Work Plan DR 02
Work Plan DR 02
ors Jul 23, '23 Jul 30, '23 Aug 6, '23 Aug 13, '23
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W
1 Platte River 19.25 days Mon 7/24/23Tue 8/15/23
2 Manure 19.25 days Mon 7/24/23Tue 8/15/23
3 Fabrication of pump supports1 day Mon 7/31/23Mon 7/31/23 Woc
4 Pumps and supports installation
1 day Tue 8/1/23 Tue 8/1/23 3 EqEs
5 Plumbing (Complete 1 day Mon Mon EqEs
pump discharge piping) 7/31/23 7/31/23
6 Support Plumbing 1 day Wed 8/2/23 Wed 8/2/23 4 EqFe
7 Agitators and suports install
1 day Thu 8/3/23 Thu 8/3/23 6 EqFe
8 Compaction and Fill 1 day Mon 7/24/23Mon 7/24/23 MaJo
9 Flowable Fill 1 day Tue 7/25/23 Tue 7/25/23 8 CoAd
10 Bollards 1 day Mon 7/31/23Mon 7/31/23 CoMa
11 Metal Structure 3 days Mon 7/24/23Wed 7/26/23 Wsa
12 SoilnHaul off 1 day Tue 7/25/23 Tue 7/25/23 8 MaJo
13 Grating 1 day Tue 8/15/23 Tue 8/15/23 Woc
14 Guardrail 1 day Fri 7/28/23 Fri 7/28/23 Woc
15 Paint touch up 2 days Mon 7/31/23Tue 8/1/23 14 EqEs
16 Drywell 14.5 days Wed 7/26/23Fri 8/11/23
17 Fabricate Drywell suction pipe
2 days Wed 7/26/23Thu 7/27/23 Wra
18 Install Drywell pump 1 day Fri 7/28/23 Fri 7/28/23 17 EqEs
19 Grout Suction pump 1 day Mon 7/31/23Mon 7/31/2318 CoMa
20 Finish Fabrication 1 day Fri 7/28/23 Fri 7/28/23 17 Woc
discharge piping
21 Metal Structure 2 days Mon 8/7/23 Tue 8/8/23 Wsa
22 Paint touch up 3 days Wed 8/9/23 Fri 8/11/23 21 EqVa
23 Chloride Tank 3 days Wed 7/26/23Fri 7/28/23
24 Set ladder 1 day Wed 7/26/23Wed 7/26/23 EqJo
25 Emergency shower 1 day Thu 7/27/23 Thu 7/27/23 24 EqJo
26 Install anchor cables 1 day Fri 7/28/23 Fri 7/28/23 25 EqJo
27 H2S 7.75 days Wed 7/26/23Thu 8/3/23
28 Anchor and epoxy 1 day Wed 7/26/23Wed 7/26/23 CoAd
29 Grout 1 day Thu 7/27/23 Thu 7/27/23 28 CoMa
30 Remove existing piping 1 day Fri 7/28/23 Fri 7/28/23 29 EqEs
31 Reinstall new piping 1 day Mon 7/31/23Mon 7/31/2330 EqFe
32 Fill the H2S Towers 3 days Tue 8/1/23 Thu 8/3/23 31 AyVa
33 Tanks Area 10.5 days Thu 8/3/23 Tue 8/15/23
34 Remove existing piping 1 day Thu 8/3/23 Thu 8/3/23 EqRo
35 Installation Vent piping 1 day Fri 8/4/23 Fri 8/4/23 34 EqFe
36 Fabrication of support for 2 days Mon 8/7/23 Tue 8/8/23 35 Wra
Vent piping
37 Installation of supports 1 day Wed 8/9/23 Wed 8/9/23 36 EqEs
for Vent piping
38 Painting pipe supprts 2 days Wed 8/9/23 Thu 8/10/23 36 AyVa
39 BioRem tower with carbon2fill days Wed 8/9/23 Thu 8/10/23 36 AyVa
40 Cow 10.5 days Thu 8/3/23 Tue 8/15/23
41 Bolt up cow piping finish1 day Fri 8/11/23 Fri 8/11/23 39 EqFe
42 Blast and coated 16" pipe2 days Mon 8/14/23Tue 8/15/23 41 AyVa
43 LWR feed pump 1 day Thu 8/3/23 Thu 8/3/23 EqFe
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Schdule Platte River 00
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 7/25/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1