Software Project Management Unit-3 - 3 PDF
Software Project Management Unit-3 - 3 PDF
UNIT-3 (Lecture-3)
Forward Pass & Backward Pass Techniques
Forward pass
The forward pass is carried out to calculate the earliest dates on which each activity may be
started and completed. Significance-calculation method used in Critical Path Method.
Backward pass
The second stage in the analysis of a critical path network is to carry out a backward pass to
calculate the latest date at which each activity may be started and finished without delaying the
end date of the project. The calculating the latest dates, we assume that the latest finish date for
the project is the same as the earliest finish date that is we wish to complete the project as early
as possible.
Total Float = LS – ES or LF – EF
Total Float shows the difference between the Earliest Start (ES) and Latest Start (LS) of an
activity before the completion date is delayed.