Analysis and Design of Bridge Substructures in Eurocodes Using Java Programming Language
Analysis and Design of Bridge Substructures in Eurocodes Using Java Programming Language
ISSN No:-2456-2165
Umeonyiagu I. E. (PhD)1
Mbachu I. C.2
TITLE 2400
ABSTRACT 2401
TABLE OF CONTENT 2402
CHAPTER ONE INTRODUCTION 2403
CHAPTER TWO LITERATURE REVIEW 2405
CHAPTER THREE METHODOLOGY 2425
CHAPTER FOUR DESIGN, RESULTS AND 2442
ANALYSIS
CHAPTER FIVE CONCLUSION AND 2466
RECOMMENDATION
REFERENCES 2467
A computer software package for the analysis and design of substructures for concrete bridges with simply supported spans
based on Euro codes will be developed using the Java programming language in this research work.
Aim
Design and analyze reinforced concrete bridge substructures on Eurocodes 2, using manual and Java programming language.
This study aims to create interactional, easy computer software for the analysis and design of reinforced concrete bridge
substructures that has simply supported spans.
Objectives
The objectives of this study are:
D. Scope of Study
This study will design and analyze simply supported bridge substructures based on eurocodes 2, using manual and computer
methods. Two types of piers will be considered namely: Wall and hammer head type with round shaft. Wind, earthquakes, as well
as hydrodynamic effects will all have an impact on gravity and lateral loads. At both the ultimate and elastic states, the well
foundation analysis is conducted. For both vertical and lateral loads, only under-reamed and drilled cast-in-place piles in frictional
and cohesive soils are used in the analysis and design of the pile foundation. Structural design of pile and pile-cap will be included
in this work. Analysis and design of bridge superstructural components are not considered here.
Bearing Capacity:
Compare the maximum bearing pressure that can be applied to the maximum bearing pressure that is allowed.
Overturning:
This check is exceptionally, significant for spread base abutments that regularly needs to endure horizontal soil strain on the
backwall and for spread footing piers which will have enormous tipping over (overturning) moments, in particular, assuming they
have tall piers.
Sliding:
Spread base abutments, will generally have to defy lateral soil pressure action on backwall, require this check to be
performed very carefully.
Settlement:
While considering spread bases in soil, the normal settlement of the structure will have to be within the tolerable settlement
calculated.
Spread footings are mostly used when solid rock is found at shallow depths, but they can be used to build foundations on soil
where scour is not a factor.
The recommended values of the resistance factors for spread foundations is given in Fig 2.1
{See Fig 2.1 Partial Resistance Factors (gR) for Spread Foundations (Fig A.5 of EN 1997-1), page 1 Tables for Research
work}.
B. Deep Foundations
Deep foundations give backup to foundations, in manners that essentially not the same as spread footings. Driven piles or
bored shafts, known as bored piers or bored caissons, are the two most common types of deep foundations. Deep foundations like
Values of the resistance factors for retaining structures recommendations are given in Fig 2.2
{See Fig 2 Partial Resistance Factors (gR) for Retaining Structures (Fig A.13 of EN 1997-1) page 1 Tables for Research
work}.
Subsurface Considerations:
Relying on the situation of the subsurface conditions, drilled shafts and piles each have likes and dislikes. These
circumstances frequently clearly favour one over the other.
Structural Conditions:
Piles or drilled shafts may be selected based on the loading conditions and structural configurations. Individual driven piles
for a smaller size may not be as effective at conveying lateral loads and moments as individual drilled shafts of a larger diameter.
Environmental Factors:
Environmental degradation is more severe with some foundation construction methods and types than with others. In order
to access the environmental impacts and environmental commitments that is likely to influence the selection of the chosen type of
foundation and construction method, the contractor will collaborate with specialists in environmental permitting.
Piles
Pile Types
According to FHWA (2012), there are numerous circumstances when selecting between pile foundations and bored shaft
foundations, including:
Subsurface Considerations:
Relying on the situation of the subsurface conditions, drilled shafts and piles each have likes and dislikes. These
circumstances frequently clearly favour one over the other.
Structural Conditions:
Piles or drilled shafts may be selected based on the loading conditions and structural configurations. Individual driven piles
for a smaller size may not be as effective at conveying lateral loads and moments as individual drilled shafts of a larger diameter.
Environmental Factors:
Environmental degradation is more severe with some foundation construction methods and types than with others. In order
to access the environmental impacts and environmental commitments that is likely to influence the selection of the chosen type of
foundation and construction method, the contractor will collaborate with specialists in environmental permitting.
Caution has to be applied as battered (or “brace”) piles are utilized. As long as the lateral capacity is meticulously evaluated,
giving that battered piles tolerate lateral capacity of the pile foundations, there is increase in axial load as regard the effect of
lateral load. Hence, check for possible pile hindrances. Additionally, "too many battered piles" are brought to the notice of
designers. In some circumstances, mainly in abutments, where piles may be battered in one direction alone to withstand lateral soil
pressures, the substructure may "walk backward" into the retained fill if the longitudinal component of the battered pile axial loads
is bigger than the passive pressure of the retained fill of the substructure. The idea was that the out-of-plumbness and out-of-
position top of pile tolerances during construction should be considered by designers. The pile design ought to consider these axial
load application due to eccentricities allowance. It is essential to take note of that relying upon how the contract was written his
capacity to manage piling the impacts of out-of-plumbness and top of pile out of position might be must do. A pile might, for
example, be notably out of position at its lower end while, yet fulfilling the out-of-plumbness necessity, while at the same time,
fulfilling the out-of-position prerequisites by being out of position at opposite direction, at top of the pile. In these circumstances,
the combination of the two effects results in the net effective eccentricity.
Fig 2.3 Pile Classifications on the Basis of Load Transfer Mechanism (Patel, 2008).
When loaded, a pile transfers the load through point bearing at the pile's tip and skin friction along its length. As a result, the
assumption that a pile's ultimate bearing capacity is the sum of its total ultimate point or end bearing resistance 𝑞𝑝 and its total
ultimate skin friction fs can be used to calculate its ultimate capacity 𝑄𝑢 (Patel, 2008).
Q u = Q s + Q p, = fs As + qp Ap, (2.1)
Where
For piles in Cohesionless soil, the unit point bearing resistance is given as by (Patel, 2008):
qp = ̅̅̅(N
pv q − 1) + λs γBNγ (2.2)
For piles in cohesive soils, Patel (2008) gave the point bearing resistance and the skin frictional resistance as follows:
q p = cu Nc (2.3)
cu = undrained cohesion at the pile tip and
Nc = bearing capacity factor generally taken as 9
fs = αcu (2.4)
Where
α = adhesionfactor
Q Myy xi Mxx yi
Qi = + + (2.5)
n ∑ x2 ∑ y2
Where
If the calculated load on a pile exceeds its safe bearing capacity, then the piles are required to be redesigned. The option is
that, the number of piles or the spacing between piles can also be increased to reduce the maximum load acting on the pile.
Fig 2.4 Computation of Settlement for end bearing Piles & Friction Piles (Terzaghi and Peck (1967)
H p
̅̅̅v + ∆p
Si = 2.303 log10 ( ) (2.6)
C pv
̅̅̅
Where
1.5qc
C = constant of compressibility = (2.7)
∆p
Where, qc = average static cone penetration resistance for the layer considered
Cc H p̅̅̅v + ∆p
Si = log10 ( ) (2.8)
1 + C0 pv
̅̅̅
Where
Where
Cc H pv + ∆p
̅̅̅
Si = log10 ( ) (2.9)
1 + C0 pc
Fig 2.5 Piles in Expansive Soils can Control Seasonal Movements (Patel, 2012)
Drilled Shafts
The variety of deep foundation types is somewhat more limited when it comes to drilled shafts. Drilled shafts most likely
share a few characteristics in common: a round, relatively deep hole that was bored in the ground and filled with reinforced
concrete. O'Neil, et al., contains two useful references on the construction and design of drilled shafts: (1999) as well as Barkar et
al., (1991). Penetrated shafts are some of the time classified according to wellspring of their lateral capacity as either end bearing
bored shafts, side friction bored shafts, or a mix of the pair.
According to FHWA (2012), several additional characteristics vary from application to application for drilled shafts:
Casing:
Steel casing is frequently used to hold the drilled hole open till concrete is casted when shafts are drilled through caving-
prone soils. The casing may then be removed in some instances, while in other instances, it may remain in place.
Bottom Configuration:
For the increment of the end bearing area, the bottom of a drilled shaft may be expanded in some instances. Due to the bell-
shaped shape at the shaft's tip, these are referred to as "belled" drilled shafts.
Rock Attachments:
At times where penetrated shafts are introduced in rock with soil overburden, the shafts are bored a short profundity into
rock to get solid end bearing or to accomplish lateral fixity. At times, measurement of these stone attachments is somewhat not
exactly same as that of the remainder of the penetrated shaft.
F. Conventional Abutments
These attributes recognize regular abutments, otherwise called seat-type abutments: a joint that isolates the bridge deck from
the abutments backwall and front slab/front pathway, as well as a member that isolates the superstructure from the abutment,
bearings. The regular design and construction of abutments can be improved on account of these divisions. Consequently, the
interface between the superstructure and substructure is distinct and well-defined. Contrarily, conventional abutments call for the
use of expansion joints, which demand an upkeep and have the possibility to jam or leak, putting the girder, bearing, or abutment
at greater risk of deterioration. Furthermore, integral or semi-integral abutments are more robust and redundant than conventional
abutments.
Height:
Conventional abutments can be broadly categorized in terms of height as either stub abutments or tall abutments. In a stub
abutment, the depth of the abutment cap is set at a nominal, and usually fairly shallow, depth, typically not much deeper than the
cap width, or less. Stub abutment caps depths are often standardized as an owner-agency preference. Stub abutments usually also
feature a header slope in front of the abutment cap. The grade of the header slope can be as shallow as 4:1 or shallower or as steep
as 1:1 or steeper, depending on owner-agency typical preferences, aesthetic considerations, clearance considerations, and notably,
slope stability considerations, including consideration of the type of slope protection used, if any. Tall abutments, on the other
hand, function as retaining walls as well as supports. Tall abutments are often used when horizontal clearance requirements below
the bridge prohibit the use of a header slope, or where superstructure span lengths restrict the location of the abutment.
Sometimes, a stub abutment is used in conjunction with a separate retaining wall in front of the abutment. This can be done to
achieve similar geometric goals as a tall abutment in terms of maintaining horizontal clearances. Any of a number of retaining
wall types can be used: Mechanically Stabilized Earth (MSE) walls, soil nail walls, drilled shaft walls, etc. There are a few
caveats, however. First of all, careful coordination is required to ensure the abutment foundation elements do not interfere with
any of the wall elements, especially when the wall uses straps, tie-backs, soil nails, etc. Also, the wall designer needs to be fully
informed of the abutment configuration when designing the wall to make sure that all loads are correctly quantified in the wall
analysis. At a minimum the abutment and its backfill represent a surcharge loading on the wall, and depending on the abutment
and the wall configurations, additional loads may exist as well.
Width:
The width of an abutment cap is being controlled by many conditions, include:
The demand to fit bearings and anchor bolts with adequate edge distances.
The demand to fit one or more rows of piles or drilled shafts with enough spacing and edge distance.
The demand to meet seismic detailing guidelines related to required seat widths.
Wingwall Configuration:
Wingwalls are made to retain the backfill which would otherwise “spill around” the ends of the abutment backwall and cap.
Wingwalls can be oriented in a number of directions including parallel to the cap, angled at some angle (e.g., 30 deg., 45 deg.),
turned back (parallel to the roadway, pointed away from the span), or turned forward (parallel to the roadway, pointed toward the
span). The preferred orientation and layout of wingwalls is usually determined by owner-agency preference or local practice.
Expansion Joints:
The design of expansion is done in such a way it allows for free anticipated movements of the superstructure relative to the
abutment. Care should be taken in calculating these movements to account for all potential sources of movement. Thermal
expansion and contraction are typically the primary sources of these movements but other sources may exist, particularly for
longer structures or structures subjected to seismic events. Expansion joints also need to be designed structurally for anticipated
vehicle loading, although in many cases this boils down to selecting an appropriate joint from a selection of standard owner-
agency or vendor designs based simply on the anticipated traffic. Many different joint types exist, satisfying a wide range of
design criteria. Since joints require maintenance, it is generally advisable to have significant input from the owner-agency
regarding choice of the best joint type, so that, many owner-agencies have very explicit rules on aforementioned topic.
Approach Slabs:
Serviceability, design, and detailing of approach slabs vary significantly between owner-agencies and designers, as does the
shapes of the structures (integral versus non-integral abutments, for example) and regions of the country. The length of approach
slab, the design methods used, the preferences for the detailing. How to deal with skews, how to connect to the abutment
backwall, and even whether or not to provide approach slabs are all questions to which the responses vary greatly from owner
agency to owner agency. Approach slab guidelines should be discussed with the appropriate owner-agency by designers.
Drainage:
Drainage issues fall into two categories: top surfaces drainage detailing of the abutment as well as the backfill material
behind the abutment. To keep water from amassing or ponding on the highest point of the abutment, presence of mind rules ought
to be observed to make slants that appropriate drainage channel. Owner-agencies frequently combine their chosen details for the
abutment or their chosen details for the backfill material with standard drainage details for the drainage of the backfill material
behind the abutment. These will consolidate the usage of free-draining granular top off materials, drainage strip materials set
against the abutment backwall, weep openings are furthermore given in the abutment, underdrain structures, etc.
According to FHWA (2012), the conventional abutments elements require some degree of design as follow:
Abutment Caps:
Designing the cap for lateral loading, the beams length runs between the foundation elements. This might the point where the
meet abutments on spread footings. The design should involve conditions for lateral moment and shear. The design may need to
treat torsion as well, especially if the abutment or its backwall are tall in particular, or if there is noticeable eccentricity between
the centerline of application of superstructure reactions (centerline of bearing) as well as the centerline of the foundations.
Abutment Backwalls:
Backwalls are generally constructed as cantilever retaining walls that transmit backfill material-induced lateral soil pressure.
Tractive forces must also be applied to the backwall's top as demanded by some agencies.
Abutment Wingwalls:
Almost all designers practice some discretion in the design of wingwalls due to the complex nature of their support and
connection to the rest of the abutment. Designers are encouraged to develop rational design procedures based on careful and
realistic consideration of the particular detailing of the wall. Some wingwalls, particularly longer walls, rest on pile or drilled shaft
foundations, some use spread footing foundations, some are cantilevered off the abutment cap. Some are square and some are
tapered. Most wingwalls will generally behave in a manner that can be adequately captured by a conservative, simplified
cantilever beam analyses. In other cases, an analysis based on plate theory may be more appropriate.
Earth Pressures
Active earth pressures (Kaγh) are considered to ensure that the abutment is stable.
At rest earth pressures (Koγh) are considered to ensure that the structural elements are adequate.
Passive earth pressures (Kpγh) are only considered for integral abutments or where shear keys are provided.
According to Childs (2015), tensions begin to develop on the back of the abutment wall at the beginning of development and
while the refill material is compacting. Therefore, the structural parts must be designed to withstand these forces. Any rotational
movements or deflection of the structure caused by the pressure at rest will reduce the pressure on the back of the wall. A state of
equilibrium is reached when the passive pressure drops to the value of the active earth pressure. As a result, the structure's stability
can be evaluated using active earth pressures. As the structure rests up against the soil, passive pressures are initiated, the
abutment foundation is designed not to slide, and for this to take place, active pressure will be more than the passive pressure.
Naturally, dynamics needed to initiate passive pressure to occur is greater than active pressure. Hence, abutment will be designed
to attain stability on its own without having earth in front of its footing. If shear keys are required to prevent sliding, they are used
with a factored value of passive pressure, under the base's rear half, the key should be. According to Childs (2015), integral
bridges are subjected to passive pressures on the back of the abutment wall when the deck expands.
Abutment Construction
The rules of backfilled cantilever retaining walls with spread footings or piled foundations is outlined in Departmental
Standard BD 30. The format of the abutment will have suggestions on the design which ought to be thought of.
Abutment Loading
Through the bearings, load from the deck is transferred to the abutment. Based on the deck analysis, the maximum vertical
bearing loads and the kind of restraint required to support the deck will determine the bearing type.
The sources of horizontal loads that come from the deck are wind load, temperature effects, creep movements, traction,
braking and skidding loads, collision loads when high level containment parapets are used, centrifugal loads when using BS 5400-
2 if the horizontal radius of curvature of the carriageway is less than 1000 metres, and centrifugal loads carriageway is less than
1500 metres when using EN 1991-2. The deck will be subjected to temperature-induced longitudinal loads depending on the
bearing used. Elastomeric bearings are effectively 'stuck' set up between the deck soffit and the abutment bearing plinth, with the
objective that the bearing requirements to bend when the deck expand and contracts. The longitudinal force of the deformation is
influenced by both the magnitude of the movement and the shear stiffness of the bearing. Sliding bearings, on the other hand,
produce a longitudinal load that is proportional to the dead (permanent) load reaction and the sliding surface friction coefficient.
Contingent upon the bearing's sort and stress, the coefficient of friction (μ) can go from 0.01 to 0.08 (BS 5400 Section 9:1, Tables
2 and 3).
Fig 2.15 Both Abutments with Elastomeric Bearings only (Childs, 2015)
Both abutments will be affected equally by the temperature effect's longitudinal load. The friction at the bearing under dead
(permanent actions) and superimposed dead loads (variable actions) equals the load transmitted when sliding bearings are used.
According to Childs (2015), when elastomeric bearings are utilized, the load carried is proportional to the force required to distort
the bearing by the length of time the deck expands or contracts.
Figure 2.17 Free Abutment with Sliding or Elastomeric Bearings (Childs, 2015)
Fig 2.18 Both Abutments with Elastomeric Bearings only (Childs, 2015)
Because the deck is very stiff in the axial direction, horizontal loads won't affect how long the deck is. As a result, it is
assumed that the fixed abutment alone carries longitudinal loads caused by skidding, traction, and braking. According to Childs
(2012), the loads caused by traction, braking, and skidding are shared between the two abutments when only elastomeric bearings
are utilized instead of a fixed one. Only the fixed and sliding-guided bearings will be used to transfer transverse deck loads to the
abutment. Although it is unlikely that these loads will affect a full-height abutment's stability, the bearing plinths must be analyzed
to withstand the loads. Small abutments like bank seats' stability may need to be checked for these loads. A surcharge load is a
representation of the live load at the back of the abutment (PD 6694-1:2011 clause 7.6) or BS 5400 Part 2:2006 clause 5.8.2.
When utilizing EN 1991-2:2003, traction, braking, and skidding loads at the rear of the abutment are not required to be taken into
consideration (clause 4.9.2). The curtain wall (likewise called up stand wall) does anyway expect to be intended for slowing down
forces. Because they are assumed to have sufficient mass to resist the collision loads for global purposes (BD 60/04 clause 2.2 or
NA to BS EN 1991-1-7:2006 clause NA.2.13), vehicle collisions on abutments do not normally require consideration.
Sliding
Overturning
Failure of the foundation soil
Slip failure of the surrounding soil.
A comprehensive Ground Investigation Report is required for the structural design of the bridge. Expected to give data with
respect to the events happening underneath the ground of the foundations, holes are bored. In addition, adequate sampling and
testing were required to obtain the foundation-level friction and cohesion values of the soil as well as the design parameters for the
allowable bearing pressures. Utilizing BD 30, the effects of sliding and overturning are determined using nominal load and
dynamic earth pressures. A factor of safety of 2.0 is used to guarantee the abutment's stability against sliding and overturning.
When adhering to EN 1997-1:2004, serviceability and ultimate limit states prerequisite for stability. A couple of load cases hope
to be considered to ensure all loading conditions are obliged. Abutment wall will be backfilled to the bearing shelf level when
constructed, this will give access for pavement construction, while compacting the backfill materials by the heavy compacting
equipment, a surcharge load is subjected on its wall. this surcharge load will cause critical load case, due to the fact that the
abutment active earth pressure initiated by the action of the machinery compacting the backfill material, has no counter load
which should have been provided by the pavement permanent load. The ground survey gives the allowable bearing pressure of the
soil, which help to evaluate the settlement limit of the structure, which is between 20 to 25mm. According to PD 6694-1:2011
Condition 5.2.2, the maximum SLS pressure under the foundation can be limited to a small portion (one third) of the ground
strength. It is advisable to determine the allowable pressure which will assist in depth and size of the footings. It is imperative to
assume loads and footing sizes, to know if there will be redesigning until a stable value for the allowable pressure, loads and
footing size is achieved (Childs, 2015). According to BS 8002, the following soil locations may experience a slip failure:
The wall is constructed on sloping ground that is close to limiting equilibrium in and of itself or,
The structure is underlain by strata within which high pore-water pressures may develop from natural or artificial sources, or,
The strata are founded on a relatively strong stratum underlain by weaker strata, or
The structure is underlain by a significant depth of clay whose undrained strength increases only gradually with depth.
If none of these considerations are present, then a slip failure analysis will not be necessary.
J. Piers (Bents)
The term "pier" or "bent" refers to interior span that are located away from the end upholds. To maintain consistency, the
term "pier" will be used throughout this module. It is expected to concern any structural member that carries the superstructure at
moderate intervals between end upholds. According to Patel's definition, piers are substructural components that are situated at the
ends of bridge spans at intermediate points between abutments. The usage of piers is to transmit the superstructure vertical
weights to the foundation and to go against all longitudinal and lateral forces on the bridge. Piers are typically built with
reinforced or masonry concrete. Contingent upon the kind, size, and aspects of the superstructure, they take on different structures
and add to the extension construction's stylish allure.
Fig 2.21 Different Types of Pier Caps for Multi-Column Piers (FHWA, 2012)
The following is a list of some of the most common combinations of these elements, but this list should not be considered
exhaustive or restrictive (FHWA, 2012):
Pile Bents:
A "pile bent" is a pier cap supported on multiple steel or precast concrete piles. In most cases, there is no clear difference
between the "columns" and "foundations" in a pile bent; the foundations are simply extensions of the piles that are supporting the
cap.
Fig 2.22 Different Types of Pier Caps for Single Column Piers (FHWA, 2012)
Straddle Bents:
Straddle bent is a pier with many columns, that the spacing is majorly wide which allowed for passage of a roadway directly
below the pier, such that the pier is “straddling” the roadway below. Due to the remarkably wide column spacing and the long
span of the pier cap, straddle bent pier caps are often special structures such as steel box beam caps or post tensioned concrete
caps.
Integral Piers:
The construction of pier caps that are integrated with the superstructure is sometimes desirable. Sometimes this gives
advantages in terms of structural efficiency, sometimes it gives aesthetic benefits, and sometimes it assists to reduce structure
depth and improve lateral clearances. Integral pier caps for steel girder bridges have been constructed using both steel (Wassef,
2004) and concrete (FHWA, 1997).
Steel Piers:
Even though most of the piers are made of reinforced, prestressed or post-tensioned concrete, there are still cases demanding
the use of steel for part or all of a pier. One common chance to make use of steel piers is for temporary bridge structures, such as
temporary construction sites bridges. In these instances, contractors often prefer using steel substructures =because they have light
weight and easy to manipulate, comparatively quick to install, and possibly reusable. Steel elements can also be used in straddle
bent caps and integral pier caps owing to its long span, Steel piers are perhaps used less frequently, but can render good solutions
in the right context. For instance, various steel girder bridges have been built with integral slant-leg steel piers or steel delta-piers
to provide solution to tough design problems in challenging sites. Furthermore, steel pipe piles filled with concrete can be used to
give many values for both systems when rightfully applied.
Dead Load: Dead load of superstructure and substructure above the base level of pier.
Live load: This consist of live load of traffic passing over the bridge
Buoyancy
Wind Load
Horizontal forces due to water current: Horizontal forces due to water current are considered on that part of substructure that
lies between the water level and the base of pier. The water current pressure is given as
P = KV 2 (2.10)
Where
P = intensity of pressure in kN/m2 due to water level and the base of the pier
K = a constant having different values for different shapes of piers
The values of this constant for different pier shapes are present in Fig 2.3
V is the current velocity in meters per second at the location where the pressure intensity is calculated. It is accepted that the
speed circulation in stream is to such an extent that V2 is greatest at the free surface of water, zero at the most profound scour
level and fluctuates in the middle between them. Additionally, it is assumed that the flow's maximum velocity is √2 times the
current's velocity.
{See Fig 2.3 Value of constant k for pressure Intensity due to water current (Patel, 2008) page 1 Tables for Research work}.
Hence, the pressure along the pivot of the pier and transverse to it is respectively given by,
M. Bridge Bearings
Bearings connect the superstructure with the substructure allowing for movements, yet transfer forces
N. Software Availability
There are many different kinds of software that can design some or all of a substructure. The design of a bridge substructure
can be completed in its entirety with the help of some commercial software packages. These kinds of programs can fabricate the
base shapes, assemble the superstructure calculation, ascertain loads on the base, perform internal load stresses of the pier caps,
columns, and foundations, and afterward sizes of various components, as well carryout detailed design analysis. Nevertheless,
mostly, these programs have some limitations on the complexity of designs they can handle, such as complex loading,
superstructure types, and complex geometry etc. Designers are encouraged to fully comprehend these "all in one" substructure
design programs' capabilities and, more importantly, their limitations, according to FHWA (2012). A combination of general FEM
analysis models and specific design software can also be used to design substructures. Regularly, designers will do the load
calculations manually, then input these load values into frame model of the abutment or pier (or into a more complicated model if
necessary), run the model to decide the internal load stresses, distribute loads and do detailed design checks making use of
commercial or home-made software, coding etc. or blending of more than one.
Thermal and wind actions along with creep & shrinkage of PC girders are not considered for load combinations. Thus,
effects of displacement and deformations are assumed to be negligible.
Permanent Actions
Variable Actions
The width remaining area of the carriage way = 7.2 2 3 1.2 m (BS EN 1991-2-2003).
{See Table 3.1 Load Model 1: Characteristic Values (BS EN 1991-2-2003) page 1 Tables for Research work}.
Fig 3.3 Application of Load Model 1, on a Deck with Two Notional Lanes
Span 23.2
2.11 > 2. Hence, it is adequate.
width 11
Longitudinal beams are interconnected by symmetrically spaced cross girders of adequate stiffness, according to Courbon’s
Method, getting higher results on most end girders. So, girder “A” was selected for critical loading condition (Fig 3.4).
P Pe
Ri = ± (3.1)
n I
2
x
But, I
x
1 e𝑥
Then, R i = P ( ± ) (3.2)
n ∑ 𝑥2
where; ∑ X 2 = (22 + 42 ) × 2 = 40
and, n = 5
X is positive for the considered girder, with the direction from center line. Assume unit load,
P = 1, by substituting above values with different x values for Girder “A” (Fig 3.4).
As indicated by the code, pair frameworks (TS) on contiguous notional paths are considered, they might be brought nearer,
with a distance between wheel axles not underneath 0.5m (BS EN 1991-2:2003 Condition 4.3.2 (5)). Each tandem system is
replaced in each lane by a one-axle concentrated load of equal weight to the combined weight of the two axles if the span is
greater than 10 meters (BS EN 1991-2:2003 Clause 4.3.2(6)).
The following loading arrangement shall be considered for the Courbon's Method(Fig 3.5).
Other actions on selected beam with self weight of the structures are going to uniformly distributedon the beam which is
proprotion to effective depth. (Fig 4.1).
B. Structural Components
The components to be designed include the following; (1) Abutment, ( 2) Pier.
Legend: RL = Reduced level; HFL = Hydraulic flow level; SFL = Structural finished level.
Calculation of abutment height is based on the provided reduce levels with manipulated structural finish level based on the
girder and slab finish details.
Assume pore water presure dissipate along the provided weep holes.
Assume abutment is RCC foundation and place at the rock level with scouring being considered up to the bed.
Where;
(1 − Sinφ)
Lateral pressure coefficient K a = (3.4)
(1 + Sinφ)
(1 − Sin30)
Ka = = 0.33 (from Equation 3.4)
(1 + Sin30)
Surcharge, due to non availability of data were considered 20 kN/m2 (Cl.5.7.1 CIRA).
20 × 3 × 2
So, Surcharge acting on wall = = 10.3 kN/m2 (PD6694 − 1: 2011).
11.6
2
Line load from surcharge actingon Wall, HS = 2 × 330 × 0.33 × = 37.6 kN/m
11.6
Pore water pressure on wall (wasnot required due provision of weep holes).
The following preliminary section parameters were considered for the abutment, (Fig 3.7).
Abutment weight, W1 = (1.25 × 5.1 + 1.2 × 4.1 + 4.1 × 0.5 × 0.3 + 1.35 × 0.3) × 25 = 307.875 kN
{See Fig 3.2 Center of Gravity, Area of the Abutment, page 2 in Figures for Research work}.
34 .3861
COG of abutment = = 2.792 m from Toe.(Table 3.3)
12 .315
Earth fill on abutment base = 2.4 × 5.45 × 19 = 248.52 kN/m
So, with the wall and load configurations, the folllowing dimensional arrangementswere considered for the stability
evaluation (Fig3.8).
Fig 3.8 Active Forces on the Earth Retaining Wall side of the Abutment.
{See Fig 3.4 Restoring Moment and Stabilizing Forces on the Abutment wall around the Toe of Span 23.2m, page 2 in Fig for
Research work}. Fig 3.4 shows the analysis of figures 3.7 and 3.8.
{See Fig 3.5 Overturning Moment and Destabilizing Forces on the Abutment wall around the Toe of Span 23.2m, page 3 in
figures for Research work}. Fig 3.5, was gotten from the result analysis of sections 3.5, 3.5.1 and figure 3.8.
{See Fig 3.6 Axial Forces on the Abutment of Span 23.2m, page 3 in figures for Research work}. For axal forces on the
abutment wall, lever arm is measured from wall center to load center, horizontally (lateral force on wall).
{See Fig 3.7 Shear Force on Abutment of Span 23.2m, page 3 in figures for Research work}. Shear forces on the abutment
wall,lever arm is measured from base top level to load center vertically.
Considering traction and breaking forces on piers,water current and log impacts on pier and wind force on the bridge and
assumming pier foundation is RCC pad placed at the rock level with scouring considered up to the rock.
Therefore, use Q1k = 422.64 kN and distribute along the pier beam.
Collision force on the pier = 1000 kN along the bridge or 500 kN perpendicular to the bridge(BS EN 1991-2-2003, Cl.
4.7.2.1).For the calculation, Load Case 2 full load condition was considered.
Assume wind speed is Vb,0 = 22 ms −1 for Zone 3 (National Annex (Cl: 4.3))
(EN 1991-1-4:2005+A1:2010)
1
qb = ρ × Vb2 (EN 1991-1-4:2005+A1:2010, Cl: 4.5.1) (3.10)
2
Where K t = 1
{See Fig 3.8 Bridge Traffic Load, page 3 in figures for Research work}.
`
Fig 3.12 Wind Force Acting on the Bridge Deck (All dimensions in mm)
d2 = 2.5 m
d3 = 3.9 m
d2 = without traffic
d3 = with traffic
b 11.6
Without traffic, = = 4.6 SO, Cf = 1.15
dtot 2.5
b 11.6
With traffic, = = 3.0 SO, Cf = 1.5
dtot 3.9
Consider Cs Cd factor =1 (EN 1991-1-4:2005+A1:2010, Cl:6.2.1a)
So, wind force effective on deck to pier without traffic condition = 23.2 × 1.09953 × 2.5
= 63.77 kN(Table 3.8), and wind force effective on deck to pier with traffic condition
= 23.2x1.09953 = 99.49 kN (Fig 3.8).
P = 52kV 2 (3.15)
{See Fig 3.9 Restoring Moment and Stabilizing Forces on the Abutment Wall around the Toe of Span 25m, page 4 in Figures
for Research work}. Fig 3.9 shows the analysis of figures 3.7 and 3.8.
{See Fig 3.10 Overturning Moment and Destabilizing Forces on the Abutment Wall around the Toe of Span 25m, page 4 in
Figures for Research work}. Fig 3.10, was gotten from the result analysis of sections 3.5, 3.5.1 and figure 3.8.
{See Fig 3.11 Axial Forces on Abutment Walls of Span 25m, page 4 in Figures for Research work}. For axal forces on the
abutment wall, lever arm is measured from wall center to load center, horizontally (lateral force on wall).
{See Fig 3.12 Shear Forces on Abutment of Span 25m, page 5 in Figures for Research work}. Shear forces on the abutment
wall,lever arm is measured from base top level to load center vertically.
{See Fig 3.14 Overturning Moment and Destabilizing Forces on the Abutment Wall around the Toe of Span 30m, page 5 in
figures for Research work}. Fig 3.14, was gotten from the result analysis of sections 3.5, 3.5.1 and figure 3.8.
{See Fig 3.15 Axial Forces on Abutment Walls of Span 30m, page 6 in Tables for Research work}. For axal forces on the
abutment wall, lever arm is measured from wall center to load center, horizontally (lateral force on wall).
{See Fig 3.16 Shear Forces on Abutment of Span 30m, page 6 in Tables for Research work}. Shear forces on the abutment
wall, lever arm is measured from base top level to load center vertically.
{See Fig 3.17 Restoring Moment and Stabilizing Forces on the Abutment Wall around the Toe of Span 35m, page 6 in
figures for Research work}. Fig 3.17 shows the analysis of figures 3.7 and 3.8.
{See Fig 3.18 Overturning Moment and Destabilizing Forces on the Abutment Wall around the Toe of Span 35m, page 7 in
figures for Research work}. Fig 3.18, was gotten from the result analysis of sections 3.5, 3.5.1 and figure 3.8.
{See Fig 3.19 Axial Forces on Abutment Walls of Span 35m, page 7 in figures for Research work}. For axal forces on the
abutment wall, lever arm is measured from wall center to load center, horizontally (lateral force on wall).
{See Fig 3.20 Shear Forces on Abutment of Span 35m, page 7 in figures for Research work}. Shear forces on the abutment
wall,lever arm is measured from base top level to load center vertically.
{See Fig 3.21 Restoring Moment and Stabilizing Forces on the Abutment Wall around the Toe of Span 40m, page 8 in Fig for
Research work}. Fig 3.20 shows the analysis of figures 3.7 and 3.8.
{See Fig 3.22 Overturning Moment and Destabilizing Forces on the Abutment Wall around the Toe of Span 40m, page 8 in
Figures for Research work}. Fig 3.18, was gotten from the result analysis of sections 3.5, 3.5.1 and figure 3.8.
{See Fig 3.23 Axial Forces on Abutment Walls of Span 40m, page 8 in Figures for Research work}. For axal forces on the
abutment wall, lever arm is measured from wall center to load center, horizontally (lateral force on wall).
{See Fig 3.24 Shear Forces on Abutment of Span 40m, page 9 in Figures for Research work}. Shear forces on the abutment
wall,lever arm is measured from base top level to load center vertically.
Package SUBBridge
This package shall contain the main classes which include SUBMain, SUBDetails, SUBTables and SUBGraphs.
Fig 3.22 The Main Application Window for the Developed Computer Program
{See Fig 4.1 Load Distribution by Bridge Components, page 9 in Tables for Research work}.
23.22
Middle moment (uniformly distributed load)UDL dead = 25 × = 1682 kNm
8
23.22
Middle moment UDL traffic = 11.895 × = 800.3 kNm
8
23.22
Middle moment pedestrian = 3.74 × = 251.19 kNm
8
23.2
Mddle moment from TS = 340 × = 1972 kNm
4
Figure 4.2 shows the moment envelope diagram of bridge deck span of
ULS1: 1.35Gkj,sup + 1.0 Gkj,inf + 1.35 (TS + UDL + 0.4 × qfk ) (4.1)
So,maximum moment at middle for first combination of ultimate limit state (ULS)
1.351682 264.6 1.35800.3 1972 0.4 251.19 6506.16kNm (from Equation 4.1)
So, maximum shear force at beam end for first combination of ULS
1.35290 54 1.35170 138 0.4 43.31 903.563 kN (from Equation 4.1)
Fig 4.3 Moment at Middle of the Beam for First Combination Diagram of Span 23.2m
Lever arm were considered from the center of the base. Fig 4.2, shows the stability check for the abutment.
{See Fig 4.2 Stability Check of Span 23.2m, page 9 in Tables for Research work}.
Moment around the base center = 764.1537 kNm (Fig 4.3 and 4.4).
N 6M
M = ± (4.2)
BD BD2
922.698 764.1537
Mmax = +6× = 357.1966 < Ground bearing capacity of 670 kN/m2
(5.1 × 1) (5. 12 )
922.698 764.1537
Mmin = −6× = 4.6458 < Ground bearing capacity of 670 kN/m2
(5.1 × 1) (5. 12 )
{See Fig 4.3 Calculations of Moment for the Determination of Bearing Failure of Span 23.2m, page 9 in Figures for Research
work}.
{See Fig 4.4 Calculations of Moments for the Determination of Bearing Failure of Span 23.2m, page 10 in Figures for
Research work}.
The reinforcement design for the abutment, as per the stability calculations following, the EC0 and EC4 load combination,
are given by:
𝑄𝑘 + 1.5𝐺𝑘 + 1.5𝐺𝑘𝑖 𝜓𝑖
Where;
{See Fig 4.5 Summary of Stability Check of Span 23.2m, page 10 in Fig for Research work}.
Fig 4.6 shows, thesummary of the wall design moment,axial force and shear force at base top level (Fig 3.6 and 3.7).
{See Fig 4.6 The Summary of all the Forces acting on the Abutment of Span 23.2m, page 10 in Tables for Research work}.
So, axial force capacity is higher than the existing axial force. So, it shall be considered as a cantilever wall.
M ed
k= 2 (4.4)
bd f ck
M ed
As (4.5)
0.87f y z
6
935.90 10 2
As 1927.43mm (from Equation 4.5)
0.87 500 1116.25
bd
Asmin = 0.13 × (4.6)
100
Where; Α
smin = area of minimum reinforcement.
366693 2
Design Shear stress on wall = 0.31N/mm
1000 1175
1
Shear capacity of concrete, VRdc = 0.12k 100 ρf ck 3 bd (4.7)
VRdc = 372.38 kN > 366.69kN (from Equation 4.7)
Therefore, shear capacity is adequate as per the design calculation on bearing pressure calculation.
Base moment at bottom RHS = (362.4 + 273) × 0.5 × 1. 22 × 0.5 = 228.744 kNm/m
Base moment at bottom LHS = (4.6 + 168) × 0.5 × 2. 42 × 0.5 = 248.544 kNm/m
6
248 .544 10
k 2
0.0072 , (from Equation 4.4)
1000 1175 25
6
248 .544 10 2
As 522 .869 mm (from Equation 4.5)
0.87 500 1093
Fig 4.5, shows the shear force diagram for the bridge span of 25 m.
252
Middle moment UDL dead = 25 × = 1953.125 kNm
8
252
Middle moment UDL traffic = 11.895 × = 929.297 kNm
8
252
Middle moment pedestrian = 3.74 × = 292.188 kNm
8
25
Mddle moment from TS = 340 × = 2125 kNm
4
Thus, SLS resultant middle moment = 264.6 + 2125 + 292.188 + 929.297 + 1953.125 = 5564.21kN
The Fig4.6 shows the momoent envelope diagram of bridge deck span of 25 m
The ULS diagram for bridge span of 25m was shown in Fig 4.7.
940.981 738.9232
Mmax = +6× = 354.9613 < Ground bearing capacity of 670 kN/m2
(5.1 × 1) (5. 12 )
(from Equation 4.2)
940.981 738.9232
Mmin = (5.1×1)
−6× (5.12 )
= 14.0509 < Ground bearing capacity of 670 kN/m2 (Fig 4.5)
(from Equation 4.2)
{See Fig 4.7 Calculations of Moments for the Determination of Bearing Failure of Span 25m, page 10 in Figures for
Research work}.
{See Fig 4.8 Calculation of Moment for the Determination of Bearing Failure of Span 25m, page 11 in Figures for Research
work}.
{See Fig 4.9 Summary of Stability Check of Span 25m, page 11 in Figures for Research work}.
Fig 4.10 shows, thesummary of the wall design moment, axial force and shear force at base top level (Fig 3.6 and 3.7 in
Chapter Three). {See Fig 4.10 The Summary of all the Forces Acting on the Abutment of Span 25m, page 11 in Figures for
Research work}.
6
939.76 10
k 2
0.0272 , (from Equation 4.4)
1000 1175 25
6
939.76 10
As
2
1935.38mm (from Equation 4.5)
0.87 500 1116.25
366693 2
Design shear stress on wall = 0.31N/mm
1000 1175
Fig 4.8, shows the shear force diagram for the bridge span of 30 m.
302
Middle moment UDL traffic = 11.895 × = 1338.188 kNm
8
302
Middle moment pedestrian = 3.74 × = 420.75 kNm
8
30
Mddle moment from TS = 340 × = 2550 kNm
4
Thus, SLS resultant middle moment = 264.6 + 2550 + 420.75 + 1338.188 + 2812.5 = 7386.038 kNm
The Fig 4.9 shows the momoent envelop diagram of bridge deck span of 30 m.
The ULS diagram for bridge span of 30m was shown in Fig 4.10.
Moment around the base center = 691.5412 kNm, (Fig 4.11 and 4.12).
991.766 691.5412
Mmax = (5.1×1)
+6× (5.12 )
= 368.3937 < Ground bearing capacity of 670 kN/m2 (from Equation 4.2)
991.766 691.5412
Mmin = (5.1×1)
−6× (5.12 )
= 189.4639 < Ground bearing capacity of 670 kN/m2 (from Equation 4.2)
Therefore, selected abutment parameters are adequate in terms of structural stability (Fig 4.19)
{See Fig 4.12 Calculation of Moment for the Determination of Bearing Failure of Span 30m, page 12 in Figures for Research
work}.
{See Fig 4.13 Summary of Stability Check of Span 30m, page 12 in Figures for Research work}.
Fig 4.14 shows, thesummary of the wall design moment, axial force and shear force at base top level (Figures 3.6 and 3.7in
Chapter Three).
{See Fig 4.14 The Summary of all the Forces Acting on the Abutment of Span 30m, page 12 in Figures for Research work}.
6
950.46 10
k 2
0.0275 , (from Equation 4.4)
1000 1175 25
6
950.46 10 2
As 1957.46mm (from Equation 4.5)
0.87 500 1116.25
366693 2
Design shear stress on wall = 0.31N/mm
1000 1175
Fig 4.11, shows the shear force diagram for the bridge span of 35 m.
352
Middle moment UDL dead = 25 × = 3828.125 kNm
8
352
Middle moment UDL traffic = 11.895 × = 1621.142 kNm
8
352
Middle moment pedestrian = 3.74 × = 572.688 kNm
8
35
Mddle moment from TS = 340 × = 2975 kNm
4
Thus, SLS resultant middle moment = 264.6 + 2975 + 572.688 + 1621.142 + 3828.125 = 9261.555 kNm
The Fig 4.12 shows the momoent envelop diagram of bridge deck span of 35 m
The ULS diagram for bridge span of 35m was shown in Figu 4.13.
Moment around the base center = 666.4155 kNm,( Fig 4.15 and 4.16).
1042.552 666.4155
Mmax = +6× = 358.1511 < Ground bearing capacity of 670 kN/m2
(5.1 × 1) (5. 12 )
(from Equation 4.2)
1042.552 666.4155
Mmin = −6× = 50.6929 < Ground bearing capacity of 670 kN/m2
(5.1 × 1) (5. 12 )
(from Equation 4.2)
Therefore, selected abutment parameters are adequate in terms of structural stability(Fig 4.17)
{See Fig 4.15 Calculation of Moment for the Determination of Bearing Failure of Span 35m, page 12 in Figures for Research
work}.
{See Fig 4.16 Calculation of Moment for the Determination of Bearing Failure of Span 35m, page 13 in Figures for Research
work}.
{See Fig 4.17 Summary of Stability Check of Span 35m, page 13 in Figures for Research work}.
Fig 4.18 shows, thesummary of the wall design moment, axial force and shear force at base top level (Figures 3.6 and 3.7in
Chapter Three).
{See Fig 4.18 The Summary of All the Forces Acting on the Abutment of Span 35m, page 13 in Figures for Research work}.
6
961.21 10
k 2
0.0278 , (from Equation 4.4)
1000 1175 25
6
961.21 10 2
As 1979.55mm (from Equation 4.5)
0.87 500 1116.25
1175
Α smin 0.13 1000 = 1527.5mm2 (from Equation 4.6)
100
366693 2
Design shear stress on wall = 0.31N/mm
1000 1175
Fig 4.14, shows the shear force diagram for the bridge span of 40 m.
402
Middle moment UDL dead = 25 × = 5000 kNm
8
402
Middle moment UDL traffic = 11.895 × = 2379 kNm
8
402
Middle moment pedestrian = 3.74 × = 748 kNm
8
40
Mddle moment from TS = 340 × = 3400 kNm
4
Thus, SLS resultant middle moment = 264.6 + 3400 + 748 + 2379 + 5000 = 11791.6 kNm
The Fig 4.15 shows the momoent envelop diagram of bridge deck span of 40 m
The ULS diagram for bridge span of 40m was shown in Fig 4.16.
Moment around the base center = 655.1684 kNm,( Fig 4.19 and 4.20).
1093.337 655.1684
Mmax = (5.1×1)
+6× (5.12 )
= 365.5144 < Ground bearing capacity of 670 kN/m2 (from Equation 4.2)
1093.337 655.1684
Mmin = (5.1×1)
−6× (5.12 )
= 63.2452 < Ground bearing capacity of 670 kN/m2 (from Equation 4.2)
Therefore, selected abutment parameters are adequate in terms of structural stability (Fig 4.21)
{See Fig 4.19 Calculation of Moment for the Determination of Bearing Failure of Span 40m, page 13 in Figures for Research
work}.
{See Fig 4.20 Calculation of Moment for the Determination of Bearing Failure of Span 40m, page 14 in Figures for Research
work}.
{See Fig 4.21 Summary of Stability Check of Span 40m, page 14 in Figures for Research work}.
Fig 4.22 shows, thesummary of the wall design moment, axial force and shear force at base top level (Fig 3.6 and 3.7in
Chapter Three). {See Fig 4.22 The Summary of all the Forces Acting on the Abutment of Span 40m, page 14 in Figures for
Research work}.
AssumeAbutmentconcretegradeis 25 N/mm2
Med = 971.93 kNm (Fig 4.22).
6
971 .93 10
k 2
0.02816 , (from Equation 4.4)
1000 1175 25
6
971.93 10
As 2001 .63 mm
2
(from Equation 4.5)
0.87 500 1116.25
366693
Design shear stress on wall = 0.312 N/mm 2
1000 1175
P = 52kV 2 (4.8)
P = 52 × 1.5 × 1.1 × 1.1 = 94.4 kg/m2 = 0.94 kN/m2 (from Eqution 4.8)
Water current force shall be applied over the height of pier and debris and log impact load to be applied at the, HFL level
normal to the river flow direction.
6
1202 10
k 2
0.05619 , (from Equation 4.4)
1000 925 25
6
1202 10 2
As 3144 .49 mm (from Equation 4.5)
0.87 500 879
100
1202.5 mm2 < 3144.49 mm2
1197000 2
Design shear stress on beam = 1.29 N/mm
1000 925
Shear Links
f
VRmax 0.124 bd 1 ck f ck = 2580.75 kN > Ved =1197 kN (4.10)
250
Asw Ved
= = 1.33 ( 4.11)
s (0.78 dfyk cot θ)
A sw 78
=2× = 1.56 (from eqution 4.11)
s 100
Hence, adequate.
B. Analysis of Results
Figure 4.19 shows the bending of bridge span of 23.2m. The maximum moment is 4970.09 kNm. The diagram also showed
the diaphragm loads, tandem system loads, uniformly distributed load and serviceability limit state at varying span distances of the
bridge deck.
The maximum moment at middle of the beam for first combination of ULS is 6506.16 kNm as shown in Figure 4.20.
Fig 4.20 Moment at Middle of the Beam for First Combination Diagram of Span 23.2m
Abutment Design of Span 23.2m
The summary of all the forces acting on the abutment for bridge span of 23.2m, which include the design moment, design
shear force and axial force having 932.90 kNm, 366.69 kN and 682.48 kN respectively, as shown in Table 4.23.
{See Fig 4.23 The Summary of all the Forces Acting on the Abutment of Span 23.2m, page 14 in Figures for Research work}.
Figure 4.22 shows the bending of bridge span of 25m. The maximum moment is 5564.21kNm. The diagram also show the
diaphragm loads, tandem system loads, uniformly distributed load and serviceability limit state at varying span distances of the
bridge deck.
The maximum moment at middle of the beam for first combination of ULS is 7274.84 kNm as shown in Figure 4.23.
Fig 4.23 Moment at Middle of the Beam for First Combination Diagram of Span 25m
Abutment Design of Span 25m
The summary of all the forces acting on the abutment for bridge span of 25m, which include the design moment, design
shear force and axial force having 939.76 kNm, 366.69 kN and 708.21kN respectively, as shown in Table 4.24.
{See Fig 4.24 The Summary of all the Forces Acting on the Abutment of Span 25m, page 14 in Figures for Research work}.
The maximum moment is 7386.04 kNm, as shown in Figure 4.25. The bridge span of 30m in consideration, also show the
diaphragm loads, tandem system loads, uniformly distributed load and serviceability limit state at varying span distances of the
bridge deck.
The maximum moment at middle of the beam for first combination of ULS is 9630.34 kNm as shown in Figure 4.26.
Fig 4.26 Moment at Middle of the Beam for First Combination Diagram of Span 30m
{See Fig 4.25 The Summary of all the Forces Acting on the Abutment of Span 30m, page 14 in Figures for Research work}.
The bending moment for bridge span of 35m, has the maximum moment of9261.56 kNm. The diagram also show the
diaphragm loads, tandem system loads, uniformly distributed load and serviceability limit state at varying span distances of the
bridge deck.
Fig 4.29 Moment at Middle of the Beam for First Combination Diagram of Span 35m
{See Fig 4.26 The Summary of all the Forces Acting on the Abutment of Span 35m, page 15 in Figures for Research work}.
Figure 4.31 shows the bending moment of a bridge span of 40m. The maximum moment is 11791.6 kNm. The diagram also
show the diaphragm loads, tandem system loads, uniformly distributed load and serviceability limit state at varying span distances
of the bridge deck.
Fig 4.32 Moment at Middle of the Beam for First Combination Diagram of Span 40m
{See Fig 4.27 The Summary of all the Forces Acting on the Abutment of Span 40m, page 15 in Figures for Research work}.
{See Fig 4.29 Shear Force at Beam end for First Combination of ULS, page 15 in Figures for Research work}. The shear
forces at the beam end for the first combination of ultimate limit state at various spans 23.2m, 25m, 30m, 35m, and40m,from
manual calculation and the developed computer program, are given in Table 4.29. The percentage differences between values
obtained for the various spans are also less than 1%.
The maximum moments on the abutment at various spans 23.2m, 25m, 30m, 35m, and40m, from manual calculation and the
developed computer program, are given in Table 4.30. The percentage differences between values obtained for the various spans
are less than 1%..
{See Fig 4.31 Axial Forced, Ned (kN), page 16 in Figures for Research work}.
For spans 23.2m, 25m, 30m, 35m, and40m, the axial forces, Ned, from manual calculation and the developed computer
program, are given in Table 4.31. The percentage differences between 23.2m and 25m are 0.00880% and 0.00423% respectively.
These results show that, the manual calcualtions and those from the developed program are close.
{See Fig 4.32 Area of Steel Required (mm2), page 16 in Figures for Research work}.
For spans 23.2m, 25m, 30m,35m, and 40 m, the area of steel required from manual calculation and the developed computer
program, are given in Fig 4.32. The percentage differences for 23.2m and 25m spans are 0.1947% and 0.1113% respectively.
These results show that the manual calcualtions and the ones from the developed program are close.
A. Conclusion
The study's objectives were to create a java-based computer program for the quick and accurate design and analysis of bridge
substructure components on shallow foundations and to manually analyze and design bridge substructures. This research work did
analysis and design using Eurocodes 2, on bridge abutment, pier and pier cap beam. Design moments, design shear forces, axial
forces, the area of the steel, and the number of steel reinforcement bars are among the outcomes that can be derived from both
manual and computer methods. The results of the manual and computer program were compared for similarities, and the he found
out that the percentage difference of moments, shear forces, axial forces and the area of steel were negligible. All designs were
carried out in accordance with provisions and other standard literature, as well as the Eurocodes BS EN 1992-1-1, BS EN 1991-1-
4, and BS EN 1991-2.
B. Contribution to Knowledge
For the purpose of analyzing and designing bridge substructures in accordance with Eurocodes and other relevant standards,
this study performed both manual design and the development of a Java-based computer program. The developed program would
be a valuable tool for practicing structural engineers as well as a useful interactive program for teaching structural engineering
students.
C. Recommendations
The study designed and analyzed bridge substructures in Eurocode, using both a manual approach and a Java-based
computer program. Reinforced concrete was used to build the bridges. On a profound establishment, future specialists can plan
projections and docks physically or utilizing a PC. However, Eurocodes were used to write the majority of the computer programs
developed in this study. The program can be extended to include the design of bridge substructures using other internationally
recognized bridge design codes in subsequent projects. Last but not least, the developed software is able to connect to common
CAD applications like AutoCAD to generate working drawings and details for the bridge substructures.
[1]. Al-Sarraf, et al., (2005); Analysis of Composite Bridge Superstructures Using Modified GRillage Method.
[2]. Anwar, N. (2015); Analysis and Modeling of Bridge Substructure; Asian Institute of Technology (AIT) Consulting
[3]. Arockiasamy, M., Narongrit, B., Sivakumar, M., “State-of-the-Art of Integral Abutment Bridges: Design and Practice,”
American Society of Civil Engineers (ASCE) Journal of Bridge Engineering, Vol. 9, No. 5, September/October 2004, pp.
497-506.
[4]. Arora, K. R (2003); “Soil Mechanics and Foundation Engineering (Sixth Edition)”; Standard Publishers Distributors, New
Delhi.
[5]. Barker, R.M., Duncan, J.M., Rojiani, K.B., Ooi, P.S.K., Tan, C.K., and Kim, S.G., Manuals for the Design of Bridge
Foundations, NCHRP Report 343, Transportation Research Board, December 1991.
[6]. Bouassida, Y., et al (2010), Bridge Design to Eurocodes, worked examples; Worked examples presented at the Workshop
“Bridge Design to Euro codes”, Vienna, CEN 2002. Euro code: Basis of structural design. EN 1990: 2002. European
Committee for Standardization (CEN): Brussels.
[7]. Briaud, J.-L., et al, Pier and Contraction Scour in Cohesive Soils, NCHRP Report 516, Transportation Research Board, 2004.
[8]. CEN 2004. Euro code 7: Geotechnical design - Part 1: General rules. EN 1997-1:2004 (E), November 2004, European
Committee for Standardization: Brussels.
[9]. CEN 2005. Euro code 8: Design of structures for earthquake resistance - Part 5: Foundations, retaining structures and
geotechnical aspects. EN1998-5:2004 (E), May 2005, European Committee for Standardization: Brussels.
[10]. CEN 2007. Euro code 7: Geotechnical design - Part 2: Ground investigation and testing. EN1997-2:2007 (E), March 2007,
European Committee for Standardization: Brussels.
[11]. Davaine, L. 2010a. Global analysis of a steel-concrete composite two-girder bridge according to Euro code 4, Note for
Workshop “Bridge design to Euro codes” to be held in Vienna, 4-6 October 2010, June 2010, 39 pages.
[12]. Davaine, L. 2010b. Excel sheet with a synthesis of the reactions and supports, e-mail to TC 250/HGB: June 09, 2010 6:24
pm.
[13]. Davaine, L. 2010c. Supplement for support reactions, Private written communication, Workshop “Bridge design to
Eurocodes”, Vienna, 4-6 October 2010, June 2010, 16 August 2010, 2 pages.
[14]. De Beer, E., And Marten (1957); “Method of Computation on Upper limit for the Influences of Heterogeneity of Sand
Layers in the Settlement of Bridges”; Proc. 4 th Int. Conf. On SMFE, London, Vol.1.
[15]. Federal Highway Administration (FHWA), Seismic Design of Bridges, Design Examples No. 1 through 7, Publication Nos.
FHWA-SA-97-006 through FHWA-SA-97-012, October 1997.
[16]. Federal Highway Administration (FHWA), Steel bridge Design Handbook, Substructure Design Publication No. FHWA-IF-
12-052 - Vol. 16 2012
[17]. Gifford, D.G., Wheeler, J.R., Kraemer, S.R., and McKown, A.F. (1980), Spread Footings for Highway Bridges, Report No.
FHWA/RD-86/198, 1986.
[18]. Hannigan, P.J., Goble, G.G., Thendean, G., Likins, G.E., and Raushe, F. (1997), Design and Construction of Driven Pile
Foundations, Report Nos. FHWA-HI-97-013 and -014, 1997.
[19]. Kesarwani, S., et al., (2018); Analysis of T-Beam Along with Deck Slab by Courbon’s Method.
[20]. Kolias, B. 2010a. Squat piers with seismic isolation. Summary of seismic design results. Note for Workshop “Bridge design
to Euro codes” to be held in Vienna, 4-6 October 2010, June 2010, 25pages.
[21]. Kolias, B. 2010b. Flexible piers with limited ductile behaviour. Summary of seismic design results.
[22]. Mahadevan, A.K., (2005); To Design a Code for the Building of Skew Bridges.
[23]. Malakatas, N. 2010. Example of application for Wind actions on bridge deck and piers, Report for Workshop “Bridge design
to Eurocodes”, Vienna, 4-6 October 2010, January 2011, 20 pages.
[24]. Manohar, et al., (2018); Finite Element Analysis of Slabs, Cross girders and Main girders in RC T-Beam Deck Slab Bridge.
[25]. MELT-Ministère de l'Equipement, du logement et des transports 1993. Règles Techniques deConception et de Calcul des
Fondations des Ouvrages de Génie Civil (in French: Technical Rulesfor the Design of Foundations of Civil Engineering
Structures). Cahier des clauses techniques générales applicables aux marchés publics de travaux, FASCICULE N°62 -Titre
V, TextesOfficiels N° 93-3 T.O., 182 pages.
[26]. Mitchell, D., Collins, M., Bhide, S., and Rabbat, B., “AASHTO LRFD Strut-and-Tie Model Design Examples, Portland
Cement Association, 2004.
[27]. Note for Workshop “Bridge design to Euro codes”, Vienna, 4-6 October 2010, July 2010, 14pages.
[28]. O’Neil, M.W., and Reece, L.C., Drilled Shafts: Construction Proceedures and Design Methods, Report FHWA-IF-99-025,
August, 1999.
[29]. Patel, A.M. Analysis and design of bridge substructures using VB.NET, Department of Civil Engineering Indian Institute of
Technology Roorkee, Roorkee-247 667 (India) June, 2008.
[30]. Prakash, S. (1979); “Analysis and Design of Foundations and Retaining Structures”; Sarita Prakashan, New Delhi.
[31]. Prayerful, N.K., and Hanumant, B., (2015); Comparative Analysis of T-Beam Bridge by Rotational Method and Staad Pro.
Ass. Prof, Civil engineering, Jay Want College of Engineering Sangli, India, B.E. Student. Civil Engineering, Jay Want
College of Engineering Sangli, India.