Work Plan DR 02

This document outlines a project schedule for work on the Platte River over 19.25 days from July 24th to August 15th. The schedule includes 43 separate tasks related to manure handling infrastructure, including fabricating and installing pumps, piping, drywells, tanks, and towers. Key milestones include completing the metal structure for the drywell by July 26th and finishing piping work for the tanks area by August 15th.

Uploaded by

David Rodriguez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views1 page

Work Plan DR 02

This document outlines a project schedule for work on the Platte River over 19.25 days from July 24th to August 15th. The schedule includes 43 separate tasks related to manure handling infrastructure, including fabricating and installing pumps, piping, drywells, tanks, and towers. Key milestones include completing the metal structure for the drywell by July 26th and finishing piping work for the tanks area by August 15th.

Uploaded by

David Rodriguez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start Finish Predecessors Jul 23, '23 Jul 30, '23 Aug 6, '23

ors Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W
1 Platte River 19.25 days Mon 7/24/23Tue 8/15/23
2 Manure 19.25 days Mon 7/24/23Tue 8/15/23
3 Fabrication of pump supports1 day Mon 7/31/23Mon 7/31/23 Woc
4 Pumps and supports installation
1 day Tue 8/1/23 Tue 8/1/23 3 EqEs
5 Plumbing (Complete 1 day Mon Mon EqEs
pump discharge piping) 7/31/23 7/31/23
6 Support Plumbing 1 day Wed 8/2/23 Wed 8/2/23 4 EqFe
7 Agitators and suports install
1 day Thu 8/3/23 Thu 8/3/23 6 EqFe
8 Compaction and Fill 1 day Mon 7/24/23Mon 7/24/23 MaJo
9 Flowable Fill 1 day Tue 7/25/23 Tue 7/25/23 8 CoAd
10 Bollards 1 day Mon 7/31/23Mon 7/31/23 CoMa
11 Metal Structure 3 days Mon 7/24/23Wed 7/26/23 Wsa
12 SoilnHaul off 1 day Tue 7/25/23 Tue 7/25/23 8 MaJo
13 Grating 1 day Tue 8/15/23 Tue 8/15/23 Woc
14 Guardrail 1 day Fri 7/28/23 Fri 7/28/23 Woc
15 Paint touch up 2 days Mon 7/31/23Tue 8/1/23 14 EqEs
16 Drywell 14.5 days Wed 7/26/23Fri 8/11/23
17 Fabricate Drywell suction pipe
2 days Wed 7/26/23Thu 7/27/23 Wra
18 Install Drywell pump 1 day Fri 7/28/23 Fri 7/28/23 17 EqEs
19 Grout Suction pump 1 day Mon 7/31/23Mon 7/31/2318 CoMa
20 Finish Fabrication 1 day Fri 7/28/23 Fri 7/28/23 17 Woc
discharge piping
21 Metal Structure 2 days Mon 8/7/23 Tue 8/8/23 Wsa
22 Paint touch up 3 days Wed 8/9/23 Fri 8/11/23 21 EqVa
23 Chloride Tank 3 days Wed 7/26/23Fri 7/28/23
24 Set ladder 1 day Wed 7/26/23Wed 7/26/23 EqJo
25 Emergency shower 1 day Thu 7/27/23 Thu 7/27/23 24 EqJo
26 Install anchor cables 1 day Fri 7/28/23 Fri 7/28/23 25 EqJo
27 H2S 7.75 days Wed 7/26/23Thu 8/3/23
28 Anchor and epoxy 1 day Wed 7/26/23Wed 7/26/23 CoAd
29 Grout 1 day Thu 7/27/23 Thu 7/27/23 28 CoMa
30 Remove existing piping 1 day Fri 7/28/23 Fri 7/28/23 29 EqEs
31 Reinstall new piping 1 day Mon 7/31/23Mon 7/31/2330 EqFe
32 Fill the H2S Towers 3 days Tue 8/1/23 Thu 8/3/23 31 AyVa
33 Tanks Area 10.5 days Thu 8/3/23 Tue 8/15/23
34 Remove existing piping 1 day Thu 8/3/23 Thu 8/3/23 EqRo
35 Installation Vent piping 1 day Fri 8/4/23 Fri 8/4/23 34 EqFe
36 Fabrication of support for 2 days Mon 8/7/23 Tue 8/8/23 35 Wra
Vent piping
37 Installation of supports 1 day Wed 8/9/23 Wed 8/9/23 36 EqEs
for Vent piping
38 Painting pipe supprts 2 days Wed 8/9/23 Thu 8/10/23 36 AyVa
39 BioRem tower with carbon2fill days Wed 8/9/23 Thu 8/10/23 36 AyVa
40 Cow 10.5 days Thu 8/3/23 Tue 8/15/23
41 Bolt up cow piping finish1 day Fri 8/11/23 Fri 8/11/23 39 EqFe
42 Blast and coated 16" pipe2 days Mon 8/14/23Tue 8/15/23 41 AyVa
43 LWR feed pump 1 day Thu 8/3/23 Thu 8/3/23 EqFe

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Schdule Platte River 00
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 7/25/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress