SBA2021 04 Elevated Water Storage Tower Project COMPLETE REPORT
SBA2021 04 Elevated Water Storage Tower Project COMPLETE REPORT
SBA2021 04 Elevated Water Storage Tower Project COMPLETE REPORT
Recommendation
Background
On July 26, 2012, the Town began a MEA, Schedule B Class Environmental
Assessment (EA) to determine the need for increased water storage within the
Town of Shelburne.
Work on this EA continued through 2012 and the Notice of Study completion
was issued in February 2013 indicating that an additional water storage
reservoir was required to meet the Town’s existing and future water storage
demands.
The urgency of this project became more apparent over the past couple years
with water storage levels in the existing tower being depleted during the warm
summer months requiring the need to issue water use bans for the past
several summers.
In 2020, the tower water levels were low enough during August 2020 that
minimum water levels for fire protection became a concern. OCWA required
special permission from MECP to run Wells 7 & 8 concurrently to bring the
water levels back to safe levels.
Based on these factors, a priority was placed on the water storage tower
project. Council approved the design to commence in late 2020 with the goal
of completing design in mid 2021. The construction of an elevated water
storage tower is approximately a 12 month (1 year) project. It is estimated
the project will be completed by mid to late 2022 and just prior to the EA
expiration.
Analysis
The original budget for this capital project was $3.5 Million.
The Request for Proposal (RFP) process which was undertaken in summer
2021 and is summarized in Appendix 1.
The RFP for a new 3,400 cu.m water storage facility was issued and posted on
Merx and Biddingo on June 18, 2021 and closed on July 15, 2021.
The one bid received for $6,754,000 plus applicable taxes was significantly
over the $3.5 Million allocated for the construction budget of this project. A
few factors have led to the significant increase in project costs.
One factor effecting the price was that during the design phase it was
determined that the scope of the site works and watermain connections for
the proposed project required additional and expanded work. The water
system modeling completed as part of the design phase revealed that two
watermain extensions were required to connect the new water tower to the
existing water infrastructure and to create a loop watermain connecting to
both Luxton Way and Franklyn St./Simon St. to ensure sufficient pressures
within the system. Normally a water tower can be connected to just one local
watermain connection.
Also, during the design phase, it was concluded with Town staff that the
preferred location for the water tower was at the rear of the purchased site.
This was strategic with regards to the future use of the public works site as it
provides room for expansion on the site for future cold storage, auxiliary
buildings, etc. However, this did direction did increase the access road and
watermain connection costs to the Luxton Way access location.
Lastly, during the design phase it was determined that the inclusion of a
chemical chlorination system, standby generator and water truck fill were
items that should be included in the new facility. These have been identified
as significant shortcomings of the existing water storage facility, especially
during emergencies.
Based on the pricing received, the total site works and watermain component,
where most of these enhancements to the project are included, resulted in an
increase cost of approximately $900,000 in site works and watermain
extensions.
The watermain looping and site works enhancements were not included in the
original water storage tower budget of $3.5 Million. Had they been known and
then included at the time the project budget would have instead been in the
$4.3 to $4.4 Million range.
The most significant effect on pricing is that COVID has significantly affected
several supply chains. Steel makes up a large portion of this facility. The price
of steel has risen close to 300% from Spring 2020 to Summer of 2021.
The COVID supply chain effect was also seen earlier this year with wood prices
increasing 400% from winter to mid summer. COVID has also caused
significant increases in electrical and mechanical components due to supply
shortages and delivery delays. These have all had a significant effect on the
bid pricing.
These negotiations were completed by SBA and all proposed value engineering
items were reviewed with senior Town staff as well as OCWA. On August 30,
2021, Landmark Structures Co. provided updated proposal costs. Landmark
reduced the base price to $5,983,050 excluding taxes and contingency. While
this revised value is still approximately $2.5M over the original budget and
approximately $1.6M over the anticipated project with the enhanced site
works scope, it does appear to be inline with the current COVID pricing.
A review of a recent tender which closed in June 2021 for the Township of
Mapleton showed a similar increase in pricing due to COVID and steel
increases. The water tower in Mapleton which was approximately 30% smaller
than the tower proposed for Shelburne. In that case the project cost was
approximately $6.5 Million when the estimated budget was $4 Million and this
project had little to no site work related costs.
The bid received from Landmark Structures Co. was reviewed for any
mathematical errors and no errors were found. The contractor also provided
the required Bid Bond and Agreement to Bond amounts required in the RFP
process.
SBA has worked with Landmark Structures Co. on several water tower projects
and can confirm both their professionalism and quality of work on previous
projects. Landmark was also the contractor hired to complete the
refurbishment of the existing water tower in Shelburne.
Financial Impact
Following the EA Notice of Study completion that was issued in February 2013,
footnotes in the Water Capital Budget have identified annually since 2014 the
need for Future Water Storage. The water storage land purchase took place
in 2018 and is located on Luxton Way adjacent to the Public Works Yard. The
source of financing for the water storage construction has always been
identified as long term borrowing.
In the 2021 adopted Water Capital budget, the Water Storage Project was
identified at a cost of $3,461,600 with the project being partially funded by
Development Charges and Reserves leaving the amount of 2.5 million to be
funded by long term debt.
At the July 12, 2021 council meeting, staff report FS 2021-09 outlined that
borrowing from Infrastructure Ontario would be the recommended source of
financing for the long term debt portion. Although the RFP for the water tower
had not closed yet, the following is an excerpt from the motion that was
passed allowing staff to proceed with making application once figures were
known:
“And That Council directs staff to proceed with the Long-Term Borrowing Loan
Application(s) and associated By-Laws with Infrastructure Ontario (IO), to
assist with funding the new Water Storage Tower and the upgrades to Well
3.”
In consideration of the significant increase in the cost of the project, staff have
not yet applied for any funding and this was delayed until the report and
recommendation from the Town’s Engineer was presented to Council.
In addition to the rising costs outlined from the RFP process, one other notable
difference is that the non-construction (engineering) costs to facilitate the
project have now been added to the total cost of the capital project. In the
2021 budget it was estimated that this cost would be passed on through the
water rates operating budget. Due to the now increased interest charges that
are associated with the long-term loan and funded through water rates, staff
have instead included the engineering fees in the capital cost of the project.
The total interest paid for the term of the loan will total approximately
$1,411,579.87 or on average $70,579 a year. Infrastructure Ontario now
offers monthly payment plans that has helped to reduce the amount of interest
costs incurred.
The 2020 Development Charge (DC) study identified the project cost to be
$3.5 million (same as the budget) and identified that amounts collected would
be utilized to offset principal debt payments. By taking $1,169,746 initially
from the DC water service, in order to decrease the amount of borrowing
required, will mean that during the next DC review the additional costs of the
project will be captured in order to cover the principal debt payments until the
end of the 20-year term.
The lending rates published on the IO site for September 20, 2021 for a 20
year term stated 2.59% which is down slightly from the 2.63% reported in
staff report FS 2021-09 from July.
Section 4.7 of the Debt Management Policy states that the maximum
permitted amount of long-term borrowing shall not be more than 40% of the
amount determined under the Province’s Annual Debt Repayment Limit (ARL).
The borrowing of $5,000,000 for 20 years at a rate of 2.59% added to the
town’s existing debt would put that amount at approximately 30.5%. Two
loans will be paid out in 2026 freeing up almost 11% of borrowing room.
This still leaves sufficient room for borrowing for the Well 3 arsenic project for
which the RFP is closing September 30, 2021 and staff have applied for
funding for this project under the Investing in Canada Infrastructure Program
(ICIP) Green Stream for up to 4 million.
This report algins with the following Sustainability and Engaged Goals;
_________________________________ __________________________
Stephen Burnett, Municipal Engineer Carey Holmes, Director of
Financial Services / Treasurer
Reviewed by:
_______________________________
September 3, 2021
Town of Shelburne
203 Main Street East
Shelburne, ON L9V 3K7
Dear Jim,
S. Burnett & Associates Limited (SBA) has prepared the following letter to summarize the bids received
from Contractors regarding the Town of Shelburne, Elevated Water Storage Tank Project. The Request
for Proposal (RFP) document was uploaded to Merx and Biddingo on June 18, 2021. A total of
23 Contractors, subcontractors and suppliers downloaded the RFP document. The following is the list of
plan takers:
A pre-tender site meeting was not held for this project as it is a green-field construction project. It was
the Bidder’s responsibility to familiarize themselves with all aspects of Project’s scope and opportunities
to view the site were made if requested.
A total of five (5) addenda were issued throughout the RFP process that addressed questions by the
Contractors and additional clarifications. Addendum No. 3 extended the close date for one (1) week from
the original close date of Thursday, July 8, 2021.
One (1) bid was received by the closing date of Thursday, July 15, 2021, at 2:00 pm local time. The bid
submission was sent via email by the Contractor to Jaclyn Pouw-Dagenais at S. Burnett & Associates
Limited. The bid received was from the following Contractor:
Table 1 below presents the initial bid summaries received from the Contractor.
SBA has checked the submissions for mathematical errors and found no errors to the bid submitted by
Landmark Structures Co. A copy of the submitted bid has been attached for your review and records.
Landmark provided the required Bid Bond and Agreement to Bond amounts as outlined in Part 2: General
Terms and Conditions of the RFP document.
Town of Shelburne, Elevated Water Storage Tank RFP Page 3 of 4
Bid Summary
SBA File No: M20009
As discussed with staff prior to the RFP close, it became apparent that prices would most likely come in
greater than the allocated budget for this project. There has been a significant increase in material and
supply pricing including steel prices which are up over 300% in 2021 verses 2020 pricing. Similar issues
were experience with wood prices over 2021 reaching a high of 400% over 2020 pricing. Just prior to the
RFP close, similar results had been seen in other municipalities including Mapleton which closed
approximately one (1) month before this RFP at a bid price of approximately $6.5M and being
approximately $2.5M over the anticipated budget for a storage facility that is approximately 70% the size
of the Shelburne facility.
Given the significant overage, it was recommended by SBA that negotiations be opened up with the low
RFP bidder to determine whether there were any savings that could be realized and still make this
essential project viable. Several discussions and meetings were held with the low RFP bidder as well as
with senior Town staff and OCWA to review any potential savings and negotiations.
Ultimately following this process, Landmark Structures Co. provided an updated Proposal cost on
August 30, 2021, which lowered the base bid for the project by $692,000.00. It was agreed to move the
dewatering allowance of $95,800.00 from the base bid to the contingency allowance so that it would only
be allocated if necessary.
The revised bid amount was based on negotiated items that did not compromise any of the original design
items, nor compromise on safety, security or storage volume and has been reviewed by senior staff and
OCWA for acceptance of credit items. Based on this, SBA would recommend that if sufficient funds can
be allocated to this project to cover the increased cost, that it be recommended that the Water Storage
Tower RFP be awarded to Landmark Structure Co. for a base price of $5,983,050.00 excluding tax and
contingencies.
Should you have any questions, please do not hesitate to call me.
Yours truly,
Incl.
cc: Carey Holmes, AMCT, Director of Financial Services / Treasurer, Town of Shelburne
Denyse Morrissey, Chief Administrative Officer B.A; M.P.A., Town of Shelburne
1.0 ‐ Siteworks
Savings for alternate site subcontractor $ 93,600
Relocate Tank SW by 6m (+/‐) to permit sufficient access around tank / pedestal $ 11,800 Adjusting the location will permit more efficient access around the tank
Stockpile 950 m3 +/‐ surplus topsoil on site (add to berm) $ 22,200 Quantity shown is estimated
Stockpile 800 m3 +/‐ surplus excavated material on site (add to berm) $ 18,700 Quantity shown is estimated
Eliminate dewatering allowance. Owner to complete test digs to confirm ground water elevations $ 95,800 Credit amount to be finalized once test dig is completed
Provide 6m wide manual slide gate in lieu of 10m wide manual slide gate $ 6,800
Delete overflow discharge headwall and replace with rodent screen $ ‐ Credit offering was $5,900
Replace trench drain with Catch Basin at Truck fill location $ 2,400
Sanitary Line ‐ Relocate floor drain lines to soak‐away pit in lieu of specified detail $ 41,200 Final credit amount subject to further discussion with SBA on detail
Total road closure during tie‐ins $ 3,500 Final credit amount subject to further discussion with SBA on detail
Change CSP culvert to Armtec Big O $ 2,400
Eliminate concrete sidewalk and provide granulars $ 10,600
Change Vinyl coated chain link fence to Hot Dipped Galvanized $ ‐ Credit offering was $5,900
Subtotal $ 309,000
2.0 ‐ Mechanical / Electrical
Single inlet / outlet pipe with isolation valve. Includes changing all Stainless Steel piping from 316L to 304L. Credit
Modify inlet / outlet configuration per the attached drawing $ ‐ offering was $271,900
Eliminate the storage room and cladding on all masonry walls $ 34,000
Eliminate recirculation pump and associated piping $ ‐ Credit offering was $13,400
Eliminate truck fill line $ ‐ Credit offering was $32,500
Eliminate chemical feed system $ ‐ Credit offering was $49,400
Eliminate HVAC and plumbing systems $ ‐ Credit offering was $66,400
Eliminate standby generator, transfer switch and related civil efforts $ ‐ Credit offering was $42,400
Cost savings for reduction in Electrical scope $ 6,300 Storage Room electrical including HVAC
Decrease overflow pipe size to 200mm $ 16,800 200mm is sufficient with specified flow rates
Delete insulation requirement on Overflow riser pipe $ 7,500 Insulation not required on overflow
Delete 75mm tank drain line including valve, heat trace & insulation $ 8,500 Drain provided at grade level ‐ bypass to Overflow
Subtotal $ 73,100
3.0 ‐ Elevated Tank Structure
Foundation settlement limit per AWWA D107 $ 85,900 Specified settlement limit is less than that allowed by AWWA D107
Eliminate reverse cone feature at top of tank $ 22,000 Existing tank has the reverse cone feature
Provide ‘standard’ roof handrail in lieu of specified architectural handrail $ 21,300 Existing tank has the architectural handrail
Reduce thickness of floor plate from .250" to .188" $ ‐ Credit offering was $7,500
Eliminate Cathodic Protection System $ ‐ Credit offering was $23,100
Eliminate pedestal exterior sweep blast $ 13,000
Eliminate rigging rail at top of pedestal interior $ ‐ Credit offering was $8,800
Eliminate epoxy coated slab on grade except for the Chemical Room $ 4,400
Eliminate Division 10 items (work bench, chair, cabinet) in valve room $ ‐ Credit offering was $2,600
Reduction of items in Section 01075 – Tools and Safety Equipment per revised specification $ 2,600
Eliminate the supply of specified rescue equipment $ 34,800 Majority of tank owners do not own / maintain fall arrest and rescue equipment. Annual inspections &
maintenance required on these items. Maintenance is required per manufacturers instructions.
Eliminate the supply of harnesses, trolleys, lanyards $ ‐
Subtotal $ 184,000
4.0 ‐ Miscellaneous
Delete requirement for Consulting Engineer Trailer $ 22,700 We can provide a larger site office trailer with separate office for SBA representative (Shared trailer)
Reduction of Commissioning, start‐up / training based on scope reduction $ ‐ Credit offering was $40,000
Reduction of Bonds, Insurance and Overhead based on scope reduction $ 34,600 5% of credited amount
Contractor, Subcontractor and major supplier credit offering $ 68,600
Eliminate 2% maintenance holdback $ ‐ Credit offering was $5,000
Subtotal $ 125,900
ORIGINAL BID PRICE $ 6,754,000
PROPOSED VALUE ENGINEERING CREDIT OFFER $ 692,000 Total sum of above credit offering
SUBTOTAL $ 6,062,000
LESS SCHEDULE 'C' ‐ CONTINGENCY ITEMS $ 78,950
REVISED CONTRACT VALUE $ 5,983,050
Proposal for Town of Shelburne:
Elevated Water Storage Tank
www.teamlandmark.com
Proposal for Town of Shelburne, Elevated Water Storage Tank
Request for Proposal
SBA File No: M20009
Section C: Experience
C-1 Corporate Experience - Completed Contracts Summary
C-2 Experience – Design Engineer (Wes Pogorzelski)
C-3 Experience – Project Management (Paul DiPelino)
Section X: Appendices
X-1a Insurance – General Liability, Auto, Excess, Professional Liability
X-1b Insurance – CCDC Bid Bond
X-1c Insurance – Agreement to Bond
X-2 Affidavit - No Exceptions
X-3 List of Subcontractors
X-4a Brochure – Landmark Composite Elevated Tanks
X-4b Brochure – Landmark Shop Fabrication
X-4c Brochure – Landmark Coatings
X-4d Brochure – Landmark Mixing System
www.teamlandmark.com
Nibhana Suvarna
Water/Wastewater Engineer
and
Town of Shelburne
203 Main Street East
Shelburne, Ontario L9V 3K7
We at Landmark appreciate the opportunity to respond to this request for Contractor Selection for the
Design Build of a new water storage tank for the Town of Shelburne.
Our proposal presents our dedicated team and describes our broad range of capabilities that align with this
project. We trust that you will find our submission favourable and we look forward to a successful project.
The Landmark company originated in Hamilton and is the industry leader in elevated water storage tank
construction in North America. We are the largest elevated tank specialist globally. We are very passionate
about providing the highest level of safety, quality and service.
Thank you for the opportunity to present this proposal. We look forward to serving you.
Yours sincerely,
Landmark Structures Co,
Brent Marini
Director of Canadian Operations
Proposal for Town of Shelburne, Elevated Water Storage Tank
Request for Proposal
SBA File No: M20009
Company Profile
History
Landmark is an engineering and contracting company founded in 1974 and is the originator of the
Composite Elevated Tank (CET). This innovation was a paradigm shift from the way elevated
towers had traditionally been constructed, incorporating the use of a concrete pedestal to
significantly reduce long-term maintenance costs. Landmark’s expertise in this type of construction
led to the company passing the industry’s established giants to become the market leader in high-
capacity elevated storage construction throughout North America.
The Landmark philosophy is simple: Setting and advocating the highest standards delivered on
several fronts:
• Comprehensive attention to detail.
• Dedication to collaborative project execution.
• Providing the best ownership cost.
Design / Build
As a design-build company, Landmark has a broader perspective on the engineering function, and
takes ownership of its work right through to project completion. Our design, engineering and
detailing staff are experts on the technical challenges that lie beneath the outwardly simple lines
and shapes of tanks. We employ the most advanced tools and our expertise extends to related civil
and mechanical systems.
Each project presents its own technical challenges. Landmark’s design and engineering groups
apply specific knowledge and resources to a wide range of issues, including:
• Finite Element models to assess dynamic forces in high seismic areas
• Non-linear buckling analyses to determine the optimum tank configurations
• Computational fluid dynamics (CFD) to design tank mixing systems
• In depth soil-structure interaction analysis to design the most efficient foundation solutions
Project Management
In addition to the precision of our work, and the value of our best cost solutions, performance is a
key Landmark attribute.
It relates to how we perform for you, and to our dedication to collaborative project management,
thorough execution, and the resolve to do things right. Beyond how we build, we recognize that how
we work with clients and partners can determine the quality of a project, and the resulting referrals
and repeat engagements that create long term mutual success.
This philosophy accounts for our design-build orientation, in which we assume responsibility and
manage all the concurrent functions to completion. Our approach to business is consistent,
regardless of where it is in our extensive portfolio of capabilities.
Fabrication:
Landmark’s high capacity steel tank and component operations incorporate the finest equipment,
materials and talent. Our extensive use of mill-primed steel plate eliminates mill scale and
preserves the blast profile. Plus, the ability to roll wide plate to precise tolerances reduces welding
requirements, simplifying production and enhancing results.
Landmark has two state-of-the-art steel fabrication facilities strategically located to serve North
America with highway and rail access, multiple staging locations and storage options on site.
Locations in Burlington, Ontario and Decatur, Texas provide launch points for turnkey custom
component fabrication, all with the latest technology.
Landmark has a broad range of fabrication capabilities to meet the most demanding configurations
and requirements. We set a higher standard for quality and productivity.
Site Development
Site selection, analysis and preparation are core competencies for Landmark, refined in civil work
and hundreds of design-build projects over the past 40 years. Our knowledge of soil types, drainage
and compaction requirements, and close work with geotechnical specialists enables us to provide
valuable insights as well as execution on your project.
Concrete Structures
Our skill in achieving architectural concrete is testimony to Landmark’s commitment to building
concrete structures that combine aesthetic as well as functional excellence. Architectural concrete
is comparable to pre-cast concrete in its precision and consistency, and since it is permanently
exposed to view, the Portland Cement Association cites the special care required in the selection of
concrete ingredients, forming, placing, consolidating and finishing to obtain the desired
appearance. This is the standard that Landmark sets for its work.
With more than 10,000 wall placements and one million cubic yards of concrete placed, Landmark’s
concrete specialists are experts in managing mix designs, the critical impact of environmental
conditions on the placement process, rigorous quality control procedures, and the all-important
involvement of their supplier partners. The result is a superior track record in an area that has
become a true specialty.
Steel Erection
Landmark carries the quality and refinements achieved in fabrication right through to steel erection
on the project site, where we consistently implement process improvements for faster, safer and
more accurate construction. Recent examples include the cable suspension of steel plate for
welding and finishing, which eliminates the need for cumbersome jigs, reducing cycle time and
increasing quality. Quality Control / Quality Assurance programs ensure exceptional weld quality in
preparation requirements for coatings phase.
Specialty Coatings
Landmark has developed complete surface preparation and coatings services for all the structures
that we design, build and repair. This commitment and Landmark’s high standards of process and
product quality have been recognized by the Society for Protective Coatings with their QP-1
Certification. It evaluates candidate firms in four key areas:
• Management procedures
• Technical capabilities
• Quality control
• Safety procedures and record keeping
This places Landmark in a relatively small group of companies in the world to earn the QP-1
certification. It means that you can depend on the Landmark coatings team and its fully equipped
mobile crews for preparation and coating of virtually all types of steel structures, with a wide range
of materials.
Mechanical Systems
Landmark’s expertise in structures and storage extends to the piping and control systems that serve
them. This ranges from the design and fabrication of stainless steel piping for water storage tanks
and related tank mixing systems to their control valves, pump stations and monitoring equipment,
and cathodic protection. It also includes the piping and controls associated with larger tank farms
and systems, making Landmark an integrated resource for a wide range of projects.
While Landmark’s EHS policies are addressed in detail and integrated throughout work practices
and procedures, they are managed with four key tools:
• Hazard Identification & Risk Assessment (HIRA)
• Site EHS Evaluation
• Root Cause Analysis
• Comprehensive EHS Training
The goal of Landmark’s EHS management system is simple: Incident-free projects and workplaces
that maintain the integrity of the environment, utilize attention and care to eliminate cost and delay,
and above all, protect the quality of life and futures for those at work.
We are very proud to announce that Landmark is COR Certified! – effective January 2021.
All are employed directly out of the Burlington head office location. Additionally, Landmark
has another 300 employees directly employed out of our Fort Worth, Texas location.
Our Burlington office serves as the center for overall Project Management, Engineering, Drafting,
Procurement, Fabrication, logistics, control and evaluation functions for operations. All employees
who support these services are direct employees of Landmark Structures.
During project operations, command and control functions transfer to the project site, with support
operations executed by Landmark’s corporate and support staff who are located on-site in
Burlington.
Landmark employees will be assigned to the Project Delivery Team and contribute in their area of
expertise.
Our team has extensive experience and knowledge specific to elevated tank design, construction
and maintenance. Landmark is uniquely qualified to successfully manage this project.
The project is based on concepts Landmark invented and developed in the 1970s. Key team
members have been with Landmark throughout the development of this product, and have worked
directly with all aspects of management, design, fabrication, construction and maintenance. The
proposed team is the most experienced group of individuals available anywhere for this type of
project.
Reporting to the Operations Manager (Don Nikulka), and the President of Landmark (Chris Lamon),
Wes Pogorzelski will be the Engineer of Record for the Elevated Tank Project.
Wes will be directly responsible for the structural design of the Shelburne Elevated Water
Storage Tank ensuring the Tank is designed in accordance with governing codes and project
specifications. Wes and his Engineering Team will deliver complete, comprehensive design
calculations and drawings for review and implementation.
Wes is accountable for leading and managing the Project Engineering Team.
Don Nikulka has over 30 years project and construction management experience specific to
elevated tanks and is proposed as the primary individual accountable for delivering the project. Don
leads the project team and has the accountability to manage the project on a day-to-day basis.
Our site-specific management team consists of Operations Manager (Don Nikulka), Project
Manager (Paul DiPelino), Health and Safety Manager (Blake Morton) and a series of phase-
specific Site Managers that are deployed to the project site as work progresses.
Chris Lamon is the senior leader of the Landmark group of companies and is accountable for all
commercial, technical and operations functions at Landmark. He has over 35 years’ direct
experience in all aspects of management, project controls, engineering, development, procurement
and construction of tall, thin shell, heavily loaded vessels.
Chris, along with Brent Marini (Director Canadian Operations) will be directly engaged in the
project, assisting in oversight of project planning, project controls, and ensuring the availability of
key resources.
Brent Marini is responsible for the direction and coordination of the Canadian division of the
Landmark organization. He has over 20 years of progressive leadership in strategic planning,
organizational development, business development, finance, contract negotiation, and all phases of
design / build operations. Brent has extensive experience in Project Management and Construction
Operations Management.
Brent will be directly engaged in the project, assisting in oversight of project planning, project
controls, and ensuring the availability of key resources.
The following organizational chart identifies the Landmark team that will be accountable to deliver
the Elevated Tank Project.
The enclosed resumes provide detailed information on members of the proposed team. Key
members have 20 to 30+ years each of direct elevated tank experience.
Lead Project Engineer Director – EHS Quality Manager Fabrication Manager Sr. Project Manager Estimating Manager
Wes Pogorzelski, P.Eng. Tim Fetters, CSP Michael Faubel Jim Darnell Paul DiPelino Ken Cardwell
Rolf Pawski, P.Eng. Blake Morton, NCSO Mina Agaybi Brenda Cantlon
Key Personnel
President
Chris Lamon has over 35 years’ experience in all aspects of management, engineering,
procurement and construction with leading specialized design / build organizations. Chris has
extensive experience in site specific design, manufacturing, construction, and quality management
of tall, thin shell, heavily loaded structures engineered to withstand significant wind and seismic
environmental loads.
Chris has been accountable for legal, financial, risk management, engineering, procurement,
project management and operations management functions on a diverse portfolio of projects
over extensive geographical areas. He is responsible for significant contributions in the writing and
development of ANSI standards in the elevated water storage space and the design and patent
development of numerous products involving fluids and structural designs.
Professional Experience
Landmark Companies (1983 – Present) – CEO / Owner
o Senior leader of the Landmark group of companies – a leading EPC firm specializing in
elevated water storage and large complex industrial vessels.
o Strategy and direction for business development, engineering, project management,
manufacturing, construction and asset management teams.
o Accountable for all commercial, technical and operations functions.
Education
Operations Manager
Don Nikulka has over 30 years of experience in all phases of heavy civil engineering procurement
and construction operations, and is Canada’s leading expert in with respect to elevated tank
management and construction.
Don has hands on experience in construction trades, site supervision, field engineering, design,
detailing, contract negotiation, project management, construction operations, subcontract
management, quality management and safety. Year after year, Don has completed many
concurrent multi-million-dollar projects by successfully coordinating trades, developing partnerships
and building a positive relationship with customers, consulting engineers, local officials, vendors
and staff. Don is well versed in contract negotiations, document preparation, procurement, building
codes and regulations.
Professional Experience
Landmark Structures Co., Burlington, ON (1985 – Present) – Senior Project and Construction
Manager
o Responsible for the overall leadership, management, direction, and development of shop,
field and office support staff for the execution of construction works in support of near and
long- term business objectives
o Manage multiple project managers across 25+ concurrent projects throughout the United
States and Canada
o Inspect work in progress, both shop and field, to ensure that workmanship conforms to
drawings, specifications, company standards, procedures and quality expectations
o Develop and implement project controls processes (cost, quality and schedule)
o Develop internal standards, policies, and procedures for execution of construction
operations; identify areas for improvement, develop solutions and implement changes
o Initiate, implement, delegate and monitor special projects involving construction methods
and processes to improve the quality, productivity and safety of the organization
Education
Brent Marini
Director of Operations
Brent Marini is responsible for the direction and coordination of the Canadian division of the
Landmark organization. He has over 16 years of progressive leadership in strategic planning,
organizational development, business development, finance, contract negotiation, and all phases of
design / build operations. Brent has extensive experience in Project Management and Construction
Operations Management.
Brent has successfully delivered multi-million-dollar projects while developing partnerships and
building a positive relationship with customers, engineering firms, subcontractors and vendors. He
has experience leading projects in multiple and diverse business units within Landmark and
specializes in Lead Abatement, Structural Rehabilitation, Industrial Coatings and Asset
Management. Brent is accountable for all projects from conception to completion.
Professional Experience
Landmark Structures Co., Burlington, ON (2003 – Present) – Director of Operations
o Manage Landmark Canada – all divisions. Develop and implement standards.
o Senior manager of EHS, Quality Management and project controls – all divisions.
o Responsible for the overall leadership and technical direction of Landmark Municipal
Services, the leading provider of water storage asset management services in Eastern
Canada.
o Collaborate with clients to design, develop and implement cost effective corrosion
management solutions for water and industrial storage
o Directly manage multiple projects and project managers for the execution of rehabilitation
construction works.
Education
Mohawk College, Architectural Engineering Technologist
Wes Pogorzelski has extensive advanced experience in all aspects of structural behaviour,
analysis and design of tall, thin shell, heavily loaded structures engineered to withstand
significant wind and seismic environmental loads. Wes is an expert in in foundations and soil /
structure behaviour and has advanced capabilities in fluid dynamics as it relates to large storage
vessel behaviour.
Wes is accountable for the analysis and design of the tallest free-standing structure using
advanced non-traditional building materials and complex details.
Professional Experience
John Otter Engineering Services Ltd., (1991 – 2002) – Senior Structural Engineer
o Design of girder launching gantry equipment for large bridge structures
o Analysis and design of construction equipment, scaffolding, and shoring
o Structural design of elevated tanks and bridges
Education
Tim Fetters
Tim Fetters has over 20 years’ experience in health, safety, security and environmental
systems management, with additional expertise in program development, inspection and
management of construction delivery methods. His extensive education and training in
manufacturing as well as industrial, commercial, power generation, chemical, and petroleum
industries make him the ideal manager for workplace and jobsite safety and related initiatives for
Landmark.
Professional Experience
Landmark Structures I LP (2007 – present) – Director of Environmental Health & Safety
o Responsible for development, implementation and maintenance of Landmark’s
corporate EHS System.
o Developed and executed new, comprehensive EHS program at Landmark; including
procedures, training, tracking and analysis, which has resulted in improved performance,
while raising awareness and commitment.
Jacobs Engineering, Houston, TX (2000 – 2007) – Regional EHS Manager, British Petroleum
(BP) Corporate Headquarters
Sabre / EDS Corporate Campus (1999 – 2001) – EHS Manager
Fluor Corporation, North Texas (1997 – 1999)
o EHS Manager, (1998 – 1999) – Texas Utilities Power Plant Maintenance, Multiple
Projects
o EHS Manager, (1997 – 1998) – Amoco Polypropylene Project, Chocolate Bayou Plant,
Alvin, TX
Education
Michael Faubel
Quality Manager
Michael Faubel has over 20 years’ experience with the technical and design aspects of construction
materials and over 10 years’ experience specific to quality management. Michael has led the
development and implementation of industry standards with organizations such as ASTM, ACI,
AWWA, ASQ, NACE and SSPC, and is recognized for his commitment to improving the concrete
and tank coatings industries.
Michael has experience leading initiatives for diverse business units within Landmark including
certification as an ASME fabricator of pressure vessels and authorization of pressure vessel repairs
by the National Board.
Professional Experience
Representative Projects
Education
Jim Darnell
Fabrication Manager
Jim has been instrumental in the design and launch of Landmark's fabrication facilities and
equipment as well as the expansion of capabilities to include highly complex forming of multi curved
vessel components.
Professional Experience
Education
Paul DiPelino
Paul is highly experienced in contracts, negotiations, procurement, building codes and regulations.
Professional Experience
Representative Projects
Education
Ken Cardwell
Estimating Manager
Ken Cardwell is a design / build construction professional with over 25 years’ of experience in
project engineering, project management and estimating. Specializing in elevated water storage
facilities, he has been integrally involved in the estimating, planning, execution and completion of
many complex projects.
Professional Experience
Education
Rolf is one of the foremost elevated tank design experts in the industry, with over 50 years’
experience. Rolf is active in managing complex design problems and maintaining engineering policy
in the face of multiple changing standards and codes. Rolf is well recognized in the industry for his
major contributions to the advancement of elevated tank design, and for his significant writing
efforts on behalf of the industry standards and codes. Rolf also has extensive experience in
geotechnical, soil structure interaction, foundations and structural behaviour under severe
environmental loading.
Rolf Pawski has served as Landmark’s principal engineer for the past 24 years’ and is responsible
for all tank structural design, design programs and engineering policies for the company.
Professional Experience
Chicago Bridge & Iron Company, Chicago, IL (1981 – April 1995) – Senior Design Engineer
o Led the design of concrete and steel structures, foundations and general civil structures.
o Civil Design Supervisor for Woodside (Australia) LPG prestressed concrete full
containment structures completed in 1995.
o Involved in the development and use of prestressed concrete structures for the
secondary containment of low and cryogenic temperature liquids.
o Development of design procedures / construction equipment for composite elevated
tanks.
o Led the design of prestressed concrete safety walls, foundations, and concrete and steel
framed structures
o Prepared designs for ammonia and LPG safety walls in Australia, the US and Taiwan.
o Provided engineering site supervision for prestressing work.
o Worked for the Chief Structural Engineer (1981-1983) in development and consulting.
o Prepared designs and studies for Arctic offshore exploration structures, lightweight
insulating concrete and composite elevated tanks.
Chicago Bridge & Iron Company, Chicago, IL (June 1969 – Jan 1979) – Design Engineer
o Designed foundations for storage tanks, process equipment, pipelines and equipment.
o Performed field inspection of piling and drilled pier installation, foundation excavation
and earthwork, large concrete placements and geotechnical investigations.
o Development of construction sites for offshore structures in the US, Venezuela and
Brazil.
o Designed the first prestressed concrete safety wall built by CBI in 1979 at Botany Bay,
Australia for the secondary containment of ethylene.
Education
Blake Morton
Blake Morton is an Environmental Health and Safety (EHS) Manager with extensive experience in
the construction, industrial and solar energy markets. Blake has specific expertise in the creating
and implementation of health and safety policies and programs for companies and has a proven
track record of successfully managing health and safety issues to ensure employees are safe on
the work site.
Blake works directly with all employees and Landmark leadership: EHS Director (Tim Fetters),
Director of Operations (Brent Marini) and Senior Project / Construction Manager (Don Nikulka)
Professional Experience
Landmark Structures Co., Burlington, ON (2017 – Present) – EHS Manager
The Donald Group of Companies, Etobicoke, ON (2016 – 2017) - EHS Manager
Algoma Energy Solutions, Sault Ste. Marie, ON (2014 – 2016) - Senior Health and Safety
Advisor
H.E.L.P Safety Services, Acton, ON (2011 – 2014) - Field Manager and Health and Safety
Coordinator
The Manarin Group of Companies, Toronto, ON (2008 – 2011) - Construction Services
Health and Safety Manager
Education
Keiler Mackay Collegiate Institute – Honor Graduate
Mina Agaybi
Project Coordinator
Mina Agaybi is a recent Civil Engineering Graduate majoring in Structural and Environmental
Engineering. Mina has hands-on experience in Project Coordination and Management: reviewing
construction schedules, submittal review and tracking, subcontractor management, procurement,
scheduling equipment and material deliveries, project closeout documentation and coordination. In
addition, he has experience in monitoring quality control, changes in construction procedures, and
reviewing drawings & specifications. He has worked on multiple Water Storage Tank Projects and
assisted to a successful project close out to the client’s satisfaction.
Professional Experience
Representative Projects
Education
Ryerson University, Bachelor of Engineering – Civil Engineering
Brenda Cantlon
Project Administrator
Brenda Cantlon has over 20 years’ experience in all aspects of design / build construction
project administration from design phase to project completion. Brenda assists with Project
Management duties such as procurement, logistics, and coordinating trades. Brenda communicates
with functional leads and managers to compile weekly and monthly project progress reports.
Brenda brings high value to the project, with over 12 years direct experience coordinating Landmark
elevated tank projects.
Professional Experience
Representative Projects
Stefan Stelmach has over 30 years’ experience in detail design, engineering coordination,
engineering standards development, and management of CAD services. Stefan has provided detail
designs on hundreds of elevated tanks and other tank vessels and structures in Canada and US.
He is a CAD systems expert with specialty in systems programing, implementation and
development.
Stefan is accountable to ensure timely and accurate delivery of design drawings associated with
Landmark projects.
Professional Experience
Representative Projects
Complete comprehensive delivery of engineered drawing packages:
o Kettle Stony Point FN, Elevated Tank – Current
o City of Brantford, Composite Elevated Tank – Current
o Correctional Services Canada, Warkworth Institution Composite Tank – Current
o Brant County Airport Elevated Tank – Current
o Town of Bradford, Bondhead Composite Elevated Tank – Current
o Elsipogtog First Nation, NB Composite Elevated Tank – 2018
o Township of North Glengarry, Maxville Composite Tank – 2018
o Municipality of Edmundson, NB - AWWA D100 Tank – 2017
o Bonavista, NL Composite Elevated Tank – 2017
o Township of Huron Kinloss, Ripley Elevated Tank – 2017
o Town of Shediac, NB Composite Elevated Tank – 2017
Education
Chris Levair
Site Manager
Chris Levair serves as Landmark’s primary representative at the project site who interacts and
reports internally and to owners, engineers, inspectors. Chris implements project safety and
quality objectives at the construction trade and subcontractor level, ensuring high quality
construction is delivered in a safe and efficient manner.
Chris has extensive experience managing and directing multiple trades workers and subcontractors
and is a proven leader / motivator with excellent interpersonal and managerial skills.
Professional Experience
Representative Projects
WHMIS
St. John’s Ambulance First Aid/CPR
Traffic Control
Propane Safety
Fall Protection
Confined Space Entry and Rescue
High Angle Rescue
SwingStage
Proposal for Town of Shelburne, Elevated Water Storage Tank
Request for Proposal
SBA File No: M20009
Project Engineer
Razmyar Ghateh has over 10 years’ experience as a Structural Designer. He has analyzed over
100 elevated water storage facilities using finite element analysis and computer modeling
programs. Razmyar has extensive knowledge in nonlinear analysis of structures using FEMA
methods, and is an expert in Canadian structural design codes and standards.
Professional Experience
Landmark Structures Co., (2014 – Present) – Structural Designer
o Nonlinear static, nonlinear dynamic and seismic analysis of structures
o Design of liquid containing and shell structures
o Retrofitting and rehabilitation of structures and developing strengthening plans
o Analysis and design of heavy construction lifts
Representative Projects
Elevated Tank Analysis and Engineer of Record:
o Regional Municipality of York – Stouffville Elevated Tank Refurbishment – 2018
o Municipality of Chatham Kent – Dresden Composite Tank Refurbishment – 2018
o Region of Niagara – Virgil Composite Elevated Tank Telecommunication Support – 2018
o Others available upon request
Education
Tyler Hindle
Tyler Hindle has over 15 years’ experience specific to fabrication and construction of steel storage
tanks. He serves as Landmark’s key representative on the jobsite during steel erection / welding
phases. Tyler interacts with project and construction management, owners, engineers, inspectors
and government agencies to ensure a quality product is produced according to specifications and in
a timely and safe manner.
Professional Experience
Representative Projects
Site Superintendent – Steel Erection, Recent and Current Project Experience:
o City of Brantford, Composite Elevated Tank – 2019
o Correctional Services Canada, Warkworth Institution Composite Tank – 2019
o Brant County Airport Elevated Tank – 2019
o Town of Bradford, Bondhead Composite Elevated Tank – 2019
o Elsipogtog First Nation, NB Composite Elevated Tank – 2018
o Township of North Glengarry, Maxville Composite Tank – 2018
o Town of Shediac, NB Composite Elevated Tank – 2017
o Municipality of Niagara, Port Colborne Composite Tank – 2016
o University of Guelph Thermal Storage Tank - 2015
Education
Rick DeJong
Rick DeJong has over 20 years heavy construction experience. He is an expert in Civil Construction
and is Landmark's key representative on the jobsite for the following phases:
Rick has a proven track record in delivering high quality projects in a safe and efficient manner.
Rick continuously updates and interacts with project and construction management, owners,
engineers, inspectors and government agencies.
Professional Experience
Landmark Structures Co., (1994 – Present) – Civil Superintendent
Representative Projects
Perry Compton
Perry is accountable to manage quality, safety and efficiency of all coating’s phases. He has a
proven work ethic, a solid sense of accountability and excellent leadership qualities.
Professional Experience
Dalco Services Inc., Bonnyville, AB (2006 – 2014) – Field Operations and Branch Manager
Representative Projects
Section C: Experience
Landmark has designed and constructed over 1,000 Composite Elevated Tanks and is the leading
design/build elevated tank specialist company in North America. This is a small sampling of
completed projects that meet your specified criteria; several more references are available upon
request.
2010 1.7 MIG Queensville, ON York Region - Shivan Narine (905) 895-1231
2010 1.1 MIG Georgetown, ON Halton Region - Cam McDougall (905) 825-6000
2009 1.8 MIG Waterdown, ON City of Hamilton Angela Doyle (905) 564-2424
2008 0.9 MIG Bayfield, ON Mun. of Bluewater - Jeff Newel (519) 236-4351
2008 2.0 MIG Caledon, ON Region of Peel - William Turner (905) 791-7800
2008 1.0 MIG Kapuskasing, ON Town of Kapuskasing - Eric Cote (705) 335-2341
2008 1.2 MIG Moncton, NB City of Moncton - Ensor Nicholson (506) 853-3333
2007 1.7 MIG N. Richmond Hill, ON York Region - Shivan Narine (905) 895-1231
2007 1.2 MIG East Woodstock, ON Oxford County - Paul Eybergen (519) 539-0015
2006 1.4 MIG Tilbury, ON Chatham-Kent PUC - Rob Bernardi (519) 360-1998
2006 1.0 MIG Riverview, NB Town of Riverview - Mike Ouellet (506) 387-2020
2006 1.2 MIG Baden, ON Region of Waterloo - Winnie Chan (519) 575-4400
2005 1.4 MIG Stouffville, ON York Region - Shivan Narine (905) 895-1231
2005 0.8 MIG Saint John, NB City of Saint John - Dean Price (506) 658-4770
2004 1.5 MIG Kingston, ON Utilities Kingston - Chris Phippen (613) 546-1181
2004 1.0 MIG Moncton, NB City of Moncton - Ensor Nicholson (506) 853-3333
Please note that all tanks listed above are the same Tank design and were constructed using the
same methods and forming system as outlined in the RFP.
Section C: Experience
Wes Pogorzelski is the most experienced elevated tank designer in Canada. The following
represents a small sample of projects that he has been involved in as the person
responsible for the structural design. Additional projects are available upon request.
Section C: Experience
Paul DiPelino is the most experienced Project Manager in Canada that specializes in
elevated tanks. The following represents a sample of projects he has been involved in.
Additional projects are available upon request.
P ROCE S S / C O N T E N T S
Summary.............................................................. 1
Coatings/pre-hoist….................................. ……...6 Since then it has become the established standard for large
Hoist...............................................................…...7
capacity water storage. It offers distinct advantages over
Tank erect & coatings/post-hoist...................…...8
1
Major Elements of the Landmark
Composite Elevated Tank
Geotechnical investigation
Once a suitable site with the necessary clearances and access
has been determined, the project owner or engineer orders
a geotechnical investigation from a qualified geotechnical
engineer familiar with local soil conditions. The resulting
report will suggest the most appropriate foundation type and
design, based on factors specific to composite elevated tanks,
including pedestal height and diameter, structure and water
weight, plus wind and seismic loads. Landmark typically
recommends and provides the foundation design as part of
its role, with seismic expertise resident within its internal
engineering group. With hundreds of projects completed
in locations across the country, and close collaboration with
all types of geotechnical engineering firms, Landmark
applies significant specialized experience to this first stage
in the process.
2
Foundation
Following engineering, submittals and mobilization, site
preparation and excavation for the foundation begins.
Based on the recommendation, this could involve a mat-type
or pile-type foundation, the latter either driven steel or poured
concrete as depicted. While site prep and excavation are
often subcontracted to local crews with the required
equipment, Landmark provides the first of its specialized
Foundation layout crews for actual foundation construction, including layout,
piping, forms and reinforcement, as well as coordination
with the local concrete provider.
Mat-type foundation
For each lift, vertical bulkheads are placed inside the wall
forms at approx. 25-foot intervals, based on the number of
truckloads of concrete required. The bulkheads’ three-piece
design allows continuous reinforcement to pass through,
around the entire wall. When concrete is poured into two
adjacent segments, the vertical bulkhead between them is
removed, and the concrete is vibrated for consistent surface
quality. This process continues on a daily form strip, form
set, and concrete placement cycle, until the pedestal wall is
finished. Forms are then positioned for the pouring of the
Vertical bulkheads define each segment
concrete dome, which completes the pedestal and provides
a strong structural base for the tank.
5
Coatings/pre-hoist
The coatings phase also occurs on the ground, managed
according to the requirements of the Society for Protective
Coatings’ (SSIP) QP-1 standard. Landmark is only one of
about 230 companies worldwide to earn this certification,
which recognizes management procedures, technical
capabilities, quality control, safety procedures and record
keeping. In addition to the ability to apply a wide variety of
coating types, Landmark can also execute custom logos and
graphics that utilize the composite tank’s large unobstructed
surface areas. Completing the coating phase on the ground
also helps control waste and maintains air quality, typically
eliminating the need for containment. During this phase,
the tank/roof access tube is also positioned, prior to the
tank hoist.
6
Hoist
Upon completion of exterior coatings, the tank is hoisted with
a system of hydraulic jacks and cables, usually a 3-5 hour
operation once preparations are completed.
7
Tank erect & coatings/post-hoist
Once in place above the pedestal, the tank is permanently
secured by pouring a reinforced concrete ring beam. Next,
steel floor plate is grouted and welded in place, serving both
as a tank floor and moisture barrier over the concrete dome.
The roof panels are then hoisted into position and welded in
place, prior to the application of interior tank coatings, and
then application of exterior roof coatings. The flat structural
roof provides easy access to roof-mounted appurtenances,
which are installed at this stage as well.
Pouring ring beam
Tank floor plate over pedestal dome Tank roof with hatches, vents, and rail
Commission
At the final commissioning stage, Landmark technicians test
all systems, disinfect the tank and address all checklist items
before turning the tank over to the owner or operating entity.
........................................................................
www.teamlandmark.com
© Copyright 2010 Landmark Structures
9
Proposal for Town of Shelburne, Elevated Water Storage Tank
Request for Proposal
SBA File No: M20009
Scope
This document describes quality assurance and quality control measures with respect to
construction procedures, concrete supply and operations, formwork removal, and general
compliance with project specifications.
Responsibilities
Landmark Site Superintendent is responsible for ensuring this Quality Plan is implemented and
properly followed.
Landmark Site Superintendent shall designate a competent person(s) to perform construction
control measurements, tests, and observations.
Record Forms
Measurements and data shall be recorded in the project field book, dated and initialed, and
transferred to record forms.
Form No. Title
QA_PED1 Strength Calibration Testing - Procedure
QA_PED2 Strength Calibration Testing – Maturity Factor
QA_PED3 Concrete Monitoring – Placement, Testing and Form Removal
QA_PED4 Dimensional Control - Pedestal
Foundation
Shallow Foundation
Implement the following controls prior to and during construction operations:
• Determine elevations according to an established benchmark.
• Verify elevation and dimensions are in accordance with IFC (Issued for Construction) drawings.
• IFC drawings and field as-formed dimensions checked to verify calculated concrete quantity.
• Verify placement of reinforcement, embedment devices and block outs are in accordance with
IFC drawings prior to concrete placement.
• See Support Wall for concrete controls.
Support Wall
Support Wall – Form System and Dimensional Control
Implement the following controls prior to and during support wall forming operations:
• Wall Thickness - Prior to concrete placement of the first lift, confirm wall thickness is in
accordance with IFC drawings and specification tolerance.
• Radial Position of Forms – Confirm radial dimensions at the exterior form face are in
accordance with IFC drawings and specification tolerance. Record prior to concrete placement.
• Vertical Position of Forms – Confirm elevation at the top edge of the form are in accordance
with IFC drawings and specification tolerance.
• Wall Plumbness – Check vertical plumb using a transit set up a distance from the pedestal at
two points 90 degrees apart.
• Placement of Reinforcement, Embedments and Blockouts – Provide 2 independent checks of
reinforcement placement, embeds, and blockouts.
• Temporary bulkheads – Provide temporary steel plates and angles are at strategic points in the
wall to allow for individual batch consistency throughout wall height.
• As-Built Radial Dimensions – Following form removal, record as-built radial dimensions.
• Radial Dimension Adjustment - Radial dimension adjustment, in any individual lift, shall not
exceed 6 mm from the previous lift, at any given location, without authorization from Landmark
management.
• Out-of-Tolerance - Any deviation from the theoretical radius exceeding 12 mm in any one lift is
reported immediately and no further concrete placements shall proceed until authorized by
Landmark Operations Management.
• Observation and Performance of Concrete Testing – Perform tests for slump, concrete and air
temperature, air-entrained content, and unit weight by qualified personnel per CSA A 23.2.19. In
case discrepancies are observed in test methods and/or results, re-tests may be performed.
• Cast cylinders per CSA A23.2.19 and as required by project specification.
• Reporting – Record data regarding concrete placement. See Record Form QA_Ped3
are positioned. The maturity factor (TTF) or estimated strength is recorded prior to jumping
the last interior form.
- Report any significant anomalies in maturity results. Suspend concrete placements until
authorized by Landmark Operations Management.
Remove blankets in a systematic manner to regulate the decrease in concrete temperature over
time.
• Insulated Wall Forms – Provide closed-cell insulating foam securely attached to the form
exterior.
• Supplemental Heat Sources – Provide indirect-fired or high-wattage electrical equipment placed
near the concrete to maintain temporary heating of the forms or concrete.
• Combined Protection – Insulated forms, insulated blankets, and supplemental heat shall be
combined for use in severe cold weather conditions.
• Concrete Placement Temperature – Concrete temperature at the point of delivery shall be per
CSA A23.1.19 Table 14 (10 C minimum) unless supplemental heat is used. If supplemental heat
is used for at least 24 hrs after placement, then concrete temperature at placement shall be
minimum 4 C.
Scope
This document describes Landmark quality assurance measures for steel tank construction.
Responsibilities
Landmark Superintendent designates competent persons to perform construction control
measurements, tests, and observations.
Record Forms
Measurements and data of as-built measurements and construction control data are recorded and
submitted to the Owner on completion of construction.
Form No. Title
QA_STL1 Elevation Control – Cone & Shell
QA_STL2 Cone Survey – Dimensional Tolerances
QA_STL3 Welder & Radiograph Location – Cone & Shell
QA_STL4 Shell Survey – Dimensional Tolerances
QA_STL5 Concrete Control
QA_STL6 Welder Location – Roof & Floor Liner
Tank – Cone
The 45-degree cone is made up of multiple courses with each course having multiple segments.
The segments are placed in fixtures and fit in preparation for welding.
Implement the following control procedures during cone construction:
• Fit each course and adjust weld gap and plate alignment within tolerance. Record elevations.
Contact Landmark Operations Management if elevation tolerance is exceeded. Record data in
form QA_STL1.
• After cone welding is complete, perform radial line survey of interior surface at 30-degree
intervals. Take measurements every 300 mm along radial. Tolerance shall not exceed AWWA
D107 requirements. Record data in form QA_STL2.
• Complete welder location log. Visually inspect all welds for standards compliance and initial by
the competent person.
• Perform radiograph inspection per AWWA D107 by a qualified third-party inspection company.
Record radiograph locations and inspection results in form QA_STL3.
Tank Hoist
Hoist tank to the top of the concrete support pedestal using Landmark's proprietary equipment and
procedures.
• Set tank on steel shims at the proper elevation.
• Record elevations at 90-degree intervals prior to and after hoist.
1.0 Scope
This specification defines general surface preparation and coating process control and quality
assurance requirements for surface preparation and coating activities.
Project specific requirements are contained in the Landmark Protective Coatings Schedule as well
as the Project Specification prepared by CIMA+.
2.0 Scope
The focus of this quality assurance document is for the control of the surface preparation and
coating application process. Implementation is by jobsite supervision and coatings management.
ASTM E337 – Standard Test Method for Measuring Humidity with a Psychrometer
ASTM G95 - Standard Test Method for Cathodic Disbondment Test of Pipeline Coatings
(Attached Cell Method)
4.6 Other
Occupational Safety and Health Act, 1990 and Regulations for Construction Projects.
Environmental Protection Act, R.S.O. 1990 c E. 19, Regulations with regard to abrasive
blast cleaning and painting procedures
5.0 Materials
5.1 Coatings
5.1.1 All coating materials shall be handled per manufacturer’s instructions and should be
stored in original, unopened containers in well ventilated areas protected from damage and
extreme temperatures.
5.1.2 All coating containers shall bear legible product designation, batch number and date of
manufacture.
5.1.3 Coating material shall be used within the manufacturer’s recommended pot life.
5.1.4 Containers of coatings or components shall not be opened unless for immediate use.
5.2 Abrasive
5.2.1 Abrasives for blast cleaning shall be clean and dry and shall be free of oil or contaminants.
The particle size shall be identified by the product number or generic formulation.
6.0 Equipment
6.1 Application equipment shall be per the coatings manufacturer’s recommendation and shall be
suitable to apply the coatings as specified.
6.2 Equipment air supply shall have moisture traps and filters to remove water, oil and
contaminants.
6.3 Painting equipment shall be selected to provide effective application and acceptable finish for
the material being coated.
The following Major Construction Equipment is intended for use during the surface preparation and
coating application of the Water Tower:
Compressed air equipment hoses shall be properly sized. Moisture traps and filters are installed
and in good working order to remove water, oil and contaminants.
Abrasive blasting equipment is properly rated, and all couplings are properly connected, pinned with
proper whip checks in place at all times. Prior to use, Dead Man Switches are verified as fully
functional and not “chocked” or taped in an open position.
Work access equipment such as aerial lifts and swing stages are inspected prior to use each day by
Landmark’s designated competent worker(s). Personal Protective Equipment such as harnesses,
lanyards, rope grabs, life lines, etc. is not used in any manner other than intended by the equipment
manufacturer and it is properly stored when not in use.
Inspection equipment is properly maintained, and calibration verified before each use in accordance
with the manufacturer’s instruction.
Surface preparation (Abrasive Blasting) shall not be performed if any of the following conditions
exist:
• Relative humidity is greater than the manufacturer’s published limit,
• Moisture is present on the surface of the item to be blasted
• Abrasive is contaminated or wet
• Equipment has defects that affect safety or quality in any way
cleaning, prime, and stripe with a topcoat material of a colour contrasting with the primer
coat colours.
3. Mixing, application and curing of coating material is in strict accordance with the
manufacturer’s published instructions. All mixing shall strictly adhere to the ratio specified by
the manufacturer. Do not mix partial paint kits.
4. Coating Uniformity:
a. Apply all coatings uniformly without sags, contamination, or other blemishes.
b. At the discretion and direction of the 3rd party coatings inspector, remove defects and
repair before proceeding with subsequent coat.
c. Thoroughly mix all ingredients prior to use and agitate often enough during
application to keep the pigment in suspension.
5. Application Method:
a. Apply all coatings by spray according to the manufacturer's published instructions
unless prohibited under the OHSA.
b. Where spray is prohibited, use roller application except that brushing will be
accepted where rolling would not be effective.
c. All rollers shall be lint free.
d. Mix and thin coatings, including plural-component materials, only in accordance with
the manufacturer's instructions.
e. Keep containers closed when not in use to avoid contamination.
f. Do not use mixed coatings beyond pot life limits.
g. Use application equipment, tools, pressure settings, and techniques in accordance
with the manufacturer's instructions.
6. Spray Pressure:
a. Regulate pressures on the spray gun to achieve optimum atomization of the paint at
the lowest possible pressure.
7. Spray Technique:
a. Overlapping (50%) vertical passes followed by overlapping (50%) horizontal passes
(or vice versa) with each spray coat to obtain uniform film thickness.
b. Apply a complete wet coat in each operation
c. If sagging occurs, use a mist coat/full coat application technique to obtain wet film
thickness per coat.
d. Excessive dry spray, or overspray, will not be accepted.
8. Dew Point
a. Do not apply coating materials when the surface to be coated is less than 3 degrees
Celsius above the dew point.
b. Use a surface temperature thermometer in intimate contact with the steel for
monitoring purposes.
c. Apply coatings in accordance with maximum Relative Humidity (R.H.) conditions as
advised by the coating manufacturer, except do not apply coating above 80% R.H.
d. Do not apply coating when steel temperature is above 59 degrees Celsius.
9. Curing
a. Strictly follow manufacturer's published curing schedule, using steel temperature
rather than ambient temperature as the basis of cure times.
10. Ventilation
a. Ventilation shall conform to all applicable requirements of AWWA D102, Section 7.3
and the requirements of the Ontario Ministry of Labour.
10.3 Required Daily Records (Detailed in the Daily Surface Preparation and Coating Record)
10.3.1 Compressed air quality
10.3.2 Ambient conditions
1. Analysis Description
The Finite Element Method analysis has been performed by means of ANSYS Release 11.0
program. The linear static type of analysis has been used. The objective of the analysis was to
find the response of the interface region of the tank, comprised of dome, steel tank and support
pedestal. The results of the analysis are presented in form of plots and listings of the
sectional forces (moments, shears and axial loads).
2. Geometry.
The analyzed tank has a usable capacity of 1,000,000 gallons. Important dimensions used in the
analysis:
3. Model Description.
The first model has been built to analyze sectional forces in the dome and the wall. The elements
used are SHELL51 – axisymmetric shell element and PLANE42 –2-D solid element. The dome,
the wall and the steel tank have been modeled with the shell elements, the ring beam has been
modeled with the plane elements. A set of constraint equations has been used to model rigid
connections between the dome, the ring beam and the wall.
The second model has been created with the same elements as the first one except that the
dome and the wall have been modeled with the plane elements. The objective of the model was
to find a more realistic distribution of the circumferential stresses.
401.1
STEEL TANK
201
RING BEAM
DOME
456.4
SHAFT
4. Load Cases.
1. Load Case 1 – Dead Load, Roof Load and Water Pressure due to H = 518.29”.
2. Load Case 2 – Dead Load, Roof Load and Water Pressure due to H = 130”.
Access tube reaction of 70,290 lbs. was applied to the uppermost section of the dome in both
load cases. Roof reaction of 86,410 lbs. was applied at the top of shell in both load cases.
Dead loads were applied as gravity loads at the element centroids. Cases 1 and 2 have been run
with the modulus of elasticity for concrete of 3605 ksi. All point loads are applied on 360 deg
basis. The hydrostatic pressures are applied as unit loads in accordance with Ansys convention
for the axisymmetric model.
Constraints applied to the model are: displacement degree of freedom constraints applied in
three directions at the base of the wall, circumferential degree of freedom constraint applied at
the uppermost section of the dome.
5. Results.
The results of Model 1 analysis for sections at the dome base and the top of the wall are
presented in Table 1. Sign convention used: for axial forces – compression negative, for dome
moments – positive when tension on top, for wall moments – positive when tension (or lesser
compression) inside.
Table 2 lists total circumferential forces in the ring beam and the top lift. The forces have been
computed by integrating the circumferential stresses over the area. Sign convention used:
compression negative.
The diagrams show plots of moment, shear and axial force in the dome and in the upper part of
the wall. All forces are shown on 360 deg basis, i.e. in order to calculate a force per unit length it
has to be divided by the perimeter. The results are shown in Table 1
Figures 1G, 1H, 2G and 2H show plots of circumferential stresses in the ring beam and the
upper part of the wall.
5. Strength check
The maximum compressive stress in the ring beam region does not exceed 283 psi and the
maximum tensile stress does not exceed 65 psi locally. Plain concrete section is capable of
resisting stresses of such magnitude.
Sections at the base of the dome and the top of the wall have been checked for interaction of
three forces: axial force, shear and moment (Table 3). All loads were multiplied by a conservative
load factor of 1.6 and by the imperfection sensitivity factors based on a large tank study. The
interaction has been checked by means of the ‘Response 2000’ program developed by the
University of Toronto. The program is based on the Compression Field Theory. Figures 3B and
3D show the results of the strength check for the governing Load Case 1. Figures 3A and 3C
show the section properties used in the analysis. The reinforcement provided is capable of
resisting the computed forces.
APPENDIX A
Finite Element Analysis of Interface Region
1 MG Elevated Water Tank
CONTENTS:
Strength check
Fig. 1A
Fig. 1B
Fig. 1C
Fig. 1D
Fig. 1E
Fig. 1F
Fig. 1G
Fig. 1H
Fig. 1I
Fig. 2A
Fig. 2B
Fig. 2C
Fig. 2D
Fig. 2E
Fig. 2F
Fig. 2G
Fig. 2H
Fig. 2I
Fig. 3A
Load Case 1:
Pu = -71 k/ft = φPn = -71 k/ft
Mu = -13.1 k-ft/ft < φMn = 15.4 k-ft/ft
Vu = 7.5 k/ft < φVn = 13.7 k/ft OK
Fig. 3B
Load Case 2:
Pu = -18.2 k/ft = φPn = -18.2 k/ft
Mu = -3.6 k-ft/ft < φMn = 5.5 k-ft/ft
Vu = 2.4 k/ft < φVn = 5.7 k/ft OK
Fig. 3C
Fig. 3D
Load Case 1:
Pu = -118 k/ft = φPn = -118 k/ft
Mu = -1.3 k-ft/ft < φMn = 18.6 k-ft/ft
Vu = 0.9 k/ft < φVn = 16.6 k/ft OK
Fig. 3E
Load Case 2:
Pu = -25 k/ft ≈ φPn = -25 k/ft
Mu = -3.3 k-ft/ft < φMn = 8.8 k-ft/ft
Vu = -1.7 k/ft < φVn = 6.7 k/ft OK
Fig. 3F
The following plans and procedures are prepared for bid submittal purposes only, and will be
refined once the final design is completed.
The owner shall ensure that all personnel accessing the facility receive and satisfy all applicable
legislative occupational health and safety and workplace safety requirements and training.
The owner shall ensure that the workplace meets and satisfies all applicable legislative
occupational health and safety and workplace safety requirements, including the creation of any
accredited health and safety management system.
All workers accessing the facility are required to be adequately trained and qualified as required by
all legislative health and safety workplace requirements and training. It is the duty of the owner to
ensure that the health and safety of all workers is protected.
It is the duty of the owner to ensure all fall arrest and rescue equipment is inspected and maintained
by a competent person in accordance with the recommendations of the manufacturer. All safety
equipment must be inspected at the manufacturer’s recommended intervals to ensure it is in good
working order, by a person with adequate knowledge, training, and experience who is appointed by
the owner.
It is recommended that all work procedures, access procedures, and rescue procedures, as well as
training, be conducted on a yearly basis. The owner should prepare a written training instruction
record for each worker, which should include the worker’s name and date of training, and be signed
by both the owner and worker.
• The ‘outer’ paint rail (edge of tank roof) can be accessed by a dedicated Roof hatch
positioned at the outboard edge of the tank roof.
• The ‘inner’ paint rail (around the access tube) can be access by the Hatch to tank interior
B. Elevated Tank Exterior Surfaces (for washing, coating repairs, re-coating, etc.)
• Typically, the exterior surfaces of an Elevated Tank can be accessed by either of the
following:
o Crane with Personnel Basket / Aerial Lift
o Swingstage
• The Elevated tank will be constructed with Swing stage anchorage points located on the
tank roof for future swing stage / safety line connections. The anchors will be positioned
such that all exterior surfaces can be accessed by a swing stage.
TOWN OF SHELBURNE
No.: Date: By: Revision:
WP WDE
CAN 0391
Landmark Structures Co. BM
3091 Harrison Court Burlington, Ontario, L7M 0W4
Tel: (905) 319-7700 Fax: (905) 319-7706
2021.07.05 N.T.S.
Sk - 1
Roof 536.21m
[1759.22]
HWL / Overflow
0.41m
[1.33']
11.40m
[37.10']
Steel Tank
0.48m
[1.56']
524.81m
[1721.84']
LWL
Ring Beam
5.93m
[19.46'] 203 [8"] Reinforced
Concrete Dome
Top Landing
Rest Seat
(typ.)
489.00 m
[1604.33'] 488.85 m
( t/o Foundation ) [1603.83']
1.66m
[5.45']
487.40 m
[1599.09'] ( Finished Grade )
485.75 m
[1593.67']
( b/o Foundation ) 10135
Foundation
[33'-3"]
TOWN OF SHELBURNE
No.: Date: By: Revision:
WP WDE
CAN 0391
Landmark Structures Co. BM
3091 Harrison Court Burlington, Ontario, L7M 0W4
Tel: (905) 319-7700 Fax: (905) 319-7706
2021.07.05 N.T.S.
Sk - 2
Mk. Qty. Description Length Spec. Ref. Dwg. Wt. (lbs.)
NORTH
DOOR SCHEDULE
SIZE
DOOR MARK QTY WIDTH, W HEIGHT, H FRAME MATERIAL FINISH
(mm) (mm)
Recirculation
12" Inlet Pump
12" Outlet
Electrical Rack
'A' 'A'
1'-0 1/2"
1 1/2" 2" 9"
Galvanized Mezzanine MK~W1
Handrail Chamber Room Exterior Wall 3/4"
MK~D102
(above) 8" Concrete Pedestal Clear 1-15M Deck Closure (typ.)
6'-0" W x 7'-0" H
Double Door 1" Air Gap (full length of Partition wall)
2" SM Insulation Deck Closure (typ.) Grout Top Course
8" CMU Interior Wall 1-10M continuous 8" Lintel Block- Last Course full Length of
(full length of curved wall) 6" CMU Partition wall
Storage Room (full length of curve wall) ( Fill with Grout)
3'-0" W x 7'-0" H
Single Door
SOUTH
[2 1/2"]
178
[7"]
Hatch Mount Angle
64
Anchorage Connector
635
102
[4"]
[2'-1"]
(to Hatch)
[2'-8"]
813
152
[6"]
400mm [16"] Frost Proof Combination 'A' 'A'
Vent/Vacuum Relief Unit
400 [16"] Ø
Vent Mount
Access Hatch 64 914
Hinges (typ.) [2 1/2"] [3'-0"]
900 [36"] Sleeve
Couplings: 1099 Half Pipe
Detail 'A' 4 pc's - 38 [1 1/2"] through Top w/ Plug [3'-7 1/4"]
4 pc's - 50 [2"] through Top w/ Plug (to Hatch)
4 pc's - 80 [3"] through Top w/ Plug 6[1/4"] Plate
1181
[3'-10 1/2"] (Each Side)
(to c/l 900 [36"] Half pipe)
DETAIL 'A'
Tank Vent
900 [36"] x 900 [36"] Hatch
1981
[6'-6"] 228 686 900 [36"] x 900 [36"] Hatch
[9"] [2'-3"] 64 851
[2 1/2"] [2'-9 1/2"]
Top Cone
6[1/4"] Plate
Non Slip Surface
900 [36"] x 900 [36"] Hatch
Within Handrail
[2'-2 1/2"]
[3'-1 3/4"]
672
960
Support Cone
8[5/16"] Plate
900 [36"] Tank
152
[6"]
Obstruction Access Sleeve
Access Tube Sleeve
Light Mount 1200 [48"] O.D. x 8[5/16"] Wall Pipe SECTION 'A'
NOTES:
1. In lieu of a raised platform (15001 Item 1.9.15.2) roof plate thickness of 0.250
(exceeds design thickness of 0.1875.) will be provided along with a non slip
surface within the handrail.
2. In lieu of a "pod flange" ( 15001 Item 1.9.9.6.7 ) couplings are being provided
per Item 1.9.9.6.2/3.
784
[1763.12']
Upper Cone
Plate 6.4 [.250"]
762
Stiffening Bar
Shell #3 13 x 203 [1/2" x 8"] Flatbar
Plate 6.4 [.250"] ( 42 Pc's )
[24'-11 3/8"]
Shell #2
7605
Plate 6.4 [.250"]
[43'-0 1/2"]
1200 [48"] Ø Access Tube
13119
Shell #1
Plate 8.1 [.320"]
Cone #2
[13'-0 1/4"]
Plate 12.1 [.477"] Floor
3969
Plate 6.4 [.250"]
Cone #1
Plate 16.3 [.641"]
Ring Beam
5931 381
[19'-5 1/2"] [1'-3"]
TOWN OF SHELBURNE
No.: Date: By: Revision:
WP WDE
CAN 0391
Landmark Structures Co. BM
3091 Harrison Court Burlington, Ontario, L7M 0W4
Tel: (905) 319-7700 Fax: (905) 319-7706
2021.07.05 N.T.S.
Sk - 5
Proposal for Town of Shelburne, Elevated Water Storage Tank
Request for Proposal
SBA File No: M20009
Project# 1124
Project # 1140
Project # 1097
Project # 1160
Project #1147
Project # 1050
Project # 504
Project # 1065
Project # 1089
Project # 1051
ID Task Task Name Work Start Finish % Aug '21 Sep '21 Oct '21 Nov '21 Dec '22 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '23 Jan
Calendar Duration Complete 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22
1 None 331 d Tue Sep 07 Fri Dec 30 0%
OWNER CONTRACT Sep 07 Dec 30
7 5x10 CET Configuration & Design 0d Tue Sep 07 Tue Sep 07 0% Sep 07
8 5x10 CET Foundation & Pedestal Drawings 20 d Tue Sep 14 Tue Oct 12 0% Sep 14 Oct 12
9 5x10 CET Submission for Approval 0d Tue Oct 12 Tue Oct 12 0% Oct 12
10 5x10 CET Owner Review & Comment 10 d Wed Oct 13 Tue Oct 26 0% Oct 13 Oct 26
11 5x10 CET Misc Iron & Tank Drawings 20 d Wed Oct 13 Tue Nov 09 0% Oct 13 Nov 09
12 5x10 CET Submission for Approval 0d Tue Nov 09 Tue Nov 09 0% Nov 09
13 5x10 CET Owner Review & Comment 10 d Wed Nov 10 Tue Nov 23 0% Nov 10 Nov 23
14 5x10 CET Final Drawings 20 d Wed Nov 10 Tue Dec 07 0% Nov 10 Dec 07
15 5x10 CET Submission for Approval 0d Tue Dec 07 Tue Dec 07 0% Dec 07
16 5x10 CET Owner Review & Comment 10 d Wed Dec 08 Tue Dec 21 0% Dec 08 Dec 21
17 5x10 CET Design Complete 0d Tue Dec 21 Tue Dec 21 0% Dec 21
18 5x10 CET 261 d Mon Nov 01 Mon Nov 14 0%
Construction Nov 01 Nov 14
̄Task Milestone Rolled Up Critical Task Split Group By Summary Inactive Milestone Duration-only Start-only
Critical Task Summary Rolled Up Milestone External Tasks Deadline Inactive Summary Manual Summary Rollup Finish-only
Progress Rolled Up Task Rolled Up Progress Project Summary Inactive Task Manual Task Manual Summary
J
S
S. BURNETT
& ASSOCIATES LIMITED
ENGINEERING X ENVIRONMENTAL
Section A
Form of Proposal
Town of Shelburne, Elevated Water Storage Tank June 2021
Request for Proposals Section A
SBA File No: M20009 Addendum No. 4
FORM OF PROPOSAL
Town of Shelburne
Elevated Water Storage Tank
SBA File No: M20009
4
This proposal submitted by:
Brent Marini 4
Name
4
Landmark Structures Co.
Company Name 4
3091 Harrison Court, Burlington, ON L7M 0W4 4
Address
4
905.319.7700
Telephone Number
4
4
[email protected]
Email Address 4
4
Signature
4
July 15, 2021
Date of Submission
4
Having carefully examined all Quotation Documents related thereto, including the General Terms and
4
Conditions, Description of Works, Schedule of Unit Prices and Form of Proposal and Addendum / Addenda
No. 1 to 5 , I do hereby provide this Proposal in accordance with the Proposal Documents and
4
all specifications, including detailed drawings as may be supplied from time to time, to furnish all 4
materials, labour and equipment and all things necessary within the time specified as described in the
following Sections. 4
The undersigned agrees to accept as full payment, therefore, the sums calculated in accordance with the 4
actual measured quantities.
4
Notes:
1. Proposal to include Harmonized Sales Tax (HST). 4
2. Proposal provided is deemed to be valid for a period of sixty (60) days from date of closing of proposals.
3. All works to be completed by mid August 2022 December 31, 2022, weather permitting, based on award of Contract
within two (2) weeks of date of closing of proposal.
4
M20009_RFP_Shelburne Elevated Water Storage Tank_Add#4_7July21.docx Page 1 of 7
S. Burnett & Associates Limited Project No. M20009
Page No. 2
Contractor: Landmark Structures Co. Notes:
A4 Allowances:
A7 Supply, Erect and Maintain Signs and Traffic Control Devices and 1.00 LS $12,000.00 $12,000.00
Maintain Traffic Flow
SUBTOTAL: $677,000.00
viii) Supply and Install Interior Process Piping, Concrete Support Pads and 1.00 LS $38,600.00 $38,600.00
Pipe Supports (75mm dia. piping and associated valves, fittings,
pipe/equipment supports/housekeeping pads, etc.)
ix) Supply and Install one (1) Vertical In Line Recirculation Pump c/w VFD 1.00 LS $9,600.00 $9,600.00
and Ancillary Equipment
x) Supply and Install Chemical Feed Equipment (Includes: Sodium 1.00 LS $49,400.00 $49,400.00
Hypochlorite Chemical Supply (200 L), All Tankage, Secondary
Containment, Storage, Feed Piping, etc.)
xi) Supply & Install Process Piping, Pump, Magnetic Flow 1.00 LS $24,400.00 $24,400.00
Monitoring, Valves, Fittings, Level Switch, Gauges and
Associated Mechanical Equipment
xii) Supply & Install Plumbing Components (Includes: Piping, 1.00 LS $39,000.00 $39,000.00
Drainage Piping, Plumbing Fixtures, Sink with Counter, Eye
Wash Station, etc.)
xiii) Supply and Install Miscellaneous Metals 1.00 LS $136,900.00 $136,900.00
xiv) Supply and Install of Piping, Backflow Preventor, 1.00 LS $32,500.00 $32,500.00
Instruments, Valves, Drain, Hose Connection, Weather Proof Control
Panel, Lighting, Splash Pad with Catch Basin etc. for Truck Fill Station
xv) Communication Support Structure & Navigational Beacon 1.00 LS $10,200.00 $10,200.00
Infrastructure (as per Nav-Can Requirements)
xv i) Operator Workbench, Chair, Cabinet, etc. 1.00 LS $2,600.00 $2,600.00
xvii) Graphics 1.00 LS $22,800.00 $22,800.00
xviii) Painting 1.00 LS $670,400.00 $670,400.00
xix) Cladding and Insulation for Rooms inside the Shaft (Chemical, Storage 1.00 LS $25,700.00 $25,700.00
and Equipment Room)
xx) Supply and Install Fire Extinguishers and First Aid Kits 1.00 LS $1,200.00 $1,200.00
xxi) Pressure Testing, Swabbing & Flushing and Disinfection 1.00 LS $8,200.00 $8,200.00
xxii) As-Builts 1.00 LS $4,400.00 $4,400.00
xxiii) Close Out Report 1.00 LS $1,600.00 $1,600.00
SUBTOTAL: $4,522,300.00
c) Supply and Installation of HVAC Equipment and Ancillary 1.00 LS $21,600.00 $21,600.00
Components
d) Supply & Installation of Plumbing Components (Includes: 1.00 LS $6,800.00 $6,800.00
Drainage Piping, Plumbing Fixtures, etc.) in the Equipment,
Chemical and Storage Rooms
e) Supply and Installation of Ventilation Equipment 1.00 LS $25,300.00 $25,300.00
f) Supply and Install:
i) Chlorine analyzers (2), Flowmeters (2), Temperature 1.00 LS $42,000.00 $42,000.00
Transmitter (1), Pressure Transmitter (1)
ii) Associated process piping, Isolation valves, drain 1.00 LS $12,400.00 $12,400.00
connections etc.
g) Supply and Installation of Electrical Power Distribution System and Control 1.00 LS $252,500.00 $252,500.00
Equipmcnt
h) Supply and Installation of PLC hardware, Communication 1.00 LS $78,000.00 $78,000.00
Modem and Antennas, c/w Panel Door Mounted SCADA
Computer and Instrumentation and Associated Components
within the Tower
i) Supply and Installation of Standby Natural Gas Power Generator and Concrete 1.00 LS $42,400.00 $42,400.00
Foundation Pad
j) Supply and Installation of All Exterior and Interior Lighting, 1.00 LS $86,600.00 $86,600.00
including Fixtures and Receptables
k) PLC, SCADA and Alarm Annunciation Programming 1.00 LS $42,000.00 $42,000.00
B2 Yard Piping:
a) Supply and Installation of HDPE/PVC Watermain (from Tower 105.00 m(l) $1,000.00 $105,000.00
to Luxton Way):
b) Supply and Installation of HDPE/PVC Watermain (from Tower to Simon St.) by:
c) Supply and Installation of All Watermain Isolation Valves, Valve Boxes, 1.00 LS $52,000.00 $52,000.00
Reducers and Fittings, etc.
d) Final Connections and All Coordination Costs by the General 1.00 LS $55,800.00 $55,800.00
Contractor Associated with Connection of the Distribution
Watermain from the Tower to Luxton Way and Simon St.
e) Supply and Installation of 150mm dia. DR28 PVC Sanitary 100.00 m(l) $408.00 $40,800.00
Sewer
f) Supply and Installation of 1200 mm dia. Sanitary Manhole (MH- 1.00 LS $24,400.00 $24,400.00
01) on Luxton Way
g) Final Connections Including All Coordination Costs by the 1.00 LS $25,600.00 $25,600.00
General Contractor Associated with Connection of the Sanitary Sewer (including
manhole etc. as shown on the contract drawings) on Luxton Way
h) Supply and Installation Overflow Structure to Besley Drain 1.00 LS $132,600.00 $132,600.00
(Including: Swale, Drainage Culvert, Rip-Rap/Armorstone
Treatment, Concrete Splash Pad, Outfall Headwall, Truck Fill
Station Drain Trench, Drainage Piping, etc.)
SUBTOTAL: $1,208,550.00
B3 Site Works:
a) Supply and Construct Granular Access Road to Tower 1.00 LS $89,400.00 $89,400.00
Location
SUBTOTAL: $267,200.00
C1 Excavation of Unsuitable Soil Below Grade Specified incl. 100.00 cu.m. $84.00 $8,400.00
Placement of Additional Granular Bedding Material &
Disposal of Excavated Material
C2 Supply, Place & Compact Granular incl. Excavation & Disposal of
Existinq Material:
a) Granular A 50.00 cu.m. $84.00 $4,200.00
b) Granular B 50.00 cu.m. $82.00 $4,100.00
c) 19mm Clear Stone 25.00 cu.m. $94.00 $2,350.00
d) Rip-Rap 50.00 cu.m. $119.00 $5,950.00
e) Pre-mixed Concrete (25 MPA) 20.00 cu.m. $244.00 $4,880.00
C3 Labour Rates for Additional Work:
(The rate shall include payroll burden, overhead & profit)
SUBTOTAL: $78,950.00
COST SUMMARY
SCHEDULE OF UNIT PRICES
DESCRIPTION CONTRACTTOTAL
SUBTOTAL: $6,754,000.00
HST13%: $878,020.00
TOTAL: $7,632,020.00
A certified cheque or Bid Bond for the sum of: 10% is enclosed.
(Minimum of $)
ADDENDUM No. 1
1
Date: June 25, 20221 Project No: M20009
Project Name: Request for Proposal: Town of Shelburne, Elevated Water Storage Tank
1
To: All Bidders 1
This Addendum consists of 27 pages total. 1
Please make the following changes / additions to the Request for Proposal Document. Bidders are 1
responsible to ensure that all addenda have been received. Bidders shall be required to acknowledge
addenda in the space provided in Section A of the Proposal Form. 1
This addendum will form part of the terms, conditions and specifications outlined in the above noted
Request for Proposal Contract Document. All other components of the Bid documents shall remain
1
unchanged.
1
***REMINDER: BIDDERS MUST IDENTIFY THIS ADDENDA IN THE SPACE PROVIDED IN SECTION A OF THE
PROPOSAL FORM***
1
CLARIFICATIONS / MODIFICATIONS / DELETIONS
1
1. Bidders shall REMOVE AND REPLACE page 15 of 23 of the Request for Proposals Contract
1
Document, with the attached.
1
2. Bidders shall REMOVE AND REPLACE page 5 of 6 of the Scheduled Unit Prices with the attached. 1
3. Bidders shall REMOVE AND REPLACE the following Specifications: 1
Specification 09002: Painting - Interior & Exterior of Elevated Tank & Appurtenances,
page 1 of 3 1
Specification 15001: Water Tower Design Criteria, page 5 and page 32 of 39
Specification 15425: Water Quality Monitoring Equipment, in its entirety 1
4. Bidders shall ADD the following Specifications to the Contract Documents, in their entirety:
1
Specification 16865: Electric Heating & Cooling
Specification 16920: Process Narrative
1
5. Bidders shall REMOVE AND REPLACE the following Contract Drawings with the attached:
1
Drawing C2.3: Proposed Grading Plan Overflow & Emergency Outlet Plan and Profile 1
Drawing W5.2: Standard Details -2
www.sbaengineering.com I al JM
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 2 of 3
Addendum No. 1
SBA File No: M20009
Question 1: With regards to Section 15402 Flowmeters, please confirm if ABB Magnetic Flowmeters 1
supplied by SCG Process (formally Metcon) is approved. These meters have been supplied
and serviced locally to OCWA. 1
Response 1: Yes, ABB is an acceptable manufacturer for flowmeters. 1
1
Question 2: Section 16900: 2.3 Pressure Transmitter - Please confirm Siemens will be considered as
acceptable manufacturer for pressure transmitter. Siemens has been acceptable supplier 1
in past tenders.
1
Response 2: Yes, Siemens is an acceptable manufacturer for pressure transmitter.
1
Question 3: Section 16900 2.3.13 - Confirm 2000 psi is required range.
1
Response 3: 2000 psi is not the range. The measuring device in the pressure transmitter shall be
capable of handling a maximum working pressure of 2000 psig.
1
Question 4: Section 15402 2.1.3 - Carbon steel housing and flanges acceptable?
1
Response 4: Carbon steel housing and flanges with epoxy coating is acceptable. Dielectric couplings
1
should also be provided to prevent corrosion.
1
Question 5: We have prepared a specification for a Goulds equivalent to the Grundfos CRN pump that
has been specified. We believe that the Goulds product meets the specifications and
1
standards that has been laid out in the RFP. My question is to whether an ODP style motor 1
(OPEN DRIP PROOF) would be acceptable in the installation, or is the preference for a TEPE
(Totally Enclosed Premium Efficiency) motor. With the pump being installed in an indoor 1
equipment room, an ODP motor should be acceptable.
1
Response 5: TEPE motor is preferred.
1
1
1
1
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 3 of 3
Addendum No. 1
SBA File No: M20009
1
Brent Marini, Director - Landmark Structures Co. Bidder's Name
1
Signature 1
June 25, 2021 Date 1
1
M20009_Add#1_FINAL_25June21.docx
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
S BURNETT
SBA, & ASSOCIATES LIMITED
A ENGINEEIIIR & E1I1110111F,NTAL
ADDENDUM No. 2
Date: June 30, 20221 Project No: M20009
2
Project Name: Request for Proposal: Town of Shelburne, Elevated Water Storage Tank
1. Bidders are advised that all requests for equivalents will be received and reviewed following
2
Award of Contract. 2
2. Bidders shall REMOVE AND REPLACE pages 4 and 6 of Section A: Form of Proposal, Schedule of 2
Unit Prices with the attached.
2
Bidders shall REMOVE AND REPLACE the following Specification:
3.
Specification 15001: Water Tower Design Criteria, pages 33 and 36 of 39.
2
4. Bidders shall ADD the following Specification, in its entirety, to the Contract Documents:
2
Specification 16480: Motor Control Centers
2
2
2
2
2
www.sbaengineering.com I LI JM
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 2 of 2
Addendum No. 2
SBA File No: M20009
Question 1: Item .8 Butterfly valves, sub -section .5 torque tube. Please confirm that the torque tube
can be made out of schedule 40 steel (epoxy in/out) versus stainless steel. Typically these
are made out of stainless steel. 2
Response 1: Torque tube shall be made out of stainless steel.
2
2
Question 2: Can CAD files for the Civil Drawings be provided. As a minimum we require the
topo/grading plan. 2
Response 2: CAD files to be provided to the successful Bidder upon award of Contract. However, the
2
Contractor should satisfy themselves of the actual condition of the site, if necessary.
2
Question 3: Can an excel version of Section A Form of Proposal be provided?
2
Response 3: An Excel version of Section A: Form of Proposal has been included with this
Addendum No. 2, as requested.
2
2
I have read the foregoing Addendum and have considered it in my Proposal. 2
2
Brent Marini, Director - Landmark Structures Co. Bidder's Name
2
Signature 2
June 30, 2021 Date 2
2
M20009_Add#2_FINAL_30June21.docx
2
2
2
2
2
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
S BURNETT
SBA, & ASSOCIATES LIMITED
A ENGINEEIIIR &ENI1110111F,NTAL
ADDENDUM No. 3
Date: July 5, 20221 Project No: M20009
Project Name: Request for Proposal: Town of Shelburne, Elevated Water Storage Tank 3
To: All Bidders
3
This Addendum consists of 1 page total.
3
Please make the following changes / additions to the Request for Proposal Document. Bidders are
responsible to ensure that all addenda have been received. Bidders shall be required to acknowledge
3
addenda in the space provided in Section A of the Proposal Form.
3
This addendum will form part of the terms, conditions and specifications outlined in the above noted
Request for Proposal Contract Document. All other components of the Bid documents shall remain
3
unchanged.
3
***REMINDER: BIDDERS MUST IDENTIFY THIS ADDENDA IN THE SPACE PROVIDED IN SECTION A OF THE
PROPOSAL FORM*** 3
CLARIFICATIONS / MODIFICATIONS / DELETIONS 3
1. Bidders are advised that the closing date for the RFP has been extended until: 3
Thursday, July 15, 2021, at 2:00 pm, local time.
3
The Question has now ended. Responses to questions will be addressed by
Period
Wednesday, July 7, 2021.
3
2. Bidders shall note that the Schedule of Unit Prices Excel document provided in Addendum No. 2
3
was for reference purposes only and that all formula correctness will be the responsibility of the
Bidder.
3
3
I have read the foregoing Addendum and have considered it in my Proposal.
3
Brent Marini, Director - Landmark Structures Co. Bidder's Name 3
Signature 3
July 05, 2021 Date 3
M20009_Add#3_FINALO5July21.docx
3
www.sbaengineering.com I E9 ®® 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
S BURNETT
SBA, & ASSOCIATES LIMITED
A ENGINEEIIIR & E1I1110111F,NTAL
ADDENDUM No. 4
Date: July 7, 20221 Project No: M20009
Project Name: Request for Proposal: Town of Shelburne, Elevated Water Storage Tank 4
To: All Bidders
4
This Addendum consists of 37 pages total.
4
Please make the following changes / additions to the Request for Proposal Document. Bidders are
responsible to ensure that all addenda have been received. Bidders shall be required to acknowledge
4
addenda in the space provided in Section A of the Proposal Form. 4
This addendum will form part of the terms, conditions and specifications outlined in the above noted 4
Request for Proposal Contract Document. All other components of the Bid documents shall remain
unchanged. 4
***REMINDER: BIDDERS MUST IDENTIFY THIS ADDENDA IN THE SPACE PROVIDED IN SECTION A OF THE
4
PROPOSAL FORM***
4
CLARIFICATIONS / MODIFICATIONS / DELETIONS 4
1. Bidders shall REMOVE AND REPLACE pages 1, 3, 4 and 7 of Section A: Form of Proposal, Schedule 4
of Unit Prices with the attached.
4
2. Bidders shall refer to attached Addendum No. E-03 from Runge & Associates.
4
3. Bidders shall REMOVE AND REPLACE the following Specifications:
Specification 15420: Chemical Fee Pumps & Accessories, in its entirety.
4
Specification 15001: Water Tower Design Criteria, pages 15 and 36-38 of 41.
4
4. Bidders shall ADD the following Specification, in its entirety:
Specification 16915: SCADA Software and Accessories.
4
4
5. Bidders shall ADD the following Permits and include them in the Contract Documents:
Ministry of the Environment, Conservation and Parks, Drinking Water Works Permit 4
NAV Canada
Nottawasaga Valley Conservation Authority. 4
4
www.sbaengineering.com I al JM
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 2 of 10
Addendum No. 4
SBA File No: M20009
6. Bidders shall ADD the following Contract Drawings and include them in the Contract Documents:
A1.1: Door and Window Schedule
E3.2: PLC Instrumentation Loop Diagrams, Sheet 2.
7. Bidders shall REMOVE AND REPLACE the following Contract Drawings and include them in the
4
Contract Documents:
E3.3: PLC Panel Layout, Power Distribution & Communication Topology (previously
4
named E2.3).
4
QUESTIONS AND REPSONSES 4
Question 1: Spec section 15100, 1.9.17.5 (overflow piping) - Calls for the use of a duckbill check valve. 4
There is no specification for such valve. I request Proco rubber check valves be included in
this spec. Please see the attached literature for details. 4
Response 1: Duckbill valve shall be made of NSF -61 certified product elastomers with mounting clamps 4
or retaining rings made of 304 or 316 stainless steel. The valve shall be engineered to crack
open at 1"-2" head pressure and shall be designed for a maximum working pressure of 4
75 psig. Approved Manufacturer: Tideflex, Proco or approved equal.
4
Question 2: Drawing C2.4 - please confirm we can extend the location of the silt fence further west
and south (keeping within the Project Area) to allow sufficient room to construct the
4
elevated tank. 4
Response 2: Yes. 4
Question 3: Drawing W2.2 the tank is shown with an "upper return" at the intersection of the tank 4
roof and the side wall. However, it is not dimensioned or described in Section 15001. Is an
upper return required? If so, we suggest the following industry standard nominal 4
dimensions of 450 mm H / 750 mm V.
4
Response 3: This is a design build contract. Tank design shall be as per Contractor's recommendation
for operation as intended to be approved by Engineer.
4
4
4
4
4
www.sbaengineering.com I II (g® 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 3 of 10
Addendum No. 4
SBA File No: M20009
Question 4: Part 1- Description of Works - Item 3.2 requires the Proposal Submission to include a list
of all subcontractors as well as names and experience records for each person. We have
no issues naming our subcontractors however, we request any experience documentation
be made a post bid submission as we will not know who our low subcontractors will be
until just prior to bid closing. 4
Response 4: This is acceptable with the understanding that the Owner will have the right to review and
4
approve all subcontractors named by the General Contractor for this project.
4
Question 5: Part 1- Description of Works - Item 7.3 describes a 90 -day bid validity. However, Section A
Form of Proposal Page 1 of 7 describes a 30 -day bid validity. Please clarify.
4
4
Response 5: Bid validity shall be 60 -days. Please refer to updated Section A: Form of Proposal, Page 1,
attached to this Addendum No. 4. 4
Question 6: Part 2 - General Terms and Conditions- Item 5 describes a completion of no later than 4
mid -August 2022. Can the completion date be revised to December 31, 2022?
4
Response 6: Yes, the Project Completion Date has been extended to December 31, 2022. Please refer
to updated Section A: Form of Proposal, Page 1, attached to this Addendum No. 4.
4
Question 7: Section A, Form of Proposal - Schedule of Unit Prices Page 5 Item 83.g - Addenda 1
4
removed this item from the Bid Schedule, but the revised drawings still show the
requirement for the outfall and rip rap check dam - please clarify.
4
Response 7: Scope of work for the construction of the outfall and rip rap check dam is included under
4
Item B2 h). 4
Question 8: Section A, Form of Proposal Page 7 of 7. The Bid Bond amount is not identified. The General
Terms and Conditions only require the Bidder to include with their proposal an Agreement
4
to Bond. Please confirm a Bid Bond is not required. 4
Response 8: As referenced in Part 2: Item 18: Submissions and Item 20: Insurance and Bonding, a 4
certified cheque or bid bond is required with the Proposal submission. The Bid Bond
amount shall be 10% of the Proposal amount and sealed by a corporation duly authorized 4
to transact the business of Surety slip. Please refer to Section A: Cost Summary, attached
to this Addendum No. 4. 4
4
4
www.sbaengineering.com I II I:g @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 4 of 10
Addendum No. 4
SBA File No: M20009
Question 9: Section 09002 Item 1.1.2 says the Contractor is responsible for full time coating inspection.
However, the Form of Proposal, Schedule of Unit Prices Item A.4.d.ii includes a $15,000
cash allowance for Coating Inspections. Please confirm any 3rd party coating inspection
costs will be paid under the cash allowance.
4
Response 9: Yes.
4
Question 10: Section 15001 Item 1.14.2 says the Contractor is responsible for part time welding
inspection. However, the Form of Proposal, Schedule of Unit Prices Item A.4.d.i includes a
4
$15,000 cash allowance for Welding Inspections. Please confirm any 3rd party welding
inspection costs will be paid under the cash allowance.
4
4
Response 10: Yes.
4
Question 11: Section 15001 Item 1.14.6 - Please confirm 3rd party concrete inspection costs will be paid
under the cash allowance. 4
Response 11: Yes 4
Question 12: Section 15001 Item 1.1 lists the equalization volume as 1064 m3 and the fire/emergency
4
volume as 1751 m3 for a total volume of 2,815 m3. This differs from the Drawings and
elsewhere in Section 15001.
4
Response 12: These are 20 -year estimated equalization, fire/emergency volumes requirements. Volume
4
of tank required is 3,410 m3 same as the existing Shelburne Water Tower.
4
Question 13: Please confirm the tank Volume as 3,410 m3.
4
Response 13: Yes 4
Questionl4: Section 15001, Item 1.9.7.4.5 - please specify the thickness of insulation on the inlet and 4
outlet risers.
4
Response 14: Insulation thickness on the inlet and outlet risers shall be 50 mm.
4
Question 15: Section 15001, Item 1.9.7.4.5 - please specify the quantity of both duty and standby heat
trace cables on the inlet and outlet risers. 4
Response 15: Refer to attached Addendum No. E-03 from Runge & Associates.
4
4
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 5 of 10
Addendum No. 4
SBA File No: M20009
Question 16: Section 15001, Item 1.9.7.4.5 - please specify the quantity of controllers for both duty and
standby heat trace cables on the inlet and outlet risers.
Response 16: Refer to attached Addendum No. E-03 from Runge & Associates.
4
Question 17: Section 15001, Item 1.9.7.5.4 - please confirm the overflow riser does not require heat
trace and insulation.
4
Response 17: Insulation is required on the overflow riser. Heat Trace is not required. Thickness of
4
insulation shall be 50 mm.
4
Question 18: Section 15001 Item 1.9.5.3 specifies a 5 m diameter roof handrail. Section 15001 4
Item 1.9.5.4 specifies a 7 m diameter roof handrail. Please confirm only (1) roof handrail
is required at 7 m diameter. 4
Response 18: We would recommend 7 m, however Contractor to confirm the most appropriate 4
diameter required for size of proposed tank.
4
Question 19: Section 15001 Item 1.9.9.3 specifies (4) sets of fall arrest trolleys however Item 1.16.10.7
specifies (3) sets of trolleys. Please clarify.
4
Response 19: Provide (4) sets of fall arrest trolleys.
4
Question 20: Section 15001 Item 1.9.8 (Page 6 of 39) - we suggest this item be struck from the
4
specification as there are no exterior aluminum ladders. 4
Response20: Contractor to note Section 15001 items are required as applicable. 4
Question 21: Section 15001 Item 1.9.9.6.7 (Page 8 of 39) specifies a "pod flange" this is not required 4
since there are multiple steel spools being installed at the top of the access tube
(Item 1.9.9.6.2/3). Please strike Item 1.9.9.6.7 from the specification. 4
Response 21: Contractor to note Section 15001 items are required as applicable. 4
4
4
4
4
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 6 of 10
Addendum No. 4
SBA File No: M20009
Question 22: Section 15001 Item 1.9.15.2(Page 13 of 39) describes a raised platform to be used as a
walkway without stepping on the roof when accessing the outer rail and the 6 antennae
locations. It is common to walk directly on the roof as the roof is more than robust enough
to support that activity without cracking any coating. Please strike this item from the
specification. 4
Response 22: Contractor to note Section 15001 items are required as applicable.
4
Question 23: Section 15001 Item 1.14.14.2 (page 22 of 39) references a roof leak test for an aluminum
4
dome room. Please strike this item from the specification.
4
Response 23: Contractor to note Section 15001 items are required as applicable. 4
Question 24: Section 15001 Item 1.14.14.3 (page 22 of 39) references a tank leak test for a AWWA D103 4
bolted tank. Please strike this item from the specification.
4
Response 24: Contractor to note Section 15001 items are required as applicable.
4
Section 15001, Item 1.14.19.3.1 (Page 25 of 39) describes an aluminum dome roof per
Question 25:
AWWA D108. This sentence should be reworded: Erection of the roof shall be in
4
accordance with the requirements of AWWA D107.
4
Response 25: Contractor to note Section 15001 items are required as applicable.
4
Question 26: Section 15001, Item 1.14.19.3.2 (Page 25 of 39) describes an aluminum dome roof. This
can be corrected by replacing "dome" with "roof".
4
4
Response 26: Contractor to note Section 15001 items are required as applicable.
4
Question 27: Section 15001 makes occasional references to AWWA D100, please confirm any reference
to AWWA D100 should reflect AWWA D107. 4
Response 27: Contractor to note Section 15001 items are required as applicable. 4
Question 28: Section 15001, Item 1.16.3 instructs to grind exposed welds smooth and flush. We suggest
4
the following clarification - which is industry standard. Grinding of weld contour shall
approximate Condition D of NACE Standard SP0178.
4
Response 28: This is acceptable.
4
4
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 7 of 10
Addendum No. 4
SBA File No: M20009
Question 29: Section 15001, Item 1.21.13.2 (Page 36 of 39) - we suggest this item be struck from the
specification as there is no requirement for any aviation markings.
Response 29: Contractor to note Section 15001 items are required as applicable.
4
Question 30: Are any roads leading to this tank site (Victoria Street, 2 Line, 30 Side Road, Prentice Drive,
Luxton Way) subject to Spring load weight restrictions?
4
Response 30: Annual load / weight restrictions will be in effect for: County Road 11, 30th Sideroad and
4
Prentice Drive from March 31 to May 31. In -town municipal roadways are exempt from
load restrictions.
4
4
Question 31: Section 15420 Item 2.1.9 - We request you add Blue -White M Series Peristaltic Pumps
supplied by SPD sales limited as an acceptable product for chemical feed pumps. 4
Response 31: Watson Marlow pumps are a preference of the water tower operating authority (OCWA) 4
and the Town of Shelburne.
4
Question 32: Section 015001 Item 1.10 Cathodic Protection -Are Magnesium anodes acceptable?
4
Response 32: Yes.
4
Section 015001 Item 1.10 Cathodic Protection - Are cathodic protection monitoring
Question 33:
reference electrodes required?
4
Response 33: Yes.
4
Question 34: Drawing E3.2 Detail 3 shows a 2000VA UPS, Detail 3 shows a 3000VA UPS. Please clarify.
4
Response 34: Refer to attached Addendum No. E-03 from Runge & Associates.
4
4
Question 35: Drawing E3.2 Detail 3 - Please provide a spec and part number for both the cellular dialer
and the antennas. 4
Response 35: Refer to attached Addendum No. E-03 from Runge & Associates. 4
4
4
4
www.sbaengineering.com I II (g® 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 8 of 10
Addendum No. 4
SBA File No: M20009
Question 36: Drawing E2.1 Detail 1- should this be titled 208V single line diagram?
Response 36: Refer to attached Addendum No. E-03 from Runge & Associates. 4
Question 37: Drawings E2.1 Detail 1- should this be labeled PC06? 4
4
4
LUZ
4
t 4
Response 37: Refer to attached Addendum No. E-03 from Runge & Associates. 4
Question 38: Drawing E2.1 Detail 1- please provide a specification on the primary feeder.
4
EW11.4 -P1.14 E
adEAUDE. LErhic E
4
1.11. Es PA.E LP k E
LOCAL LMLIT.'
MILE 'till FUSE
cur-ours
4
2idalr fte,?' rr:
4
THAMININIER
4
4
Response 38: Refer to attached Addendum No. E-03 from Runge & Associates.
4
Question 39: Section 16400 Item 2.9 -is there shore power to the generator? Currently no breaker
shown for this on E1.1.
4
Response 39: Refer to attached Addendum No. E-03 from Runge & Associates.
4
4
Question 40: Can a door schedule be provided?
4
Response 40: Please refer to Drawing A1.1: Door and Window Schedule attached to this
Addendum No. 4. 4
4
www.sbaengineering.com I I @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 9 of 10
Addendum No. 4
SBA File No: M20009
Question 41: Does the entire slab on grade receive an epoxy floor finish, including the vestibule?
Question 42: Do the room interior masonry walls receive any coatings? 4
Response 42: Yes.
4
Question 43: Please specify the block size of the interior masonry walls, both single and double wall.
4
Response 43: For structural interior walls 190 mm thickness blocks shall be utilised. For non-structural
4
interior walls 140 mm thickness blocks shall be utilized. All the blocks regardless of being 4
structural or non-structural shall be anchored to the underside concrete slab by 15M bars
at 400 mm spacing. 4
Question 44: Does the top side of the chamber roof receive any coatings? 4
Response 44: No. Refer to Drawing W2.1. 4
Question 45: Section 08800 - Item 2.3 - what Is the size of the window between the chemical room and
4
the valve room.
4
Response 45: Please refer to Drawing A1.1: Door and Window Schedule attached to this
Addendum No. 4.
4
Question 46: Section 08800 Item 2.4 - please confirm this is not applicable to this contract.
4
Response 46: Yes, not applicable.
4
Question 47: Are there and bore hole logs for the anything other than the tank pedestal? -if not what
4
amount/ thickness of topsoil is to be assumed as part of the site preparation. 4
Response 47: Minimum of 100 mm thickness of topsoil will be required. 4
Question 48: Is a Permit To Take Water needed for the watermain and outfall works north of the 4
proposed tower?
4
As per the new guidelines, the Contractor does not need to get a PTTW unless dewatering
Response 48:
exceeds 400,000 L/day.
4
4
www.sbaengineering.com I II @ @I 0
Tel (519) 941-2949 I Fax (519) 941-2036 I [email protected]
210 Broadway, Unit 203 Orangeville, ON L9W 5G4
Town of Shelburne, Elevated Water Storage Tank Page 10 of 10
Addendum No. 4
SBA File No: M20009
Question 49: There are no details for the road restoration to tie into the exiting sanitary line but for
asphalt specifications.
ADDENDUM No. 5
Date: July 9, 2021 Project No: M20009
5
Project Name: Request for Proposal: Town of Shelburne, Elevated Water Storage Tank
4. COVERAGES
This is to certify that the policies of insurance listed below have been issued to the insured named above for the policy period indicated notwithstanding any requirements, terms
or conditions of any contract or other document with respect to which this certificate may be issued or may pertain. The insurance afforded by the policies described herein is
subject to all terms, exclusions and conditions of such policies.
LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS
EFFECTIVE EXPIRY LIMITS OF LIABILITY
INSURANCE COMPANY DATE (Canadian dollars unless indicated otherwise)
TYPE OF INSURANCE DATE
AND POLICY NUMBER AMOUNT OF
YYYY/MM/DD YYYY/MM/DD COVERAGE DED.
INSURANCE
2021/04/26 2022/04/26 COMMERCIAL GENERAL LIABILITY $2,500
COMMERCIAL GENERAL LIABILITY Intact Insurance Company - BODILY INJURY AND PROPERTY DAMAGE
5A5004801 LIABILITY - GENERAL AGGREGATE
CLAIMS MADE OR ✔ OCCURRENCE
- EACH OCCURRENCE $2,000,000
✔ PRODUCTS AND / OR COMPLETED OPERATIONS
PRODUCTS AND COMPLETED OPERATIONS $2,000,000
✔ EMPLOYER’S LIABILITY AGGREGATE
✔ CROSS LIABILITY PERSONAL INJURY LIABILITY
OR
PERSONAL AND ADVERTISING INJURY
✔ LIABILITY $2,000,000
MEDICAL PAYMENTS $50,000
✔ TENANTS LEGAL LIABILITY TENANTS LEGAL LIABILITY $500 $500,000
POLLUTION LIABILITY EXTENSION POLLUTION LIABILITY EXTENSION
✔ NON-OWNED AUTOMOBILES Intact Insurance Company - 2021/04/26 2022/04/26 NON OWNED AUTOMOBILE $2,000,000
HIRED AUTOMOBILES 5A5004801
AUTOMOBILE LIABILITY Intact Insurance Company - 2021/05/31 2022/04/26 BODILY INJURY AND PROPERTY
DESCRIBED AUTOMOBILES AF5701952 DAMAGE COMBINED $2,000,000
✔ ALL OWNED AUTOMOBILES BODILY INJURY (PER PERSON)
✔ LEASED AUTOMOBILES ** BODILY INJURY (PER ACCIDENT)
** ALL AUTOMOBILES LEASED IN EXCESS OF
30 DAYS WHERE THE INSURED IS REQUIRED
TO PROVIDE INSURANCE PROPERTY DAMAGE
EXCESS LIABILITY Intact Insurance Company - 2021/04/26 2022/04/26 EACH OCCURRENCE $10,000 $15,000,000
✔ UMBRELLA FORM 5A5004801
AGGREGATE $10,000 $15,000,000
5. CANCELLATION
Should
Should any
anyof
ofthe
theabove
abovedescribed
describedpolicies
policiesbebecancelled
cancelledbefore
beforethe
theexpiration
expirationdate
date thereof, thethe
thereof, issuing company
issuing company willwillendeavor to mail
endeavour ________
to mail days
30 days written
written notice
notice to the
to the certificate
certificate holder
holder
namednamed
above,above, but failure
but failure to mailtosuch
mail notice
such notice shall impose
shall impose no obligation
no obligation or liability
or liability of anyofkind
anyupon
kind the
uponcompany,
the company, its agents
its agents or representatives.
or representatives.
6. BROKERAGE/AGENCY FULL NAME AND MAILING ADDRESS 7. ADDITIONAL INSURED NAME AND MAILING ADDRESS
(but only with respect to the operations of the Named Insured)
The Mitchell & Abbott Group Insurance Brokers Town of Shelburne and S. Burnett & Associates Limited
SIGNATURE OF
DATE July 5, 2021 EMAIL ADDRESS [email protected]
AUTHORIZED REPRESENTATIVE
CSIO C0910ECL - CERTIFICATE OF LIABILITY INSURANCE - 2010/09 c 2010, Centre for Study of Insurance Operations. All rights reserved.
DonnaB
Proposal for Town of Shelburne, Elevated Water Storage Tank
Request for Proposal
SBA File No: M20009
Appendices
I, Chris Lamon, being the President of Landmark Structures Co., (Bidder) do hereby confirm that no
exceptions are taken to the requirements and procedures described in the specifications for the
above noted project.
List of Subcontractors
Composite
Elevated Tanks
for Water Storage
2 | Composite Elevated Tanks for Water Storage © 2020 Landmark | 3
$$
SPHEROID
$$$$
FLUTED COLUMN
$$$$
The protected space inside the pedestal adds the economic and functional advantages of multiple use opportunities—for pump
stations, office space and storage space or control centers, with build-outs to suit a range of applications for full utilization.
MULTI-LEGGED
4 | Composite Elevated Tanks for Water Storage © 2020 Landmark | 5
Tank Diameter
200,000 25 - 30 38 - 44 20 - 24
250,000 30 - 35 38 - 44 20 - 24
300,000 30 - 35 44 - 48 20 - 24
Head Range
400,000 30 - 35 46 - 52 24 - 28
500,000 30 - 38 51 - 55 24 - 28
600,000 30 - 40 53 - 62 24 - 28
750,000 30 - 40 59 - 65 28 - 32
1,250,000 30 - 40 68 - 74 32 - 38
1,500,000 35 - 40 75 - 80 38 - 42
1,750,000 38 - 45 82 - 87 42 - 46
2,000,000 40 - 45 90 - 95 42 - 46
2,250,000 40 - 50 95 - 100 46 - 54
2,500,000 40 - 50 95 - 100 46 - 54
2,750,000 40 - 50 100 - 110 54 - 60
3,000,000 40 - 50 102 - 112 54 - 60
3,250,000 40 - 50 105 - 115 54 - 60
3,500,000 45 - 55 112 - 123 60 - 66
3,750,000 45 - 55 115 - 125 60 - 66
4,000,000 45 - 55 116 - 128 60 - 72
Pedestal Diameter
Superior Aesthetics of
Architectural Concrete
Landmark consistently delivers the “uniform color, absence
of defects, and aligned and even surfaces” defined in the
ACI 303R-04 standard for architectural concrete. Heavy-
duty forming systems, highly refined placement processes
and extensive team experience ensure industry-leading
quality control.
6 | Composite Elevated Tanks for Water Storage © 2020 Landmark | 7
Available Appurtenances
Following is a list of available appurtenances to consider for your application:
Landmark Hydrodynamic
Mixing Systems
Landmark Hydrodynamic Mixing
Systems protect against aging and
contamination by forcing movement
within the entire storage area each
time the tank is filled. Common quality
concerns including taste and odor
issues, bacterial growth and nitrification
are mitigated by creating a homogenous
The Landmark CET: mix of stored and newly added water.
Every Landmark mixing system is based on extensive CFD analysis of the
A Closer Look tank’s unique geometry, operation cycle and flow magnitude. Seasonal
demand changes and future operating parameters can also be modeled
to ensure proper configuration of the system.
8 | Composite Elevated Tanks for Water Storage © 2020 Landmark | 9
Siting, budgeting and the geotechnical evaluation are the essential starting points for a new tank project. In general, a
square site with 200-foot sides is an ideal location. But many tanks are constructed on sites with a unique set of obstacles.
Access, grades, power lines and trees can greatly affect the price of the project, and potential sites should be carefully
considered. Landmark can provide information about the cost impact of these variables as they relate to both initial
construction and future maintenance.
Once candidate sites have been prequalified and selected, the responsible party should engage a qualified geotechnical
engineer with knowledge of local soil conditions. Landmark’s technical bulletin, “Guidelines for Geotechnical Reports”
provides recommendations for getting a high-quality geotechnical report to ensure that elevated tank builders can provide
the most efficient foundation allowable. Landmark can also provide required information such as tank and pedestal
dimensions, structure and water weight, and wind and seismic loads.
Prior to bid advertisement, Landmark can assist with a final documents review and provide a detailed budget based on
project specifics.
CONSTRUCTION Engineering Mobilize Foundation Pedestal Ground Phase Erection and Coating Tank Raise Air Phase Erection and Coating Electrical, mechanical site work Commission
Contact Landmark for a preliminary schedule for your project. Schedules are subject to variations in local permitting
processes and other factors.
10 | Composite Elevated Tanks for Water Storage © 2020 Landmark | 11
truck lane for loading and unloading, with extensive Fabrication’s high capacity steel,
material handling capabilities. Outside, similar crane
tank and components operations
systems enable efficient management of the main
Landmark Fabrication technicians can provide design assistance for to precise tolerances can reduce welding
requirements, simplifying production and
prototyping and production processes in carbon steel, stainless steel,
enhancing results.
aluminum or other metals; create jigs and fixtures; and recommend the
galvanizing and other special requirements. Capabilities are matched to Press Forming
Produces precise spherical and double
your needs, whether a single critical part or complete production sequence.
curved shapes, with a 750 ton capacity.
Our investments in the finest equipment, materials and talent deliver precise Provides the ability to dish plate from
results, superior quality and exceptional value for structural elements as 3/16 to 2" thick at any radius or
Welding
Landmark employs a wide range of
precision welding equipment for large and
small components including a 10’ x 60’
gantry welder equipped with four 350 amp
flux core welding machines, ideal for long
continuous fillet welds.
Landmark
Coatings
Specialty Mobile
Operations
Uncompromising commitment to
to your site.
Developed and refined throughout 25 years of storage tank coatings and lining • Measurement of environmental conditions
work, Landmark’s specialty crews work wherever you need them…on projects • Verification of surface cleanliness prior to coating or lining
that we design, fabricate and build, or on existing infrastructure requiring repair • Wet and dry film thickness measurement
and recoating. The Society for Protective Coatings (SSPC) has recognized our • Holiday testing (low or high voltage, depending on lining thickness)
technical skills and processes with their prestigious QP-1 certification, so you
Daily logs track all inspection activity, and are available upon request.
can rely on thoroughly tested multi-craft services on the most demanding jobs,
with the added benefits of uncompromising safety and nationwide mobility. Specialized equipment enables Landmark to manage dehumidification on work in
enclosed spaces such as tank lining and recoating, and to protect the
complete extraction of dusts for not only a cleaner surface prior to paint
the environment. We apply equally rigorous standards for all locations, require
Mobility
............................................... ...
ongoing training and testing for all crews, and utilize site evaluations, Hazard Landmark capabilities are completely mobile for deployment nationwide or
Identification and Risk Assessments (HIRA) and root cause analysis beyond, without limitations. Specially outfitted trailers move containerized
to continually drive performance improvement. Landmark employs the best equipment to the project site, and then serve as mobile command centers for the
available safeguards for the job, such as advanced, self-contained respiratory crews. All required assets are at hand, coordinated with local supply lines as
equipment on many applications. And we stay at the forefront of best practices appropriate.
and efficient reporting with our membership in ISNetworld. Core values and
comprehensive safety and health programs, along with SSPC C-3 accredidation
Skill
............................................... ...
Landmark’s technical capabilities start with specification assistance, based on in-
depth knowledge of industry suppliers and their latest products, and insights from
our own operations. Our crews are fully equipped to perform surface preparation
and coatings work on virtually any type of steel structure, utilizing a broad array
Quality Assurance Manual for Surface Preparation and Coating. They are trained
to your site.
www.teamlandmark.com
Landmark Leadership in Water Quality
• Industry leader in Hydrodynamic Mixing System development, with first systems designed and installed
in the 1990s
HYDRODYNAMIC
• Invented the two leading mixer styles: “2-Tier 2-Y” and “Trillium”
• Four mixing system patents —in U.S. and Canada MIXING SYSTEMS
• Unparalleled warranty and customer support
WATER MIXING FOR STORAGE
TANKS AND RESERVOIRS
water from aging and contamination. A properly designed mixing system provides a • Outlet ports with wafer check valves are separated from inlet nozzles to maintain circulation
solution that will automatically mitigate common factors leading to taste and odor
issues, bacterial growth, and nitrification:
Low inlet velocity: Inlet pipes designed for maximum flow and low head loss result
in low inlet velocity, low dispersion and poor circulation. High velocity mixing system
nozzles equalize and reduce depletion of disinfectant residuals, and preclude ice cap
formation and damage.
Short-circuiting: Common or close inlet and outlet pipes can result in a LIFO
(last-in, first out) condition. New water entering the tank during fill is the first removed,
leaving the balance to stagnate and age. Mixing eliminates short-circuiting.
Low cycling: High demand periods require full tanks, however water ages if retained • Design considerations include tank geometry, operation cycle and flow magnitude, as well as seasonal,
and not cycled adequately. Hydrodynamic Mixing System design provides for adequate emergency and future demand
• Inlet and outlet valves are NSF 61 certified for highest standards of quality and safety
• Materials of construction are selected to meet customer specific needs and provide maintenance–
free performance
• Services includes consultation, monitoring and best practice recommendations for maximizing system
benefits in everyday operation
LANDMARK HYDRODYNAMIC MIXING SYSTEM
water from aging and contamination. A properly designed mixing system provides a • Outlet ports with wafer check valves are separated from inlet nozzles to maintain circulation
solution that will automatically mitigate common factors leading to taste and odor
issues, bacterial growth, and nitrification:
Low inlet velocity: Inlet pipes designed for maximum flow and low head loss result
in low inlet velocity, low dispersion and poor circulation. High velocity mixing system
nozzles equalize and reduce depletion of disinfectant residuals, and preclude ice cap
formation and damage.
Short-circuiting: Common or close inlet and outlet pipes can result in a LIFO
(last-in, first out) condition. New water entering the tank during fill is the first removed,
leaving the balance to stagnate and age. Mixing eliminates short-circuiting.
Low cycling: High demand periods require full tanks, however water ages if retained • Design considerations include tank geometry, operation cycle and flow magnitude, as well as seasonal,
and not cycled adequately. Hydrodynamic Mixing System design provides for adequate emergency and future demand
• Inlet and outlet valves are NSF 61 certified for highest standards of quality and safety
• Materials of construction are selected to meet customer specific needs and provide maintenance–
free performance
• Services includes consultation, monitoring and best practice recommendations for maximizing system
benefits in everyday operation
Landmark Leadership in Water Quality
• Industry leader in Hydrodynamic Mixing System development, with first systems designed and installed
in the 1990s
HYDRODYNAMIC
• Invented the two leading mixer styles: “2-Tier 2-Y” and “Trillium”
• Four mixing system patents —in U.S. and Canada MIXING SYSTEMS
• Unparalleled warranty and customer support
WATER MIXING FOR STORAGE
TANKS AND RESERVOIRS
APPROVAL: COUNCIL
1. DEFINITIONS:
Annual Debt Repayment Limit – (ARL) Schedule 81 of the Financial Information Return (FIR) provided annually
by Ministry of Municipal Affairs and Housing
Annual Debt Servicing Costs – annual required debt payment that includes both principal and interest
Debt – any obligation for the payment of money. Debt would normally consist of debentures as well as either
notes or cash loans from financial institutions; Debt includes temporary, short term, and long term borrowing
and may also include loans from Reserve Funds or other financial obligations such as leases.
Lease - a contract by which one party conveys land, property, services, etc. to another for a specified time,
usually in return for a periodic payment.
Line of Credit - A line of credit can also be referred to as revolving credit. A LOC is a standing amount of money, similar
to a loan, that a bank extends to a customer. A customer may draw upon the available line of credit, provided that the
amount does not exceed the limit
Own Source Revenues – direct municipal revenues such as property taxes, user fees and charges. Does not
include grants, deferred revenue, donated or assumed assets, gain/(loss) on the sale of land or capital assets.
*Special note – the town’s revenues, as indicated on the Financial Information Return, include revenues from
the consolidated boards of the town*
Promissory Note - a financial instrument that contains a written promise by one party (the note's issuer or maker) to
pay another party (the note's payee) a definite sum of money, either on demand or at a specified future date
Page 1 of 4
Reserve – an allocation, at the discretion of council, of accumulated net revenues that can be built up over
several years that have no reference to any specific asset or project; or for use specifically for an identified
project for a future year – discretionary reserve. Reserves do not require their own bank account, do not earn
their own interest. As a general practice, reserve and reserve fund may both be referred to as reserve
Reserve Funds – a fund that has been set aside either by municipal by-law or a requirement of provincial
legislation to meet future capital needs (Development Charges, Gas Tax); reserve funds have a separate bank
account, earn their own interest, and have annual reporting requirements.
Term Loan - A term loan is a loan from a bank for a specific amount that has a specified repayment schedule and either
a fixed or floating interest rate
2. PURPOSE:
To establish a policy that provides guidelines for, and puts limits upon, the use of debt as a method of financing
capital projects. This policy will serve to enhance the quality of decisions and rationalize the decision-making
process with respect to ensuring compliance with statutory requirements and long-term financial flexibility and
sustainability.
3. POLICY STATEMENT:
The Town of Shelburne shall maintain its level of Debt within the guidelines set by the Province of Ontario, by
Ont. Regulation 403/02, and further by the internally set guidelines in the Policy. Debt is a financing source, but
not a funding source. Debt should only be considered when, after deducting all available funding sources such
as Development Charges, Grants, Reserves, is greater than 1% of a tax levy increase. Borrowing from Reserve
Funds is not a valid option (see section 4.5 regarding internal borrowing)
4. PROCEDURES:
4.1 Types of Debt:
a. Short Term Debt – Under 1 Year
The town may borrow temporarily for cash flow purposes from any one or a combination of the
following resources:
i) Bank Line of Credit
ii) Short-term Promissory Note
iii) Reserve Funds
iv) Any other source of short-term indebtedness
The Town’s combined limit of borrowing from the above sources is subject to the limits set in the annual
Borrowing By-Law. Effort should be made to have short term debt repaid prior to December 31st, of the
year the debt is incurred or within one year thereafter as possible.
Page 2 of 4
b. Medium Term Debt – 1 Year to Under 5 Years
Medium term financing requirements, for periods greater than one year but less than five years will
be financed through any one or combination of the following resources:
i) Lease
ii) Term Loan
iii) Promissory Note
iv) Reserve Funds (Internal Loan) (not to exceed 50% of the total fund balance; an interest
rate not less than the prime rate at the time of borrowing)
v) Capital Line or Capital Loan as offered by Infrastructure Ontario
4.2 The Town shall issue long-term debt for the following purposes only:
• New building construction;
• Building additions;
• New road construction, bridges, culverts, or other roads infrastructure needs;
• Water and wastewater capital projects, or other water and wastewater infrastructure needs;
• Purchase of property, with or without existing structures
4.3 Term of Long-Term borrowing should be 20-25 years for buildings, 15-20 years for new roads, water or
wastewater infrastructure, or alternatively to correspond to the expected useful life of the related asset.
Flexibility shall be allowed in term length, based on where interest rate levels are in the marketplace (for
example, may go to 20 years for roads when rates are low). Terms beyond 25 years are not permitted
with the exception of vacant land, which is a non-depreciable asset, and if available, a 30-year term for
vacant land is permissible.
4.4 Temporary borrowing during the period of construction, for cash flow purposes, is permitted, and the
interest is to be added to the cost of the asset being constructed. The temporary loan amount shall be
converted to long-term debt once the project is complete. Interest on the long-term debt becomes an
operating budget expense.
4.5 There shall be annual reporting to Council of the Town’s long-term debt and remaining borrowing capacity,
as required by Ont. Reg. 403/02, before any new debt may be approved.
Page 3 of 4
4.6 When determining the debt level under point 4.6, both external borrowing and internal borrowing, from
Town Reserve Funds, will be combined in order to measure the debt capacity remaining. Internal borrowing
should only take place when the capital asset can pay for itself within a reasonable time period, not to exceed
10 years or the life expectancy of the asset, whichever is less.
4.7 The maximum permitted amount of long-term debt shall be not more than 40% of the amount determined
under the province’s Annual Debt Repayment Limit (ARL) calculation, received annually from the Ministry
of Municipal Affairs, or 10% of the town’s own source revenues. The conversion of the ARL figure for debt-
servicing into a gross amount of debt shall be done using an interest rate that is reflective of current market
conditions, and a term that conforms to point 4.3 of this Policy.
4.8 The Town shall arrange borrowing through Infrastructure Ontario, through the Town’s bank, or through a
fiscal agent working in the debenture marketplace. The best loan arrangements available shall determine
the choice of the source of borrowing.
Page 4 of 4