5065761401

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Service

Letter SL-0011
Instruction for implementation Date: 10 April 2019

of water guide jacket “C-clamp” Implementation:


Immediate
attention

For WinGD X62DF/X72 DF engines Maintenance Information:


Supplementary instruction to
Operation manual / troubleshooting
guidance.

Concerns:
Owners and operators of WinGD Dual-
Dear Sirs fuel Engines with implemented old
execution of lower water guide jacket
This service letter applies to WinGD X62DF / X72DF holding support.
engines which have the current standard execution
(topside fixation) of the lower water guide jacket fixing
Summary:
support, and informs about the implementation
procedure for the Retrofit design named “C-clamp”. Instruction to ensure proper
installation of new version of water
guide jacket fixing support.

Yours faithfully

Adrian Siegfried Wolfgang Dunker


Product Manager General Manager
X62DF/ 72DF License Management

Winterthur Gas & Diesel Ltd. Schützenstrasse 3 Tel. +41 (0)52 264 8844
Winterthur Gas & Diesel AG. PO Box 414, CH-8401 Fax +41 (0)52 264 8866
Winterthur Gas & Diesel B.A. Winterthur, Switzerland
Service
Letter SL-0011
Contents
1 Introduction ......................................................................................................................................................... 2
2 Retrofit solution “C- clamp” ................................................................................................................................. 2
3 Retrofit implementation guideline ....................................................................................................................... 3
4 Contacts............................................................................................................................................................... 8

1 Introduction
Cases have been reported from ships in operation, where randomly liner wall temperature sensors
showed a sudden increase of the liner wall temperature (LWT), while other unit LWT remained in the
normal operating range.

The reason was found related with a hot water bypass of the cylinder liner. Due to the lower water guide
jacket (WGJ) slipping downwards, the cooling water was allowed to bypass the liner cooling bores, which
led to a locally reduced cooling efficiency and an increase of the LWT’s on that unit (see Figure 1).

Figure 1: Slippage of lower WGJ and resulting cooling water bypass

2 Retrofit solution “C- clamp”


WinGD has developed a more robust, retrofittable solution to prevent the lower WGJ from slipping down.
This solution consists of a new design of holder (See Figure 2) in the form of a “C- clamp” which clamps
the WGJ and cylinder liner together to improve the sealing.

Figure 2: Retrofit solution “C-clamp”

Page 2 of 8
Service
Letter SL-0011
3 Retrofit implementation guideline
3.1 Cooling piping system works
Before beginning work ensure General Safety Precautions as mentioned in the Engines Maintenance
Manual (Chapter 0011−1/A1) are followed.

1) Stop the HT cooling water pumps.


2) Drain the cooling water system engine side.
3) Loosen the connections and flanges of cylinder liner inlet and WGJ inlet pipes (see Figure 3) to
remove any possibility of twisting of the WGJ.

Loosen water
inlet pipes

Figure 3: Cooling water pipes around cylinder liner

3.2 Replacement of current support

1) Mount 3 eyebolts on WGJ topside (M10) holder


(Figure 4). Connect to engine room crane /
Eyebolt
support with chain blocks against slipping.
(Other methods may apply target is avoid
slipping down of WGJ during holder exchange
works).
2) Remove the old holders (first M12 top side
bolts, then M16 liner holding bolts)
(see Figure 5).
3) Check WGJ cast underside for flatness and
condition. Grind to achieve flat contact
for M20 bolt (if required).
Figure 4: Current design holder

Page 3 of 8
Service
Letter SL-0011
4) Install the new “C-clamps” (see figure 5).
5) Tighten the 2 (M16) bolts towards cylinder liner
with 200Nm.
6) Mount vertical M12 (previously installed) bolts
without sleeves – for angular positioning of WGJ
(not shown on Figure 5)

M16 bolts, tighten with 200 Nm

Figure 5: New “C-clamp”

3.3 Re-alignment of lower water guide jacket


The fixation bolt (M20) for support is to be tightened in three steps, with a confirmed gap clearance
between liner and lower water guide jacket.

The nominal clearance between liner and lower WGJ is 3.0mm +/- 0.2 mm on X72DF, and 2.0mm
+/-0.2mm on X62DF (see Figure 6). Note: The clearance may be different due to effective tolerances on
liner & WGJ however there should not be variations in excess of 0.4mm on a single cylinder liner. In such
a case where these conditions cannot be met, a contact check with engineer’s blue should be performed.

Figure 6: Clearance between WGJ and Cylinder Liner (X72DF example)

Page 4 of 8
Service
Letter SL-0011
Tightening procedure of new M20 fixation bolt:
1st step 50 Nm of tightening force and check (plus record) of initial clearances.
2 step
nd 100 Nm of tightening force and check clearances
3rd step 150 Nm of tightening force and check final clearances (plus record final values in
template supplied, refer to page 7)

The locking nut (see Figure 7) to be tightened with 80 Nm, then remove the vertical M12 bolts (they are
no longer required).

Locking nut

M20 Fixation bolt

Figure 7: Extract from assembly drawing showing enlarged cut-section of C-clamp

3.4 Piping reassembly


After WGJ holder mounting, reassemble water piping without inducing undue stress in to the piping. In
case of gaps bigger than 1mm apply a second sealing gasket.

Repeat the WGJ holder replacement procedure for each cylinder one by one.

Store recorded clearances using the attached table (see page 7) on board.

Page 5 of 8
Service
Letter SL-0011
3.5 Re-filling jacket cooling water system
After refilling the cooling water system, follow the below steps for correct air venting (see Figure 8):
1) Open cylinder liner inlet valve (pos 1)
2) Open air vent valve (pos 2)
3) Open manual air vent common line (pos 3)
4) Open JCW outlet valve (pos 4)
5) Open cylinder cover inlet valve (pos 5
3

2 4

Figure 8: HT Cooling water circuit

3.6 Follow up actions


1) Check WGJ to Cylinder liner clearances (see step 3.3) after 2~3 weeks in service and compare with
initial records. Check for loosened bolts.
2) Perform a check again after 6 months in operation

Page 6 of 8
Service
Letter SL-0011
3.7 Clearance Recording Template
Table 1: Port Engine

Cylinder FE side DE side EXH side FP side


1 50 Nm
150 Nm

2 50 Nm
150 Nm

3 50 Nm
150 Nm

4 50 Nm
150 Nm

5 50 Nm
150 Nm

6 50 Nm
150 Nm

7 50 Nm
150 Nm

Table 2: Starboard Engine

Cylinder FE side DE side EXH side FP side


1 50 Nm
150 Nm

2 50 Nm
150 Nm

3 50 Nm
150 Nm

4 50 Nm
150 Nm

5 50 Nm
150 Nm

6 50 Nm
150 Nm

7 50 Nm
150 Nm

Page 7 of 8
Service
Letter SL-0011
4 Contacts

How to contact WinGD


For questions about the content of this Service Letter, or if you need WinGD’s assistance, please contact your
nearest WinGD representative office.
If you don’t have the contact details at hand, please follow the link “Contact us” on the WinGD webpage:

https://www.wingd.com/en/about-wingd/contact-us/

Contact details of WinGD Service Partners:


For engine maintenance-, operation- support, service and other questions about operation and Service, please
contact the following link “Service Partners” on the WinGD webpage to find further information about our Service
Partners CMS and Wärtsilä Services Switzerland which can provide worldwide support.

https://www.wingd.com/en/service-support/service-partners/

© 2019 Winterthur Gas & Diesel Ltd. — All rights reserved

No part of this publication may be reproduced or copied in any form or by any means (electronic, mechanical, graphic,
photocopying, recording, taping or other information retrieval systems) without the prior written permission of the copyright
holder. Winterthur Gas & Diesel Ltd. makes no representation, warranty (express or implied) in this publication and assumes no
responsibility for the correctness, errors or omissions of information contained herein. Information in this publication is subject
to change without notice.

Unless otherwise expressly set forth, no recommendation contained in this document is to be constructed as provided due to a
defect in the engine, but merely as an improvement of the engine and/or the maintenance procedures relating thereto. Any
actions by owner/operator as a result of the recommendations are not covered under any warranty provided by Winterthur Gas
& Diesel Ltd. and such actions will thus be at the owner/operators own cost and expense.

NO LIABILITY, WHETHER DIRECT, INDIRECT, SPECIAL, INCIDENTAL OR CONSEQUENTIAL, IS ASSUMED WITH RESPECT TO THE
INFORMATION CONTAINED HEREIN. THIS PUBLICATION IS INTENDED FOR INFORMATION PURPOSES ONLY.

Page 8 of 8

You might also like