Work Plan DR 03

The document outlines a project schedule with 43 tasks over multiple areas including manure, drywell, H2S, tanks area, and CAL. The tasks have durations from 1 to 18.25 days and are scheduled from July 23rd to August 15th with most tasks having 0% completion so far.

Uploaded by

David Rodriguez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views3 pages

Work Plan DR 03

The document outlines a project schedule with 43 tasks over multiple areas including manure, drywell, H2S, tanks area, and CAL. The tasks have durations from 1 to 18.25 days and are scheduled from July 23rd to August 15th with most tasks having 0% completion so far.

Uploaded by

David Rodriguez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ID Task Task Name Duration % Start Finish Predecessors Jul 23, '23 Jul 30, '23 Aug 6, '23

Predecessors Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23
Mode Complete S M T W T F S S M T W T F S S M T W T F S S M T W
1 Platte River 18.25 days 2% Tue 7/25/23 Tue 8/15/23
2 Manure 17.25 days 0% Wed 7/26/23Tue 8/15/23
3 Fabrication of pump supports1 day 0% Mon 7/31/23Mon 7/31/23 Woc
4 Pumps and supports installation
1 day 0% Tue 8/1/23 Tue 8/1/23 3 EqEs
5 Plumbing (Complete 1 day 0% Wed 8/2/23 Wed 8/2/23 4 EqEs
pump discharge piping)
6 Support Plumbing 1 day 0% Thu 8/3/23 Thu 8/3/23 5 EqFe
7 Agitators and suports install
1 day 0% Fri 8/4/23 Fri 8/4/23 6 EqFe
8 Compaction and Fill 1 day 0% Wed 7/26/23Wed 7/26/23 MaJo
9 Flowable Fill 1 day 0% Fri 7/28/23 Fri 7/28/23 CoAd
10 Bollards 1 day 0% Mon 7/31/23Mon 7/31/23 CoMa
11 Metal Structure 3 days 0% Mon 7/31/23Wed 8/2/23 Wsa
12 SoilnHaul off 1 day 0% Wed 7/26/23Wed 7/26/23 MaJo
13 Grating 1 day 0% Tue 8/15/23 Tue 8/15/23 Woc
14 Guardrail 1 day 0% Mon 7/31/23Mon 7/31/23 Woc
15 Paint touch up 2 days 0% Tue 8/1/23 Wed 8/2/23 10 EqEs
16 Drywell 14.5 days 0% Wed 7/26/23Fri 8/11/23
17 Fabricate Drywell suction pipe
2 days 0% Wed 7/26/23Thu 7/27/23 Wra
18 Install Drywell pump 1 day 0% Fri 7/28/23 Fri 7/28/23 17 EqEs
19 Grout Suction pump 1 day 0% Mon 7/31/23Mon 7/31/2318 CoMa
20 Finish Fabrication 1 day 0% Fri 7/28/23 Fri 7/28/23 17 Woc
discharge piping
21 Metal Structure 2 days 0% Mon 8/7/23 Tue 8/8/23 Wsa
22 Paint touch up 3 days 0% Wed 8/9/23 Fri 8/11/23 21 EqVa
23 Chloride Tank 3 days 33% Tue 7/25/23 Thu 7/27/23
24 Set ladder 1 day 100% Tue 7/25/23 Tue 7/25/23 EqJo
25 Emergency shower 1 day 0% Wed 7/26/23Wed 7/26/2324 EqJo
26 Install anchor cables 1 day 0% Thu 7/27/23 Thu 7/27/23 25 EqJo
27 H2S 13.5 days 0% Wed 7/26/23Thu 8/10/23
28 Anchor and epoxy 1 day 0% Wed 7/26/23Wed 7/26/23 CoAd
29 Grout 1 day 0% Thu 7/27/23 Thu 7/27/23 28 CoMa
30 Remove existing piping 1 day 0% Fri 8/4/23 Fri 8/4/23 EqEs
31 Reinstall new piping 1 day 0% Mon 8/7/23 Mon 8/7/23 30 EqFe
32 Fill the H2S Towers 3 days 0% Tue 8/8/23 Thu 8/10/23 31 AyVa
33 Tanks Area 10.5 days 0% Fri 7/28/23 Wed 8/9/23
34 Remove existing piping 1 day 0% Fri 7/28/23 Fri 7/28/23 EqRo
35 Installation Vent piping 1 day 0% Mon 7/31/23Mon 7/31/2334 EqFe
36 Fabrication of support for 2 days 0% Tue 8/1/23 Wed 8/2/23 35 Wra
Vent piping
37 Installation of supports 1 day 0% Thu 8/3/23 Thu 8/3/23 36 EqEs
for Vent piping
38 Painting pipe supprts 2 days 0% Thu 8/3/23 Fri 8/4/23 36 AyVa
39 BioRem tower with carbon2fill days 0% Thu 8/3/23 Fri 8/4/23 36 AyVa
40 CAL 5.75 days 0% Thu 8/3/23 Wed 8/9/23
41 Bolt up cow piping finish1 day 0% Mon 8/7/23 Mon 8/7/23 39 EqFe
42 Blast and coated 16" pipe2 days 0% Tue 8/8/23 Wed 8/9/23 41 AyVa
43 LWR feed pump 1 day 0% Thu 8/3/23 Thu 8/3/23 EqFe

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Schdule Platte River 00
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 7/26/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Duration % Start Finish Predecessors Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23
Mode Complete S M T W T F S S M T W T F S S M T W T F S S M T W
1 Platte River 18.25 days 2% Tue 7/25/23 Tue 8/15/23
2 Manure 17.25 days 0% Wed 7/26/23Tue 8/15/23
3 Fabrication of pump supports1 day 0% Mon 7/31/23Mon 7/31/23 Woc
4 Pumps and supports installation
1 day 0% Tue 8/1/23 Tue 8/1/23 3 EqEs
5 Plumbing (Complete 1 day 0% Wed 8/2/23 Wed 8/2/23 4 EqEs
pump discharge piping)
6 Support Plumbing 1 day 0% Thu 8/3/23 Thu 8/3/23 5 EqFe
7 Agitators and suports install
1 day 0% Fri 8/4/23 Fri 8/4/23 6 EqFe
8 Compaction and Fill 1 day 0% Wed 7/26/23Wed 7/26/23 MaJo
9 Flowable Fill 1 day 0% Fri 7/28/23 Fri 7/28/23 CoAd
10 Bollards 1 day 0% Mon 7/31/23Mon 7/31/23 CoMa
11 Metal Structure 3 days 0% Mon 7/31/23Wed 8/2/23 Wsa
12 SoilnHaul off 1 day 0% Wed 7/26/23Wed 7/26/23 MaJo
13 Grating 1 day 0% Tue 8/15/23 Tue 8/15/23 Woc
14 Guardrail 1 day 0% Mon 7/31/23Mon 7/31/23 Woc
15 Paint touch up 2 days 0% Tue 8/1/23 Wed 8/2/23 10 EqEs
16 Drywell 14.5 days 0% Wed 7/26/23Fri 8/11/23
17 Fabricate Drywell suction pipe
2 days 0% Wed 7/26/23Thu 7/27/23 Wra
18 Install Drywell pump 1 day 0% Fri 7/28/23 Fri 7/28/23 17 EqEs
19 Grout Suction pump 1 day 0% Mon 7/31/23Mon 7/31/2318 CoMa
20 Finish Fabrication 1 day 0% Fri 7/28/23 Fri 7/28/23 17 Woc
discharge piping
21 Metal Structure 2 days 0% Mon 8/7/23 Tue 8/8/23 Wsa
22 Paint touch up 3 days 0% Wed 8/9/23 Fri 8/11/23 21 EqVa
23 Chloride Tank 3 days 33% Tue 7/25/23 Thu 7/27/23
24 Set ladder 1 day 100% Tue 7/25/23 Tue 7/25/23 EqJo
25 Emergency shower 1 day 0% Wed 7/26/23Wed 7/26/2324 EqJo
26 Install anchor cables 1 day 0% Thu 7/27/23 Thu 7/27/23 25 EqJo
27 H2S 13.5 days 0% Wed 7/26/23Thu 8/10/23
28 Anchor and epoxy 1 day 0% Wed 7/26/23Wed 7/26/23 CoAd
29 Grout 1 day 0% Thu 7/27/23 Thu 7/27/23 28 CoMa
30 Remove existing piping 1 day 0% Fri 8/4/23 Fri 8/4/23 EqEs
31 Reinstall new piping 1 day 0% Mon 8/7/23 Mon 8/7/23 30 EqFe
32 Fill the H2S Towers 3 days 0% Tue 8/8/23 Thu 8/10/23 31 AyVa
33 Tanks Area 10.5 days 0% Fri 7/28/23 Wed 8/9/23
34 Remove existing piping 1 day 0% Fri 7/28/23 Fri 7/28/23 EqRo
35 Installation Vent piping 1 day 0% Mon 7/31/23Mon 7/31/2334 EqFe
36 Fabrication of support for 2 days 0% Tue 8/1/23 Wed 8/2/23 35 Wra
Vent piping
37 Installation of supports 1 day 0% Thu 8/3/23 Thu 8/3/23 36 EqEs
for Vent piping
38 Painting pipe supprts 2 days 0% Thu 8/3/23 Fri 8/4/23 36 AyVa
39 BioRem tower with carbon2fill days 0% Thu 8/3/23 Fri 8/4/23 36 AyVa
40 CAL 5.75 days 0% Thu 8/3/23 Wed 8/9/23
41 Bolt up cow piping finish1 day 0% Mon 8/7/23 Mon 8/7/23 39 EqFe
42 Blast and coated 16" pipe2 days 0% Tue 8/8/23 Wed 8/9/23 41 AyVa
43 LWR feed pump 1 day 0% Thu 8/3/23 Thu 8/3/23 EqFe

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Schdule Platte River 00
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 7/26/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Duration % Start Finish Predecessors Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23
Mode Complete S M T W T F S S M T W T F S S M T W T F S S M T W
1 Platte River 18.25 days 2% Tue 7/25/23 Tue 8/15/23
2 Manure 17.25 days 0% Wed 7/26/23Tue 8/15/23
3 Fabrication of pump supports1 day 0% Mon 7/31/23Mon 7/31/23 Woc
4 Pumps and supports installation
1 day 0% Tue 8/1/23 Tue 8/1/23 3 EqEs
5 Plumbing (Complete 1 day 0% Wed 8/2/23 Wed 8/2/23 4 EqEs
pump discharge piping)
6 Support Plumbing 1 day 0% Thu 8/3/23 Thu 8/3/23 5 EqFe
7 Agitators and suports install
1 day 0% Fri 8/4/23 Fri 8/4/23 6 EqFe
8 Compaction and Fill 1 day 0% Wed 7/26/23Wed 7/26/23 MaJo
9 Flowable Fill 1 day 0% Fri 7/28/23 Fri 7/28/23 CoAd
10 Bollards 1 day 0% Mon 7/31/23Mon 7/31/23 CoMa
11 Metal Structure 3 days 0% Mon 7/31/23Wed 8/2/23 Wsa
12 SoilnHaul off 1 day 0% Wed 7/26/23Wed 7/26/23 MaJo
13 Grating 1 day 0% Tue 8/15/23 Tue 8/15/23 Woc
14 Guardrail 1 day 0% Mon 7/31/23Mon 7/31/23 Woc
15 Paint touch up 2 days 0% Tue 8/1/23 Wed 8/2/23 10 EqEs
16 Drywell 14.5 days 0% Wed 7/26/23Fri 8/11/23
17 Fabricate Drywell suction pipe
2 days 0% Wed 7/26/23Thu 7/27/23 Wra
18 Install Drywell pump 1 day 0% Fri 7/28/23 Fri 7/28/23 17 EqEs
19 Grout Suction pump 1 day 0% Mon 7/31/23Mon 7/31/2318 CoMa
20 Finish Fabrication 1 day 0% Fri 7/28/23 Fri 7/28/23 17 Woc
discharge piping
21 Metal Structure 2 days 0% Mon 8/7/23 Tue 8/8/23 Wsa
22 Paint touch up 3 days 0% Wed 8/9/23 Fri 8/11/23 21 EqVa
23 Chloride Tank 3 days 33% Tue 7/25/23 Thu 7/27/23
24 Set ladder 1 day 100% Tue 7/25/23 Tue 7/25/23 EqJo
25 Emergency shower 1 day 0% Wed 7/26/23Wed 7/26/2324 EqJo
26 Install anchor cables 1 day 0% Thu 7/27/23 Thu 7/27/23 25 EqJo
27 H2S 13.5 days 0% Wed 7/26/23Thu 8/10/23
28 Anchor and epoxy 1 day 0% Wed 7/26/23Wed 7/26/23 CoAd
29 Grout 1 day 0% Thu 7/27/23 Thu 7/27/23 28 CoMa
30 Remove existing piping 1 day 0% Fri 8/4/23 Fri 8/4/23 EqEs
31 Reinstall new piping 1 day 0% Mon 8/7/23 Mon 8/7/23 30 EqFe
32 Fill the H2S Towers 3 days 0% Tue 8/8/23 Thu 8/10/23 31 AyVa
33 Tanks Area 10.5 days 0% Fri 7/28/23 Wed 8/9/23
34 Remove existing piping 1 day 0% Fri 7/28/23 Fri 7/28/23 EqRo
35 Installation Vent piping 1 day 0% Mon 7/31/23Mon 7/31/2334 EqFe
36 Fabrication of support for 2 days 0% Tue 8/1/23 Wed 8/2/23 35 Wra
Vent piping
37 Installation of supports 1 day 0% Thu 8/3/23 Thu 8/3/23 36 EqEs
for Vent piping
38 Painting pipe supprts 2 days 0% Thu 8/3/23 Fri 8/4/23 36 AyVa
39 BioRem tower with carbon2fill days 0% Thu 8/3/23 Fri 8/4/23 36 AyVa
40 CAL 5.75 days 0% Thu 8/3/23 Wed 8/9/23
41 Bolt up cow piping finish1 day 0% Mon 8/7/23 Mon 8/7/23 39 EqFe
42 Blast and coated 16" pipe2 days 0% Tue 8/8/23 Wed 8/9/23 41 AyVa
43 LWR feed pump 1 day 0% Thu 8/3/23 Thu 8/3/23 EqFe

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Schdule Platte River 00
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 7/26/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1