AASHTO GSBTW-1995 Guide Design Specifications For Bridge Temporary Works - Revision 1
AASHTO GSBTW-1995 Guide Design Specifications For Bridge Temporary Works - Revision 1
Executive Cornmitttee
1994-1995
Voting Members
OfJers:
Regional Representatives:
Non-Voting Members
11
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
A A S H T Q T I T L E GDSBTW 95 H Ob39804 0031bbb 381 H
iii
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
A A S H T O T I T L E GDSBTW 95 Ob39804 0033667 218
PREFACE
Objective
In 1991, a study was initiated by the Federal Highway Administration (FHWA) to identify the current state of
the practice in the United Stat& and abroad for designing, constructing, and inspecting the falsework and formwork
used to construct highway bridge structures. The findings of this study were published in MA-RD-91-062,
Synthesis of Falsework, Formwork, and Sc@olding for Highway Bridge Structures.“)
As part of the aforementioned study, a questionnaire was developed and sent to the fifty U.S. highway
departments. Information relating to design and administrative policies for falsework and formwork construction,
and the bridge construction activity for each State was requested. Virtually every State was found to have general
requirements and guideiines for the consmaion and removal of falseworkand fomwork. However, only about half
of the States specified design criteria. Similarly, only 22 States had accompanying design or construction manuais
that included specific design information.
In addition to identifying the content of State specifications,the survey also provided Some insight regarding each
State’s respective administrativepolicies concerning faisework and formwork. About two-thirds of the States require
the submittai of plans and calculations, sealed by a registered professional engineer, for any significant faisework
construction. By definition, significant faisework generally corresponds to anything that spans over 16 ft (4.9 m)
or rises more than 14 ft (4.3m) in height. The survey showed that a majority of Sîates also conduct their own
reviews and inspections, subject to availability of staff, complexity of design, and so forth. While the proposed
design specification herein does not include procedural guidelines, recommended guidelines can be found in the
Guide Standard Specflcation for Bridge Temporary Works recently issued by the FHWA.@’
Based upon a review of current State practice, the authors of the Synthesis concluded that design procedures vary
considerably from one State to another. As expected, States that are more active constructing cast-in-place concrete
highway bridges generally have more comprehensive specifications and design guidelines. There are also many
States, however, with significant bridge inventories that do not faii into this group. Therefore, despite the available
information, there appeared to be a clear need to develop unified design critena and standards for the temporary
structures used to construct highway bridges.
The objective of this study has been to develop a guide design specification for use by State agencies to update
their existing standard specifications for faisework, formwork. and related temporary construction. The guide
specification was prepared in a format similar to the American Association of State Highway and Tmsportation
Officials (AASHTO) Standard Specflcationsfor Highway Bridge Structures.(3)
Research Approach
Virtually all of the potential reference or source documents necessary to develop the guide design specification
and commentary were identified in the Synthesis noted above. The reference material included applicable AASHTO
standards; the standard specifications of the FHWA and several States;Canadian, British, and New Zealand codes
of standard practice and specifications; and standards or guides prepared by other agencies and industry
a~sociations!”~) While the existing foreign standards served as good models, they were not found to be entirely
adaptable to U.S. codes and construction practices or the proprietary systems common to the U.S. construction
industry. Where applicable, selected provisions of other standards were either adopted directly from the reference
material or slightly modified. However, no single reference document was found that covered the entire scope of
the guide design specification.
After reviewing the reference material, a preliminary outline was developed by Wiss, Janney, Elstner Associates,
Inc. (WJE) and submitted to an industry advisory group for further comments. The outline was, in turn, submitted
to the FHWA for approval. The preliminary draft was developed in the same manner, then revised after receiving
the collective comments of the advisory group and the FHWA.
V
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
AASHTO T I T L E GDSBTW 95 Ob39804 0033668 354
Throughout the study, the primary objective was to develop a consensus document that would be readily adopted
by the State agencies and AASIïïû. The evaluation criteria in the project guidelines stipuiated that the proposed
guide specification reflect generally accepted practice, be acceptable to industry, and be supported by existing
research. The finai draft was revised to reflect the consensus of WJE and the advisory group, the FHWA, and other
individuals or associations identified in the acknowledgement. In addition, a commentary was developed to provi&
background on the provisions and to assist in the application of this specification.
The following guide design specification closely reflects the current state of the practice for the falsework,
formwork, and temporary retaining structures used in highway bridge Construction and is offered for adoption by
AASHTO.
The authors recommend distributing this document to the appropriate State agencies for use in revising their
current standard specifications. The authors also recommend soliciting further comments from the State bridge
authorities, AASHTO, and industry groups. After trial use of this specification, it is recommended that the FHWA
Task Group reconvene to consider any revisions or additions that may be proposed.
Acknowledgments
This study was conducted under FHWA Contract No. DTFH61-91-C-00088by Wiss, Janney, Elstner Associates,
Inc., Northbrook, Illinois. The project was directed by the Scaffolding, Shoring, and Formwork Task Group of the
FHWA, whose comments and review were very helpful in the preparation of this document The task group
consisted of the following Federal, State, and industry representatives:
WJE assembled an outside advisory group of individuals who served as consultants on this project. The
primary role of the advisory group was to review the guide design specifícation prior to submiüai to the FHWA Task
Group. The advisory group consisted of the following members:
Additional informationand input was solicited from other individuals and industry associatiOnsin their fields
of interest. Their comments were incorporated, where appmpfiate, in the finaidraft. Special mgnition is extended
to representatives of the Shoring and Forming Engineering Commitke of the Scaffolding, Shoring, and Fonning
Institute; W."homas Scott, C a o Concrete Construction; Aian D.Fisher, Cianbm Corporation;Flora A. Caiabmse,
Donald F.Meinheit, William F. Perenchio, and Raymond H.R. Tide.
vi
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
AASHTO T I T L E GDSBTW 95 = Ob39804 0 0 3 1 6 6 9 O90
TABLE OF CONTENTS
SECTION 1 .INTRODUCTION
SECTION 2 .FALSEWORK
vii
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
AASHTO T I T L E GDSBTW 95 = Ob39804 0033670 802 M
SECTION 3 .FORMWORK
viii
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
AASHTO T I T L E GDSBTW 75 Ob39804 0033673 797
COMMENTARY ................................................................ 31
APPENDIX A .Maximum Design Values for Ungraded Structural Lumber..................... 47
..............53
APPENDIX B .AISC Provisions for Webs and Flanges Under Concentrated Forces
..................
APPENDIX C .Design Wind Pressures and Forces from Selected Model Codes
49
..................................... 63
APPENDIX D .Foundation Investigation and Design
.......... 69
APPENDIX E .Conversion of Equations from U.S. Customary Units to S.I. Metric Units
REFERENCES ................................................................. 75
ix
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
AASHTO T I T L E GDSBTW 75 H Ob37804 0031672 6 8 5
LIST OF FIGURES
Figure No .
2.1 Basicwind Speed .......................................................... 8
4.1 Guidelines for Estimating Earth Pressure on Walls with Two or More Levels
of Anchors Constructed from the Top Down [modified after Terzaghi and Peck (1967)l ......25
4.2 Simplified Earth Pressure Distributions for Permanent Flexible Cantilevered
Walls with Discrete Vertical Wall Elements ...................................... 26
LIST OF TABLES
Table No .
2.1 Material Properties ......................................................... 4
C3.1 Form Materials with References for Design and Specification ......................... 41
ABBREVIATIONS
GENERAL NOTATION
in. inches
ft feet
Plf pounds per linear foot
psi pounds per square inch
ksi kips per square inch
PSf pounds per square foot
ksf kips per square foot
tsf tons per square foot
PCf pounds per cubic foot
fps feet per second
m meters
N newtons
hr hour
xi
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
AASHTO T I T L E GDSBTW 95 = 0639804 003Lb74 458 M
ÕOC Y
xii
COPYRIGHT American Association Of State Highway and Transportation Office
Licensed by Information Handling Services
A A S H T O T I T L E G D S B T W 95 ü b 3 9 8 0 4 0033675 3 9 4 M
Section 1
INTRODUCTION
Analysis and Design of Reinforced Concrete Post Shore - Individual vertical member
Bridge Structures (ACI 343R-88),American Concrete used to support loads, including adjustable timber
Institute, Detroit, MI, 1988. single-post shores, fabricated single-post shores, and
timber single-post shores.
Soil Mechanics, Foundations, and Earth
Structures (NAVFAC DM-7),Departmentof the Navy, Scaffolding - An elevated work platform
Alexandria, VA, May 1982. used to support workmen, materials, and equipmens
but not intended to support the structure being
Suggested Design and Construction constructed.
Procedures for Pier Foundations (ACI 336.3 R-72),
American Concrete Institute, Demit, MI, Revised Shoring - A componentof falsework such as
1985. horizontal. vertical, or inclined support members. For
the purpose of this document this term is used
13 DEFINJTIONS interchangeably with falsework.
For the purposes of this specification, the Temporary Retaining Structure - For the
following definitions apply: purpose of this document, temporary retaining
structure refers to both earth-reraining structures and
Brace - A member placed diagonally with cofferdams.
respect to the vertical or horizontal members of
falsework or scaffolding and fixed to them to provide -
Tube and Coupler Shoring An assembly
stability. used as a load-carrying structure, consisting of tubing
or pipe that serves as posts, braces and ties, a base
Cofferdam - A cofferdam is a watertight supporting the posts, and special couplers that serve
structure that aiiows foundations to be constructed to connect the uprights and join the various members.
under dry conditions.
-
Ultimate Load The maximum load that
U
Engineer - This term used with a capital "E" may be placed on a structure, causing failure by
refers to the owner's engineer. buckling of column members or failure of some other
component.
-
Factor of Safety The ratio of predicted
ultimate load to the calculated maximum serviceload. 1.4 MmRIC CONVERSIONS
-
Faisework Temporary construction used to Conversion equations from U.S.Cuseomary
support the permanent stnicture untu it becomes self- units to S.I. mehic units are provided in Appendix E.
supporting. Falsework would include steel or timber
beams, girders, columns, piles and foundations, and
any proprietary equipment including modular shoring
frames,post shores, and horizontal shoring.
Section 2
FALSEWORK
2.0 FALSEWORK DRAWINGS drawings shall show the location of all such openings,
including horizontal and vertical clearances and the
Ail elements of the falsework system shall be location of temporary railing.
shown on working drawings, hereinafter r e f e d to as
falsework drawings. The falsework drawings shall Where temporary bracing is to be used
include the information and details necessary to during erection and removal of falsework over or
enable the falsework to be constructed without adjacent to public traffic, the falsework drawings shall
reference to any supplemental drawing, calculation show the sequence of erection and removal and
sheet, design standard, or other source or reference details of the temporary bracing system to be used.
document.
The falsework drawings, when submitted to
The falsework drawings shall include all the owner, shall be accompanied by one set of the
design-controllingdimensions,includingbeam length, design calculations. The calculations shall show the
beam spacing, post location and spacing, vertical stresses and deflections in load-supporijng members.
distance between connections in diagonal bracing,
height of falsework bents, and similar dimensions 2.1 MATERIALS AND MANUFACTURED
controliing falsework design and erection. COMPONENTS
I I
Type Steel Seamless Steel Pipe Carbon Steel Sin~udiiralTubing Carbon Steel
Equivalent ASTM
Designation
AASHTO
I 2f36
M183
I A53
Grade B
_--
I A5ûûRound
--_
I A500Squareand
Rectangular
-__
A501
_--
A529
---
Designation Grade 36
Minimum Tensile 58,000 w@o GradeA 45,000 GradeA 45,000 58,000 @,000
S@engthPA Pi Grade B: 58,000 Grade B: 58,000
G r a d e C 62,000 GradeC 62,000
Minimum Yield 36,000 35,000 Grade A: 33,000 GradeA 39,000 36,000 42,000
Strength (FYI,psi GradeB: 42,000 GradeB: 46,000
GradeC 46,000 GradeC 50,000
2.1.23 Salvaged Steel Society, except 2.3.2.4, 2.5, 8.13.1.2, and Section 9,
as appropriate, apply to work performed under this
Used structural steel, satisfying ASTM A6 specification.
criteria for surface imperfections, may be used at the
allowable working stresses for new material, provided 2.1.3 Timber
the grade of steel can be identified to the owner’s
satisfaction. 2.1.3.1 Allowable Stresses
When the grade of used structural steel All species of wood to which allowable unit
cannot be identified, the design working stresses shall stresses have been assigned in the National Design
not exceed the following: Specijication for Wood Construction (NOS)
Supplement, 1991 edition, azc acceptable for use in
Tension, axial, and flexural . . . . . . . . . 22,000 psi faisework.
Compression, axial . . . . . . 16,000 - 0.38(L/r)2 psi, Design working stresses for new lumber shall
except U r shall not exceed 120. not exceed the design values for visually graded
dimension lumber and visually graded timbers as
Shear on gross section of web of rolled tabulated in the National Design Specification for
shapes . . . . . . . . . . . . . . . . . . . . . . . 14,500 psi Wood Construction (NDS) Supplement, 1991 Edition.
The listed values are for normal load duration and d q
Web crippling for rolled shapes . ..... 16,000 psi service conditions, and shall be modified as provided
herein.
Compression, flexural . . . . 12,ûûû,ûûû/(Ld/bt) psi,
but not more than 22,000 psi. 2.1.33 Modifcation Factors
In the formulas, L is the unsuppoaed length; Modification factors for service conditions
d is the least dimension of rectangular columns, or the and duration of load shall be as prescribed by NDS
width of a square of equivalent cross-sectional area except that the normal service condition for falsework
for round columns, or the depth of beams; b is the members shall be considered to be dry and reduction
width and t is the thickness of the compression for wet service conditions will not apply. All
flange; and r is the radius of gyration of the member. modification factors are cumulative.
Minimum Tensile Grade 100 up to 2% in.: 110,000 Grade42 60,000 70,000 Grades I & II: 70,000
Strength (FA psi Grade 100 over 244 in. to 6 in.: 100,OOO Grade 50 65,000 1 GradeIII: 65,000
I I I
Minimum Yield Grade 100 up to 2% in.: 100,ûûû Grade42 42.000 50,000 Grades I, II, & III: 50,000
Strength (FJ psi Grade 100 over 2% in. to 6 in.: 90,000 Grade 5 0 50,000
Subject to the owner's concurrence, used The design of materiais other than structural
lumber of known species may be used in accordance steel and timber shall conform to the applicable
with the following: design standard or specification for such material.
Unless otherwise permitted by the owner, The maximum load to be used on any
lumber of unknown species may not be used at higher manufactured component, under any load sequenceor
stress levels than those listed in Appendix A €or combination, shali not exceed the manufacturer's
"MIXED MAPLE." Said stresses are maximums and recommendations.
shall not be increased by application of load duration
or other stress-adjustment factors. When requested by the owner, a
manufacturer's catalog, technical bulletin, or similar
The owner may require any lumber proposed publication shall be furnished with the faisework
€or use under paragraphs (a) or (b) above to be drawings showing the use of manufactured
regraded prior to use. components. The information furnished shall include,
The factor of safety for jacks that are not a The construction live load shall consist of the
part of a shoring system, and all types of actual weight of any equipment to be supported
manufactured assemblies, shall not be less than the applied as concentrated loads at the points of contact,
minimum factor of safety required by the industry plus a uniform load of 20 psf (960 N/m2)applied over
standard for the particular device, and in no case shall the area supported, plus 75 plf (1100 N/m) applied at
the factor of safety be less than 2. the outside edge of deck overhangs.
The borizontai design load shall consist of For members and components subject to
the sum of any actual horizontal loads due to impact during lifting operations, the sîatic
equipment, construction sequence, or other causes, load due to the payload shall be increased by
excluding the specified wind load, but in no case shall not less than 30percent for mechanicaüy
the horizontal design load be less than 2 percent of operated lifting equipment and not less than
the total dead load to be supported at the point under 15 percent for manually operated lifting
consideration. equipment.
Pursuant to the provisions in Section 2.3.1, If motorized carts are used, the uniform live
the vertical and horizontal design loads shall be load shall be increased an additional 25 psf
increased as necessary to account for the effect of (1200 N/m2).
load redistribution due to prestressing, shrinkage, or
other causes.
23.4 Minimum Vertical Load where diagonal bracing is not used. The basic wind
pressure for each height zone shall be increased by
The minimum total design vertical load for 5 psf (240 N/m? for falsework members over or
any falsework member shall be not less than 100 psf adjacent to üaffic openings.
(4800Nh? for the combined dead and live load,
exclusive of any increase for impact, regardless of 23.53 Stream Flow
slab thickness.
When falsework supports are placed in
23.5 Environmental Loads flowing water, water pressure on the supports shall be
determined by the following formula:
2.2.5.1 Wind
Height Zone (ft Pressure, psf for Indicated Wind Velocity, mph
above ground) 70 80 90 100
O to 30 1.5 Q 2.0 Q 2.5 Q 3.0 Q
30 to 50 2.0 Q 2.5 Q 3.0 Q 3.5 Q
~ ~~ ~~ ~~ ~~ ~~
Noles:
(a) Vdues arc futut-mile apeeda .t 33 fi (10 rn) .bow ground f a expoaure cstegary C riid ut wociatcú with an annual probability of 0.02.
@) Lineu iiaerpolation bstwecn wind speed contaus ir rcceptoble.
(c) Cuition in the we of wind speed contours in mountainous regions of Alaska is advised.
(d) Conversion: 1 mph = 1.609 km/hr; 1 mi = 1.61 km
.
23 DESIGN The entire superstructure cross section,
except railing, shall be considered to be placed at one
23.1 General time except as otherwise provided herein. Girder
stems and connected bottom slabs, if placed more
Tbe Ealsework design analysis shall consider than 5 days prior to the top slab, may be considered
the effect of foundation settlement, interaction to be self-supporting between falsework posts at the
between elements of the falsework system and time the top slab is placed, provided that the distance
completed portions of the permanent stnicture, and between falsework posts does not exceed four times'
load redistribution due to shriniage and dead load tbe depth of the portion of the girder placed in the
&flection. The falsework design shall accommodate first pour.
these factors if necessary. For cast-in-place
prestressed construction, the falsework shall be The support system for form panels
&signed to support any increased load resulting from supporting concrete deck slabs and overhangs on
load reùisbibution caused by the prestressing forces. girder bridges shall be considered to be falsework and
shall meet all falsework design criteria and Except for bracing required to prevent I
requirements. Additionally, such falsework shall be overturning or collapse of the falsework system or
designed so no differential settlement will occur any element of the system, the ability of falsework
between the girders and the deck forms during members to resist horizontal loa& may include the
placement of the deck concrete. contribution to stability provided by the supported
structure. Bracing required to prevent overtuming or
23.2 Load Combinations collapse shaii be designed to resist the fuli horizontal
design load with the falsework in the unloaded
The groups given in Table 2.3 represent (before the concrete is placed) condition, except for
combinations of loads and forces to which the cable bracing used to externally brace heavy-duty
falsework may be subjected. shoring systems. Such cables may be designed to
resist the difference between the overturning and
Ail elements of the falsework, or the resisting moments.
foundation upon which it rests, shall be designed to
resist the Group I, II, III, and IV load combinationsat 23.4 Combined Stresses
the percentage of the basic allowable stress shown.
The adequacy of falsework members
23.3 Stability Against Overturning subjected to both axial and bending stresses shall be
determined by the following combined stress
The falsework system, including individual expression:
elements and units of the system that are subject to
overturning forces, shall be analyzed for stability -
f,
Fa
+ -
fb !5 1.0
Fb
(2-2)
against overturning with the falsework in the loaded
and unloaded condition; that is, with and without the
dead load of the concrete. The ratio of the resisting where, respectively, f, and fb are the calculated axiaI
moment to the overturning moment shall be equal to and bending stresses and F, and Fbare the allowable
or greater than 1.2 for all load combinations. axial and bending stresses.
10
take into account the non-unifonnity and uncertainty the falsework design. The worlananship shall be of
of the site conditions. such quality that the falsework will support the loads
imposed on it without excessive settlement or take-up
These values apply for the ground water beyond that shown on the falsework drawings.
level at a depth below the foundation greater than the
width of that foundation. Continued flooding or wet 2.5.2 Foundations
weather wili soften clay soils. Where site flooding
andor high ground water levels are likely to be Falsework footings shall bear uniformly on
experienced, the presumed allowable bearing pressure the supporting material, which shall be safe from
in Table 2.4 shall be multiplied by the factor given in undermining and protected against softening.
Table 2.5.
When requested by the owner, the Contractor
Pursuant to the provisions in Section 2.0, the shall demonstrate by suitable load tests that the soil-
allowable soil-bearing value used in the foundation bearing values assumed for the falsework design do
design shall be shown on the falsework drawings. not exceed the supporting capacity of the foundation
material.
Footings with eccentric loadings shall be
designed so that no portion of the footing has uplift The load-carrying capacity of driven piles,
pressures. Footings with lateral loading shall be unless driven by a drop hammer, shall be determined
designed to provide a 1.5 factor of safety against by the ENR or other recognized pile driving fonnula.
sliding. If a drop hammer is used, the allowable piIe capacity
shall not exceed the value indicated by the driving
2.4.3 Pile Foundations formula divided by a factor of safety of 1.5.
When timber piles are used, the load applied 25.3 Timber Construction
to any pile in the foundation under any loading
condition shall not exceed 45 tons (400 kN). Timber beams, stringers, and joists shall be
of the size and timber grade specified, and shall be
When steel piles are used, the load applied to straight and undamaged.
any pile in the foundation under any loading condition
shail not exceed the capacity of the pile when Adequate splice details shall be used where
analyzed as a short column. the splicing of timber members is unavoidable.
Wherever practical, continuous or overlapping
When piles extend above the ground line, the members shall be used.
load-carrying capacity of both individual piles and
piles within a framed bent shall be evaluated under Where the use of discontinuous members is
the combined action of the vertical and horizontal permitted, joints shall be made over the center of
design loads. supports. Where a beam comprises a pair of
members, joints in the members shall be staggered
2.4.4 Foundations for Heavy-Duty Shoring between supports. Paired members used to form a
Systems single beam shall be of identical depth.
11
12
2.5.5 Proprietary Shoring System banier and the falsework footing and at least 1 fi
(0.3 m) between the barrier and aii other falsework
Proprietary shoring systems shall be members.
undamaged and assembled using only the components
supplied by the manufacturer for the particular Temporary bracing required pursuant to the
system. provisions in Section 2.3.9 shaü be instailed
concutrently with the restrained element of the
Proprietary systems shall be installed in falsework system.
accordancewith the manufacturer’s recommendations,
with provision for vertical adjustment. For faisework over or adjacent to a traffic
opening, all details that contribute to horizontal
Extension tubes shall be braced as required stability and resistance to impact, except bolts in
and erection tolerances shall not exceed the tolerances bracing, shall be instailed at the time each element of
recommended by the manufacturer. the falsework is erected and shall remain in place
until the falsework is removed.
25.6 Manufactured Components
25.9 Adjustment
When manufactured components are used in
the falsework, the owner shall be furnished with a 2.5.9.1 Wedges
letter of certification signed by the supplier of the
component or his authorized representative. Said Wedges shall be installed in sets of two
letter of certification shall state that the component is wedges (matched pair) except that a single wedge
being used in accordance with the manufacturer’s may be used on a sloping surface. Wedges shall have
recommendations for loads and conditions of use. a height not exceeding one-thiid of their length.
When instailed, wedge sets shall be in contact over at
2.5.7 Noncommercial Components least haif of their sloping faces.
If the falsework construction incorporates Wedges may be used at either the top or
generic or homemade components fabricated from bottom of a post or strut, but not at both ends.
steel or timkr, such as overhang brackets, beam
supports and similar devices, the owner may require 25.9.2 Jacks
a load test to establish the safe load-carrying capacity
of such a component. Such tests shall be performed Screwjacks shall not be extendedbeyond the ,
in the field, on components randomly selected by the limit set by the manufacturer.
owner, under conditions that will simulate the
intended use in the falsework. The allowable capacity Where hydraulic jacks are used for
of any such component shall not exceed 40 percent of adjustment, the load imposed by the supported
the ultimate load-carrying capacity as indicated by the member shall be transferred at the end of the
load test. adjustment cycle to a permanent means of support
capable of resisting the load without additional
2.5.8 Traffic Openings settlement or distortion.
Unless otherwise provided, the minimum Where sand jacks are used, the annular
dimensions of clear openings to be provided through distance between the confining element of the jack
falsework for roadways that are to remain open to and the edge of the base plate shall not exceed % in.
traffic during construction shall be at least 5 ft (6 m).
(1.5 m) greater than the width of the approach
traveled way, measured between barriers when used, 2.5.10 Camber Strips
and 14 ft (4.3m) high, except that the minimum
vertical clearance over interstate routes and freeways When directed by the owner, camber strips
shall be 14.5 ft (4.4 m). shall be furnished and installed to compensate for
beam deflection, vertical alignment, and anticipated
Falsework at traffic openings shall be structure deflection.
protected by a temporary concrete barrier system.
The falsework shall be constructed so as to provide
clear distances of at least 3 in. (80 mm) between the
13
2.5.11 Loading
2.5.12 Removal
2.5.13 Dismantling
14
FORMWORK
15
The minimum design load for combined dead with a maximum of 2,000psf, a minimum of 600 psf,
and live loads shail not be less than 100psf but in no case greater than 150 h.
(4,800N/m2), or 125 psf (6,000N/m2) if motorized
carts are used. where R = rate of placement, ft per how,
T = temperature of concrete in the form, O F .
33.2 Lateral Pressure OP Fluid Concrete
33.3 Horizontal Loads
33.2.1 Unless the conditions of
Section 3.2.2.2apply, formwork shail be designed for Vertical wall or side form bracing shall be
the lateraï pressure of the newly placed concrete given designed to meet the minimum wind load
by Equation 3-1. requirements of ASCE 7-88(fomerly ANSI A58.1)
or the local building code, whichever is more
stringent. For wall foms exposed to the elements,
the minimum wind design load shail not be less than
where p = lateral pressure, psf; 15 psf (720N/m2). Bracing for wall forms shall be
w = unit weight of fresh concrete, pcf; designed for a horizontal load of at least 100plf
h = depth of fluid or plastic concrete, ft. (1,500N/m) of wall, applied at the top.
16
direction between studs, joists, form stiffeners, form Exposed outside edges should be chamfered
fasteners, or wales. Undulations exceeding either 118 with a minimum Min. ( 1 3 m ) material unless
in. (3.2 mm) or 1/î40 of the center-to-center distance otherwise shown. Bevels are permitted at formwork
between studs, joists, fonn stiffeners, form fasteners, projections such as beam copings, girders, and other
or wales will be considered to be excessive. Should difficult intersections to facilitate formwork removai.
any form or forming system, even though previousiy Spreader blocks and bracing shaü be removed during
approved for use, produce a concrete surface with concrete placement.
excessive undulations, its use shall be discontinued
until modifications satisfactory to the Engineer have 3.43 Tolerances
been made. Portions of concrete structures with
surface undulations in excess of the limits herein may All formwork shall be built and erected true
be rejected by the Engineer. to line and grade as specified in Contract Documents.
Sufficient support systems must be designed to
33.4 Safety Factors for Form Accessories maintain formwork alignment during construction.
Minimum factors of safety for formwork Unless specified in the Contract Documents,
accessories such as form ties, form anchors, and form the fonnwork shall be constructed to conform with
hangers shall conform with the safety factors the tolerance limits of Standard Spec$îcatwn for
<
presented in Table 3.1. In selecting these accessories, Tolerancesfor Concrete Construction and Materials
the formwork designer shall make Certain that (AC1 117-90).('9) The class of surface shail ais0 be
materials furnished for the job meet these minimum specified in accordance with AC1 117 documents.
strength safety requirements.
Formwork shall be inspected by the
3.4 CONSTRUCTION Contractor in the presence of the Engineer prior to
placement of concrete. Such inspection does not
3.4.1 General relieve the Contractor of the responsibility of
obtaining a concrete structure and finish within the
All forms shall be constructed and specified tolerances, free of warping, bulging, or other
maintained in a mortar-tight condition, including defects. In the event of a defect, the repair method,
compensation for lumber shrinkage. Formwork shall including removal and replacement, must be approved
be constructed and erected in such a manner as to by the Engineer and shall be completed at the
prevent injury and to facilitate stripping and removal. Contractor's expense.
Prior to concrete placement, specified formliners shall
be placed and inspected to ensure proper positioning. 3.4.3 Joints
Where required, formwork joints shali be filled with
an approved material that is impervious to moisture, Expansion joints, coristniction joints, and
will not stain concrete, and produces a tight joint. isolation joints shall be located as shown on the
Contract Documents. The location of joints that
Note:
(a) Safety factors are based on ultimate strength of accessory.
17
18
19
For a cantilever retaining system or walls Q = angle of internal friction which usually
with a single level of bracing, lateral pressures shall ranges from 26" to 30" for medium to
be computed by the Rankine or Coulomb method. dense soils.
For active pressure calculation, friction between the
soil and the wall element shall be neglected. For Hydrostatic water pressure shall be added below the
passive pressure calculation by the Coulomb method, water table.
the angle of wail friction shall be less îhan one-third
the effective angle of internal friction for the soil.
21
22
23
24
,,, t0.25"
-'t
0 . 4 ~
H
(3)
Figure 4.1 Guidelines for Estimating Earth Pressure on Wails with Two or More Levels of Anchors
Constructed from the Top Down [modified after Tenaghi and Peck (1%7)]
Notes:
(a) K, = tan2(45"-$'/2)
(b) K, = 1 - m (2qJyH), but not less than 0.25
m = 1 for overconsolidated clay
m = 0.4 for normally consolidated clay
(c) Value of 0.4 should be used for long-term excavations; values between 0.4 and 0.2 may be used for short-
tenn conditions.
(d) Surcharge and water pressures must be added to these three earth pressure diagrams. The two lower
diagrams are not valid for permanent walls or walls where water level lies above bottom of excavation.
(e) Conversion: 1 tsf = 96 W h 2 .
Notation:
H final wall height
% = active earth pressure CoefficienPb)
Y - effective angle of internai friction
Y - effective soil unit weight
Y - total soil unit weight
m - reduction factor
e - unanfïned compressive strength
25
26
4.
v*
Sum moments about the point of action of F
to determine the embedment (Dh for which
the net passive pressure is sufficient to
provide equilibrium.
5. Determine the depth (point a)at which the
shear in the wall is zero (i.e., the point at
which the areas of the driving and resisting
pressure diagrams are equivalent).
6. Calculate the maximum bending moment at
the point of zero shear.
7. Calculate the design depth, D = 1.2D0 to
1.4D, for a safety factor of 1.5 to 2.0.
Figure 4 3 Shplifîed Earth Pressure Distributions and Design Procedures for Permanent
Flexible Cantilevered Walls with Continuous Vertical Wall Elements
Notes:
(a) Surcharge and water pressures must be added to the above earth pressures.
(b) Forces shown a ~ per
e horizontal foot of vertical wall element.
27
FIGURE 5.6.2.C.o ~ .
(Y
H
; - 2s")H1
2
-
3b (D I 5 b )(4Su-7; H l
Pp
I
FOR TANB*(I eb
r
LJ
ri
i
Figure 4.4 Simplified Earth Pressure Distributions for Temporary Flexible Cantilevered
Walls with Discrete Vertical Wall Elements
Notes:
(a) For temporary walls embedded in granular soil or rock, refer to Figure 4.2 to determine passive resistance
and use diagrams in Figure 4.4 to determine active earth pressure of retained soil.
(b) Surcharge and water pressures must be added to the indicated earth pressures.
(c) Forces shown are per verticai wail element.
(d) Pressure distributions below the exposed portion of the wall are based on an effective element width of 3b,
which is valid for 12 5b. For 1 < 5b, refer to Figures 4.3 and 4.5 for continuous wail elements to determine
pressured distributions on embedded portions of the wail.
(e) Refer to Reference 3 for determination of &.
28
COHESIVE
SOIL II
DO
l
Figure 4.5 SimplifW Earth Pressure Distributions for Temporary Flexible Cantilevered Walls with
Continuous Vertical Wall Elements [modified after Teng (1962))
Notes:
(a) For wails embedded in granular soil, refer to Figure 4.3 and use above diagram for retained cohesive soil
when appropriate.
(a) Refer to Figure 4.3 for simplified design procedure.
(c) Surcharge and water pressures must be added to the above earth pressures.
(d) Forces shown ate per horizontai foot of vertical wall element.
(e) Refer to Reference 3 for determination of &.
Notation:
Y - Effective unit weight of soil
s, - Undrained shear strength of cohesive soil
ß - Ground surface slope behind wall (+ for slope up from wall, - for slope down from wall)
K , = Active earth pressure coefficient
29
COMMENTARY
Section 2
FALSEWORK
The specification allows the use of both new and salvaged structurai steel. Salvaged (used) steel is subject
to the same ASTM A6 criteria for surface imperfections as new steel.@) The prescribed working stresses for
unknown steel grades are based on the assumed use of structural steel conforming to ASTM A36. For reference,
some of the more common steel designations preüating ASTM A36 are provided in Table C2.1.
1924- 1931 ASTM A7 structura Steel 55,000 to 65,000 41 T.S. or not less than 30,000
ASTM A9 smictural Steel 55,000 to 65,000 H T.S. or not less than 30,000
1939-1948 ASTM A7-A9 structural Steel 60,oOO to 72,000 M T.S.or not less than 33,000
1939-1949 ASTM A141-39 Rivet Steel 52,000 to 62,000 H T.S. or not less than 28,000
While it is recognized that many provisions of the Structural WeMing Code, AWS DZ.Z-92 may not be
applicable to falsework construction, the intent of Section 2.1.2.3 is to require the same quality of workmanship for
temporary works as for permanent construction. The noted exceptions are the same as those found in the AZSC
Specificationfor Structural Steel Buildings.@)
2.1.3 Timber
Since falsework is seldom subjected to maximum loading for more than seven days, a load duration factor
of 1.25 will be applicable to most falsework designs. In the case of loads of shorter duration, such as wind,a larger
factor is appropriate. A duration-of-load factor of 2.0 (impact loading) may be used in the design of the connection
at the base of a falsework post adjacent to a traffic opening.
The maximum design values for ungraäed structurai lumber tabulated in Appendix A are based on the lowest
stresses for each size classification. These apply only for normal load duration and dry surface conditions, unless
noted otherwise. Refer to the NDS Supplement-Design Valuesfor Wood Construction for a description of applicable
adjustment factors and species designationjq
Vertical shoring systems consist of individual components that may be assembled and erected in place to
form a series of internally braced steel towers of any desired height. Safe working loads for these shoring systems
are generally determined empirically by full-scale load tests, where the ultimate capacity is based upon uniform and
concentnc loading of the tower legs. Therefore, the shoring capacity published by the m a n u f a c m should be
considered the maximum load that the shoring is able to safely support under ideal loading conditions. Horizontai
loads, eccentricity due to unequal spans or an Imbalanced pouring sequence, and uneven foundation settlement
generally will have an adverse effect on the vertical shoring assembly, and warrant special consideration.
32
Manufactured assemblies are commercial products; such as jacks, hangers, brackets, and similar items; the
use of which is governed by conditions or limitations imposed by the manufactmr. When approved for use, these
products become an identifiable component of the falsework system.
The specifications limit the load op the deflection or both, of any commercial product to the maximum
recommended of allowed by the manufactmr of the product. The manufacturer’s recommendation should be shown
in a catalog or design manual published by the manufacturer, or in a statement of compliance pemining to a
particular project.
2.2 LOADS
22.1 General
The minimum lateral load is intended to ensure that sufficient horizontal load capacity is available so that
the falsework remains stable under normal conditions, when environmental lateral loads are not present. The
horizontal design load should be considered separately in both the transverse and longitudinal directions.
For post-tensioned construction, it is generally recognized that redistribution of gravity loads occufs after
the superstnicture is prestressed. The distribution of load in the falsework after post-tensioning is dependent on
factors such as spacing and stiffness of falsework supports, foundation stiffness, superstructure stiffness, and tendon
profile. The amount of load redistribution can be significant and may be a governing factor in the falsework design.
Accordingly, the vertical load due to dead load transfer should be added to the remaining gravity loads to obtain the
total vertical load for the falsework design.
Overall tempemure variations result in contraction or expansion. The induced forces must be resisted or
the movement accommodated by the falsework.
Construction live loads are inherently transient and, therefore, for a given falsework scheme the potential
combinations of these loads should be considered.
In bridge deck consiruciion, a concentration of live load generally occurs at or near the edge of the bridge
deck during concrete placement and finishing. To account for this loading, the guide specifications include a 75 plf
(1100 N h ) live load applied along the outside edge of all deck overhangs. In the case of long falsework spans,
however, the application of 75 plf (1100 N/m) to falsework components below the overhang support system may
be unduly conservative. Therefore, it is recommended that the 75 plf (1100 N h )be applied as a moving load over
a length of 20 fi (6 m) and positioned to produce the maximum stress in the underlying falsework component being
considered.
23.3.2 Impact
The allowance for impact assumes n o d care in the placing of structural elements. It is not intended to
cover excessive impact loads resulting from dropping materiais onto the falsework or dragging structural elements
into position.
33
23.5.1 Wind
The basic reference for computation of wind load is the UnlformBuiúfing Code. 1991 oeidnt@
i.)' Table 2.2
was developed assuming an average Ce coefficient for exposure categories B and C, C, = 1.3 to 1.4 (depending upon
the height zone) and I = 1.0. The Q-factor was adopted from Caltran~.(~) Detailed provisions for calculating the
design wind pressures are reproduced in Appendix C.
Given the regional preferences for different model codes, the relevant wind provisions from ASCE 7-88
(formerly ANSI A58.1) and the BOCA National Building Code are also provided in Appendix C.(29s30) The wind
provisions in ASCE 7-88 consist of the same general equations that appear in the AASHTO StandardSpecfications
for Structural Supports for Highway Signs, Luminaires, and Trafic
For heavy-duty shoring, the wind impact is assumed to be the total projected area of all the elements in the
tower face normai to the applied wind. For all other falsework, the wind impact area is assumed as the gross
projected area of the falsework and any unrestrained portion of the permanent structure, excluding tbe area between
falsework posts or towers where diagonal bracing is not used.
23 DESIGN
For stability analysis, it is generally assumed that the horizontal design load produces a moment that acts
to overturn the falsework system or element of the system under consideration. When calculating overturning
moments, the horizontal design load will be applied to the faisework in accordance with the following:
O
Actual loads (such as those due to construction equipment or to the concrete placing sequence) will
be considerd as acting at the point of appiication to the falsework.
O Wind loads should be considered as acting at the centroid of the wind impact area for each height
zone. When wind loads govern the design, however, the horizontal design load (to be used in
calculating the overturning moment) is applied in a plane at the top of the faisework post or
shoring.
All other horizontal loads, including the minimum load when the minimum load governs, should
be assumed as acting in a plane at the top of the falsework posts or shoring.
The intent of Section 2.3.3 is to insure that for each load combinationidentified in Section 2.3.2, the righting
moment shall be at least 1.2 times the overturning moment.
23.5 Deflection
The theoretical deflection is the deflection that would occur if ail of the concrete in the bridge superstructure
were to be placed in a single pour. Theoretical deflection is limited to ln40of the span of the falsework beam. This
limiting value is included in the specifications to ensure a Certain degree of rigidity in the falsework and thereby
minimize distortion of the forms, Theoretical deflection (deflection under the weight of the entire superstructure)
is usually greater than the actual deflection for a given falsework member.
Actual deflection is the deflection that occurs as the falsework beam is loaded. When calculating the actual
deflection, it is necessary to include the weight of foms and falsework supported by the beam as well as the weight
of the concrete the beam actually supports. It is also necessary to consider such factors as the sequence of
construction and the depth of the bridge superstructure when two or more concrete pours are involved.
34
Readily identifmble components of the deflection arise from elastic shortening of support members and
foundation settlement, but additional and often more significant deflections may occur due to take-up arising from
the straightening of bent sole plates, crushing of timber packers, and other causes. The magnitude of &fleaions
arising from takeup is largely dependent on the properties of packing materials and joint details. As a general nile,
however, the vertical take-up may be on the order of 1/16in.(2 mm) for every lumber surface in contact with anotha
wood member or steel component.
The current AISC specificationshave been extensively modified to distinguish between local web yielding,
web crippling, and sidesway web buckling.@) The current web yielding criteria conespond to the original web
crippling equations, and are an indication of the load level required to yield the web steel below the top flange. The
new web crippling provisions limit concentrated loads to prevent column-type buckling of the web, and the sidesway
web buckling provision limits magnitudes of concentrated load to prevent the tendency of a flange to "kick-out"
under heavy compression loads.
In the United States, there are several manufacturers of proprietary shoring systems. However, then? are
no industry standards for the various components of these systems and, as a general rule, towers or components
produced by different manufacturers should not be intermixed. Some other limiîations or general characteristics of
modular systems are as follows:
e Extemai bracing is recommended when the height exceeds four times the least base dimension.
e Allowable leg capacities are generally reduced when the screw jacks, or extension legs, are fully
extended.
e Multi-tiered towers stacked in excess of two fiames high have lower allowable leg capacities than
single- or double-tier towers.
e The drift characteristics of proprietary systems can vary considerably,depending upon their bracing
configurations. Ladder frames exhibit the least lateral stiffness, and very little benefit is derived
from the horizontal braces.
Some manufacturers allow a 4 to 1 differential leg loading between two legs of a frame, or two frames in
a tower. Examples of where this type of differential leg loading could occur would be a skewed overpass where the
underlying right-of-way is maintained, or the exterior shoring towers of a bridge deck supporting screed loads and
the overhang falsework. Significant differential leg loads are generally discouraged however, unless substantiating
data can be furnished by the manufacturer that indicate that the differential loading wili not overstress the tower
components.
The modified design load requirement is adopted from Calirans, where experience has shown that the
downward force exerted by the bridge superstructure increases after the deck concrete is placed.") The increased
force is the result of deck shrinkage during the curing period; consequently, it will be larger at falsework bents
located near the center of the bridge span than at bents near the abutments or columns. The increased force is of
greater concern in the case of cast-in-place prestressed structures (which have little load-camying capacity until
tensioned) than in conventionally reinforced concrete structures.
35
2.4.1 General
Falsework foundations are generally set at M o w depths because the loading is frequently temporary anci
may only last for months as opposed to loadings from permanent smctures that will last for years. The foundations
should be designed with an adequate safety factor against failure of the supporting ground and without detrimental
settlements. The ground support factors that need to be considered include:
2.4.2 Footings
The use of presumptive bearing values for design is based upon judgment and experience developed on a
large number of projects. For most situations, the presumptive bearing pressures, as given in Table 2.4 of the
specification, are conservative. However, the presumptive bearing values do not consider important factors such as
foundation size and embedment, soil stress bistoxy, and stress distribution of layered soils. Thus, the presumptive
soil pressures should be considered to be an upper bound value. The design bearing pressures should be based upon
site specific information and a more thorough analysis. The designer should also check the local building code,since
presumptive bearing values in these codes are based upon local experience.
Soil descriptions used in Table 2.4 are in accordance with the Unified Soil ClassifiCaton System, briefly
described in Table D.4. These values are based upon typical soil properties for various types of deposits. For the
pressures listed, settlements should be in an acceptable range.
Both uniform and differential settlement can affect the adequacy of the falsework foundations. For soil
Groups 1 and 2 in Table 2.4, settlement should not be a major factor. However, settlement may be si@icant for
the soil Group 3 and a more detailed settlement analysis shall be carried out. For soil Group 4, the use of shallow
foundations is generally not acceptable. Deep foundations are normally used for support of the falsework in these
deposits. The amount of movement that can occur in soil Group 5 is a function of local conditions, climatic effects,
and other geologic considerations. A local gwtechnical engineer shall be consulted regarding these matters.
36
If the surface deposits provide insufficient bearing capacity, or the shallow foundations are p~edictedto
I
deform more than allowed., it WUbe necessary to extend the foundations &rough the surface deposits to a more
competent bearing stratum, If piles are to be used, the driving aiteria should be selected on the basis of a wave
equation analysis or an accepted driving formula. The penetration data of the last 5 ft (1.5 m) of driving should be
recarded and submitted to the designer of the falsework foundations. Guidelines for the design of pile foundations
are presented in Chapter 4 of AASHTO Standard Spec8catwns for Highway Bridges.‘”
2.4.4 Foundations for Heavy-Duty Shoring
In any case where the maximum leg load within a given tower exceeds 30 kips (130w), the tower
foundation should be designed and constnicted to provide uniform settlement under all legs of the tower under all
loading conditions. Ihisrequirement is included in the specifications to prevent distortion of the tower components
as a consequence of unequal leg sealement.
The effect of unequai leg settlement becomes more severe as leg loads increase; consequently, the tower
foundation design, including the method employed to ensure uniform settlement, is relatively more importantwhen
leg loads are high.
2.5 CONSTRUCTION
25.2 Foundations
Surface water from rainfall or other sources could cause scour around foundations, leading to loss of
supporL The surface water drainage should be diverted to prevent erosion or scour d u h g the time the falsework
foundations are in use.
Construction activity taking place in the vicinity of the foundation can alter the foundation support. This
can occur when trenches or pits are dug adjacent to the foundation, thereby reducing lakral support of the soil below
the foundation level. Heavy construction equipment can cause nitîing that will disturb the soils below the foundation
level, thereby weakening them and perhaps leading to unacceptable settlements. Equipment might also be stoclrpied
next to foundations, causing additional loading that was not considered in the design. AU construction activities
should be reviewed prior to being implemented so as to maintain the adequacy of the foundations.
Ceriain soils are susceptible to densification from vibrations and, under the right conditions, may even
liquify. These vibrations can occur from construction-related operations such as the driving of piles or sheet piling.
Vibrations could also occur from movement of construction equipment across the site. Soil types A, B, and D in
Group 3 of Table 2.3 are most susceptible to settlement from vibrations.
Friction between the joists and the top fiange of a steel beam wili provide some iaterai resîraint, but the
amount is indeterminate. Therefore, as a general nile, friction between the joists and top fiange should be neglected
when investigating flange buckling.
Timber cross bracing between adjacent steel beams is commonly used for flange suppûrt in falsework
construction. In this method, timber struts are set diagonally in pairs between the top flange of one beam and the
bottom flange of the adjacent beam, and securely wedged into place. However, timber cross bracing alone will not
prevent flange buckling because the timber struts resist only compression forces. A more effective flange support
method uses steel tension ties welded, clamped, or otherwise secured across the top and bottom of adjacent beams
in combination with timber cross bracing between the beams.
When beams are continuous over two or more spans of unequal length, and if an end span is considerably
shorter than the adjacent span, beam uplift may occur at the end of the short span. This uplift condition (negative
deflection at the end support) is an indication of system instability and must be considered in the analysis. if
theoreticai uplift cannot be prevented by loading the short span first, the end of the beam must be tied down or the
span lengths changed.
The clearances from falsework over traffic cited in this section are minimums based on Article 2.4,
"Highway Clearances for Underpasses"of the AASHTO Standard SpecifzcutionsforHighway Bridges.") Some States
routinely speciîy greater clearances, that is, verticaï clearances of 15 ft (4.6 m) over freeways and truck routes, and
horizontal clearances to include nominal shoulders. Increased horizontal clearances should be specified when
indicated by traffic needs or existing roadway geometrics at specific sites. Temporary barriers or railings to protect
the falsework from vehicular impacts are normaïiy required at ail locations except where traffic speeds and volumes
are very low.
2.5.12 Removal
In general, ail elements of the falsework system must remain in place for a specified time period or until
the concrete attains a specified strength or, in the case of cast-in-phce prestressed construction, untü stressing is
completed. However, these limitations do not apply to bracing, including cable bracing, which is installed to prevent
overturning gr collapse of the falsework system. Such bracing may be removed on the day following concrete
placement in any m e where the in-place concrete provides horizontal stability. Note that the concrete will provide
horizontal stability if, in the Engineer's judgment, it is capable of transferring horizontal forces from the falsework
to previously constructed elements of the bridge substructure.
38
Section 3
FORMWORK
Bridge formwork can be divided into two categories: vertical and horizontal formwork Vertical formwork
can be generally consbucted using job-built systems or prefabricated systems. Horizontal formwork can be
constructed utilizing a job-built, prefabricated, or permanent stay-in-piace system. These systems are defined as:
Job-Built - a formwork system designed and built for a specific application, most commonly using
plywood and lumber.
O
Prefabricated Formwork - most commonly a modular system that has the durability for multiple
reuses and normally is built with plywood with a metal framing. Prefabricated formwork can be
built for custom uses on special projects.
Stay-in-Place Formwork - a formwork system designed such that the formwork is not removed
after consîruction. This system most commonly consists of stay-in-place metal decks or precast
concrete planks.
Fonnworkfor Concrete describes the formwork materials commonly used in the United Siaies and provides
extensive related data for form design.'") Information is also available from manufaclmers and suppliers of materials.
Table C3.1 indicates other specific sources of design and specification daia for formwork materials. This tabulated
information should not be interpreted to exclude the use of any other materials that can meet quality and safety
requirements established for the completed work.
3.1.2 Sheathing
Sheathing is defined as the supporting layer of formwork closest to the concrete. It may be in direct contact
with the concrete or separated from it by a form liner. Sheathing materials consist of wood, plywood, metal, or other
products capable of transferring the load of the concrete to supporting members such as joists or studs.
In selecting and ushg sheathing materials, important considerations are: (1) strength; (2) stiffness; (3) ease
of release; (4) reuse and cost per use; (5) surface characteristics imparted to the concrete such as wood grain transfer,
gloss, and paintabiiity; (6) resistance to mechanical damage, such as from vibrators and abrasion from slip forming;
(7) workability for cutting, drilling, and attaching fasteners; (8) adaptability to weather and extreme field conditions,
temperature, and moisture; and (9) weight and ease of handling.
In areas where form removal is expensive or hazardous, the use of stay-in-place (S.1.P) forms may be
desirable. The additional dead weight of the deck slab, appearance, and corrosiveness of the environment are some
of the factors that should be considered when deciding if metal or concrete S.I.P. forms should be used. Some States
have developed criteria for allowing the use of corrugated steel S.I.P. forms. These criteria are generally based on
the FHWA Instructional Memorandum 40-3-72 (no longer an active FHWA policy), except that deflections are
limited to If240 or % in. (20 mm), whichever is less.
Since a large proportion of formwork accessories consists of proprietary equipment, the designer shall, prior
to use in designs, ensure that the engineering data provided by equipment suppliers include the foliowing:
The basis on which the safe working loads were determined, and whether the factor of safety is
based on yield load or ultimate load.
O A statement as to whether the supplier's data are based on calculations or test results.
39
Insuuctions compatiblefor use and maintenance,including points that may require specialattention
during formwork erection or dismantling.
Detailed information on mass, dimensions,load capacities, deflxtions, shear, bending moment, and
torsional strength as may be applicable.
O
Number of reuses before refurbishment is required.
When threaded parts are utilized in the formwork design, the designer must call out thread type and
dimensions to ensure that the Component parts have compatible threads. Caution is warranted when interchanging
component formwork accessories from different manufacturersbecause most formwork accessories are designed and
tested as a system. Interchanging component parts may affect load-carrying capacity or formwork connections,
leading to premature failures. Manufacturers’ recommended procedures and instructions must be followed in
formwork design and construction.
Table C3.1 Form Materiais with References for Design and Specification
Item Princioal use Reference data
Lumber Form framing, sheathing, and National Design Speci3cation for Wood Construction (NDS),
shoring Reference 26, 3 2
Plywood Form sheathing and panels Constructionand Indutrial Plywood, Reference 36.
Steel Panel framing and bracing Manual of Steel Construction, Reference 25.
Form ties, anchors, and For securing formwork against See Table 3.1 for recommended safety factors.
hangers placing loads and pressures
Steel frame shoring Formwork support Gu& to HorYmta~ Shoring Beam Erection P m e d u n for
P t d o r w y Systems, Reference 43.
Form insulation Cold weather protection of con- AC1 306R Reference 45.
crete
40
3.2 LOADS
The lateraì pressure formulas (3-2) to ( 3 4 , adopted from AC& are empirid equations based on data and
conditions that have changed over the yeam, particularly admixture usage and placement rates. The pressure
formulas are applicable under the following conditions:
o The concrete weighs 150 pcf (23.6 kN/m3), is made with Type I cement, and has a slump of not
more than 4 in. (100 mm). For concrete weighing other than 150 pcf (23.6 kN/m3), the resulting
pressure from the equations is multiplied by the ratio of actual unit weight to 150 pcf (23.6 kN/m3).
o The concrete contains no admixtures or pozzolans. When a retarding admixture, or fly ash or &er
pozzolan replacement of cement is used in hot weather, an effective temperature less than that of
the concrete in the forms should be used.
o Column forms are assumed to have a maximum plan dimension of 6 ft (1.8 m). Othenvise they
are classified as wall forms.
If concrete is pumped from the base of rhe form, the form should be designed for full hydrostatic head of
concrete plus a minimum allowance of 25 percent for pump surge pressure. If there are significant restrictions to
the flow of concrete being pumped from the bottom, such as large anchorages or precast elements inside the forms,
pressures may be as high as the face pressure of the pump piston.
33 DESIGN
For formwork materiais with limited reuse, allowable stresses specified in the appropriate design d e s or
for temporary loads on permanent st~cturesmay be used. Where there will be a considerable number of formwork
reuses or where formwork is fabricated from materiais such as steel, a i d n u m , or magnesium, it is recommended
that the formwork be designed as a permanent structure carrying permanent loads.
3.4 CONSTRUCTION
3.4.2 Tolerances
Dimensional tolerances for cast-in-place concrete bridges prescribed by ACI 117 are as foiiows:
41
AC1 Committee 347 defines four classes of formed surfaces, shown in Table C3.2. Class A is suggested
for surfaces prominently exposed to public view, where appearance is of special hportance. Class B is intendeú
for coarse-textured concrete formed surfaces intended to receive piaster, stucco, or wainscoting. Class C is a general
standard for permanently exposed surfaces where other fmishes are not specified. Class D is a minimum quality
requirement for surfaces where roughness is not objectionable, usually applied where surfaces will be permanently
concealed.
Table C3.2 Permitted Irregularities in Formed Surfaces
(Checked with a 5-ft Template)"3)
Type of irregularity Class of surface
Abrupt
Conversion: 1 io. = 25.4 mm, 1 ft = 0.3048 m.
3.4.3 Joints
In continuous bridges, with center spans that exceed 150 ft (45.7 m), the positive and negative moment areas
should be poured separately, with a transverse consbuctionjoint installed near the point of dead load counterflexure.
The placing sequence should be determined on an individual basis and shown on the Contract Documents. Positive
moment regions should be placed first to avoid separation of the deck at the construction joint and to limit deck
cracking in the negative moment region.
On wide bridges, a longitudinal bonded construction joint may be placed at the edge of an intermediate
traffic lane. Placement of a joint within a traffic lane should be avoided. The joint should be located within the
center half of the deck slab.
Shoring und cenfering removal: should follow recommended practices in Sections 3.5 and 3.7 (see
committee report). In no case should supporting forms and shores be removed from horizontai members before
concrete strength is at least 70 percent of design strength, as determined by field-cured cylinders or other approved
methods, unless removal has been approved by the Engineer. In continuous structures, support should not be released
in any span until the first and second adjoining spans on each side have reached the specified strength.
Form removal: forms for ornamentai work,railings, parapets, and vertical surfaces that require a surface
finishing operation should be removed not less than 12 hours, nor more than 48 hours, after casting the concrete,
depending on weather conditions. Bulkheads at constructionjoints should not be removed for a period of 15 hours
after casting adjacent concrete. Fomis under slab spans, beams, girders, and brackets must not be removed until the
concrete has attained at least 70 percent of its design strength.
42
4.1 GENERAL
Excavations required for construction of foundations and any 0îhe.r below-grade components of structures
are made with sloping sides or with verticai or near vertical sides, depending on severai factors such as available
space, type of soil, water table, depth of cut, duration of the work, etc. In al1 cases,the conditions must provide for
stability and protection of workmen as well as the newly constmcted and adjacent existing structures. OSHA has
specified certain minimum slopes for the various types of soils and shoring requirements far vertical-sided trenches.
However, actual of site soils and neighboring conditions may require supplementary measures such as flaüening of
slopes, dewatering, and additional bracing.
The influence zone of surcharge pressures will depend on the type of soil. In weak soils, the zone of
influence may be flatter than 45" from the base of excavation.
The formulae for laterai pressures given in Section 4.3 are for the simple case of a vertical cut in
homogenous ground with a level surface. For complicated geometry, either a simplified model can be made, or an
analysis can be done using the actual specific geometry and formulae given in sîandard textbooks.
The type of retaining structure is usually selected by the Contractor. nie selected scheme must satisfy the
protection requirements of the constructed and existing facilities and, of course, the workmen. Ground water control
is an essential element for maintaining the stability and support capacity of the sous. Soil retaining schemes may
include soil stabilization by grouting, freezing, soil nailing, etc. Trench boxes installed in overexcavated trenches
do not prevent ground movements. Their primary objective is protection of workmen and the installations within
the trench box.
Charts and graphs are available in many textbooks for active and passive earîb pressure coefficients related
to the soil angle of internal friction, angle of friction between the wall element (for example, sheetpiles) and the soil,
inclination of the surcharge or bacWiií, and the inclination of the wall. Various design simplificaíions are often made
in the surcharge geometry to utilize the available earth pressure coefficient charts.
For very rigid retaining structures, ground movements may not be sufficient to mobilize active pressures.
In such cases, the design should consider the higher at-rest pressures. If the retaining wall is restrained by
prestressed anchors, high pressures are usually induced at the anchor location. Fárih pressure distribution wouId be
irregular and different from the usual triangular pattern of active or at-rest state. Such cases should be designed by
an experienced geotechical engineer.
The wali movements given in the specification are for rotation about the bottom of the excavation. If the
top of the retaining structure is restrained and it acts as the fulcrum for rotation, then the earth pressure distribution
is no longer triangular and a higher pressure occurs at the location of,the support.
Cohesionless Soils: The angle of internal friction for a cohesionless soil may be estimated from standard
penetration tests and charts given in many soil mechanics textbooks and also in NAVFAC DM-7jn) Careful
evaluation of loose layers or zones is recommended because they may act as the weak zone of a potential slide.
43
Cohesive Soils: Tension cracks and fusures, etc. in cohesive soils can destroy the cohesion. Cohesion is
also lost from exposure to weather, pore pressure dissipation, erosion, remolding, and other construction activities.
Hence, a minimum active pressure coefficient of 0.25 has been specified. Where free ground water can exist, eartb
pressures should be determined for the buoyant unit weight of the soil below the water table, and separate hydrostatic
pressures added to the submerged soil piessures to determine the total earth pressure.
Mixed Soils: B e above commentary for cohesive soils is also applicable to the case of mixed soils.
Many published empirical fornuias are available for at-rest earth pressure coefficient. The selected value
should be consistent with local practice. Soil type and stress history have a significant effect on this coefficient.
Hydrostatic pressures should be added below the water table.
4 3 . U Passive Pressures
Cohesionless Soils: Passive pressure coefficients for various geometries and angles of internal friction and
wali friction can be obtained from charts given in many soil mechanics textbooks and handbook. in computing the
pixsive pressures below the water table, use buoyant unit weight of the soil and add hydrostatic pressure. The angle
of internal friction for the soil should be estimated conservatively. Charts are available in textbooks that relate the
angle of internal fiction to the relative density or standard penetration test values. Seepage gradients will reduce
the passive pressure.
Cohesive Soils: The formula given for the passive pressure is for undrained conditions. Pore pressure
dissipation can reduce îbe passive resistance significantly. For long duration exposure, passive pressures should also
be evaluated for the drained effective friction angles using the formulas for cohesionless soils and the design based
on the lower pressures. Ground water table conditions must also be considered in the analysis of earth pressures.
Mixed Soils: The above commentary for cohesionless and cohesive soils is also applicable to the mixed
soils. Hydrostatic pressures in cohesionless layers interbedded in cohesive layers can cause uplift and heaving and
reduce passive pressures significantly. The design should consider relief of uplift pressures, as appropriate.
Bracing should be designed for various stages of the excavation, corresponding to the cuts necessary to
install the braces at each level. The uppermost stage is analyzed for a cantilever condition, using active pressures.
The next stage with a single brace is also analyzed using active pressures and passive pressures. The b r a d case
empirical diagrams are generally used for conditions of two or more levels of bracing.
The location of the hinge point fur determining reactions at bracing levels may be estimated from the
position of net zero pressure (where the passive pressure equals the active or the empirical design pressure). The
wali elements must have sufficient embeäment below the assumed hinge position to obtain passive reaction greater
than the required toe reaction.
The design of braces should include allowances for thermai changes from ambient temperam,
misalignments, and impact from construction activities.
Surcharges near an excavation are varied in form (for example, existing foundations, proposed foundations,
embankments, and construction equipment). Ground pressure on the crane tracks or pads vary during the operation
of the crane. Surcharge effects should be analyzed for the most severe loading conditions. Charts are available in
many soil mechanics textbooks and handòook for analysis of iaterai pressure due to various configurations of
loadings.
44
4.4 STABILITY
Where simplified analyses indicate critical stability conditions, methods for improvement of the soil
conditions should be implemented. These methods depend on soil, ground water, depth of cut, and many oîher
factors. Consultation with experienced geotechnical engineers is recommended for such a condition.
4.5 COFFJ3RDAMS
The shape and size of a cofferdam is usually selected by the Contractor. The minimum size should be
sufficient to construct the specified foundation. If piled foundations are to be constructed, strut and waler locations
should be adjusted to allow instailation of the piles.
Assumptions made in the design of cantilever walls should be shown on the drawings. This is particularly
important for surcharges, depths of cuts, water table, and dewatering requirements. In the case of cohesive soils,
passive pressure on the embedded portion of the wall shall not exceed 2S, in the case that the active pressure at the
cut level on the soil side (i.e., yH - 2C) is negative.
Design assumptions should be clearly indicated on the drawings so that constructionpersonnel do not violate
the assumptions, and variations from the design assumptions are approved by the Engineer.
45
$%%;;e
m m
O 0 0 0
M M M M 8888
v i m v i v i
Q I ~ O D W
"S m
8 7
m 8
w
47
2
Y
2
W-
Y
Y)
d
Y
W
sM.
'i
a
f
i!
B
.-a
CI
3
B
2 2 2 2
W W W W
O 0
sss1oif
0 0
8888 1
n
.s
i
a
f
4 4
48
APPENDIX B
Members with concentrated loads applied n o d to one $unge and symmetric to the web shall
have a flange and web proportioned to satisfy the local flange bending, web yielding strength, web
crippling, and sidesway web buckling critena of Sections K1.2, K1.3, K1.4, and K1.5. Members
with concentrated loads applied to bofhflanges shall have a web proportioned to satisfy the web
yielding, web crippling, and column web buckling criteria of Sections K1.3, K1.4, and K1.6.
Where pairs of stiffeners are provided on opposite sides of the web, at concentrated loads, and
extend at least half the depth of the member, Sections K1.2 and K1.3 need not be checked.
For column webs subject to high shears, see Section K1.7;for bearing stiffeners, see Section K1.8.
A pair of stiffeners shall be provided opposite the tension fiange or flange piate of the beam or
girder ft.aming into the member when the thickness of the member flange is less than:
0.4 2
where F, = column yield stress, ksi;
Pb, = the computed force delivered by the fiange or moment connection plate
multiplied by 5 4 when the computed force is due to live and dead load oniy, or
by 4/3, when the computed force is due to live and dead load in conjunction with
wind or earthquake forces, kips.
If the length of loading measured across the member flange is less than 0.15b, where b is the
member fiange width, Equation K1-1 need not be checked.
Bearing stiffeners shall be provided in beams and welded plate girders if the compressive stress
at the web toe of the fillets resulting from concentmted loads exceeds O.óóF,..
IO.óóFy
tJN + 5Æ)
b. When the force to be resisted is a concentrated load applied at or near the end of the
member:
I 0.66Fy (KI-3)
f,(N + 2.5Æ)
where R = concentrated load or reaction, kips;
f, = thickness of web, in.;
N = length of bearing (not less than Æ for end reactions), in.;
k = distance from outer face of flange to web toe of fiilec in.
49
Bearing stiffeners shall be provided in the webs of members under concentrated loads, when the
compressive force exceeds the following limits:
a. When the concentrated load is applied at a distance not less than dn from the end of the
member:
r 1
b. When the concentrated load is applied less than a distance dn from the end of the
member:
r 1
(Kl-5)
If stiffeners are provided and extend at least one-half the web depth, Equations K1-4 and
K1-5 need not be checked.
Bearing stiffeners shall be provided in the webs of members with flanges not restrained against
relative movement by stiffeners or lateral bracing and subject to concentrated compressive loads,
when the compressive force exceeds the following limits:
a. If the loaded fiange is restrained against rotation and (d,/f,,,)/(l&,)is less than 2.3:
-I
b. If the loaded flange is not restrained against rotation and (d,/tJOf) is less than 1.7:
(Kl-7)
Equations K1-6 and K1-7 need not be checked providing fdJtW)/Vbf)exceeds 2.3 or 1.7,
respectively, or for webs subject to uniformly distributed load.
50
A stiffener or a pair of stiffeners shall be provided opposite the compression flange when the web
4100t:cFYc
depth clear of fillets d, is greater than: 61-8)
Pbf
Members subject to high shear stress in the web should be checked for conformance with
Section F4.
Stiffeners shall be placed in pairs at unframed ends or at points of concentrated loads on the
interior of beams, girders, or columns if required by Sections K1.2 through K1.6, as applicable.
If required by Sections K1.2, K1.3, or Equation K1-9, stiffeners need not extend more than one
half the depth of the web, except as follows:
If stiffeners are required by Sections K1.4 or K1.6, the stiffeners shall be designed as axially
compressed members (columns) in accordance with requirements of Section E2 with an effective
length equal to 0.75h, a cross section composed of two stiffeners and a strip of the web having a
width of 25twat interior stiffeners and 12twat the ends of members.
When the load n o d to the flange is tensile, the stiffeners shall be welded to the loaded flange.
When the load normal to the flange is compressive, the stiffeners shall either bear on or be welded
to the loaded flange.
When flanges or moment connection plates for end connections of beams and gir&rs are welded
to the flange of an I- or H-shape column, a pair of column-web stiffeners having a combined cross-
sectional area A,, not less than that computed from Equation K1-9 shall be provided whenever the
P -F t (t + 5k)
calculated value of A , is positive:Abt = r
Stiffeners required by the provisions of Equation K1-9 and Sections K1.2 and K1.6 shall comply
with the following criteria:
1. The width of each stiffener plus M the thickness of the column web shaü not be less than
in the width of the flange or moment connection plate delivering the concentrated force.
2. The thickness of stiffeners shall not be less than Y, the thickness of the flange or plate
delivering the concentrated load.
3. The weld joining stiffeners to the column web shall be sized to carry the force in the
stiffener caused by unbalanced moments on opposite sides of the column.
-
Reproduced from Manual of Steel Construction Allowabk Stress Design, Ninth Edition, copyright O 1989, with the
permission of the American Institute of Steel Consíruction, Inc.
51
APPENDIX C
Sec. 2314. The minimum basic wind speed for determining design wind pressures shall be taken h m
Figure No. 23-1. For those areas designated in Figure No. 23-1as special wind regions and other areas where local
records or terrain indicate higher 50-year (meanrecurrence interval) fastest-mile wind speeds, these higher values
shall be the minimum basic wind speeds.
Sec. 2316. Design wind pressures for structures or elements of structures shall be determined for any height
in acmrâance with the following formula:
p = C,C,qJ (16-1)
where P = design wind pressure;
Ce = combined height, exposure, and gust factor coefficient as given in Table No. 2342
C, = pressure coefficient for the structure or portion of structure under consideration as given in
Table No. 23-H,
q, = wind stagnation pressure at the standard height of 30 ft (9.1 m) as set forth in Table No. 2 3 3
I = importance factor (assume equal to 1.0 for falsework).
Open-Frame Towers
Sec. 2319. Radio towers and other towers of trussed construction shall be designed and constructed to
withstand wind pressures specified in this section, multiplied by the shape factors set forth in Table No. 23-H.
53
54
--
Notes:
(a) Linear interpolation between wind speed contours is acceptable.
@) Caution in use of wind speed amtours in mountainous regions of Alaska is advised.
(c) Wind speed for HawW is 80, Puerto Rico is 95, and the Virgin Islands is 110.
(d) Wind speed m a y be assumed to te constant between the coastline and the nearest inland contour.
(e) Conversion: 1 mph = 1.609 km/hr
-
Figure No. 23-1 Minimum Basic Wind Speeds in Miles Per Hour
Reproduced from the 1991 edition of the ünifonn Building Code, copyright 8 1991, with the permission of the piblisher, the Internacional
Conference of Building Officials.
55
D e f ~ t i o n . Fastest-mile wind speed at 33 ft (10 m) above the ground of terrain Exposure C (see 6.5.3.1) and
associated with an annual probability of occurrence of 0.02.
Section 65.2. The basic wind speed V used in the determination of design wind loads on buildings and other
structures shall be as given in Figure 1 for the contiguous United States and Alaska and in Table 7 for Hawaii and
Puerto Rico except as provided in 6.5.2.1 and 6.5.2.2. The basic wind speed used shall be at least 70 mph
(113 kmfhr).
- 0.00256 K, (IV)’;
- velocity pressure coefficient as given in Table 6;
- importance factor (assume equal to 1.0 for faisework);
- basic wind speed obtained from Figure 1 and Table 7, in miles per hour;
- gust response factor as given in Table 8;
- force coefficient as given in Tables 14 and 15;
- the projected area normal to the wind.
I
0.37 I
0.77 I
1.29 1.67
56
Exposure B. Urban and suburban areas, wooded areas, or other tem with numerous closely spaced obstnictionS
having the size of singlefamily dwellings or larger. Use of this exposure category shall be limited to those areas
for which terrain representative of Exposure B prevails in the wind direction for a distance of at least 1,500 ft
(460m) or 10 times the height of the building or structure, whichever is greater.
Exposure C. Open terrain with scattered obstruction having heights generally less than 30 ft (9 m). This category
includes flat open country and grasslands.
Exposure D. Flat, unobstructed areas exposed to wind flowing over iarge bodies of water. This exposure shall apply
only to those buildings and other structures exposed to the wind coming from over the water. Exposure D extends
inland from the shoreline a distance of 1,500 ft (460 m)or 10 times îhe height of the building or structure, whichever
is greater.
-
Table 7 Basic Wind Speed, V
Location
Hawaii
Puerto Rico
Notes:
(a) 'Ihe unique topographical features common to the islands of Hawaii and Puerto Rico suggest that it may be advisable to adjust the valm
given in Table 7 to account for locally higher winds for srnudures sited near mountainous terrain, gorges, and ocean promt&es.
(b) Conversion: 1 mph = 1.609 kmlhr.
-
Table 8 Gust Response Factors, Gh and G,
Height above G,,and G,
ground level,
Exposure A Exposure B Exposure C Exposure D
(ft)
Notes:
(4 For main wind-force resisting systems, use building or simdure height h = Z.
@) Linear interpolation is acceptable for intermediate values of z.
(4 Value of gust response factor shall be not less than 1.0.
(4 Conversion: 1 ft = 0.3048 m.
57
0.025 to 0.44
0.45toto1.0
0.7 0.69
square
Towers
4.1 - 5 . 2 ~
1.3 + 0 . 7 ~
Ç
Triangular
Towers
3.7 - 4 . 5 ~
1.0 + E
459 =
The area consistent with these force coefficients is the solid area of the front face projected n o d to
Force coefficients are given for towers with structurai angles or similar fiat-sided members.
For towers with rounded members, the design wind force shall be determined using the values in the table
For triangular section towers, the design wind forces shall be assumed to act normai to a tower face.
For square section towers, the design wind forces shall be assumed to act normal to a tower face. To allow
for the maximum horizontal wind load, which occurs when the wind is oblique to the faces, the wind load
acting nomial to a tower face shall be multiplied by the factor 1.0 + 0.75 E for E < 0.5 and shaü be assumed
to act along a diagonal.
Wind forces on tower appurtenances, such as ladders, conduits, lights, elevators, and the like, shall be
calculated using appropriate force coefficients for these elements.
For guyed towers, the cantilever portion of the tower shall be designed for 125 percent of the design force.
A reduction of 25 percent of the design force in any span between guys shall be made for demination
of controlling moments and shears.
58
NOW?:
(a) Values are fastest-mile speeds at 33 fi (10 m) above ground for exposure category C and are associated with an annual probability
of 0.02
@) Linear interpolation between wind speed contours is acceptable.
(c) Caution in the use of wind speed contours in mountainous regioos of Alaska is advised.
(4 Conversion: 1 mph = 1.609 kmh
-
Figure 1 Basic Wind Speed (mpb)
ReProQid from MUiimrrm Duign LwrLI for Buildings and Other Structures, copyright 8 1990, with the permission of the American Society
of civil Engineers.
59
Section 11123.2 The basic wind speed, in miles per hour, to be used for the location of the building or other
structure shall be determined by Figure 1112.3.2. Basic wind speed for special wind regions indicated on
Figure 1112.3.2 shall be in accordance with local jurisdiction requirements.
Section 1112.3 The design and wind pressure for the main windforce-resisting system shall be determined as
follows:
Pd = Pe I2 cp
where Pe - effective velocity pressure, including gust effect as tabulated in Table 1112.3.3a(l) for
Exposure B and Table 1112.3.3b for Exposure C
I -
- importance factor of the building or other structure (assume equal to 1.0 for falsework)
CP - external pressure coefficient to be used in determination of wind loads for buildings or
for other structures (see Figure 1112.2a and Tables 1112.2~through 1112.2h)
Exposure B: Urban and suburban areas, wooded areas, or other terrain with numerous closely spaced
obstructions having the size of single-famly dwellings or larger. Use of this exposure category shall be limited to
those areas for which terrain representative of Exposure B prevails in the upwind direction for a distance of at least
1,500 ft (460 m) or 10 times the height of the building or structure, whichever is greater.
Exposure C Open terrain with scattered obstructions having heights generally less than 30 ft (9.1 m). This
category includes fiat, open country and grasslands.
Force coefficients are given for towers with structurai angles or similar flat-sided members.
For towers with rounded members, the design windforce shall be determined using the values in the above table multiplied by the
following factors:
€4.29, factor = 0.67
0.3~&<0.79,facta = 0.67s + 0.47
0.8c&<1.0, factor = 1.0
F a íriangulu section towers, the design windforces shall be assumed to act normal to a tower face.
For square section towers, the design windforces shall be assumed to ad normal to a tower face. To allow for the maximum horimntal
wind load which occurs when the wind is oblique to the faces, the wind load acting normal to a tower face shall be multiplied by the
factor 1.0 + 0 . 7 ~5 0.5 and shall be assumed to act along a diagonal.
Windforax on tower appurtenances, such as ladders, conduits, lights, elevators and the like, shall be calculated using approPnateforce
coefficients for these elements.
F a guyed towers, the cantilever portion of the tower shall be designed for 125 percent of the design windforce.
A reduction of 25 percent of the design windforce in any span between guys shaU be made for determination of controlling moments
and shears.
Notation:
E- Ratio Of solid na to GOSS Of tower.
60
0-20
20-40 10 13 17 21 25
40-60 -13 I 16 I 21 I 26 I 31
60- 100 14 18 23 28 34
-
Table 11123.3b EFFECTIVE VELOCITY PRESSURES î. (lb@)
FOR BUILDINGS A N D STRUCTURES (EXPOSURE Cl
0.20
Irsó"
I 1 5 1 2 5
i<:Wind speed
90
25
100
31
110
37
20-40 16 27 27
40-60 19 31 31
60-100 ~~ [ 20 I 33 33 ' 41 I 50
61
Notes:
(a) Values are fast&-mile speeds at 33 ft (10 m) above ground for exposure category C and are associated with an annual probabiiity
of 0.02.
(b) Linear interpolation between wind speed contours is acceptable.
(cl Caution in the use of wind speed contœus in mountainous regions of Alaska is advised.
(4 Conversion: 1 mph = 1.609 knuhr
-
Figure 111233 Basic Wind Speed ( d e s per hour)
BOCA Nationai Building Codel1990,copyrighted 1989, Building Officials and Code Administrators Inteniational. Inc. hblished by arrangements
with author. All rights repervert
62
APPENDIX D
Since all the structural loads of the falsework are eventually transferred to the soil or rock underlying the
falsework foundations,a subsurfaceinvestigation is necessary to determine the load-supporting ability of the various
strata of soil or rock. Before designing the faisework foundations, it is necessary to determine the type,depth, and
properties of the various soil or rock formations. If a foundation investigation has aiready been completed for the
pennanent structure, this informaîion can be used for the design of the falsework foundations.
In the absence of site-specific information, additional soil exploration is recommended. The subsurface
exploration can be tailored for each project and could include any of the following methods:
A. The best information is generally obtained from soil borings completed throughout the area of the
falsework foundations. The borings should be extended in depth to a level where the induced
foundation pressures from the new loading will be less than 10 percent of the overburden pressure,
but not less than 15 ft (5 m). Soil samples should be obtained at intervals not exceeding 2% ft
(0.8 m). The sampling should be done by conventional methods, resulting in test samples that are
indicative of the strength and compressibility of the soil deposits. This should include standard
penetration resistance testing (AASHTO T206-87), briefly described in Section D.3. In situ tests
provide sufficient information for foundation design even though test samples are not obtained.
These tests include cone penetrometer testing (ASTM D3441-86), pressuremeter testing (ASTM
D4719-87). and dilatometer testing. Samples obtained by Shelby tubes (AASHTO T207-87) in
cohesive soils are also acceptable when accompanied by appropriate laboratory tests, including the
unconfined compressive strength test (AASHTO T208-90) and water content testing (AASHTO
T265-86). Disturbed samples h m auger cuttings are not considered acceptable.
B. Test pits can be dug throughout the area to investigate the various soil or rock formations. Test
pits should be used to supplement the soil-boring investigation wherever erratic or discontinuous
subsurface conditions are present. It is easier to determine the thichess and character of these
deposits from a large excavation than from examination of small diameter samples. The person
logging the test pits should not only be capable of identifying the various strata, but should have
some means for determining the relative density of each deposit. The hand penetrometer is
sufficient for determining the shear strength of cohesive soils. Section D.4 provides guidelines for
estimating the unconfined compressive strength of cohesive soils based on field observations. The
determination of the relative density of granular soils is more difficult and may be subjective on
the part of the observer. However, techniques such as the dynamic cone penetrometer can be used
for this purpose. Alternatively, field density tests can be performed within the granular formations
(AASHTO T191-86).
C. Field tests can be undertaken and used as a guide where either the borings or test pits indicate
questionable surface support conditions. This should include proof-testing of the ground surface
with a fully loaded dump truck that has a minimum weight of 20 tons (18,000 kg). As the dump
truck traverses the area, the amount of ground deflection under loading should be observed.
Deflections of 2 in. (50 mm) or less under wheel load traffic are indicative of reasonably good
support conditions. Large deflections and severe rutting are indicative of very poor support
conditions.
63
Plate load tests can be performed within the potential bearing strata for the foundations. The plate
load test consists of a plate with a minimum 12-in. (305-mm) diameter with a jack used to provide
a force and a buck or other heavy object used as a reaction. Deflections should be measured with
either survey instruments or dial gauges. As the jack loads are applied, deflection readings should
be taken at the design load and at twice the design load. The plate load test only measures the
subgrade reaction of the soil within a depth of 1%times the diameter of the plate. Other deeper
strata could also affect future performance of the foundation.
D.2 Relative Density of Granular Deposits
In the United States, the most commonly used method of determining relative density of granular &posits
is the standard penetration test (SPT). It is made by dropping a 140-lb (63.5-kg)hammer onto the drill rods from
a height of 30 in. (0.76 m). The number of blows required to advance a split barrel sampling tube 1 ft (0.30 m) is
called the standard penetration resistance. AASHTO T206-87describes the test procedure. Table D.l relates the
SPT to relative density.
Note: The standard penetration resistance (SPT) values correspond to an effective overburden pressure
of 1 tsf (96kN/m2). The correction factor, CN, to be applied to field S P ï values for other
pressures is given by:
where is the effective vertical overburden pressure in tsf at the elevation of the SPT test. This
equation is valid for 6 2 0.25 tsf (24 kN/m2).
In certain mas of the country, the cone penetration test (CFï) is used for soil exploration. The approximate
relationship between SPT and C P ï is shown in Table D.2.
-
CPï
Soil Type SFT
Silts, sandy silts, slightly cohesive silt-sand mixtures 2
Clean fine to medium sands and slightly silty sands 3 to 4
Coarse sands and sands with little gravel 5 to 6
Sandy gravels and gravels 8 to 10
64
The most important index property used to describe cohesive soils is "consistency," which is qualitatively
described as "soft," "medium," "stiff," or "hard." The consistency of a cohesive soil can also be quantitatively in
terms of unconfined compressive strength. Table D.3 reiates the qualitative terms for consistency to the quantitative
values of unconfined compressive strength.
Unconfined Compressive
Consistency Field Identification
Very soft Easily penetrated severai inches by fist Less than 0.25
Soft Easily penetrated severai inches by thumb 0.25 - 0.5
Medium Can be penetrated severaí inches by thumb 0.5 - 1.0
wiîh moderate effort
Stiff Readily indented by thumb but penetrated 1.0 - 2.0
only with great effort
Very stiff Readily indented by thumbnail 2.0 - 4.0
Hard Indented with difficulty by thumbnail Over 4.0
Notes:
(4 ASTM D2488 has a slightly Merent criteria for describing consistency.
@) Conversion: 1 tsf = 96 kN/mz
The soil classification system most widely used by foundation engineers in the United States is known as
the Unified Soil Classification System and has been adopted by the American Society for Testing and Materiais as
a Standard Test Method for Classification of Soils for Engineering Purposes, ASTM D-2487. 'Ibe main points of
ASTM D-2487 are summarized in Table D.4.
According to the Unified System, soils are categorized by particle-size and plasticity characteristics.
Because this system is based on properties of the grains and of the remolded material, it does not fully describe the
engineering properties of the intact material as encountered in the field. However, it permits reliable classification
without extensive testing, and provides useful information about soils that bave been properly classified by this
method.
Certain soil deposits may experience movements that are not related to loading. These movements are due
to the geologic composition of the deposits or climatic effects. The foundation designer should be cognizant of local
problem soils and incorporate measures to reduce soil deformations.
In portions of the western and southern United States, collapsible soil deposits are sometimes encountered.
These are generally fine sands and silts that are deposited in a very loose condition. A low amount of cementation
holds the soil particles in the loose condition until they become wetted. Following wetting, the soils collapse into
a denser state, thereby leading to significant settlements.
65
Table D.4
Soil Classification according to the Unified Soil Classification System (ASTM D-2487)!"'
Group Typical
Major Divisions Symbols Names Classification Criteria
C$
GW
Well-graded gravels and
gravel-sand mixtures.
little or no fines
CX
'
-
E
C. = Dto/Dlo
DIOX D u
Greater than 4
Between I and 3
66
Throughout many parts of the United Siates, active soil deposits are present that can either significantiy
swell upon wetting or shrink upon drying. Shallow foundations supported upon these deposits should either be
located below the limit of the moisture content variations, or the area around the foundation should be protected from
an increase or decrease in moisture content.
In the northem portions of the United Scates where cold weather prevails, &zing of the bearing strata can
occur and cause movements of falsework foundations. Sandy and silty soils are more susceptible to frost than other
deposits, so foundations bearing upon these materiais in cold weather shall be protected against frost penetrating into
îhe ground. Protection can be afforded by a cover of fill or insulation such as styrofoam.
Fill deposits can vary widely in foundation support. If the fill was properly compacted in place, the support
can be excellent, similar to a stiff clay or a medium dense sand. On the other hand, loosely dum@ fill without
compaction can be very compressible, similar to deposits consisting of a soft clay or loose sand. If not properly
controlled, the fill can also be variable, with some weak pockets contained within a generally f m soil mass. This
is especially true for cohesive soil deposits, where the water content at the time of placement is crucial to the degree
of compaction that is achieved. For cohesive fill deposits, a thorough exploration program is necessary not only to
determine the properties of the cohesive deposits, but also the uniformity of the entire fill mass.
For ali deposits consisting of peat, organic silts, or very soft clays, and for some deposits with potentiai
problem soils, such as collapsible or frost-susceptible soils, extended foundationswill be necessary to carry the loads
through the weak or problem deposits to more suitable foundation-bearingmaterial. These extended foundationsshall
consist of very deep footings, drilled piers, or piles. Site improvement of organic soils and very soft clays by
compaction or other means is not considered practical.
Where deep foundations will be used, the subsurface exploration shall extend to a depth of at least 10 ft
(3 m) below the planned base of the foundation (unless rock is encountered at shallower depth) so that side Enction
and end-bearing capacity of the extended foundation can be calculated. The deep foundation design shall consider
lateral as well as vertical loads.
If piles are to be used, the driving criteria shall be selected on the basis of a wave equation analysis or an
accepted driving formula. The penetration data of the last 5 ft (1.5 m) of driving shall be recorded and submitted
to the designer of the falsework foundations. Guidelines for the design of pile foundations are presented in chapter 4
of AASHTO Standard Specijïcations for Highway Bridgesj3)
If drilled piers are used, the base of each of the drilled piers shall be monitored to see that the proper
bearing stratum has been reached and that the base of the drilled pier excavation is clean and free of sloughing and
water prior to being filled with concrete. The strength of the bearing stratum shall be tested by the monitoring
person and the results submitted to the designer of the falsework foundations. Guidelines for the design of drilled
piers are presented in the American Concrete Institute publication Suggested Design and Construction Procedures
for Pier Foundations, AC1 336.3R-72jM’
Standard Method of Test for Density of Soil In-Place by the Sand-Cone Method, (AASHTO T191)
Standard Method for Penetration Test and Split-Barrel Sampling of Soils, (AASHTO “206)
Standard Method for í%in-Walled Tube Sampling of Soils, (AASHTO “207)
Standard Method of Test f o r Unconfined Compressive Strength of Cohesive Soil, (AASHTO T208)
Standard Method of Test for Laboratory Determination of Moisture Content of Soils, (AASHTO T265)
Method of Deep, Quasi-Static, Cone and Friction-Cone Penetration Tests of Soil, (ASTM D-3441)
Test Method for Pressuremeter Testing in Soils, (ASTM D-4719)
67
APPENDM E
Section 2.133
Tension, axial, and flexural . . . . . . . . . 22,000psi Tension, axial,and flexural ..... 152,000Nimm2
Shear on gross section of web of rolled Shear on gross section of web of rolled
shapes . . . . . . . . . . . . . . . . . . . . . . . 14,500psi shapes . . . . . . . . . . . . . . .. . . . 100,000Nhnm2
Web crippling for roileú shapes . . . . . . 16,000psi Web crippiing for roiled shapes .. 110,000 N/mm2
Section 235.2
Section 3 3 3
Section 3 3 3 3
with a maximum of 3,000 psf, a minimum of 600psf, with a maximum of 144,OOO N/m2, a minimum of
but in no case greater than 150 h. 29,000 N/m2, but in no case greater than 23,600h.
For walls with a rate of piacement less than 7 ft per For w a s with a rate of placement less than 2.1 m per
hour: hour:
with a maximum of uxx) psf, a minimum of 600psf, with a maximum of %,000N/m2, a minimum of
but in no case greater than 150 h. 29,000 N h 2 , but in no case greater îhan 23,600 h.
69
U.S.CUSTOMARY METRIC
For wails with a rate of pîacement of 7 to 10 ft per For walls with a rate of placement of 2.1 to 3.0 m pet
hour: hour:
with a maximum of 2,000 psf, a minimum of 600 psf, with a maximum of %,OOON/m', a minimum of
but in no case greater than 150 h. 29,000 Nh', but in no case greater than 23,600 h.
p in psf; p in N/m$
R in fvhr; R in m/hr,
T in OF. T in OC.
Section 43.1.2
Pa = $4 - 2 c (4-2) Pa = $4- 2 c
Pa in psf; Pa in kN/m'
y in pcf; y in W h 3
H in ft; H in m;
C in psf; C in W/m2;
Qu in psf. Q,in kNhn2.
Section 43.13
Section 43.1.4
Pp = q y H (4-5) PP = E$IIK
P* in psf; Pp in kN/m$
y in pcf; y in kN/m3;
H in ft. H in m.
Pp = yH + 2 c (4-6) Pp = yH + 2 c
Pp in psf; Pp in kN/m';
Yinpcf; y in icNhm3;
H in ft; H in m;
c in psf. C in W/m'.
70
. Appendix B, Section 2
0 . 4 YC
j F (Kl-1) 0 . 4 dY C F
Appendix B, Section 4
71
t, in in.; t, in mm;
N in in.; N in mm;
d in in.; d in mm;
t in in.; 4 in mm;
Fw in ksi. Fw in N h '
Appendix B, Section 5
r 1 r 1
R = ,?li
R in kips;
+ 0.4[%]] (Kl -6) R =
I[?.
R in N,
+ CI.^[^;,:]
f, in in.; f, in mm;
h in in.; h in mm;
4 in in.; dc in mm;
1 in in.; linmm;
b, in in. bf in mm.
r 1 r 1
f, in in.; f, in mm;
h in in.; h in mm;
dc in in.; d, in mm;
1 in in.; linIlUn;
bf in in. bf in mm.
Appendix B, Section 6
, *
D
'bf
dc in in.; dc in mm;
C, in in.; tp, in mm;
FYcin ksi; Fycin Nh';
Pbfin kips. Pb,in N.
72
U.S.CUSTOMARY METRIC
Appendix B, Section 8
A, in in.) 4 in mm2;
Pbfin kips; Pbfin N,
Fycin ksi; Fycin N b 2 ;
kcin in.; k c in mm;
in in.; tinmm;
k in in.; k in mm;
i
FyI1in ksi. Fy,,in N h 2 .
Appendix C, Section 2316
F = q$3,CfAf F = &G,CfAf
F in lb; F in N,
9,in psf; e in N/m2;
A, in fe. A, in m2.
C, = 0.77 log,, 20
- C, = 0.77 log,, 1920
-
P P
5 in tsf. p in kNh2.
13
10. BRïïiSH STANDARDS INSTITUTION, Code of Practice for Falsework (BS 5975:1982), London,
England, 1982.
11. WORKS AND DEVELOPMENT SERVICES CORPORATION (NZ)Ltd.,Code ofpractice for Falsework,
Volume 1-Code und Appendices, CDP 708/A (internal document), Wellington, New Zealand, 1988.
13. AC1 COMMITIEE 347, "Guide to Formwork for Concrete (AC1 347R-88)," ACZ Manud of Concrete
Practice, Part 2, American Concrete Institute, Detroit, MI, 1989.
14. M. K. HüRD AND AC1 COMMITTEE 347, Formwork for Concrete ( S P 4 Fifth Edition, American
Concrete Institute, Detroit, MI, 1989.
15. AMERICAN NATIONAL STANDARDS INSTITUTE, American National Startdard for Constructionand
Demolition Operations: Concrete und Masonry Work-SafetyRequirements (ANSIA10.9-1983), New YO&
NY, 1982.
75
17. SCAFFOLDING, SHORING, AND FORMING INSTITUTE, ïNC., Recommended Procedure for
Compression Testing of Welded Frame Scaffolds and Shoring Equipment, Publication No. S 102, Cleveland,
OH, 1989.
18. ROSS BRYAN ASSOCLATES, mC., "RecommendedPractice for Precast Presfressed Concrete Composite
Bridge Deck Panels," prepared for the PCI Bridge Producers Committee, Prestressed Concrete Institute
Journal, March/April1988.
19. AC1 COMMïTïEE 117, "Standard Specifcations for Tolerances for Concree Construction and Materials
(AC1 117-go),"ACZ Manual of Concrete Practice, Part 2, American Concrete Institute, Detroit, MI, 1991.
20. UNITED STATES DEPARTMENT OF LABOR, Occupationai Safety and Health Adminismtion,
Occupational Safety and Health StandQrds (Parts I910 and 19261, Washington, DC, 1974.
21. R. B. PECK, W. E. HANSON, T.H. THORNBURN, Foundation Engineering, Second Edition, John Wiley
& Sons, New York, NY, 1974.
22. DEPARTMENT OF THE NAVY, Naval Facilities Engineering Command,Soil Mechanics, Foundations,
and Earth Structures, NAVFAC DM-7, Alexandria, VA, May 1982.
23. AMENCAN SOCIETY FOR TESTING AND MATERIALS, "Specification for General Requirements for
Rolied Steel Plates, Shapes, Sheet Piling, and Bars for Structural Use (ASTM A6)," Philadelphia, PA, 1992.
24. AMEñICAN INS- OF STEEL CONSTRUCTZON, Iron and Steel B e a m 1873 to 1952, Ed, by
H. W. Ferris, New York, NY, 1953.
26. NATIONAL FOREST PRODUCTS ASSOCIATION, NDS Supplement-Design Vabes for Wood
Construction, Washington, DC, 1991.
29. AMERICAN SOCIETY OF CIVIL ENGINEERS, Minimum Design Loads for Buildings and Other
Structures (ASCE 7-88), New York, NY, 1990.
76
33. UNITED STATES DEPARTMENT OF AGRICUL.TURE. Forest Service, Wood Handbook: Wood as un
Engineering Material, Handbook No. 72, Forest Products Laboratory, Washington, DC, 1987 Revision.
34. G. GURFINKEL, Wood Engineering, Second Edition, Kendail/Hunt hblishing Company, Dubuque, IA,
1981.
35. AMERICAN INSTITUTE OF TIMBER CONSTRUCTION, Timber Construction Manual, Third Edition,
John Wiley & Sons, Inc., New York, 1985.
36. AMERICAN PLYWOOD ASSOCIATION, United States Products Standard PS 1-83for Construction &
Industrial Plywood (with Typical APA Trademarks), Form No. H850C, Tacoma, WA, 1983.
&
37. AMERICAN PLYWOOD ASSOCIATION, Concrete Forming, Form No. V345P, Tacoma, WA, 1988.
39. AMERICAN IRON AND STEEL INSTITüïE, Cold-Formed Steel Design Manual, Washington,DC,1986.
41. AC1 COMMITIEE 318, BuiMing Code Requirements for Reinforced Concrete (ACZ 318-89) and
Commentary (ACZ 318R-89), American Concrete Institute, Detroit, MI, 1989.
42. STEEL JOIST INSTITüTE, Standard Specifications, Load Tables, and Weight Tablesfor Steel Joists and
Joist Girders, Myrtie Beach, SC, 1990.
43. SCAFFOLDING, SHORING, AND FORMING INSTITUTE, INC., Guide to Horizontal Shoring Beam
Erection Procedure for Stationas, Systems, Publication No. SH305, Cleveland, OH, 1983.
44. AMERICAN IRON AND STEEL INSTITUTE, Design Manual for Structural Tubing, New York, NY,
1974.
45. AC1 COMMïïïEE 306, "Cold Weaîher Concreting (AC1 306R-88)," ACZ Manual of Concrete Practice,
1 Part 2, American Concrete Institute, Detroit, MI, 1990.
46. AC1 COMMIïTEE 336, Suggested Design and Construction Procedures for Pier Foundations,
AC1 Standard 336.3R-72, American Concrete Institute, Revised 1985.
77 *UsS. G.P.0.:1993-301-717:80354