SCA Comments02
SCA Comments02
SCA Comments02
Clause Reference Page No Clause Amendment / Comment From NAL (01) ASGC Respond Amendment / Comment From NAL (02) ASGC Response-10-03-2022 NAL Response-10-03-2022
Particular Conditions
To Add - Domestic Variation with Reference to Façade Contractor to proceed for any design
No variation to the Subcontract shall be accepted unless
Variation Clause, Work to be proceeded upon changes "UPON variation confirmation letter Noted. We will add " except for domestic variations which will be confirmed by
7.o 5 the same has been agreed and approved Noted & agreed. Please clarify the last sentence . To be discussed in meeting
Providing letter for variation confrimation. (No amount considering the design changes as additional works" the Contractor"
in writing by the Contract Administrator/Employer
to be concluded in the mentioned letter) - Amount can be concluded in later stages
The Subcontractor, within 14 days after receiving this To Amend - as from signing the Subcontract
9.i 7 Noted & Agreed Agreed - To be added by IBUILD
Subcontract Agreement Agreement
and (iii) approval of prequalification / technical / material To Retract - technical / material submittal. (Not related
9.a 6 Noted & agreed Agreed - To be added by IBUILD
submittal by Employer's Consultant/Contracts Administrator to releasing the Advance Payment)
approved works shall be certified within 30 days from the To Amend - 30 Days from the Invoice submission
9.e 7 invoice date and payment amount shall be released within date and payment amount shall be released within 60 Noted & agreed Agreed - To be added by IBUILD
30 days from the certificate date, days of from the Invoice submission date
The preparation of engineering/shop drawings as per the
latest revision, submission of necessary
method statements, calculations as per latest revisions,
and any new design editions/information Subject to Clause 11 Variations as submissions for Noted. However any changes in programme of
10.a 8 that may arise during the execution of these Subcontract any additional works will vary from the originally works shall be in accordance with the Contractor's Agreed - To be added by IBUILD
Works. The obtaining of all necessary intended submission schedule approval.
approvals from relevant statutory authorities/bodies, as well
as however, not limited to the Contract Administrator/
Employer of all submissions.
The Subcontractor is responsible for all Site measurement Site Measurement Prior to Production is not
which is to be taken prior to the To Retract - Subcontractors shop drawings shall be applicable as long it will prolong production duration
It is the sole responisbility of the Subcontractor to
commencement of any of these Subcontract Works and it prepared in accordance precast concrete approved after the site construction for each villas, As Sub contractor has been already confirmed the inclusion of the site
10.m 9 comply with the actual requirement at site in terms To be discussed in meeting
sha all be the Subcontractor's shop drawings and considering tolerance specified in discussed with IBUID team, Production will follow measurements as per the signed scope of works.
of dimensions and numbers.
responsibility alone to ensure the accuracy and adequacy specifications approved Shop Drawing acoomodating Concrete
of any/all of their installations. Tolerances as per specs.
Annexure E : List of The rates for ironmongery shall include for: - Suiting under
Documents - Section master or sub-master key systems;
H - Doors and To Retract - Master key systems were considered as Requirements as per the project documents to be followed and please confirm Noted, Will double check and confirm all documents
47 No Master Key in NAL Scope
Windows - Rates and The rates shall include for providing key identification tags a requirement in Subcontractors price your compliance to the issued documents. again
Prices - F - 2 & H and split rings, and for master keying as specified or
required.
Annexure F :
Forming in Floor/ Walls - No a Part of NAL's Scope of
Responsibilities 3 Forming in Floor/ Walls (General Contractor Works only) Noted & Agreed Not in NAL Scope
Works
Matrix - Item K
NAL is not in receipt of the Baseline Programme and
requests for the Main Contractors Baseline
Shop drawings To be submitted within 2 weeks (14 Calendar days) after Subcontractor shall coordinate with the site team
Programme - NAL Programme to be submitted
submission Commencement date for the programme related concerns.
reference to BL Program and Clearances given by
IBUILD
Annexure K : Scope Item iii - Compliance with project BIM requirements as per Item iii - To Retract - BIM requirement were considered BIM will be required only incase if mentioned in the project documents. Please Noted, Will double check and confirm all documents
1-2 Please clarify Not in NAL Scope
of Works specification. as a requirement in Subcontractors price. confirm your compliance. again
Annexure K : Scope Item xii - Fly screen as per the project requirement shall be Item iii - To Retract - Fly screen requirement were FlyScreen was not included in Tender Stages, Fly screen will be required only incase if mentioned in the project documents. Noted, Will double check and confirm all documents
1-2 Please clarify
of Works under the scope o f Subcontractor. considered as a requirement in Subcontractors price. Accordingly it shall be claimed as variation Please confirm your compliance. again