Unit 14. Valuation & Construction Economics
Unit 14. Valuation & Construction Economics
Unit 14. Valuation & Construction Economics
Value
Value is the level of importance that is placed upon a function, item or solution. Value is a complex
concept. It is a measure of worth – a relative measure of the usefulness of something in relation to the cost
paid for it. It can be expressed as a function. However, value is like beauty insofar as it depends upon who
is judging it. Value is very much about perspective. This is what makes the concept of value complex in a
business context. Businesses and organizations tend to be multi-faceted comprising a
wide variety of different groups each with their own interests, priorities and perceptions of what is required.
In this context the likelihood of ill-conceived projects, waste and non-congruent business processes, is
high. An operations manager, for example, may have a completely different view of the value of a new
production process to that of a marketing manager or a human resource manager. However, the individual
requirements, perspectives and values of all stakeholders, aligned with the strategic objectives of a
business or organization, are important ingredients in setting objectives for business processes, capital
investments and continuous improvement.
Although the definitions varies, the common focus in all these definitions is that the process of Value
Engineering involves function orientation, organised approach, and creative thinking; and at the heart of it
is the basic equation, that is:
The value of a product or service is a quantity, it depends upon what is its worth or the function(s) it
performs, and the cost allocated for performing the function(s). The term “function” is used to mean the
purpose or use of a product. Thus to measure worth, the product or process is first translated into the
functions. Cost is also not simply the initial price but must also include follow-on costs during the life cycle
of the product.
Focus on value varies with the producer and the customer. To a producer value is the art of providing the
required function(s) at lower cost whereas to a customer value is the amount the least amount he spends
to get what he needs.
The value of a product can be increased by improving the functional utility without change in cost retaining
the same functions for less cost combining improved functional utility with less cost.
The value management process originated during World War II within the General Electric Company (GEC)
in the USA. GEC was faced with an increase in demand but had a shortage of key materials. Larry Miles of
GEC, instead of asking „how can we find alternative materials‟, asked „what function does this component
perform and how else can we perform that function?‟
L.D. Miles, the founder of Value Analysis, defined Value Analysis as “an organised creative approach
which has for its purpose the efficient identification of unnecessary cost, i.e. cost which provides neither
quality, nor use, nor life, nor appearance, nor customer features”.
The five questions in value analysis process, propounded by L. D. Miles, are:
What is it? It implies defining the problem and components for the analysis.
What does it do? It means identifying the basic and secondary functions of the product.
What does it cost? It involves determining the cost of each function, component-wise.
What else will do the job? It aims at finding alternate solutions that perform the same or better function.
What does that cost? Its focus is to finding costs for alternatives that produce same or higher values.
Bureau of Indian Standards terms "Value Engineering." as a discipline comprising a series of techniques
aimed at an organised systematic effort directed at analysing the function (s) of items, products,
equipment, processes and procedures for the purpose of accomplishing all the required functions at the
lowest total cost which expression covers not only initial cost but also ownership cost covering operation /
maintenance, disposal costs etc. throughout the desired or specified life cycle of the articles or subject
under study.
The Society of American Value Engineers (SAVE), defines Value Engineering as the systematic application
of recognised techniques by multi-disciplined team(s) which identify function of a product or service;
establish a worth for that function; generate alternatives through the use of creative thinking and provides
the needed function reliably at the lowest cost. The Value Engineering and Management Digest of USA
defines Value Engineering as the process of problem identifying and solving techniques that achieve the
required function at the lowest cost.
The Australian and New Zealand Standard AZ/NZS (1994) defines Value Management as “ a structured,
and analytical process which seeks to achieve value for money by providing all the necessary functions at
the lowest total cost consistent with the required levels of quality and performance.”
Norton (1995:11) describes Value Management as a systematic, multi-disciplinary effort directed towards
analysing the functions of projects for the purpose of achieving the best value at the lowest overall life cycle
costs.
The following Figure shows the introduction of the parties into the project cycle under the traditional
procurement route; this highlights the importance of involving all the key parties early in the process under
a partnering agreement or better still a long-term alliance.
Studies at the early stages of a project are much more effective and of shorter duration than those
conducted later on. This is because the opportunities for making changes reduce as the project
progresses, and the cost of making such changes increases. Indeed, once the concept has been frozen,
about 80% of the total cost has been committed – even though no design exists.
All client bodies operate a capital-approval process that calls for certain criteria to be met before passing
from one stage to the next – known as approval gateways. Each approval gateway presents a natural
opportunity to conduct a VM study to verify that the scheme, as it has evolved so far, represents optimum
value to the client. It is unusual to conduct a formal study at all of these gateways – usually two, or at most
three, are sufficient.
The first stage in any project is to establish that a project is the most appropriate way in which to deliver the
benefits which are required and then consider the following questions. Is it likely to be viable? Do the
conditions exist to enable the project to stand a chance of success? Is it affordable? Answering these sorts
of questions is the main purpose of Gateway 0 in the OGC‟s Gateway Review Process. VM can play a
significant contribution at this stage. Table identifies the key questions which should be asked at each
stage of the VM study throughout the project cycle.
Typical questions to be asked at each stage of the value management (VM) study on a new urban highway
project.
Value Analysis is based on the fundamental principle that the customer is always looking for the product,
which satisfies his requirement, at the least cost. Value is the connection between the customer
satisfaction and the price he is willing to pay. Value, then, is an essential parameter for improving a
process by reducing costs while always maintaining or increasing client satisfaction. Accordingly, the value
of a product, can be further divided into following categories:
Both Value Engineering and Cost Reduction aim at reducing costs but there is a basic difference between
these techniques. Value Engineering is functional oriented where as Cost Reduction is production oriented.
Value Engineering aims at functional cost effectiveness by avoiding unnecessary costs; it involves multi-
discipline team effort, and applies innovative and creative techniques to maximize value. On the other hand
Cost Reduction aims at changing the method of production to reduce the production cost of an item, it
involves usually an individual effort and generally its emphasis is on analysis of the past practices and
processes to reduce costs.
Function–Cost matrix
Functions Remove Erase Improve Make Transmit Display Support Protect
marks writing look marks force info lead wood
Functions category Second. Second. Second. Basic Second. Second. Second. Second.
Cost Cost Cost Cost Cost Cost Cost Cost
Component Cost
(Rs.)
Lead 1.20 1.20
Body 1.00 0.50 0.10 0.4
Paint 1.00 0.50 0.5
Eraser 2.80 2.80
Metal band 1.00 0.50 0.25 0.25
Total Rs. 7.00 2.80 0.50 0.75 1.20 0.75 0.10 0.4 0.5
Total Cost % 40% 7.1% 10.6% 17.0% 10.6% 1.5% 6.0% 7.1%
In value analysis, the accent is on function a component is required to perform and not on the component
itself. Accordingly, the cost gets related to the functions rather than the product. When a component
serves one function, the cost of the component is equal to the cost of the function. However, in some the
cases, if a component serves more than one function, then the cost of the item is apportioned within the
related functions.
Analysing the functions. The functions in the order of their cost are then selected to analyse value. The
value analysis involves application of different techniques to achieve the required objective. It
includes qualitative questioning method and the analytical optimization techniques to achieve the function
economically. The qualitative function analysis method includes the option of elimination, modification,
substitution, combination, innovation etc, whereas analytical methods are mostly employed for minimisation
and optimisation of functions.
One of the technique often used in value analysis is the „Functional Analysis System Technique (FACT).
This technique identifies a basic function and models its relationships with higher and lower level functions
by asking „HOW‟ functions are performed and testing validity by asking „WHY‟ functions are performed.
The FACT methodology uses both structured and creative techniques, to develop alternative ways to
perform necessary functions at lowest overall cost without degrading quality or performance.
Services of a Value Engineering professional are invaluable for analyzing the functions.
Scope Formulation Phase. . During this phase, the approved concepts are defined, outline specifications
are stated, and sufficient detailed information is developed. Designs, if subjected to value engineering, prior
to scope formulation, have the greatest potential for net cost saving. This is the most opportune time to
question functional performance characteristics.
Contracting Phase. During this phase, Value Engineering by the contractor or vendor can result
in reducing project construction costs resulting in saving in client‟s estimated costs and improving project
schedules,
Construction and Control Phase. Value Engineering can reducing waste, increasing material procurement
efficiency, using resources more effectively, extension of facility‟s life, reducing repair costs, improving
quality control systems and standing operating procedures.
Maintenance Phase. Value Engineering performed during the earlier phases can decrease operation and
maintenance costs.
How to Organise Value Engineering Function in a Major Project.
Value analysis as a staff function, can be entrusted to either technical manager or material manager or
planning manager. Since Value Analysis needs inter-departmental cooperation at all levels for the success,
Planning Chief, who performs the role of the project coordinator, can be perform the value analysis function
as he works in close conjunction with engineering, design, production and purchase departments. If the
project is large, it may be worth it to appoint an independent value engineer working directly under project
manager. Irrespective of the position or the type of organisation chosen, the Value Engineer must be a
part of the project management team.
Value Engineering / Value Analysis is a systematic and organised effort to identify the functions of a
product, system or procedure and to attain that function with minimum cost without jeopardising quality,
aesthetics, appearance etc. In general, Value Engineering:
Enhances value for money.
Effects improvements in function, performance and quality
Enables people to pinpoint areas that need attention and improvement.
Provides a method of generating ideas and alternatives for possible solution to a problem.
Provides a vehicle for dialogue.
Documents the rationale behind decisions.
Improves the value of goods and services.
In conclusion, it must be re-emphasised that Value Engineering is an extremely powerful methodology for
cost effectiveness and value improvement. It is applicable in all phases of project life cycle.
There are a number of techniques which are commonly used in the conduct of value management (VM)
studies. Some of these techniques are:
Function analysis.
Function analysis system technique (FAST).
Cost/worth.
SMART methodology (Simple Multi-Attribute Rating Technique).
Value drivers.
Value benchmarking (or value profiling).
Options selection.
Weighting techniques.
Creative techniques.
Evaluation techniques.
Scenarios technique.
Target costing.
Function performance specification (FPS).
Function analysis
Function analysis is a method for analysing the functions of the constituent parts of a project.
There are many approaches to function analysis, some very structured (such as the function system
analysis technique) and others less formal (such as value trees or mind maps). One of the key principles of
The RICS Valuation – Professional Standards January 2014 (the Red Book) is a comprehensive set of
standards covering the key aspects of a valuer‟s work.
The principal purpose of the standards contained in the RICS Valuation – Professional Standards January
2014 (Red Book 2014) are clearly set out as the „Overall purpose‟ in paragraphs 1–6 of the Introduction:
„1 Consistency, objectivity and transparency are fundamental to building and sustaining public confidence
and trust in valuation. In turn their achievement depends crucially on possessing and deploying the
appropriate skills, knowledge, experience and ethical behaviour, both to form sound judgments and to
report opinions of value clearly and unambiguously to clients and other valuation users.
2 Globally recognised high level valuation principles and definitions are now embodied in the International
Valuation Standards (IVS) published by the International Valuation Standards Council (IVSC). RICS has
long been a supporter of the development of such universal standards, and not only fully embraces them
itself, but also proactively supports their adoption by others around the world.
3 But acceptance alone is not enough – effective implementation is the key. If confidence and public trust
in the valuation process is to be achieved, standards must not only be uniformly interpreted and
consistently applied but also actively monitored and enforced.
4 That is the rationale for this new global edition of RICS Valuation – Professional Standards 2014,
commonly referred to as the Red Book. This formally recognises and adopts the IVS by requiring members
to follow them. It also complements the IVS by providing detailed guidance and specific requirements
concerning their practical implementation.
5 This approach is reinforced by the RICS professional standards regarding ethics, skills and conduct; and
is assured by a well-established system of regulation and by progressive introduction of a system of
practising valuer registration. The whole ensures the positioning of RICS members and regulated firms as
the leading global providers of IVS-compliant valuations.
6 The aim is simply stated – it is to engender confidence in, and to provide assurance to, clients and
recognised users alike, that a valuation provided by an RICS-qualified valuer anywhere in the world will be
undertaken to the highest professional standards overall.‟
The standards set out procedural rules and guidance for valuers. They not only cover matters relating to
ethics and conduct, but also establish a framework for uniformity and best practice in the execution and
delivery of valuations. The Red Book is a procedural manual and not a valuation text book setting out
methodology.
Structure of the Red Book
The RICS global material has now been grouped under three distinct headings. The first two cover matters
relevant to valuation assignments generally, the third covers matters relating to particular applications. The
intention is to make clear to members what is mandatory and what is advisory – thus collected together
under the first two headings is the mandatory material and under the third the advisory material.
This signals a new approach to identifying and classifying valuation practice guidance. This will be issued
either in the form of Guidance Applications, covering specific asset types or situations that are closely
linked to one or more practice statements, or in the form of Guidance Notes, in all other cases. Guidance
Applications and Guidance Notes are of equal status – they contain advisory and not mandatory material.
Although the Guidance Applications are reproduced in full in Red Book 2014, only appropriate cross-
references are included in relation to Guidance Notes. The three distinct sections in the global edition are:
RICS professional standards (PS) These are mandatory and define the parameters for compliance with the
Red Book, including IVS requirements, set out associated RICS regulatory requirements and clarify the
detailed application of the RICS Rules of Conduct for members carrying out valuation work. They comprise:
The following flowcharts are designed to provide practical assistance by providing an overview of the basic
requirements to enable you to comply with the standards contained in the Red Book relating to valuation
practice in the UK.
They are set out in the four stages you need to consider when carrying out a valuation:
A: Preliminary questions
Before commencing any valuation there are seven basic questions the valuer should ask. The answer to
some of the questions will be relevant to proper compliance with some of the standards.
In determining value of an immovable property by „Land and Building Method, another factor viz. Builder‟s
efforts is not considered. Builder‟s efforts as the name suggests is the monetary value assigned to the
efforts expected to be made by the owner of the property to get the buildingconstructed. This includes
expenses likely to be incurred by the owner for getting the building plan prepared and structural design
done, getting the building plan and other services sanctioned by the municipality, electricity board or other
local authorities etc. This may be taken as 3% of the reproduction cost of the buildings.
Therefore, value of a property by the Land and Building Method would be :
1) Value of land …………………….. A
2) Value of building :
2.1 Reproduction cost of the building
Based on CPWD-PAR ………… B
2.2 Amount of depreciation ………. (-) C
2.3 Builder‟s efforts @ 3% of B …… D
2.4 Value of building (B-C+D) …….. E
3. Value of the property ………….. A+E
(1) In the gross annual rent the following amounts should also included :
(i) Interest on deposits not being advance payment towards the rent for a period of 3 months or less @
15% P.A. on the amounts of deposits outstanding from month to month basis for the period (excluding part
of a month) during which deposit was held by the owner in previous year. if the owner paid interest on such
deposit, the amount of interest paid by owner be deducted from the amount of interest calculated @ 15%
P.A.
(ii) The amount of premium divided by the number of years of lease period, if the owner received premium
for leasing out the property.
(iii) The value of benefits or perquisite whether convertible into money or not, desired by the owner as
consideration for leasing of the property or any modification of the terms of lease.
Out Goings :
Only those outgoings which are actually paid or payable by the assessee will qualify for deduction from the
gross main tenable annual rent.
1. Municipal Taxes : The amount of taxes as actually levied or leviable by the municipalities should be
considered for deduction.
2. Repairs and maintenance Charges : The yearly expenses incurred by the assessee for repairs and
maintenance or as per stipulated condition in the rent agreement should be deducted. Normally, 1/12 of
gross annual rent should be considered for deduction as outgoings for repairs and maintenance.
3. Ground Rent : Actual ground rent paid in the case of lease hold properties.
4. Insurance Cover : The actual amount paid by the assessee for the insurance for the safety of building
only limited to the scale laid down by Fire and General Insurance Rules.
5. Management & Collection charges : This will vary depending upon the number of tenants, types of
tenants, legal disputes in collecting the rent. If there is only one tenant or the building is under occupation
Financial management:
Financial management involves planning, allocation and control of financial resources of a company.
Financial management is essential as it controls the financial operations of a company. For a construction
company, the decision to bid for a project will depend on its financial status which in turn will be governed
by financial management principles. The decision to bid for a project will depend on various factors namely
whether the company have enough funds or require outside financing, whether to acquire the equipment
through purchase or acquisition through renting or leasing, whether to carry out the entire work or
subcontract a portion of the work etc. If the company uses its own funds for the project, it may have an
adverse effect on its financial status as it will reduce the liquid asset thus affecting company‟s working
capital. The construction industry differs from other industries because of its unique characteristics and
accordingly the financial management principles are applied for using the financial resources of the
company. Generally the construction companies receive the payments from the owners at specified time
intervals as the construction work progresses and owners often retain certain amount subject to the
satisfactory completion of the project. Thus the terms and conditions for receipt of payments from owners
affect the cash flow of the construction companies and need the changes in allocation of financial
resources. Further construction companies often subcontract some portion of the work (as required) to the
subcontractors, which in turn affect the cash flow. The financial management decisions include the
decisions for investment, financing and distribution of earnings. For construction companies the investment
decisions relate to investment in the business i.e. investment of funds in acquiring the assets (both current
assts and long-term assets) to be utilized in the projects for the expected return along with the risk of cash
flows associated with uncertain future conditions. The financing decisions depend on decision to
investment the funds and the resources possessed by the construction companies. In addition the
financing decisions
are also controlled by other factors namely source of financing (from banks or other financial institutions),
cost of financing i.e. interest cost on the loan and the financing duration. The decision for distribution of
earnings or profits of the company depends on the dividends to be paid to the stockholders and the
retained earnings to be reinvested in the business to increase the return. Thus for any company or
organization, financial management has to ensure the supply of funds in acquiring the assets and their
effective utilization in business activities, to ensure the expected return on the investment considering the
risk associated and optimal distribution of the earnings. Construction accounting Construction
accounting involves collecting, organizing, recording and reporting the financial data of a construction firm.
It helps in identifying the problems encountered in effective management of financial resources of the firm
and taking the corrective measures in time. The accounting system allows for the systematic recording and
reporting the financial information form one period to another in accordance with the accounting principles.
Financial data relates to assets, liabilities, net worth, cost incurred, revenue earned etc. and is required for
preparing the financial statements of the construction firm. The most important financial statements which
are used to represent the financial status and evaluate the performance of the firm are balance sheet and
income statement. The financial statements are also used to communicate the financial status of the firm to
the shareholders and financial institutions. The shareholders and financial institutions can get the useful
information about the utilization of financial resources in the business activities, costs incurred, revenues
earned and other financial information of the firm from period to period. In addition the financial information
is also required for calculating the income tax to be paid by the firm. Construction firms use different types
of accounting methods for recognition of the revenues, costs and profit while preparing the financial
statements. These accounting methods are cash method, accrual method, percentage-of-completion
Owners’ equity or net worth of the firm represents the excess of assets of a firm over its liabilities and is
recorded on the balance sheet. For the companies, the owners‟ equity consists of three components
namely common stock, preferred stock and retained earnings. Common stock represents the major source
of investment by the stockholders in the company and provides the stockholders with voting rights to
exercise in company decisions. Preferred stock that represents the ownership in a company usually do not
provide the stockholders the voting rights to exercise in company affairs, however it ensures a dividend to
be received by stockholders (holders of preferred stock) before any dividend is paid to holders of common
stock. Retained earnings represent the profits or earnings which are reinvested in the company rather than
being distributed as dividends to the stockholders. These earnings are retained by the company to reinvest
in the business to increase the income and thus to increase the value of stock. A typical balance sheet of a
construction firm is shown below. In the balance sheet the total assets of the construction firm is equal to
the sum of total liabilities and owners‟ equity.
Financial ratios Financial ratios are used to evaluate the financial status of a company. These ratios
provide information about the company‟s ability to meet the financial obligations (i.e. ability to pay the bills,
debt payment ability), profitability, liquidity and effective use of its assets. Financial ratios represent the
relationship between the financial data shown on the financial statements (i.e. balance sheet and income
statement). These ratios are calculated by dividing a category of financial data by another category shown
on financial statements and are then compared with other companies within the industry. Through financial
ratios, it is easy to identify the changes in the financial status of the company which are not evident, by only
referring to the values of different categories of assets, liabilities net worth, revenue and expenses shown
on the financial statements. The different financial ratios which are used to assess the financial status of a
company are presented below.
Current ratio Current ratio indicates the ability of a company to meet the short-term financial obligations. In
other words it is a measurement company‟s ability to pay the current liabilities by using the current assets
and is given by;
Current assets and current liabilities shown on balance sheet are used to calculate this ratio and the details
about the current assets and current liabilities are already stated in Lecture 3 (Balance sheet) of this
module. This ratio gives information about working capital status of a company. A current ratio of less than
1.0 to 1 (i.e. 1.0:1) indicates that the current assets of the company is not sufficient to pay its current
liabilities whereas a greater value of current ratio is a strong indicator of the ability of the company to pay
its current liabilities. However on the other hand a considerably higher value of current ratio indicates that
much of the assets of the company might have tied up in the current assets and can be invested in other
business to increase the earnings of the firm.
Quick ratio (or acid-test ratio)
Quick ratio measures the ability of a firm to pay current liabilities using cash or other assets that can be
readily converted into cash. Quick ratio is also referred as acid-test ratio. It is a measure of short-term
liquidity of a firm and provides information about its immediate financial status. This ratio is calculated by
dividing quick assets (categories of current asset) of a firm by its current liabilities. The quick assets include
cash and accounts receivable. Quick ratio is given by the following relationship.
Inventories and retentions receivable (of accounts receivable) are excluded from quick assets because
these assets can not be converted into cash quickly. A quick ratio equal to or greater than 1.0:1 indicates
the ability of a firm to pay the current liabilities with the quick assets. A quick ratio of less than 1.0:1
requires that the firm needs to convert inventories and other assets into cash for payment of current
liabilities.
Debt to worth ratio This ratio is calculated by dividing total liabilities of a company by its net worth or
owners‟ equity. It is also referred as debt to equity ratio and is given by;
This ratio is a measure of a company‟s leverage and the desired value of this ratio should be less than or
equal to 2.0:1. A debt to worth ratio less than 1.0:1 indicates that the firm is not utilizing the debt in the
business to increase the return on the investment. Further a lower value of this ratio indicates that there is
more protection to the creditors as the owners of the firm are contributing majority of the funds to the
business of the firm. A debt to worth ratio of greater than 2.0:1 may result in a greater risk for the
repayment of debt along with interest during recession in the construction industry.
Return on assets ratio The return on assets ratio is calculated by dividing the net profit after taxes by the
total assets of the company. This ratio is expressed as a percentage and is given by:
The net profit after tax from income statement and total assets from balance sheet of a company are used
to calculate this ratio. Return on assets ratio measures how efficiently a company uses its assets to earn
the return and indicates profitability of a company. For a company, the efficient use of assets earns a
higher return (higher value of this ratio) whereas there is low return on assets (lower value of this ratio) for
a poorly run company.
Return on sales ratio This ratio is calculated by dividing the net profit after taxes by the net sales revenue.
Return on sales ratio is expressed as a percentage. It is given by:
In the construction projects, there is usually a time lag between completion of a portion of work and the
receipt of payment from owner of the project and thus production (sales) is not converted into cash
instantaneously. Therefore working capital is required to meet the financial requirement in daily operations
in the project. Often material suppliers and the equipment renting firm also allow a credit period to the
construction company. Thus the credit period allowed by material suppliers and equipment renting firm to
the construction company and that allowed by the construction company to the owner of the project are to
be considered while calculating working capital requirement of the construction company. The calculation
of working capital requirement of a construction company is presented in the following example.
Example -3
The estimated annual revenue of a construction company from a project is Rs.51000000. In the project, the
proportions of material cost, labour cost, equipment cost, overhead cost and profit are 37%, 23%, 16%,
14% and 10% of the estimated annual revenue respectively. On an average two months‟ credit (i.e.
average time period between commencement of a portion of work and receipt of payment from owner of
the project) is allowed to the owner of the project. The materials are purchased from material suppliers and
equipment is hired on rental charges from the equipment renting company. The credit period allowed by
material suppliers and equipment renting firm to the construction company is one month. On average, two
and half months‟ supply of materials is kept in stock at all the times. Calculate the working capital
requirement of the construction company for the operations in the project.
Solution: The working capital requirement will be calculated for meting the expenses of material, labour,
equipment and overhead. The annual material cost, labour cost, equipment cost and overhead with the
corresponding percentages of annual revenue are Rs.18870000, Rs.11730000, Rs.8160000 and
Rs.7140000 respectively.
Materials Materials held in construction work (i.e. in work in progress) = 2 months (i.e. average time period
between the use of materials in the work and receipt of payment from owner of the project) Materials in
stock = 2.5 months Credit from suppliers = 1 month The construction company must have the working
capital to meet the expense of 4.5 (i.e. 2 + 2.5) months‟ materials requirement. However the material
suppliers allow 1 month credit to the company. Thus the construction company requires the working capital
Chicago Institute For Management Training, UAE Page 51 of 52
Certificate Course in Quantity Surveying – Advanced Level
to meet the expense of 3.5 (i.e. 4.5 - 1) months‟ materials requirement. The working capital requirement for
the materials is calculated as follows;
Similarly the working capital requirement for labour, equipment and overhead are calculated and are shown
below.
Labour In work in progress = 2 months (i.e. average time period between employment of labourers in the
work and receipt of payment from owner of the project)
Equipment In work in progress = 2 months (i.e. average time period between use of equipment in the work
and receipt of payment from owner of the project) Credit from renting company = 1 mon
Overhead In work in progress = 2 months (i.e. average time period between commencement of work and
receipt of payment from owner of the project)
The working capital requirement of the construction company in the project till the receipt of payment from
the owner of the project is given by;