06 Mepd
06 Mepd
06 Mepd
(MEPD)
[email protected]
+91 6381569793
Pavement Design
Overview
(MEPD)
Overview of MEPD
Overview of MEPD
Pavement Design: Challenges
Pavement Design: Challenges
Pavement Design: Challenges
Pavement Design: Challenges
MEPD: Goal
“to keep the development of
the key pavement distresses
under acceptable tolerance
limits until a major
rehabilitation or resurfacing is
planned”
Final MEPD: Goal
Design Structural
Response
Model
Inputs
Structural Pavement
Failure
Materials Performance
Criteria Prediction
Traffic
Environment
Design
Reliability
Mechanistic-Empirical Pavement Design
• The designer first considers site conditions (i.e., traffic, climate, subgrade,
existing pavement condition for rehabilitation) in proposing a trial design for a
new pavement or rehabilitation strategy.
• The trial design is then evaluated for adequacy against user input, performance
criteria, and reliability values through the prediction of distresses and
smoothness.
Mechanistic-Empirical Pavement Design
• If the design does not meet the desired performance criteria at the
specified reliability, it is revised and the evaluation process repeated as
necessary.
• Thus, the designer is fully involved in the design process and has the
flexibility to consider different design features and materials to satisfy the
performance criterion for the site conditions.
Mechanistic-Empirical Pavement Design
Mechanistic-Empirical Pavement Design
Mechanistic-Empirical Pavement Design
Mechanistic-Empirical Pavement Design : with HMA
Mechanistic-Empirical Pavement Design : with HMA
Mechanistic-Empirical Pavement Design : with HMA
Mechanistic-Empirical Pavement Design : with HMA
Mechanistic-Empirical Pavement Design : with PCC
Mechanistic-Empirical Pavement Design : with PCC
Mechanistic-Empirical Pavement Design : with PCC
Mechanistic-Empirical Pavement Design : with PCC
Mechanistic-Empirical Pavement Design : Process
calculation of responses
1. the theory used to predict critical pavement responses (strains, stresses, deflections,
etc.), as a function of traffic and climatic loading (the mechanistic part)
2. materials characterization procedures that support and are consistent with the
selected theory; and
3. defined relationships between the critical pavement response parameter and field-
observed distress (the empirical part).
Mechanistic-Empirical Pavement Design : Benefits
• pavement rehabilitation & new pavement construction
• accommodates
• new materials,
• surface distortion in the form of rutting is caused by the plastic or permanent vertical
deformation in the HMA, unbound layers, and foundation soil.
• rutting is estimated for each sub-season at the mid-depth of each sub-layer within the
pavement structure.
• The plastic deformation for a given season is the sum of the plastic vertical
deformations within each layer.
• The model for calculating total permanent deformation uses the plastic vertical strain
under specific pavement conditions for the total number of trucks within that condition
MEPD: Prediction model for Rut Depth
• The rutting performance model developed initially based on the MoRTH R-6 Research
scheme performance data was subsequently developed into two separate models for
two different reliability levels based on the additional performance data collected for
MoRTH R-56 Research scheme.
IRC 37: Prediction model for Rut Depth
IRC 37: Prediction model for Rut Depth
• For the calculation of vertical compressive strain on top of the subgrade, horizontal
tensile strain at the bottom of the bottom bituminous layer and the horizontal tensile
strain at the bottom of cement treated base (CTB) layer, the analysis is done for a
standard axle load of 80 kN (single axle with dual wheels).
• Only one set of dual wheels, each wheel carrying 20 kN load with the centre to centre
spacing of 310 mm between the two wheels, applied at the pavement surface shall be
considered for the analysis.
• The shape of the contact area of the tyre is assumed in the analysis to be circular.
IRC 37: Prediction model for Rut Depth
• The uniform vertical contact stress shall be considered as 0.56 MPa. However, when
fatigue damage analysis of cement treated bases (CTB) is carried out (using Equations
3.5 to 3.7, the contact pressure used for analysis shall be 0.80 MPa.
• The layer interface condition was assumed to be fully bound for all the layers of the
pavement.
• The equivalent number of standard axle (80 kN) load repetitions that can be served by
the pavement, before the critical condition of the cracked surface area of 20 % or more
occurs, is given by equations 3.3 and 3.4 respectively for 80 % and 90 % reliability levels.
IRC 37: Fatigue Cracking
The fatigue performance models given by equations 3.3 and 3.4 were developed under
MoRTH R-56 scheme utilizing primarily the R-6 scheme (Benkelman Beam Studies)
performance data supplemented by the data available from R-19 (Pavement Performance
Studies) [8] and R-56 schemes.
IRC 37: Fatigue Cracking
IRC 37: Fatigue Cracking (Cement Treated Base)
IRC 37: Fatigue Cracking (Cement Treated Base)
IRC 37: Fatigue Cracking (Cement Treated Base)
IRC 37: Reliability levels