Record Management Guidelines
Record Management Guidelines
I. GENERAL
Construction inspection is performed to ensure and confirm that contract requirements are met and
documented in the contract records. The records should indicate what work was accomplished, what
checks and / or tests were made and the results of the checks and tests.
It is the responsibility of the Engineer-in-Charge (EIC) to be familiar with all sections of the Contract
Administration Manual (CAM), the Construction Inspection Manual (CIM), the Safety & Health Program
Manual, the Materials Inspection Manual (MIM) and other referenced material and to organize the
contract records, reports, forms, and other contract documents.
SiteManager is NYSDOT's primary contract administration tool and record keeping system.
SiteManager is used to record detailed inspection records, manage material acceptances, track and
process payments, track and process change orders, and as the central contract accounting system.
SiteManager is used by almost all Construction Program staff, including Inspectors, EICs, Construction
Area Supervisors, Regional Construction Engineers, Main Office Construction staff, Main Office
Materials Bureau, and Main Office Accounting.
SiteManager is a secure system that uses User Identification/Password combinations as a
replacement for signatures on paper form(s) to authorize actions. SiteManager records the date/time
that a record is approved, as well as the individual who granted the approval. An individual's authority is
controlled by the rights associated with the role that the individual is assigned and the contract(s) that
the individual is granted contract authority for. For example, the EIC on a contract will be authorized to
review and approve DWRs completed by Inspectors on the contract he/she is assigned to, but will not
be able to see any records for a different contract that he/she has not been granted access to.
Regional staff will typically be assigned contract authority for all contracts in the Region. Quick
Reference Guides (QRGs) 1-13 are available on the Department website at
https://www.dot.ny.gov/main/business-center/trns-port/modules/site-manager/construction as
references on how to perform specific tasks associated with contract recordkeeping in SiteManager.
(See Exhibit 90A.)
Locally Administered Federal-Aid construction contracts have similar record keeping requirements,
but SiteManager is not available for use by local Sponsors. Local Sponsors may use other software
such as Apia or FieldManager, or they may record inspection results on forms, in either electronic or
paper formats. Local Sponsors will have to adapt the guidance presented in this manual to the
recordkeeping system(s) utilized.
Create and maintain records contemporaneously (recorded as events occur). In particular, prepare
Contract Diary entries and Daily Work Reports (DWRs) contemporaneously. Ensure records conform
to current policies and procedures. All active contracts should adapt, insofar as possible, to the latest
revisions. Do not modify documentation that has been compiled prior to any revision retrospectively.
B. Security of Records
When not in use, keep all source documents, reports, correspondence, survey notes, computer
diskettes, etc. locked in the fire resistant file cabinets provided in the Engineers field office. Whenever
the field office is unattended, both the office and the lockable files should be locked.
C. Photographs
As part of the record keeping process, photographs should be taken before, during, and after
construction to help document progress and avoid disputes concerning pre-existing conditions.
Photographs taken by an individual standing at an identifiable location (next to a sign, pole, hydrant,
etc.) that can be identified post construction will enable better comparison of the site(s) pre and post
construction. The number of photographs required will vary greatly depending on the size and
complexity of the construction effort.
Take photographs at the lowest resolution that provides a clear representation of the desired details
the photograph is intended to show. Ensure that the date and time is displayed on the digital
photograph using the proper camera settings to aid identification for future use.
Organize and store photographs using MicroSoft PowerPoint. Reduce very large jpeg files
produced by digital cameras using (Image Resizer is available as a free download
from MicroSoft.). and Create separate files for
needed sets of photographs, using the following file naming convention: Begin each file name with the
contract D#, then PRE_, PROG_ [Progress] or POST_, and then a description. (e.g.
D123456_PRE_Rte 123 or D123456_PROG_123 Bridge Over Creek.) Separate sets of photographs
by highway, bridge, drainage, other structures, etc. to create logical sets that are readily identifiable by
the file name and result in manageable PowerPoint file sizes. Use the presenter notes in Powerpoint to
provide location, subject, photographer, and other pertinent remarks for each photograph. Store
PowerPoint
1. Pre-Construction. Take a set of photographs before construction begins. Take both overall
photographs of the site(s) and specific photographs of affected elements (i.e. bridges, intersections,
affected driveways/ properties, drainage structures to be altered, reconstruction areas, signs,
guiderail, etc.).
2. Progress. Take progress photographs as needed, including significant work zone traffic control
(WZTC) setups. Situations that may be of interest or concern should be photographed. Include a
photograph of each major piece of equipment used in the construction process.
June 2014 New York State Department of Transportation Page 2
Contract Administration Manual
Section 90 RECORD KEEPING PROCEDURES
Take photographs of areas of disputed work, locations of accidents, or other situations where
factual documentation is needed. Document those elements of work that are not visible after the
work is complete, including excavations for abutments & piers, completed pile and footing
placements, pile and structural member connections, forms, rebar placement, concrete placement
for structural elements and underground utility facility installations.
If a stop work order is issued, take photographs of the affected area when the stop work order
was issued.
of the reports available based on data entered into the custom templates are:
The reports are powerful and informative; they contain intelligence that makes them fully functional on
Smart Phones and tablet computers. Select a phone number on a smart phone and it dials the
number; click on directions and the navigation application starts and provides turn by turn directions.
I
The contract diary is one of the most important contract documents. It provides invaluable information
and evidence in the event of later contractual controversies or legal actions. Record any information
that might have a bearing on any probable dispute or claim against the State. Record factual
information, do not record opinions. Ensure that the Contract Diary contains detailed information about
conditions and actions by the various parties that have a significant effect on the progress of the job.
(See Exhibits 90C and 90D.)
Account for all personnel actively assigned to the contract in the Contract Diary for each diary date.
The Contract Diary need not repeat information provided on Daily Work Reports (DWRs). Contract
Diary remarks are to . When an Inspector's
DWR comments critically or adversely about an operation, explain how and when it was resolved,
together with proper cross references.
exercise individual judgment with regard to continuous vs. intermittent diary entry during this period and
is to so note it in the diary. Record pertinent actions and if intermittent diary entry is used, account for
unrecorded days under Remarks 3. - General.
Cease regular contract diary entries when the Regional Director recommends contract final
acceptance, or the contract completion date is reached. Contract diary entries cannot be made in
SiteManager after the contract completion date unless an administrative time extension is approved by
the RCE. An administrative time extension does NOT change the contract completion date, but it
allows additional diary entries. After cessation of regular contract diary entries, until the final agreement,
maintain a log of contract related actions (telephone calls, correspondence, conversations, etc.) that
are pertinent to contract completion. Attach the log to a contract diary in SiteManager. If the work for
preparation of the final agreement is transferred to the Regional Office, record the transfer in the log
and any additional log entries will be made by Regional Construction Contracts staff.
B. Diary Entries
Contract diary entries are not locked in SiteManager until contract final acceptance. Original entries,
later determined to be in error, must not be edited or deleted. If a previous contract diary is opened and
edited in SiteManager, it will be saved with a new date/time stamp of approval. If an error is found a
found or determined to be an error
and a reference to the original date noted with a correction made.
1. DWR Complete Leave Blank. This field is for DWR entries only and not a Diary remark.
2. WZTC Work Zone Traffic Control Indicate WZTC conditions encountered in the daily
inspection, especially with regard to necessary signs, channelization, etc and note any corrective
action ordered. (Follow through in future entries, noting final action to obtain satisfactory results.)
escription of WZTC
For multiple sites spread out over a large geographical area, or work on multiple shifts (e.g. day
3. General Indicate the details of any operation not covered by a DWR. This information may be
needed should a dispute or claim arise that requires an analysis of the Contractors total work force
and equipment usage. (See Remarks #15 Dispute below.)
Inspection of Materials: Record any samples, tests or checks taken if they are not covered by
the DWRs. Also, record by whom they were taken, whether they passed or failed, and note any
corrective action if necessary. Include samples taken by others such as Contractors, test labs, etc.,
if pertinent to a work operation.
Indicate any Subcontract
initial entry and completion of work on any easement (temporary of permanent) or fee taking.
Record weather conditions for each business day for the duration of the Contract, through a
DWR. If no operations are recorded on a day then an inspector is to be assigned to record on their
DWR. If there are no DWRs (no personnel) on the day record weather conditions in the Diary.
5. Phone Calls Document all pertinent incoming and outgoing phone conversations, including
decisions and directives. Note any directions from Construction Area Supervisor(s) or approvals by
Regional or Main Office staff. Cross reference to correspondence remarks section for e-mail
communications.
6. Visitors Record all visitors, their affiliated organization(s), and any pertinent discussions that
affect the contract.
7. Directions to Prime/Sub Document discussions with Contractor, including written and verbal
orders, final actions taken, any details important to support possible future disputes or legal action.
10. Civil Rights If a DBE has performed a Commercially Useful Function (CUF) on a FA
contract, make the following entry: [DBE Firm Name] has performed a Commercially Useful
Function (CUF) on contract [D123456] on [date].
11. Suspension/Delay Record delays, conditions, events and Contractor actions or inactions
that have or could have an effect on the Contractor's adherence to the approved schedule. Refer to
§108-01 Progress Schedule, for additional information.
12. Meetings Note the Pre-Construction meeting, regular progress meetings, and any other
pertinent meetings with Regional, Main Office or outside agencies, (e.g. meetings with
representatives of utilities, railroads, and various government agencies.) Note meetings held with
property owners, especially where agreements regarding driveways, trees, or frontage treatment,
etc. are made.
13. Utilities Record any work performed by others: i.e., permit work, utilities, land owners,
municipal personnel and others. Note start and completion of work and any pertinent conditions.
15. Dispute Describe disputed work issues, including the first date of notice. Indicate if force
account records are being maintained, or alternatively, if the Contractor has been directed to
maintain force account records. DWR should note presence of supervisory personnel and any idle
equipment so that the total on site work force and equipment is recorded. Record the presence of
supervisory personnel and idle equipment that do not appear on a DWR. This information may be
needed should a dispute or claim arise that requires an analy
and equipment usage.
17. Audit Record any audits performed by either the Department or other Agencies (i.e. OSC,
FHWA, NYSDOL, etc) and state the name(s) of the person(s) performing said audit.
B. DWR Entries
e DWR. If an
error is noted in A DWR, the DWR is returned to the Inspector for correction prior to authorization. A
DWR
DWR needs to be corrected after it is authorized by the PM, the PM must reset the DWR to
then reauthorize it. Once a contract payment
is made based on an item and quantity on a DWR, no further edits to a DWR can be made. Changes
must then be made on a correction DWR which references the original, incorrect DWR.
1. DWR Info
Contract D number
Date
Temperature and Weather for their operation(s)
Remarks
#1 DWR Complete Enter
#2 WZTC
Note procedure used, indicate any problems encountered and remedies to them. Do not use
oversimplified r with location, and details.
-87 SB passing lane from Exit 16 to Exit 15, 9:00 AM 3:00 PM.)
#3 General Remarks Enter remarks that do not pertain to a work item, including any discussions
with Contractor personnel or other relevant topics (e.g. permit work, utility work, etc.). Record
#4 - Contrctr Work Hrs (military time), - Record Contractor and/or Subcontractor times.
#5-17 are not used for typical Inspectors DWRs
2. Contractors
Select the Prime and/or Subcontractor(s) who are performing the work being recorded and their
personnel (Labor).
R personnel if the shift is either greater than or less than the
standard eight hour day, noting those hours.
3. Contractor Equipment
Record all Equipment used by the Prime and/or Subcontractor(s) performing the work by selecting
from the pulldown list.
R the duration of the shift
Record speci for Force Account operations.
Record all operating equipment as well as non-operating equipment.
4. Daily Staff
Not Used
5. Work Items
Select the Work Item in the correct Category (Fiscal Share), the Description of Work is displayed.
Record the q Placed Q .
Enter the Engineering Share if applicable.
Select the Contractor performing the work item.
Enter the location of the operation; drainage structure number, ramp name, street name, mile
marker, pour number, or other description to assist in retrieval of information. Fill in the stationing
field(s) if pertinent.
Interim Quantity: Interim quantities are estimates of the quantity of work completed. They are used
when it is more efficient to delay final measurement of quantities until a particular segment or
portion of an item has been constructed (as opposed to daily computation of item quantities of each
completed segment). This method should not be used for most items. Document computations for
interim quantities.
Interim quantities are estimates of the work completed, and must be superseded by final
quantities which are based on accurate measurements, and computations.
Final Quantity: Final quantities are the final measured or computed amounts actually used. With
most items final quantities will be used and recorded on a DWR. Base computations of volumes,
areas, etc., on final measurements made with the degree of accuracy consistent with the item.
When the final quantity is calculated for a previously entered interim quantity, record the final
quantity on a DWR and reference the date when the interim quantity was recorded, and deduct the
interim quantity.
For example: computations for excavation should not be made to the nearest hundredth (0.01)
of a cubic foot, when field measurements are made to the nearest tenth of a foot (0.1) for elevation,
and to the nearest foot (1) distance. Do not show any quantity with more than two decimal places
unless required by the specifications.
C. Specialized Operations
Certain work operations have unique record keeping requirements and
associated to the following specialized operations (work items) and are required to be used. When an
Inspector is assigned to one of these operations they are to fill out the associated template under that
work item to record delivery, temperatures, tests and any other required information.
Concrete Pavement
Structural Concrete
Asphalt Pavement
If a template is not available, upon Regional Construction Engineer concurrence, the current MURK
Detail all materials received that require acceptances or certifications (e.g.: pipe, rebar, mesh, etc.)
as required by the specification.
For materials that use hot mix asphalt or portland cement concrete, information is provided from the
plant at the end of the day's production on Form BR 316 (PCC) or BR 313 (HMA). Verify that the total
amount shipped from the plant was received.
Do not complete a sample or bulk items from acceptable sources (e.g. top soil, sub-base, select fill,
etc) that have delivery tickets and are documented via a DWR template (i.e. logging the tickets and
placing them in the appropriate item file). Retain weight or batch slips received for items paid for in
place (e.g. concrete, etc.), in the item file but do not treat them as source documents.
Ensure the Template or Sample connected to a contract pay item contains the following:
1. Material Code. Verify that all applicable material codes (primarily 700 series specifications) are
identified. If several materials are required by one contract pay item, select all the corresponding
templates or samples. (Example: 709-04)
2. Material Description. Indicate as appropriate: the type, model, option, grade, etc. of the
material received. (Example: Epoxy-Coated Bar Reinforcement)
3. Product Name. Some materials are identified by brand name, many do not have a brand
name, and therefore those entries are blank. (Example: Blank)
5. Inspection. Inspect material when it is received to ensure that it meets the material
requirements. Record the inspection on a DWR, including the date received, the quantity and any
other pertinent information that establishes compliance.
1. When more than one material acceptance is required for a contract pay item, check that all
material requirements are met before the item is accepted for incorporation into the work.
2. The various materials that make up the contract pay item identify the quantity in the unit of
measure for the contract pay item. For example, guiderail tube and posts will both identify the
length of installed guiderail that the material will supply, not length of tube and number of posts.
X. FINAL RECORDS
Final records will vary in number according to the size and complexity of the work. Whenever possible,
create and use information electronically, and avoid paper records wherever possible. If documents
are scanned, the original paper records may be retained for the duration of the contract, but need not
be archived. Organize final paper records in a bound book, loose leaf book, folder, envelope, etc.
Number boxes containing final records consecutively and list contents on the outside.
A. Critical Dates
Ensure all of the critical dates marked Required to Finalize in SiteManager are entered by the
SiteManager Regional Contract Administrator
acceptance. Do not print lists for archiving.
B. Inspection Staff
Print a copy of the report of the inspection staff assigned to the contract.
C. Final Book
Compile the Final Book at the completion of work and will include any required reports produced by
SiteManager in place at time of finalizing. Include the Final Record Index in the front of the first Final
Book. Include a hard copy of the Final Estimate, (CONR 22 - SiteManager report). Group and label all
other records as appropriate.
The Department's policy regarding the availability of construction contract records is to allow a
Contractor to inspect and if desired, to copy records, notes or documents that contain statistical or
factual tabulations or data pertaining to engineering and payment information which apply to their
contract during the period between award and final agreement. The following guidelines apply to
commonly requested construction documents:
1. Contract Diary and Daily Work Reports. Allow the Contractor to review those portions of the
contract diary and DWR's that contain statistical or factual tabulations or data under the supervision
of a Department employee.
2. Quantities. Allow the Contractor to review methods of measurement and computations for
quantities under the supervision of a Department employee.
3. Cross sections. Allow the Contractor to review cross sections under the supervision of a
Department employee.
4. FOIL Requests. Where review of contract diaries, DWRs, quantities or computations exceeds
the normal amount of time required for a comparison of quantities at a meeting with Department
staff, provide copies of the required information to and charge the Contractor in accordance with the
billing procedure provided in MAP 2.7-1.
EXHIBITS
A SiteManager Construction Quick Reference Guide (QRG) List 1-15 & 29-32
B Sample NYSDOT Custom Record Template
C Sample SiteManager Inquiry Report
D
E Sample SiteManager Daily Work Report
F Sample SiteManager Material Sample Data
G Sample SiteManager Correspondence Log