60 0.35 0.07 6,160,500 308,500 925,500
0.4 -> 0.5 0.23 0.71 0.45 0.08 5,235,000 258,000 774,000
0.5 -> 0.6 0.30 0.88 0.55 0.10 4,461,000 227,500 682,500
0.6 -> 0.7 0.33 1.10 0.65 0.12 3,778,500 151,000 453,000
0.7 -> 0.8 0.38 1.30 0.75 0.13 3,325,500 160,000 480,000
0.8 -> 0.9 0.49 1.38 0.85 0.14 2,845,500 169,500 508,500
0.9 -> 1.0 0.54 1.51 0.95 0.15 2,337,000 177,000 531,000
1.0 -> 1.1 0.53 1.73 1.05 0.18 1,806,000 138,500 415,500
1.1 -> 1.2 0.57 1.84 1.15 0.19 1,390,500 105,000 315,000
1.2 -> 1.3 0.61 1.92 1.25 0.22 1,075,500 90,000 270,000
1.3 -> 1.4 0.76 2.10 1.35 0.24 805,500 97,000 291,000
1.4 -> 1.5 0.72 2.39 1.45 0.27 514,500 84,500 253,500
1.5 -> 1.6 0.59 2.71 1.54 0.35 261,000 44,500 133,500
1.6 -> 1.7 0.33 3.69 1.64 0.53 127,500 16,500 49,500
1.7 -> 1.8 0.13 4.14 1.74 0.66 78,000 8,500 25,500
1.8 -> 1.9 0.07 5.61 1.85 0.91 52,500 6,000 18,000
1.9 -> 2.0 0.03 5.24 1.96 1.03 34,500 4,500 13,500
2.0 -> 2.1 0.02 6.42 2.04 1.18 21,000 3,500 10,500
2.1 -> 2.2 0.00 7.00 2.12 1.88 10,500 1,000 3,000
2.2 -> 2.3 - 7.00 2.27 2.71 7,500 500 1,500
2.4 -> 2.5 - 7.00 2.43 2.77 6,000 500 1,500
91
Akita University
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Tonnes Cummulative Volume (m3) Tonnes
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
2.6 -> 2.7 - 7.00 2.66 2.79 4,500 500 1,500
2.7 -> 2.8 - 7.00 2.74 2.89 3,000 500 1,500
3.0 -> 3.1 - 7.00 3.08 2.84 1,500 500 1,500
Grand Total 0.37 0.60 0.48 0.04 3,834,500 11,503,500
C. Reserve Summary
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Tonnes Cummulative Volume (m3) Tonnes
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
0.0 -> 0.1 0.01 0.14 0.03 0.01 1,123,125 128,375 385,125
0.1 -> 0.2 0.01 0.63 0.14 0.08 738,000 35,000 105,000
0.2 -> 0.3 0.01 1.06 0.25 0.16 633,000 7,875 23,625
0.3 -> 0.4 0.06 1.83 0.36 0.19 609,375 11,625 34,875
0.4 -> 0.5 0.09 1.16 0.45 0.18 574,500 14,125 42,375
0.5 -> 0.6 0.13 1.27 0.55 0.18 532,125 25,375 76,125
0.6 -> 0.7 0.18 1.69 0.65 0.21 456,000 24,250 72,750
0.7 -> 0.8 0.20 1.82 0.75 0.26 383,250 13,375 40,125
0.8 -> 0.9 0.20 2.30 0.84 0.35 343,125 10,500 31,500
0.9 -> 1.0 0.22 2.63 0.95 0.37 311,625 10,375 31,125
1.0 -> 1.1 0.26 2.54 1.05 0.34 280,500 11,625 34,875
1.1 -> 1.2 0.36 2.42 1.16 0.34 245,625 13,375 40,125
1.2 -> 1.3 0.36 2.61 1.25 0.37 205,500 13,875 41,625
1.3 -> 1.4 0.26 2.85 1.35 0.39 163,875 15,625 46,875
1.4 -> 1.5 0.48 2.94 1.44 0.42 117,000 11,875 35,625
92
Akita University
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Tonnes Cummulative Volume (m3) Tonnes
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
1.5 -> 1.6 0.37 3.47 1.55 0.49 81,375 8,250 24,750
1.6 -> 1.7 0.27 3.75 1.65 0.53 56,625 7,875 23,625
1.7 -> 1.8 0.21 4.27 1.75 0.68 33,000 4,125 12,375
1.8 -> 1.9 0.11 6.20 1.84 0.90 20,625 4,250 12,750
1.9 -> 2.0 0.04 6.00 1.95 1.17 7,875 2,500 7,500
2.0 -> 2.1 - 7.00 2.03 2.50 375 125 375
Grand Total 0.31 0.88 0.56 0.09 374,375 1,123,125
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Volume (m3) Tonnes Tonnes Cummulative
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
0.0 -> 0.1 0.01 0.10 0.05 0.02 472,500 1,417,500 7,204,500
0.1 -> 0.2 0.05 0.37 0.14 0.05 220,500 661,500 5,787,000
0.2 -> 0.3 0.09 0.54 0.25 0.07 184,500 553,500 5,125,500
0.3 -> 0.4 0.14 0.64 0.35 0.08 193,000 579,000 4,572,000
0.4 -> 0.5 0.18 0.83 0.45 0.11 141,500 424,500 3,993,000
0.5 -> 0.6 0.25 1.03 0.55 0.12 149,000 447,000 3,568,500
0.6 -> 0.7 0.22 1.17 0.65 0.15 89,500 268,500 3,121,500
0.7 -> 0.8 0.34 1.37 0.75 0.15 116,500 349,500 2,853,000
0.8 -> 0.9 0.47 1.45 0.86 0.15 131,500 394,500 2,503,500
0.9 -> 1.0 0.52 1.56 0.95 0.16 156,500 469,500 2,109,000
1.0 -> 1.1 0.54 1.73 1.05 0.19 125,500 376,500 1,639,500
1.1 -> 1.2 0.59 1.93 1.15 0.21 92,000 276,000 1,263,000
1.2 -> 1.3 0.61 1.95 1.25 0.23 85,000 255,000 987,000
1.3 -> 1.4 0.67 2.16 1.35 0.25 87,000 261,000 732,000
93
Akita University
Grade Range Minimum Grade Maximum Grade Expected Grade Std dev
Volume (m3) Tonnes Tonnes Cummulative
(kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton) (kg/ ton)
1.4 -> 1.5 0.69 2.34 1.45 0.27 75,500 226,500 471,000
1.5 -> 1.6 0.59 2.74 1.54 0.35 41,000 123,000 244,500
1.6 -> 1.7 0.34 3.67 1.64 0.54 16,000 48,000 121,500
1.7 -> 1.8 0.09 4.23 1.74 0.71 7,500 22,500 73,500
1.8 -> 1.9 0.07 5.61 1.85 0.91 6,000 18,000 51,000
1.9 -> 2.0 0.03 5.24 1.96 1.03 4,500 13,500 33,000
2.0 -> 2.1 0.02 6.58 2.04 1.28 3,000 9,000 19,500
2.1 -> 2.2 0.00 7.00 2.12 1.88 1,000 3,000 10,500
2.2 -> 2.3 - 7.00 2.27 2.71 500 1,500 7,500
2.4 -> 2.5 - 7.00 2.43 2.77 500 1,500 6,000
2.6 -> 2.7 - 7.00 2.66 2.79 500 1,500 4,500
2.7 -> 2.8 - 7.00 2.74 2.89 500 1,500 3,000
3.0 -> 3.1 - 7.00 3.08 2.84 500 1,500 1,500
Grand Total 0.44 0.77 0.05 2,401,500 7,204,500
94
Akita University
D. Cost Calculation
Operating Cost
Standard
Unit Year 2015 2016 2017 2018 2019 2020 Average
Deviation
USD Safety Cost 1,869,484 1,143,824 286,234 811,732 1,145,695 1,039,192 1,049,360 470,769
USD Labor cost 1,000,608 1,023,419 1,179,021 583,316 1,095,567 850,748 955,446 193,960
USD Materials 529,372 349,770 84,216 135,668 441,541 198,217 289,797 162,494
USD Depreciation 1,491,945 1,408,482 1,681,748 1,724,791 3,101,246 2,824,272 2,038,748 666,858
USD Others 95,564 64,943 47,940 37,105 661,762 230,894 189,701 220,736
USD Total 4,986,973 3,990,438 3,279,161 3,292,613 6,445,812 5,143,323 4,523,053 1,128,560
Ton Sn Production 199 253 75 40 274 383 204 118
USD/ton Sn COGS 25,116 15,772 98,734 82,315 23,525 13,429 43,149 34,075
USD/ton ore COGS 1.84 1.48 0.92 2.74 2.21 1.46 1.78 0.59
General Cost
Standard
Unit Year 2015 2016 2017 2018 2019 2020 Average
Deviation
Ore Tin
Ton Sn 26,361 24,347 31,035 44,514 82,522 38,235 41,169 19,727
Production
Sales
MT 30,087 26,677 29,914 33,818 64,801 50,235 39,255 13,737
Volume
Overhead
Usd/Ton 2,565 2,877 2,461 1,936 1,294 2,440 2,262 514
Cost
Smelting
USD/MT and Refining 731 701 668 1,084 857 1,000 840 156
Cost
USD/MT Sales cost 1,587 1,424 1,738 1,689 1,790 1,503 1,622 130
95